WEBVTT

00:00:00.000 --> 00:00:07.900
 It is nine o'clock, Monday, March 23rd, and this regular meeting of the Public Utilities

00:00:07.900 --> 00:00:11.000
 Board of the City of Denton is now in session.

00:00:11.000 --> 00:00:14.580
 Do we have any presentations from members of the public?

00:00:14.580 --> 00:00:15.580
 There are none.

00:00:15.580 --> 00:00:16.580
 Moving on to the consent agenda.

00:00:16.580 --> 00:00:19.000
 Would anybody like to pull anything from the consent agenda?

00:00:19.000 --> 00:00:20.000
 No?

00:00:20.000 --> 00:00:24.660
 Then I'll entertain a motion to approve the consent agenda.

00:00:24.660 --> 00:00:26.780
 Is that a motion?

00:00:26.780 --> 00:00:27.780
 Second.

00:00:27.780 --> 00:00:28.780
 And a second.

00:00:28.780 --> 00:00:29.780
 All in favor say aye.

00:00:29.780 --> 00:00:30.780
 Aye.

00:00:30.780 --> 00:00:31.780
 Against?

00:00:31.780 --> 00:00:32.780
 I'm the same.

00:00:32.780 --> 00:00:33.780
 Passes unanimously.

00:00:33.780 --> 00:00:39.400
 Items for individual consideration, consider approval of the March 9th minutes.

00:00:39.400 --> 00:00:40.400
 So moved.

00:00:40.400 --> 00:00:41.400
 So moved.

00:00:41.400 --> 00:00:42.400
 Or second?

00:00:42.400 --> 00:00:43.400
 Not a motion.

00:00:43.400 --> 00:00:44.400
 We got a second.

00:00:44.400 --> 00:00:45.400
 All in favor?

00:00:45.400 --> 00:00:46.400
 Aye.

00:00:46.400 --> 00:00:48.600
 All right.

00:00:48.600 --> 00:00:53.480
 Item B, consider recommending an adoption of an ordinance in the City of Denton to execute

00:00:53.480 --> 00:00:59.640
 a contract with Acceleron US for turbo replacement parts and service for the Denton Energy Center.

00:00:59.640 --> 00:01:08.440
 In the amount of $9,520,000 for one year.

00:01:08.440 --> 00:01:13.880
 Option of four additional years, one extension, a total of five years.

00:01:13.880 --> 00:01:14.880
 Good morning.

00:01:14.880 --> 00:01:15.880
 Excuse me.

00:01:15.880 --> 00:01:19.900
 Good morning, Chair, members of the PUP.

00:01:19.900 --> 00:01:25.800
 My name is Jose Gaitan, Executive Manager of Power Supply for DME.

00:01:25.800 --> 00:01:33.800
 I'm here to present the intricacies of this RFP that is for the turbo replacement parts

00:01:33.800 --> 00:01:38.480
 and services for the turbos at the Denton Energy Center.

00:01:38.480 --> 00:01:44.560
 So the background for this RFP is that the deck has 12 engines with two turbos each for

00:01:44.560 --> 00:01:47.920
 a total of 24 turbos.

00:01:47.920 --> 00:01:53.480
 So peak shaving operations at the Denton Energy Center causes stresses on these turbos.

00:01:53.480 --> 00:01:59.020
 Every cooling and heating cycle stresses the metals by expanding and contracting.

00:01:59.020 --> 00:02:07.640
 That expansion causes stresses on the metal, which can, over time, cause fractures.

00:02:07.640 --> 00:02:16.440
 So it is important that we have proper maintenance for these facilities, and as such, the OEM

00:02:16.440 --> 00:02:27.040
 is giving us a change in the maintenance schedule, which would basically have us look at the turbos

00:02:27.040 --> 00:02:31.840
 a little bit earlier, based on the number of start and stops, as they are seeing some

00:02:31.840 --> 00:02:37.720
 more fatigues out in the field on these turbos.

