WEBVTT

00:00:00.000 --> 00:00:04.059
- Good morning and welcome to the regularly scheduled

00:00:04.059 --> 00:00:06.599
public utilities board meeting for the city of Denton.

00:00:06.599 --> 00:00:10.519
Today is Monday, June 8th and it is 9 a.m.

00:00:10.519 --> 00:00:12.380
Our meeting is called to order.

00:00:12.380 --> 00:00:15.119
Do we have any public comments?

00:00:16.800 --> 00:00:21.120
Moving on to our next item on the agenda, consent agenda.

00:00:21.120 --> 00:00:24.800
Would any member like to pull an item for discussion?

00:00:26.800 --> 00:00:28.960
I have a few questions on item F.

00:00:28.960 --> 00:00:33.520
So I'd like to receive a presentation on that

00:00:33.520 --> 00:00:36.880
after we work through the rest of the consent agenda.

00:00:42.240 --> 00:00:44.280
- On the approval of A through E.

00:00:44.280 --> 00:00:46.880
- We have a motion for approval of the consent agenda.

00:00:46.880 --> 00:00:47.719
- Second.

00:00:47.719 --> 00:00:49.479
- Items A through E and a second.

00:00:49.479 --> 00:00:50.560
All in favor say aye.

00:00:50.560 --> 00:00:51.719
- Aye.

00:00:51.719 --> 00:00:53.320
- Any opposed?

00:00:53.320 --> 00:00:55.520
Motion carries unanimously.

00:00:55.520 --> 00:00:57.159
And now item F.

00:00:58.960 --> 00:01:01.299
(murmuring)

00:01:08.480 --> 00:01:09.519
- Good morning board.

00:01:09.519 --> 00:01:10.519
My name is Charlie Rosenthal.

00:01:10.519 --> 00:01:12.079
I'm the director of development services

00:01:12.079 --> 00:01:13.560
for the city of Denton.

00:01:13.560 --> 00:01:16.400
I don't have a presentation, but I do have some answers

00:01:16.400 --> 00:01:18.319
to some of the questions you ask.

00:01:18.319 --> 00:01:21.480
And so I just go through the list of questions here

00:01:21.480 --> 00:01:22.959
and then if anybody else has any questions,

00:01:22.959 --> 00:01:24.560
I'd be happy to answer those too.

00:01:25.599 --> 00:01:30.599
So the first one was really related to how temporary

00:01:31.099 --> 00:01:35.400
this temporary wastewater treatment facility would be.

00:01:35.400 --> 00:01:38.879
And so we're expecting the Clear Creek interceptor

00:01:38.879 --> 00:01:43.200
to be ready by the end of 2028 or early 2029.

00:01:43.200 --> 00:01:48.200
And so this developer would start the process

00:01:48.200 --> 00:01:50.319
of development after city council considers

00:01:50.319 --> 00:01:53.079
and approves the development agreement on the 16th.

00:01:53.079 --> 00:01:57.599
And so it's really dependent on how quickly they move

00:01:57.599 --> 00:02:00.319
following council approval.

00:02:00.319 --> 00:02:04.280
But at most, it's a two year timeline between now and then

00:02:04.280 --> 00:02:07.079
and with their development timeline,

00:02:07.079 --> 00:02:10.879
the plant would be online for roughly a year,

00:02:10.879 --> 00:02:11.840
a year and a half.

00:02:15.479 --> 00:02:18.379
And then the next question was if the water

00:02:18.379 --> 00:02:20.639
and wastewater was sized for future development

00:02:20.639 --> 00:02:23.080
and particularly around Craver Ranch.

00:02:23.080 --> 00:02:27.520
So this development is building a water line

00:02:27.520 --> 00:02:29.979
that's sized to our master plan.

00:02:29.979 --> 00:02:32.479
They would have to build a wastewater line

00:02:32.479 --> 00:02:34.120
and it's in a different basin

00:02:34.120 --> 00:02:36.639
than what the Clear Creek development would be.

00:02:36.639 --> 00:02:38.840
And so they would be building a wastewater line

00:02:38.840 --> 00:02:41.199
that's sized for their development.

00:02:41.199 --> 00:02:45.000
We don't have anything in the master plan in the near term

00:02:45.000 --> 00:02:48.360
for that area as far as where that wastewater line would go

00:02:48.360 --> 00:02:48.560
.

00:02:48.560 --> 00:02:52.520
And so water, yes, it would be built to serve that region

00:02:52.520 --> 00:02:54.039
in accordance with the master plan,

00:02:54.039 --> 00:02:57.080
but wastewater, it would just be for their development.

00:02:57.080 --> 00:03:00.039
- And is that just because of,

00:03:00.039 --> 00:03:03.240
so the wastewater master plan includes

00:03:03.240 --> 00:03:05.159
all of the various future developments.

00:03:05.159 --> 00:03:08.599
Like I know Craver Ranch is up there,

00:03:08.599 --> 00:03:10.360
there used to be a development in process

00:03:10.360 --> 00:03:12.919
called Hills of Denton North and there are a few others.

00:03:12.919 --> 00:03:14.840
So that the master plan already includes

00:03:14.840 --> 00:03:16.879
all of that kind of expected development in that area.

00:03:16.879 --> 00:03:19.360
- Correct, and the Clear Creek Interceptor runs

00:03:19.360 --> 00:03:22.479
through the Hills of Denton property.