00:02:37.720 --> 00:02:42.160
 So inspections are critical for these turbos.

00:02:42.160 --> 00:02:50.400
 Again, our current engines have 13,500 hours of operations, and starts are anywhere between

00:02:50.400 --> 00:02:53.960
 3,500 and 4,000 start and stops.

00:02:53.960 --> 00:02:59.920
 It varies by engine, as we kind of vary how many hours of operations start and stop, so

00:02:59.920 --> 00:03:05.560
 we're not overhauling them all at the same time, so we can stagger the maintenance.

00:03:05.560 --> 00:03:13.420
 So based on the new service schedule that is being recommended, it's recommended that

00:03:13.420 --> 00:03:20.320
 you start looking at the turbos at the 16,000 hour mark, which is our normal recommendation

00:03:20.320 --> 00:03:25.700
 when the plant was built, or 2,500 starts.

00:03:25.700 --> 00:03:31.000
 So you can see that we're above that 2,500 start/stops.

00:03:31.000 --> 00:03:37.600
 So the manufacturer issued this bulletin in February of this year, or last year, excuse

00:03:37.600 --> 00:03:45.060
 me, to prevent a catastrophic failure, to catch it before it actually occurs.

00:03:45.060 --> 00:03:53.920
 So some of the maintenance tasks is to dismantle the turbo, check clearances, clean casings,

00:03:53.920 --> 00:04:00.880
 clean nozzles, and then assess the rotator bearing parts, which could fail.

00:04:00.880 --> 00:04:05.720
 And then make sure that the balancing is good for the turbos.

00:04:05.720 --> 00:04:08.920
 So here's some of the estimates.

00:04:08.920 --> 00:04:17.480
 So the average cost should a turbo be damaged, but repairable is 125,000 per turbo.

00:04:17.480 --> 00:04:23.120
 There are 24 of them, so we could have as much as $3 million worth of repairs.

00:04:23.120 --> 00:04:29.800
 However, a complete turbo replacement, average cost is 400,000.

00:04:29.800 --> 00:04:35.080
 So it's important that we get to those turbos serviced then before we reach a catastrophic

00:04:35.080 --> 00:04:38.560
 failure, which is what we're intending to do here.

00:04:38.560 --> 00:04:47.080
 However, as an estimate, we're expecting potentially up to 10 turbos that may need to be replaced

00:04:47.080 --> 00:04:48.840
 for a total of 4 million.

00:04:48.840 --> 00:04:56.040
 Again, that can change if we can get to them before we actually reach a catastrophic failure.

00:04:56.040 --> 00:05:01.720
 And so there in the pictures you see on the left-hand side is the turbine wheel, which

00:05:01.720 --> 00:05:06.720
 is one of the ones that gets the most amount of stress because it is on the exhaust side

00:05:06.720 --> 00:05:15.040
 of the turbo, and it has a more tendency to have stress fractures.

00:05:15.040 --> 00:05:19.000
 So this RFP is for parts and services.

00:05:19.000 --> 00:05:27.480
 Again, the ODM recommends checking the operation profile of the engine to verify if we have

00:05:27.480 --> 00:05:36.200
 reached those recommendations of at least 2,500 start stops or hours of operation.

00:05:36.200 --> 00:05:43.240
 Again, turbo overhauls will be performed by the ODM at their authorized workshop.

00:05:43.240 --> 00:05:50.080
 They will provide the field services on-site and then also provide travel and accommodations

00:05:50.080 --> 00:05:53.360
 for staff that are doing their work.

00:05:53.360 --> 00:06:00.880
 Turbo parts, components, spare parts and normal maintenance intervals, inventory checks, repairs

00:06:00.880 --> 00:06:08.940
 planned and unplanned is an estimated cost of $105,000 per unit for a five-year span

00:06:08.940 --> 00:06:16.360
 on 24 turbos for a total of $2.52 million.

00:06:16.360 --> 00:06:25.120
 So the summary of expenditure again is manufacturer and authorized repairs, restocking of critical

00:06:25.120 --> 00:06:35.440
 components, restocking critical components for unplanned maintenance, 24 turbos on 12

00:06:35.440 --> 00:06:48.240
 parts with an estimated potential complete repair or I guess a totaling of up to 10 turbos

00:06:48.240 --> 00:06:55.160
 during the life of this RFP for a total of $4 million and expected overhaul costs which

00:06:55.160 --> 00:07:00.800
 would capture all of the maintenance costs that would be needed to make sure that we

00:07:00.800 --> 00:07:04.560
 don't have a catastrophic failure for all 24 turbos.

00:07:04.560 --> 00:07:09.120
 That's $3 million, that's just regular preventative maintenance.

00:07:09.120 --> 00:07:22.840
 And then we have critical components for $2.52 million for a total of $9,520,000.

00:07:22.840 --> 00:07:33.520
 Of that, $2.5 million will be cash funded, the rest will be via 10-year bonds.

00:07:33.520 --> 00:07:41.020
 And so again, the recommendation from staff is for PEB to provide the City Council recommendation

00:07:41.020 --> 00:07:48.600
 to approve the RFP to a Celeron USA Incorporated to execute a five-year contract for the turbochargers

00:07:48.600 --> 00:07:52.080
 at the Dension Energy Center.

00:07:52.080 --> 00:07:55.080
 Any questions?

00:07:55.080 --> 00:08:04.280
 Okay, so you see this at about five-year increments?

00:08:04.280 --> 00:08:09.120
 Yes, that's what we're planning on doing this go-around.

00:08:09.120 --> 00:08:15.640
 Again, the DEC was commissioned in 2018 June, so we're starting to approach the 10-year

00:08:15.640 --> 00:08:22.360
 mark so it's, you know, we don't know if we're going to see any more, you know, the

00:08:22.360 --> 00:08:29.640
 preventative maintenance is there to capture any further failures, but they are issuing

00:08:29.640 --> 00:08:35.120
 this bulletin to start the servicing sooner rather than later, which is why we're bringing

00:08:35.120 --> 00:08:41.400
 it now as opposed to at the 16,000 hour mark, which is supposed to be in about another year

00:08:41.400 --> 00:08:42.760
 and a half, two years.

00:08:42.760 --> 00:08:47.260
 So we're coming to prevent a catastrophic failure.

00:08:47.260 --> 00:08:51.100
 So every five years, we're going to start issuing this out again.

00:08:51.100 --> 00:08:55.000
 Was that common for them to come back and say, I mean, you've got, what was it, 3,500

00:08:55.000 --> 00:08:57.960
 to 4,000 hours is what your original S was?

00:08:57.960 --> 00:08:58.960
 Yes.

00:08:58.960 --> 00:09:03.040
 And now they're saying, "Well, they're not as good as we thought they were," or...

00:09:03.040 --> 00:09:07.680
 So those, it is just a recommendation by the ODM based on what they've been seeing out

00:09:07.680 --> 00:09:08.680
 in the field, right?

00:09:08.680 --> 00:09:09.680
 Well, yeah.

00:09:09.680 --> 00:09:14.640
 And so these things can last as much as 30,000 hours, right?

00:09:14.640 --> 00:09:15.640
 So...

00:09:15.640 --> 00:09:16.640
 Well, 16, it leaves, right?

00:09:16.640 --> 00:09:17.640
 Exactly, yes.

00:09:17.640 --> 00:09:22.160
 So it's important that we start the preventative maintenance now to prevent any failures that

00:09:22.160 --> 00:09:25.900
 will lead to a catastrophic failure, which is a higher cost.

00:09:25.900 --> 00:09:34.680
 So the maintenance will hopefully prevent us from having bigger expenditures later.

00:09:34.680 --> 00:09:35.680
 Okay.

00:09:35.680 --> 00:09:38.100
 What was our original budget for that?