00:03:22.479 --> 00:03:25.800
This one's a little further north off of Milam Road

00:03:25.800 --> 00:03:28.759
and there's not been a ton of development interest

00:03:28.759 --> 00:03:29.879
out that way.

00:03:29.879 --> 00:03:33.080
And then Craver Ranch is actually further east

00:03:33.080 --> 00:03:34.719
of this development.

00:03:34.719 --> 00:03:37.780
And we've been discussing with them extensions

00:03:37.780 --> 00:03:39.879
of their wastewater infrastructure in accordance

00:03:39.879 --> 00:03:42.520
with the agreement the city had for them,

00:03:42.520 --> 00:03:43.680
but it's not really in line

00:03:43.680 --> 00:03:45.379
with where this development's occurring.

00:03:45.379 --> 00:03:48.879
- Okay, so this, but this, their contributions

00:03:48.879 --> 00:03:51.680
in construction there will be appropriate

00:03:51.680 --> 00:03:55.080
for the master plan, maybe not affected by Craver Ranch.

00:03:55.080 --> 00:03:57.759
- Yeah, at least the water portion would be,

00:03:57.759 --> 00:04:00.120
wastewater would be sized for their development.

00:04:02.719 --> 00:04:05.599
I think the next question was if this delays anything

00:04:05.599 --> 00:04:08.360
with the Clear Creek Interceptor, it does not.

00:04:08.360 --> 00:04:11.000
So the way the development agreement for this would work

00:04:11.000 --> 00:04:13.919
is they would be allowed to construct a temporary plant

00:04:13.919 --> 00:04:16.399
that the city would own and operate

00:04:16.399 --> 00:04:17.920
that would come off of line

00:04:17.920 --> 00:04:21.040
when the Clear Creek Interceptors completed.

00:04:21.040 --> 00:04:23.879
And so that project's still moving forward

00:04:23.879 --> 00:04:26.519
and doesn't affect the timeline of that project at all.

00:04:31.540 --> 00:04:33.879
- Are there any other questions from the board?

00:04:35.680 --> 00:04:37.120
I have one follow-up question.

00:04:37.120 --> 00:04:39.100
The temporary water treatment plant

00:04:39.100 --> 00:04:41.720
or water reclamation facility,

00:04:41.720 --> 00:04:43.680
if it'll be any use for two years

00:04:43.680 --> 00:04:45.879
and it'll become city of Denton property,

00:04:45.879 --> 00:04:49.199
at that point, is it like a package plant

00:04:49.199 --> 00:04:52.879
that we could then sell or would it stay

00:04:52.879 --> 00:04:56.000
just parked non-operational at the site?

00:04:57.120 --> 00:04:59.839
What's the plan for disposal of this capital?

00:04:59.839 --> 00:05:04.839
- So really it would be up to our water team's decision

00:05:04.959 --> 00:05:07.759
at that point, so the way the agreement is written is

00:05:07.759 --> 00:05:10.439
it's at their cost to remove it

00:05:10.439 --> 00:05:13.600
and the city has the option either for them to remove it

00:05:13.600 --> 00:05:15.720
and dispose of it in accordance with state law

00:05:15.720 --> 00:05:18.680
or they can remove it and move it to a location

00:05:18.680 --> 00:05:19.680
of the city's choosing.

00:05:19.680 --> 00:05:23.839
So I think if we have a need for another temporary plan

00:05:23.839 --> 00:05:27.319
in another location, then we could ask them

00:05:27.319 --> 00:05:30.079
to move it to that location if there's a future city use

00:05:30.079 --> 00:05:32.800
for it or for sale or anything like that.

00:05:32.800 --> 00:05:35.240
But that's something we would consider at the time

00:05:35.240 --> 00:05:38.560
that the plan's removed, but it's at our option.

00:05:38.560 --> 00:05:40.160
- Okay, thank you, Chairman.

00:05:41.439 --> 00:05:43.199
Excuse me, good morning.

00:05:43.199 --> 00:05:47.519
Have we done such a situation like that occur?

00:05:47.519 --> 00:05:49.079
Have we done that before?

00:05:49.079 --> 00:05:51.360
- Not that I-- - So this is a first?

00:05:51.360 --> 00:05:52.839
- That's correct, yeah.

00:05:52.839 --> 00:05:54.079
- Who said that?

00:05:54.079 --> 00:05:55.040
Over the back row?

00:05:57.040 --> 00:05:59.279
(laughing)

00:06:02.240 --> 00:06:04.319
- Tony getting upset and me answering something

00:06:04.319 --> 00:06:06.120
from the gallery, Stephen Gay,

00:06:06.120 --> 00:06:08.279
General Manager of Water Utilities.

00:06:08.279 --> 00:06:11.360
We not exactly like this, but if you think back

00:06:11.360 --> 00:06:14.120
to the Robeson community, it's very similar to that, right?

00:06:14.120 --> 00:06:17.000
Where they built a plant to help their development

00:06:17.000 --> 00:06:19.399
and the city took over operation of it.

00:06:19.399 --> 00:06:21.279
And now we're leveraging that plant

00:06:21.279 --> 00:06:23.079
and part of our larger system

00:06:23.079 --> 00:06:24.959
and converting it into a lift station.

00:06:24.959 --> 00:06:27.600
So we'd have the similar option there as well.

00:06:27.600 --> 00:06:29.079
- Great, I appreciate it.