00:09:38.100 --> 00:09:43.720
 So the original budget was in the CIP for two years from now.

00:09:43.720 --> 00:09:50.680
 So we're accelerating the maintenance to prevent, again, those catastrophic failures before

00:09:50.680 --> 00:09:51.680
 they occur, right?

00:09:51.680 --> 00:09:52.680
 I understand.

00:09:52.680 --> 00:09:53.680
 So it was part of the CIP budget.

00:09:53.680 --> 00:09:54.680
 And Tony...

00:09:54.680 --> 00:09:58.920
 If you get a flat tire before you've planned on having a flat tire, you replace the flat

00:09:58.920 --> 00:09:59.920
 tire, but...

00:09:59.920 --> 00:10:03.800
 Yeah, I think as Jose mentioned, this bulletin came out and kind of advanced the need for

00:10:03.800 --> 00:10:05.840
 this project.

00:10:05.840 --> 00:10:10.720
 We've budgeted this money now for probably at least five or seven years.

00:10:10.720 --> 00:10:16.120
 We've had it in the CIP, and this is in conjunction with another project that will be coming to

00:10:16.120 --> 00:10:18.120
 you for overhauls.

00:10:18.120 --> 00:10:25.680
 But the total amount that we had was for fiscal year '29-'30, it was about $15 million total.

00:10:25.680 --> 00:10:27.680
 But now we're looking at a little bit more than that.

00:10:27.680 --> 00:10:28.680
 So...

00:10:28.680 --> 00:10:31.800
 But yeah, it's been in the CIP for some time.

00:10:31.800 --> 00:10:32.800
 Yeah.

00:10:32.800 --> 00:10:33.800
 Okay.

00:10:33.800 --> 00:10:34.800
 Thank you.

00:10:34.800 --> 00:10:35.800
 Just...

00:10:35.800 --> 00:10:36.800
 Good morning.

00:10:36.800 --> 00:10:37.800
 Good morning.

00:10:37.800 --> 00:10:47.440
 If I may, Acceleron, is this an extension of a contract we already have with them, or

00:10:47.440 --> 00:10:49.240
 is this a brand new thing?

00:10:49.240 --> 00:10:52.960
 Arthur, do we have a current contract with them?

00:10:52.960 --> 00:10:54.360
 Can you come up here?

00:10:54.360 --> 00:10:59.200
 So this is Arthur Pando, the new plant manager at the DEC.

00:10:59.200 --> 00:11:03.160
 Arthur Pando, plant manager at the DIN Ninja Center.

00:11:03.160 --> 00:11:05.880
 I can help answer any questions you all may have.

00:11:05.880 --> 00:11:15.080
 So Acceleron, do we have an existing contract besides the OME or whoever it was that brought

00:11:15.080 --> 00:11:20.320
 it to our attention, is this a brand new contract with them, or have we used them for this particular

00:11:20.320 --> 00:11:21.320
 need?

00:11:21.320 --> 00:11:22.320
 No, sir.

00:11:22.320 --> 00:11:24.440
 It'll be a brand new contract with them.

00:11:24.440 --> 00:11:25.440
 Okay.

00:11:25.440 --> 00:11:26.440
 Yes.

00:11:26.440 --> 00:11:27.440
 Could I go to...

00:11:27.440 --> 00:11:28.440
 May I?

00:11:28.440 --> 00:11:45.080
 Could you get slide three for me?

00:11:45.080 --> 00:11:47.200
 So what is the...

00:11:47.200 --> 00:11:52.320
 You may have alluded to some of this, but what do we...

00:11:52.320 --> 00:12:00.120
 Theory wise, what are we looking at as far as an expected lifetime of timeframe for these

00:12:00.120 --> 00:12:01.120
 things?

00:12:01.120 --> 00:12:02.120
 Is it by the hour?

00:12:02.120 --> 00:12:04.320
 Is it by the year?

00:12:04.320 --> 00:12:05.320
 It varies.

00:12:05.320 --> 00:12:09.360
 So we like to plan for by the hour, yes.