00:06:30.399 --> 00:06:32.920
I thought there was something else, but I wasn't sure.

00:06:32.920 --> 00:06:33.959
Thanks for being here.

00:06:36.079 --> 00:06:38.639
- Thank you, Mr. Chairman.

00:06:38.639 --> 00:06:39.839
- Any further questions?

00:06:41.399 --> 00:06:42.199
Okay.

00:06:42.199 --> 00:06:45.120
With that, I'll move approval of item F

00:06:45.120 --> 00:06:46.439
from our consent agenda.

00:06:46.439 --> 00:06:47.279
- Aye.

00:06:47.279 --> 00:06:48.360
- We have a motion and a second.

00:06:48.360 --> 00:06:49.720
All in favor, say aye.

00:06:49.720 --> 00:06:50.639
- Aye.

00:06:50.639 --> 00:06:52.000
- Any opposed?

00:06:52.000 --> 00:06:54.240
Motion carries unanimously.

00:06:54.240 --> 00:06:57.370
Now we will move on to our items for individual

00:06:57.370 --> 00:06:58.759
consideration.

00:06:58.759 --> 00:07:02.720
Our first item is approval of the May 18th minutes.

00:07:03.639 --> 00:07:05.560
Are there any corrections or comments?

00:07:06.879 --> 00:07:07.899
We have a motion.

00:07:08.839 --> 00:07:09.680
- Second.

00:07:09.680 --> 00:07:10.500
- And a second.

00:07:10.500 --> 00:07:11.339
All in favor, say aye.

00:07:11.339 --> 00:07:12.399
- Aye.

00:07:12.399 --> 00:07:14.680
- Motion carries unanimously.

00:07:14.680 --> 00:07:18.839
Our next item for individual consideration is item B.

00:07:18.839 --> 00:07:20.920
Consider recommending adoption of an ordinance

00:07:20.920 --> 00:07:22.120
authorizing the city manager

00:07:22.120 --> 00:07:23.839
to execute a professional services agreement

00:07:23.839 --> 00:07:26.199
with Corolla Engineers

00:07:26.199 --> 00:07:28.839
for the Clear Creek Water Reclamation Plant

00:07:28.839 --> 00:07:31.839
for a total not to exceed of $45,528,839.

00:07:41.040 --> 00:07:43.040
- Good morning, I'm David Brown,

00:07:43.040 --> 00:07:44.680
Water Utilities Project Manager.

00:07:44.680 --> 00:07:47.160
Today I'm here to request the approval

00:07:47.160 --> 00:07:49.160
of the design contract for the

00:07:49.160 --> 00:07:52.879
Clear Creek Water Reclamation Plant.

00:07:52.879 --> 00:07:56.000
This facility will help water utilities regionalize

00:07:56.000 --> 00:07:58.839
services in the Clear Creek Drainage Basin.

00:07:59.839 --> 00:08:03.279
The Clear Creek Drainage Basin is located just north

00:08:03.279 --> 00:08:05.120
of the Loop 288 area.

00:08:05.120 --> 00:08:08.480
You can see by this map we have together here is

00:08:08.480 --> 00:08:11.120
the Clear Creek Sewer Interceptor

00:08:11.120 --> 00:08:13.560
and the Clear Creek Water Reclamation Plant.

00:08:13.560 --> 00:08:16.560
They're noticed by the star.

00:08:16.560 --> 00:08:18.759
The Clear Creek Drainage Basin Plant,

00:08:18.759 --> 00:08:21.319
like I said, was located just north of Loop 288

00:08:21.319 --> 00:08:23.399
and compared with previous studies,

00:08:23.399 --> 00:08:25.839
we have seen accelerated development in this area

00:08:25.839 --> 00:08:28.360
compared to other areas around the city.

00:08:28.360 --> 00:08:30.199
Currently, wastewater is collected from the

00:08:30.199 --> 00:08:33.840
Clear Creek Drainage Basin and flows down in pumps

00:08:33.840 --> 00:08:37.000
into Pecan Creek Water Reclamation Plant.

00:08:37.000 --> 00:08:39.200
The Clear Creek Water Reclamation Plant,

00:08:39.200 --> 00:08:40.879
where it's treated there,

00:08:40.879 --> 00:08:42.720
treating the wastewater at that plant

00:08:42.720 --> 00:08:44.600
does have some capacity constraints.

00:08:44.600 --> 00:08:48.480
So with the development and construction of a

00:08:48.480 --> 00:08:50.600
wastewater treatment plant there at Clear Creek

00:08:50.600 --> 00:08:52.679
will help alleviate some of the constraints

00:08:52.679 --> 00:08:54.600
there at Pecan Creek.

00:08:54.600 --> 00:08:57.000
To prevent degradation of the surface water areas

00:08:57.000 --> 00:08:59.840
in that area, Denton is using a regionalization,

00:08:59.840 --> 00:09:02.840
sorry, a regionalization strategy

00:09:04.399 --> 00:09:07.120
to limit the number of small package plants,

00:09:07.120 --> 00:09:09.679
just like we talked about, in that area

00:09:09.679 --> 00:09:12.320
that is often used by developers.

00:09:12.320 --> 00:09:16.759
We'll want them to tie into our Clear Creek Interceptor

00:09:16.759 --> 00:09:20.000
and be able to treat the water there.