00:12:09.360 --> 00:12:14.920
 But based on the inspections, it can deem turbochargers to be overhauled sooner.

00:12:14.920 --> 00:12:19.500
 So main priority first is getting them inspected, checking for the damage, what the condition

00:12:19.500 --> 00:12:26.600
 is of the turbos and these rotating components, and thus then determines the life.

00:12:26.600 --> 00:12:33.000
 We've had these now, as Jose mentioned, going on almost nearing 10 years.

00:12:33.000 --> 00:12:39.020
 Original plan was probably making it to the 15, 12 year mark.

00:12:39.020 --> 00:12:41.940
 That's still what we expect.

00:12:41.940 --> 00:12:47.720
 We just need to capture it and make sure we extend the life of.

00:12:47.720 --> 00:12:54.840
 Level wise, they can go as long as up to 60,000 hours based on the service intervals happening

00:12:54.840 --> 00:12:57.400
 and being conducted.

00:12:57.400 --> 00:13:00.880
 Who have we used before this request?

00:13:00.880 --> 00:13:02.360
 Has it been in house?

00:13:02.360 --> 00:13:03.360
 It's all, yes.

00:13:03.360 --> 00:13:09.440
 All the current maintenance inspections and repairs have all been in house by plant personnel.

00:13:09.440 --> 00:13:18.720
 And so we're accelerating preventive maintenance by, forgive me, forget the hours, can we kind

00:13:18.720 --> 00:13:22.880
 of do it with something I would recognize like years?

00:13:22.880 --> 00:13:28.240
 We're accelerating the intervals by about two years.

00:13:28.240 --> 00:13:34.160
 And that's just based on the ODM recommendation that was previously been provided to us.

00:13:34.160 --> 00:13:35.880
 And they got that from what?

00:13:35.880 --> 00:13:42.800
 They got that from their own in-house inspections and then what their field service guys out

00:13:42.800 --> 00:13:45.880
 at other plants are observing.

00:13:45.880 --> 00:13:54.320
 So the contract now, how large it is based on the amount we're having to perform is why

00:13:54.320 --> 00:14:01.160
 we're bringing it to contract, just the manpower we do not have to do all 24 with the staff

00:14:01.160 --> 00:14:02.160
 we have currently.

00:14:02.160 --> 00:14:13.440
 If I may, could you go to slide five?

00:14:13.440 --> 00:14:20.920
 So where's the location of their workshop?

00:14:20.920 --> 00:14:25.140
 They are located in Florida, I believe.

00:14:25.140 --> 00:14:28.080
 They have multiple locations throughout.

00:14:28.080 --> 00:14:34.520
 Some of them are in Europe, and there is a smaller workshop where they perform minor

00:14:34.520 --> 00:14:40.240
 maintenance, just quick overhauls in Houston and Florida.

00:14:40.240 --> 00:14:47.880
 I'm just curious on that 2.5, 2 million, is that, would that be thought of as the extra

00:14:47.880 --> 00:14:54.280
 expense from what we had originally budgeted because of starting early or am I putting

00:14:54.280 --> 00:14:56.280
 that number in the wrong pigeon hole?

00:14:56.280 --> 00:15:00.960
 I'm sorry, repeat that.

00:15:00.960 --> 00:15:04.360
 So you're asking where that number stems from?

00:15:04.360 --> 00:15:12.600
 From our old way of doing our maintenance, is that this 2.5, is that the extra that we

00:15:12.600 --> 00:15:14.680
 were not ready for?

00:15:14.680 --> 00:15:15.680
 No.

00:15:15.680 --> 00:15:22.000
 We've been ready for it, but up to getting into the larger hours, it has all been very

00:15:22.000 --> 00:15:27.320
 small maintenance intervals, so a couple sensors, maybe cleaning some oil pipes, some O rings

00:15:27.320 --> 00:15:29.160
 here and there.