00:09:20.000 --> 00:09:22.440
Two critical projects, like I spoke about,

00:09:22.440 --> 00:09:24.740
are the Clear Creek Interceptor Sewer Interceptor,

00:09:24.740 --> 00:09:28.200
which is at about 60%, Charlie talked about it's on the way

00:09:28.200 --> 00:09:28.480
,

00:09:28.480 --> 00:09:30.460
it's at about 60% design,

00:09:30.460 --> 00:09:31.960
working through alignment and easements,

00:09:31.960 --> 00:09:34.679
and also today we're talking about the Clear Creek

00:09:34.679 --> 00:09:36.039
Water Reclamation Plant.

00:09:38.000 --> 00:09:42.320
The Clear Creek Water Reclamation Plant is located,

00:09:42.320 --> 00:09:44.480
will be located on city owned property

00:09:44.480 --> 00:09:47.840
near the intersection of Harley Field and Collins Road,

00:09:47.840 --> 00:09:48.919
as shown in the picture here.

00:09:48.919 --> 00:09:50.600
For clarity, I want to go ahead and show,

00:09:50.600 --> 00:09:52.120
like we put on here in gold,

00:09:52.120 --> 00:09:54.799
the Clear Creek Interceptor, which is in design,

00:09:54.799 --> 00:09:57.419
and it'll collect all the wastewater

00:09:57.419 --> 00:09:58.639
throughout the drainage basin

00:09:58.639 --> 00:10:01.580
and convey it down to the Water Reclamation Plant.

00:10:02.960 --> 00:10:05.279
Let's talk about the site.

00:10:05.279 --> 00:10:08.320
The site is permitted for a Water Reclamation Plant

00:10:08.320 --> 00:10:09.840
and a lift station,

00:10:09.840 --> 00:10:13.210
and it currently has a permit of 10 million gallons per day

00:10:13.210 --> 00:10:13.480
.

00:10:14.600 --> 00:10:15.600
If we want to look through this,

00:10:15.600 --> 00:10:17.399
here's just a rendering from 2002

00:10:17.399 --> 00:10:19.440
when we first started to design it,

00:10:19.440 --> 00:10:21.000
and let's look at the timeline.

00:10:21.000 --> 00:10:24.549
In 1998, a wastewater treatment planning report came

00:10:24.549 --> 00:10:25.200
through,

00:10:25.200 --> 00:10:28.440
and then in 2000 we purchased the property, the city did.

00:10:28.440 --> 00:10:33.039
In 2002, we had a PDR and a preliminary design report,

00:10:33.039 --> 00:10:34.919
and we're granted a .95 MGD,

00:10:34.919 --> 00:10:37.559
a partial discharge permit there.

00:10:37.559 --> 00:10:42.120
In 2003, with a downturn of development in that area,

00:10:42.120 --> 00:10:45.480
we paused because of that downturn in 2003.

00:10:45.480 --> 00:10:50.330
In 2025, we were granted a full 10 MGD TCQ discharge permit

00:10:50.330 --> 00:10:50.480
.

00:10:57.600 --> 00:11:00.440
Oh, I might have skipped one here, I don't know, maybe not.

00:11:01.320 --> 00:11:02.600
So this will, let me talk about,

00:11:02.600 --> 00:11:06.279
this will be an Advanced Water Reclamation Plant, MBR plant

00:11:06.279 --> 00:11:06.279
.

00:11:06.279 --> 00:11:09.080
With that, high efficiency screening, grit removal,

00:11:09.080 --> 00:11:12.440
a biological nutrient removal, also called BNR,

00:11:12.440 --> 00:11:14.360
we'll refer to that as BNR,

00:11:14.360 --> 00:11:17.039
membrane bioreactor, MBR,

00:11:17.039 --> 00:11:21.320
odor control system, ultraviolet disinfection,

00:11:21.320 --> 00:11:25.340
and also architectural components on operations building.

00:11:25.340 --> 00:11:29.000
Estimated construction cost now is $455 million,

00:11:29.000 --> 00:11:30.799
and you can see our timelines.

00:11:30.799 --> 00:11:33.840
Design services starting as soon as possible

00:11:33.840 --> 00:11:36.960
and ending in quarter four of 2028.

00:11:36.960 --> 00:11:40.120
Construction services start in quarter four of 2028

00:11:40.120 --> 00:11:42.000
and run through 2032.

00:11:47.039 --> 00:11:50.159
Given the location of the proposed plant site,

00:11:50.159 --> 00:11:52.100
we wanna minimize the impact

00:11:52.100 --> 00:11:53.960
on the mountain bike trails in that area,

00:11:53.960 --> 00:11:55.960
and it's a top priority of the utility.

00:11:57.039 --> 00:11:59.200
The plant, as you can see in yellow,

00:11:59.200 --> 00:12:01.840
will utilize the lower portion of the property

00:12:01.840 --> 00:12:04.200
so we could be able to use the rest of property

00:12:04.200 --> 00:12:07.240
for other designated things that may go on.

00:12:08.480 --> 00:12:10.799
Impacted trails will be rerouted,

00:12:10.799 --> 00:12:14.480
and we are exploring adding additional educational items

00:12:14.480 --> 00:12:17.639
along the fence so those visitors who come out there

00:12:17.639 --> 00:12:20.279
could get an education on wastewater treatment

00:12:20.279 --> 00:12:22.620
in the municipal, at the municipal level.

00:12:23.960 --> 00:12:26.919
(mouse clicking)

00:12:26.919 --> 00:12:31.919
Six firms were evaluated through our pre-qualified list,

00:12:31.960 --> 00:12:35.879
8312, and we have selected Corolla Engineering.