00:15:29.160 --> 00:15:33.760
 When we creep into the higher hours of the intervals, you start getting into the major

00:15:33.760 --> 00:15:39.280
 components, nozzle rings, casings, and bearings.

00:15:39.280 --> 00:15:41.000
 And if I could go page six.

00:15:41.000 --> 00:15:48.320
 And Rob, just so, so we've been budgeting about $15, $17 million at the exact number

00:15:48.320 --> 00:15:54.360
 in these turbos and these overhauls projects, now we're looking closer to $20 million.

00:15:54.360 --> 00:15:59.920
 That's about a $3 to $5 million increase now that we're starting to get these actual proposals

00:15:59.920 --> 00:16:02.880
 and actually firming those numbers up.

00:16:02.880 --> 00:16:09.240
 That $2.5 million, just as a reminder, during Yuri, after Yuri, if you remember, Brazos

00:16:09.240 --> 00:16:13.920
 didn't pay their bill and there was a settlement, that's where that 2.5 million is coming from.

00:16:13.920 --> 00:16:19.360
 We've been holding onto that 2.5 million for these projects and our hope is to continue

00:16:19.360 --> 00:16:26.240
 to add additional cash into that pot and try to minimize how much debt we're issuing for

00:16:26.240 --> 00:16:27.960
 these projects.

00:16:27.960 --> 00:16:31.760
 And then if I may ask, because that leads to my question on the original amount of let's

00:16:31.760 --> 00:16:37.840
 say $15 million or such, what time period was that to cover?

00:16:37.840 --> 00:16:42.120
 That was going to start in fiscal year '20, we were going to plan to issue that beginning

00:16:42.120 --> 00:16:47.080
 in fiscal year '29 and '30, but because of this new bulletin, we've had to accelerate

00:16:47.080 --> 00:16:48.560
 that sooner.

00:16:48.560 --> 00:16:53.800
 But that number was, the thought was a 10-year type of use.

00:16:53.800 --> 00:16:54.800
 Yeah, correct.

00:16:54.800 --> 00:16:57.480
 But now we're seeing that that may be accelerated due to ...

00:16:57.480 --> 00:17:03.660
 Due to wear and tear.

00:17:03.660 --> 00:17:04.660
 Thank you.

00:17:04.660 --> 00:17:05.660
 I needed the right term.

00:17:05.660 --> 00:17:06.660
 I didn't want to be ignorant.

00:17:06.660 --> 00:17:10.480
 I think it's important to understand, right, so the bulletin is based on inspections and

00:17:10.480 --> 00:17:15.200
 experiences that have been seen with these types of engines and other plans, right?

00:17:15.200 --> 00:17:19.520
 They're going to have to come in and look at these specific engines and then give us

00:17:19.520 --> 00:17:24.120
 those recommendations, but we're planning for the worst, right?

00:17:24.120 --> 00:17:29.280
 So then my last question, well, probably not, but I'm going to ask this one.

00:17:29.280 --> 00:17:34.400
 We've had our own self-contained maintenance program on this.

00:17:34.400 --> 00:17:39.920
 We are now coming into a phase where we're asking an outside source to do it and we've

00:17:39.920 --> 00:17:46.320
 possibly shortened the time frame to five years, let's say, versus six or seven years

00:17:46.320 --> 00:17:50.200
 for regular maintenance, and I don't want to hold you to those numbers, but I'm looking

00:17:50.200 --> 00:17:54.840
 at ... We're looking at a five-year increment on all of this, even though we're doing these

00:17:54.840 --> 00:17:59.080
 extensions one year at a time?

00:17:59.080 --> 00:18:01.080
 Correct.

00:18:01.080 --> 00:18:10.320
 The one-year increment is kind of offset, so yes, we will perform the services to get

00:18:10.320 --> 00:18:17.040
 them inspected and such, and then year two, year three is the planned and unplanned maintenance

00:18:17.040 --> 00:18:18.040
 scope of it.

00:18:18.040 --> 00:18:23.960
 So now we're just upkeeping the stuff that we can perform in-house with, and then around

00:18:23.960 --> 00:18:31.080
 year three, yeah, about in three, four is when we would do the second.

00:18:31.080 --> 00:18:34.600
 So then that's why the cost would go up to around 20 million you're talking about.

00:18:34.600 --> 00:18:38.920
 Well, and the turbos aren't going to all be done all at once, right?

00:18:38.920 --> 00:18:43.920
 They're going to be phased in over that period of time, and it may take longer.

00:18:43.920 --> 00:18:47.000
 And that's why it's a five-year type term.

00:18:47.000 --> 00:18:51.120
 And so we're paying that nine million whether they're replacing turbos or not within that

00:18:51.120 --> 00:18:52.480
 period, but they're doing inspections?

00:18:52.480 --> 00:18:53.480
 Is that what we're saying?

00:18:53.480 --> 00:18:54.480
 Sure.

00:18:54.480 --> 00:18:55.480
 No.

00:18:55.480 --> 00:18:58.600
 We won't be paying the nine million whether they do or don't.

00:18:58.600 --> 00:19:00.000
 It's all based on...

00:19:00.000 --> 00:19:01.000
 If it's needed.

00:19:01.000 --> 00:19:02.000
 If it's needed.

00:19:02.000 --> 00:19:03.000
 Correct.

00:19:03.000 --> 00:19:04.960
 Thank you for your information.

00:19:04.960 --> 00:19:10.840
 So basically, this whole budgetary thing is based on, yeah, it hadn't happened yet, but

00:19:10.840 --> 00:19:13.560
 they're telling us to look a little earlier now.

00:19:13.560 --> 00:19:14.560
 Yes, sir.

00:19:14.560 --> 00:19:19.320
 And we'd like to keep replacing motors, of course, or they would.

00:19:19.320 --> 00:19:22.020
 And not all the costs are going to hit all at once.

00:19:22.020 --> 00:19:26.800
 So we've tried to...I've asked Arthur to look at it as crystal ball and tell me, hey, if

00:19:26.800 --> 00:19:31.320
 you can cash flow this, how can you cash flow this over five years so that I'm not issuing

00:19:31.320 --> 00:19:36.300
 everything all at once, and it could potentially give us time to look at revenue funding some

00:19:36.300 --> 00:19:37.300
 of this.

00:19:37.300 --> 00:19:40.920
 You know, not to get ahead of Matt, but there'll be some financial policy recommendations

00:19:40.920 --> 00:19:44.600
 that are going to be coming to you, and we're going to be targeting some amount annually

00:19:44.600 --> 00:19:49.560
 that we're going to cash fund in our CIP, and this is one of the projects that we would

00:19:49.560 --> 00:19:53.720
 look at, cash funding versus debt funding.

00:19:53.720 --> 00:19:56.640
 Yeah, good.

00:19:56.640 --> 00:20:02.480
 Just based on my ignorance of the plant and how it operates, do these motors, are they

00:20:02.480 --> 00:20:04.960
 pretty even in the amount of hours?

00:20:04.960 --> 00:20:07.920
 I mean, they all run at the same time, right?

00:20:07.920 --> 00:20:08.920
 Correct.

00:20:08.920 --> 00:20:11.040
 You start one, you start them all.

00:20:11.040 --> 00:20:14.880
 In terms of dispatch, they are dispatched by aggregate.

00:20:14.880 --> 00:20:19.720
 So we could start, and each aggregate consists of three units per aggregate.

00:20:19.720 --> 00:20:24.080
 So aggregate A is one, two, three, B is four, five, six, so on and so on.

00:20:24.080 --> 00:20:27.480
 So there is times that, yes, that we could be called upon and say, hey, start aggregates

00:20:27.480 --> 00:20:32.840
 only, A and B is one through six, seven through 12 will stay down.

00:20:32.840 --> 00:20:34.280
 You just roll them?