00:12:35.879 --> 00:12:38.799
Corolla was selected due to the multifunctionality

00:12:38.799 --> 00:12:41.919
and efficiency of the proposed site plan.

00:12:41.919 --> 00:12:45.240
They took into consideration the mountain bike trails

00:12:45.240 --> 00:12:48.320
and put a site plan that we liked,

00:12:48.320 --> 00:12:50.559
and just the process that they conveyed

00:12:50.559 --> 00:12:53.779
in order to minimize the impact at the current site.

00:12:54.960 --> 00:12:57.320
As you can see here, design contract proposal

00:12:57.320 --> 00:13:02.320
is $45,528,839, and that is roughly at about 10%

00:13:03.720 --> 00:13:05.200
of estimated construction costs

00:13:05.200 --> 00:13:07.519
that we're seeing designed with construction costs,

00:13:07.519 --> 00:13:11.200
and we are gonna utilize the construction manager at risk

00:13:11.200 --> 00:13:14.100
to see more coordination, four-year base contract,

00:13:14.100 --> 00:13:16.360
and two-year special services.

00:13:16.360 --> 00:13:18.720
Funding breakdown, traditional debt,

00:13:18.720 --> 00:13:23.039
up to 51% will utilize, and we are also applied

00:13:23.039 --> 00:13:28.039
for the WIFIA, Water Infrastructure Finance Innovation Act,

00:13:28.320 --> 00:13:29.559
that we currently applied for,

00:13:29.559 --> 00:13:33.919
and that could fund up to 49% of the debt there.

00:13:33.919 --> 00:13:36.840
And also we applied for Texas Water Development Board

00:13:36.840 --> 00:13:39.240
Clean Water State Revolving Fund.

00:13:39.240 --> 00:13:42.879
There you can see it's in progress up to $400 million,

00:13:42.879 --> 00:13:45.799
low-interest loans, with a possibility

00:13:45.799 --> 00:13:47.820
of up to $60 million per year.

00:13:49.399 --> 00:13:51.360
With that, staff recommends the adoption

00:13:51.360 --> 00:13:53.600
of a professional service contract

00:13:53.600 --> 00:13:56.200
between the City of Denton and Corolla Engineers

00:13:56.200 --> 00:13:58.799
for design and construction-faith services

00:13:58.799 --> 00:14:01.159
for the Clear Creek Water Reclamation Plant,

00:14:01.159 --> 00:14:04.159
not to exceed the amount of $45,528,839.

00:14:07.279 --> 00:14:09.360
And I will stand for any questions.

00:14:13.840 --> 00:14:16.559
- Could you go to slide four, please?

00:14:16.559 --> 00:14:17.379
- Yes, sir.

00:14:21.279 --> 00:14:22.120
- Thank you.

00:14:26.039 --> 00:14:26.879
That's it.

00:14:26.879 --> 00:14:30.559
What is the projected capacity

00:14:30.559 --> 00:14:33.600
for that 10 million gallon daily?

00:14:34.600 --> 00:14:36.559
Obviously we're not at that stage now.

00:14:36.559 --> 00:14:39.399
What's the life expectancy of that, do you think?

00:14:39.399 --> 00:14:43.159
- I think the life expectancy would be 10 years, I think.

00:14:43.159 --> 00:14:44.919
That's what we're estimating.

00:14:44.919 --> 00:14:49.519
- And then what happens after that?

00:14:49.519 --> 00:14:50.360
- We expand it.

00:14:50.360 --> 00:14:54.039
And we are, actually the design will be expandable.

00:14:54.039 --> 00:14:56.399
It's not just capped at that 10 MGD.

00:14:56.399 --> 00:14:57.240
- That's what I was curious about.

00:14:57.240 --> 00:15:00.960
- We're gonna design it for expansion.

00:15:00.960 --> 00:15:01.799
- Thank you.

00:15:01.799 --> 00:15:02.919
And then slide five, please.

00:15:05.759 --> 00:15:08.679
I was curious on the estimated, the 455 million,

00:15:08.679 --> 00:15:12.480
is this 45 million part of that 455 million?

00:15:12.480 --> 00:15:13.320
- No, sir.

00:15:13.320 --> 00:15:14.139
- No, that's separate.

00:15:14.139 --> 00:15:14.980
- Yes, sir.

00:15:14.980 --> 00:15:15.799
- Okay.

00:15:15.799 --> 00:15:16.799
Thank you very much.

00:15:16.799 --> 00:15:17.639
- Thank you.

00:15:20.879 --> 00:15:22.440
- I took my questions.

00:15:22.440 --> 00:15:23.759
(laughing)

00:15:23.759 --> 00:15:26.279
- I went over there earlier and read our notes.

00:15:26.279 --> 00:15:27.720
(laughing)

00:15:27.720 --> 00:15:28.720
- So I just wanted to,

00:15:30.639 --> 00:15:33.240
going back to consent agenda item F,

00:15:34.279 --> 00:15:37.080
that interceptor, that's already a separate project

00:15:37.080 --> 00:15:38.159
that's already kind of in process.

00:15:38.159 --> 00:15:39.000
- Yes, sir.

00:15:39.000 --> 00:15:40.639
Capital projects is delivering that one.

00:15:40.639 --> 00:15:42.919
So we're coordinating with them.

00:15:42.919 --> 00:15:44.360
- And that basically leads to this.

00:15:44.360 --> 00:15:45.200
Like it connects to this plan.

00:15:45.200 --> 00:15:46.039
- Yes, sir.

00:15:46.039 --> 00:15:46.860
- Okay.

00:15:46.860 --> 00:15:49.320
And I do wanna comment,

00:15:49.320 --> 00:15:50.320
could you go back to the timeline?

00:15:50.320 --> 00:15:51.840
I think maybe it was slide four.

00:15:54.440 --> 00:15:56.000
- Go backwards here, I'm sorry.

00:15:56.000 --> 00:15:56.840
- No problem.

00:15:57.879 --> 00:16:01.159
Well, yeah, that one and also the mountain bike path.

00:16:01.159 --> 00:16:02.360
I just wanted to point out,

00:16:02.360 --> 00:16:07.360
this has been planned for almost 30 years.

00:16:07.840 --> 00:16:09.200
Yeah, like, you know.

00:16:09.200 --> 00:16:12.279
And I think it was a really,

00:16:12.279 --> 00:16:14.519
the purchase property in 2000

00:16:14.519 --> 00:16:18.460
and it's been able to be used for the mountain bike trails

00:16:18.460 --> 00:16:19.299
and other uses.

00:16:19.299 --> 00:16:23.240
And I think the utility department was really receptive

00:16:23.240 --> 00:16:25.200
to that idea and really helped allow,

00:16:25.200 --> 00:16:27.620
you know, it was really magnanimous perhaps

00:16:27.620 --> 00:16:30.320
to allow that secondary use on this property.

00:16:30.320 --> 00:16:32.320
I know there's people that were really concerned

00:16:32.320 --> 00:16:34.940
that that whole mountain bike trail system

00:16:34.940 --> 00:16:35.980
was gonna be destroyed

00:16:35.980 --> 00:16:38.480
and they're gonna kind of kicked off the property.

00:16:40.039 --> 00:16:43.879
But the property was purchased with this, you know,

00:16:43.879 --> 00:16:45.159
use in mind.

00:16:45.159 --> 00:16:47.720
And so I think it's really great that we've been able to,

00:16:47.720 --> 00:16:49.919
that hopefully Corolla will be able to work through

00:16:49.919 --> 00:16:51.480
and y'all will be able to work through

00:16:51.480 --> 00:16:55.200
allowing as much of that mountain bike use to stay there

00:16:55.200 --> 00:16:57.809
while still achieving the primary objective of this

00:16:57.809 --> 00:16:58.759
property.

00:16:58.759 --> 00:17:00.620
I just wanted to put that out.

00:17:00.620 --> 00:17:02.220
- I wanted to share that one of the things

00:17:02.220 --> 00:17:04.319
that Corolla brought was the idea

00:17:04.319 --> 00:17:06.279
for the mountain bike trails and how important

00:17:06.279 --> 00:17:07.960
they knew that was gonna be important.

00:17:07.960 --> 00:17:10.519
And they have some people on board that are,

00:17:10.519 --> 00:17:11.839
I guess they're called mountain bikers.

00:17:11.839 --> 00:17:16.839
So they know the people that like that type stuff

00:17:17.880 --> 00:17:20.680
and we wanna be cognizant of their concerns

00:17:20.680 --> 00:17:22.079
and we're gonna do our best.

00:17:23.079 --> 00:17:24.599
- And I have one final question,

00:17:24.599 --> 00:17:26.640
just I think the very first slide with the map

00:17:26.640 --> 00:17:28.640
or maybe the second slide with the map.

00:17:29.720 --> 00:17:31.720
- I gotta learn how to go back.

00:17:31.720 --> 00:17:32.559
Sorry.

00:17:33.839 --> 00:17:35.440
Yes, I'm gonna learn that today.

00:17:38.960 --> 00:17:42.119
- I'm assuming that outlined area in the North Denton area,

00:17:42.119 --> 00:17:44.339
that is what this will serve?

00:17:45.539 --> 00:17:46.680
- Yes, sir.

00:17:46.680 --> 00:17:50.440
- And is that the end of, on the East side,

00:17:50.440 --> 00:17:54.480
is that the end of Denton or is there actually more

00:17:54.480 --> 00:17:57.680
of Denton on the East side of Elm Fork,

00:17:57.680 --> 00:17:59.319
I guess that is?

00:17:59.319 --> 00:18:01.160
- There's more of Denton on that side,

00:18:01.160 --> 00:18:02.359
but as far as service area,

00:18:02.359 --> 00:18:05.160
I don't know exactly where it stops.

00:18:05.160 --> 00:18:06.000
- Okay.

00:18:06.000 --> 00:18:09.400
- So this is basically, I don't say a new basin,

00:18:09.400 --> 00:18:12.099
but it's gonna be a new basin that we collect from

00:18:12.099 --> 00:18:13.220
and actually go to a plant.

00:18:13.220 --> 00:18:15.960
We've been collecting some from that basin.

00:18:16.880 --> 00:18:20.039
If you go up 428 Sherman Drive

00:18:20.039 --> 00:18:22.079
and some of those developments up there,

00:18:22.079 --> 00:18:24.200
those are actually in the Clear Creek basin,

00:18:24.200 --> 00:18:26.720
but we've been serving them through the Pecan Creek

00:18:26.720 --> 00:18:30.079
and pumping them to the Pecan Interceptor

00:18:30.079 --> 00:18:31.920
and sending it south to our Pecan Creek.

00:18:31.920 --> 00:18:35.359
So we'll be able to utilize the Clear Creek Interceptor,

00:18:35.359 --> 00:18:38.680
not just for those north of the Interceptor,

00:18:38.680 --> 00:18:43.579
but also just a little bit south there along Agave Ranch

00:18:43.579 --> 00:18:44.420
and those types.

00:18:44.420 --> 00:18:47.680
We have some plans in place to serve those

00:18:47.680 --> 00:18:49.759
so there's no lift stations.

00:18:49.759 --> 00:18:53.200
And as a system, we wanna get rid of lift stations.

00:18:53.200 --> 00:18:55.200
- Yeah, I think that's really great.

00:18:55.200 --> 00:18:56.839
I know this is a little off topic.

00:18:56.839 --> 00:19:00.119
I was just curious if the other side of Elm Fork,

00:19:00.119 --> 00:19:03.960
I guess you'd probably be able to boost it across Elm Fork

00:19:03.960 --> 00:19:06.200
if needed, kind of lift it over

00:19:06.200 --> 00:19:08.440
as growth happens over there.

00:19:08.440 --> 00:19:09.279
All right, thank you.

00:19:09.279 --> 00:19:10.099
- I have just one.

00:19:10.099 --> 00:19:12.079
Have we worked with Correlo before?

00:19:12.079 --> 00:19:12.920
Or is this?

00:19:12.920 --> 00:19:13.759
- Yes, we have.

00:19:13.759 --> 00:19:14.799
- All right. - Yes.

00:19:14.799 --> 00:19:17.299
We have a couple of projects with them right now.

00:19:21.640 --> 00:19:23.079
- If there are no further questions,

00:19:23.079 --> 00:19:24.480
the Chair would entertain a motion.

00:19:24.480 --> 00:19:25.380
- So moved.

00:19:25.380 --> 00:19:26.400
- We have a motion for approval.

00:19:26.400 --> 00:19:27.599
Do we have a second?

00:19:27.599 --> 00:19:29.279
- Second.

00:19:29.279 --> 00:19:30.420
- Motion and a second.

00:19:30.420 --> 00:19:31.880
All in favor, say aye.

00:19:31.880 --> 00:19:32.880
- Aye.

00:19:32.880 --> 00:19:34.660
- The motion carries unanimously.

00:19:35.559 --> 00:19:38.559
Moving on to items for individual consideration.

00:19:38.559 --> 00:19:41.900
Item C, consider recommending adoption of an ordinance

00:19:41.900 --> 00:19:45.359
with the City of Denton with Rush Truck Centers

00:19:45.359 --> 00:19:48.000
through a buy board cooperative purchase agreement

00:19:49.680 --> 00:19:54.440
for five, for four, sorry,

00:19:54.440 --> 00:19:56.720
for one year with four additional years,

00:19:56.720 --> 00:20:01.720
total of five years for a cost of $14,679,000.

00:20:02.160 --> 00:20:03.400
- Correct, hi, good morning board.

00:20:03.400 --> 00:20:05.400
I'm Nicole Brasher, the administration manager

00:20:05.400 --> 00:20:06.799
for Fleet and Facilities.

00:20:07.680 --> 00:20:09.519
Here today seeking your recommendation

00:20:09.519 --> 00:20:12.440
for the approval of a contract through buy board

00:20:12.440 --> 00:20:16.480
with Rush Truck Center Crane, or Centers of Texas, sorry,

00:20:16.480 --> 00:20:20.640
for the five year not to exceed 14.6 million.

00:20:22.079 --> 00:20:24.559
Okay, the City of Denton Fleet Services purchases

00:20:24.559 --> 00:20:27.440
and repairs and maintains various types

00:20:27.440 --> 00:20:29.960
of heavy duty equipment utilized by departments

00:20:29.960 --> 00:20:32.440
like Solid Waste, Streets, Wastewater.

00:20:32.440 --> 00:20:35.000
They all support city services like street cleaning,

00:20:35.000 --> 00:20:38.240
refuse truck cleanup, or refuse pickups, sorry,

00:20:38.240 --> 00:20:42.480
and debris removal, as well as waterline flushing.

00:20:42.480 --> 00:20:44.960
Repair services provided by this contract ensure

00:20:44.960 --> 00:20:49.119
that the assets requiring specialized diagnostic equipment

00:20:49.119 --> 00:20:51.759
and technical knowledge remain operational.

00:20:51.759 --> 00:20:55.119
All vehicles and equipment additions will be processed

00:20:55.119 --> 00:20:57.279
through the city's annual budget process.

00:20:58.240 --> 00:21:01.240
The city will only pay for services rendered

00:21:01.240 --> 00:21:04.400
and is not obligated to pay the full contract amount

00:21:04.400 --> 00:21:05.240
unless needed.

00:21:07.680 --> 00:21:09.839
The charts highlight the contract's estimated cost

00:21:09.839 --> 00:21:10.319
breakdown

00:21:10.319 --> 00:21:12.920
by fiscal year, projected acquisition schedule

00:21:12.920 --> 00:21:17.440
based on the addition and replacement of assets needed,

00:21:17.440 --> 00:21:19.359
and the utilization rate by fund

00:21:20.460 --> 00:21:23.900
for acquisitions and services, all of which are routed

00:21:23.900 --> 00:21:26.299
through the city's collaborative budget process.

00:21:29.759 --> 00:21:32.000
Staff recommends approval of the one year

00:21:32.000 --> 00:21:33.839
with four additional one year extensions

00:21:33.839 --> 00:21:36.700
in the total five year, not to exceed amount

00:21:36.700 --> 00:21:41.700
of the rest trucks center of Texas for 14,679,000.

00:21:44.480 --> 00:21:45.319
Oops, sorry.

00:21:47.839 --> 00:21:48.900
Any questions?

00:21:50.920 --> 00:21:51.759
- Do we have any questions?

00:21:51.759 --> 00:21:52.579
Mr. Rayner?

00:21:53.880 --> 00:21:56.480
- How many Peterbilt trucks do we have?

00:21:56.480 --> 00:21:58.079
- Roughly 115.

00:21:58.079 --> 00:22:01.619
- So they're primary purchaser, we purchase, no?

00:22:01.619 --> 00:22:02.920
- No, they're just one of the options

00:22:02.920 --> 00:22:05.140
that we can buy the bodies from.

00:22:05.140 --> 00:22:08.519
- And so this particular company,

00:22:08.519 --> 00:22:11.119
their specialty is Peterbilt trucks?

00:22:11.119 --> 00:22:12.599
- Yes, they do more than that.

00:22:12.599 --> 00:22:15.599
- And so do we have others that have specialties

00:22:15.599 --> 00:22:17.920
for whatever the other vehicles are?

00:22:17.920 --> 00:22:20.900
- Correct, so any branded vehicle

00:22:20.900 --> 00:22:24.500
can be specialized diagnostics by that seller,

00:22:24.500 --> 00:22:26.279
essentially the manufacturer.

00:22:27.319 --> 00:22:30.279
- And the purpose to have that specialty on that person

00:22:30.279 --> 00:22:34.319
is better for the city than if we had just a regular,

00:22:34.319 --> 00:22:37.519
pardon the expression, a mechanic that can cover them all.

00:22:37.519 --> 00:22:38.880
- We do that as well, yeah.

00:22:38.880 --> 00:22:39.720
Fleet Services does.

00:22:39.720 --> 00:22:41.220
- So you cover everything, you got all of it?

00:22:41.220 --> 00:22:43.480
- Pretty much, we try to open up our capacity

00:22:43.480 --> 00:22:46.000
and authority for all the options as needed

00:22:46.000 --> 00:22:48.759
to optimize our acquisition process,

00:22:48.759 --> 00:22:52.079
get trucks into service as fast as we can.

00:22:52.079 --> 00:22:55.000
- And have we had a Peterbilt specialist before?

00:22:55.000 --> 00:22:56.480
- Yes, we've used this contract before.

00:22:56.480 --> 00:22:58.720
- And so is this the same company we're renewing on?

00:22:58.720 --> 00:22:59.559
- Correct.

00:22:59.559 --> 00:23:02.000
- Okay, thank you, that helps, appreciate it.

00:23:04.559 --> 00:23:05.700
Any further questions?

00:23:09.920 --> 00:23:11.259
Do we have a motion?

00:23:12.160 --> 00:23:14.680
We have a motion for approval and a second?

00:23:14.680 --> 00:23:16.519
All in favor say aye.

00:23:16.519 --> 00:23:17.880
- Thank you.

00:23:17.880 --> 00:23:19.799
- Motion carries unanimously.

00:23:19.799 --> 00:23:24.160
And now we'll move on to item D, management reports.

00:23:25.160 --> 00:23:26.680
- Mr. Chair, members of the board,

00:23:26.680 --> 00:23:30.119
we do have a follow-up item from Seth Garcia.

00:23:30.119 --> 00:23:33.200
This is a couple of questions that Mr. Rybak had,

00:23:33.200 --> 00:23:35.519
he's not here today, but Seth is here,

00:23:35.519 --> 00:23:36.920
if anyone has any follow-up questions

00:23:36.920 --> 00:23:38.279
on that particular item.

00:23:43.359 --> 00:23:47.160
Okay, and then for future agenda items,

00:23:47.960 --> 00:23:50.119
of course just again, another reminder,

00:23:50.119 --> 00:23:51.319
budget, budget, budget, right?

00:23:51.319 --> 00:23:54.680
That's coming up here pretty quick for you.

00:23:54.680 --> 00:23:57.400
Certainly looking forward to those discussions,

00:23:57.400 --> 00:24:00.839
our budget team will be bringing that forward to you guys.

00:24:00.839 --> 00:24:04.599
And then nothing on the new business action item

00:24:04.599 --> 00:24:07.720
other than the update on the quarterly reports

00:24:07.720 --> 00:24:09.200
that the water department's doing.

00:24:09.200 --> 00:24:11.980
I think the next was scheduled for July 13th.

00:24:12.920 --> 00:24:15.559
And then finally, I did send you guys an email

00:24:15.559 --> 00:24:20.240
with a recap of the den renewable goal.

00:24:20.240 --> 00:24:21.440
Certainly if you have any questions today,

00:24:21.440 --> 00:24:23.420
or if we need to put it on the next agenda

00:24:23.420 --> 00:24:25.960
for further discussion, I'm happy to do that.

00:24:25.960 --> 00:24:27.180
That's all we have.

00:24:30.319 --> 00:24:34.599
- Okay, with that, we stand adjourned.