00:20:34.280 --> 00:20:35.280
 Yes.

00:20:35.280 --> 00:20:37.480
 Yeah, we try and keep them.

00:20:37.480 --> 00:20:42.080
 So you don't, one is not start every time, it may be six that starts again.

00:20:42.080 --> 00:20:43.080
 Correct.

00:20:43.080 --> 00:20:44.080
 Okay.

00:20:44.080 --> 00:20:49.440
 So the EMO tries to start up one aggregate, see if the price holds.

00:20:49.440 --> 00:20:54.080
 If the price holds, then we bring up the next one, and then we just keep adding them in

00:20:54.080 --> 00:20:57.520
 until we make sure that the price is going to hold.

00:20:57.520 --> 00:21:05.160
 That way we avoid a start and stop unneeded and avoids this type of premature wear and

00:21:05.160 --> 00:21:06.520
 tear type of thing.

00:21:06.520 --> 00:21:10.560
 So we do try to vary the hours by aggregate.

00:21:10.560 --> 00:21:11.560
 Okay.

00:21:11.560 --> 00:21:12.560
 Got it.

00:21:12.560 --> 00:21:16.080
 I just have a question more on the 10-year bond of this.

00:21:16.080 --> 00:21:21.480
 So we're financing 10 years worth, or we're financing five years of service over 10 years.

00:21:21.480 --> 00:21:22.600
 What happens after the five years?

00:21:22.600 --> 00:21:25.640
 Do we take out another bond for another five years?

00:21:25.640 --> 00:21:31.440
 Well, I think ideally, one, so anything that is maintenance related, and that's what he's

00:21:31.440 --> 00:21:32.840
 identified here, right?

00:21:32.840 --> 00:21:37.280
 So we're targeting that two and a half million for critical components of normal maintenance

00:21:37.280 --> 00:21:43.040
 to be the cash funding component, then we're only funding the major capital assets with

00:21:43.040 --> 00:21:44.040
 10-year bonds.

00:21:44.040 --> 00:21:48.920
 Now, the idea would be is that, you know, that you do this five years, it doesn't come

00:21:48.920 --> 00:21:52.080
 around in another five, maybe 10 years, right?

00:21:52.080 --> 00:21:53.780
 So you're staggering.

00:21:53.780 --> 00:21:55.080
 So why 10 years, right?

00:21:55.080 --> 00:22:01.120
 10 years, what we're trying to do, at least this is kind of the intent, is we issued bonds

00:22:01.120 --> 00:22:04.360
 for the DEC in 2017, right?

00:22:04.360 --> 00:22:06.040
 Those were 20-year bonds.

00:22:06.040 --> 00:22:13.480
 They pay off in 2037 by limiting the life of the new bonds that we issue, we're trying

00:22:13.480 --> 00:22:20.000
 not to expand the outstanding debt for the DEC beyond 2037, right?

00:22:20.000 --> 00:22:21.360
 That's kind of the intent.

00:22:21.360 --> 00:22:26.480
 So if we had to come back here again in five years, we'd likely be looking at five-year

00:22:26.480 --> 00:22:29.040
 debt, not 10-year debt, if that was even possible.

00:22:29.040 --> 00:22:34.520
 But I think given some of the financial strategies, what we're actually talking about, at least

00:22:34.520 --> 00:22:41.840
 internally at DME, is, hey, can we build some type of cash fund that's just for capital

00:22:41.840 --> 00:22:44.280
 and minimize how much debt we're issuing for the DEC?

00:22:44.280 --> 00:22:45.280
 Yes.

00:22:45.280 --> 00:22:48.680
 I mean, and that's fundamentally what I'm thinking, is I don't want to pay 10 years

00:22:48.680 --> 00:22:51.920
 for something that I've got five years of life out of.

00:22:51.920 --> 00:22:55.640
 It just doesn't make sense that way for us, for taxpayers to continually pay interest

00:22:55.640 --> 00:22:59.360
 on a bond for an asset that's fully depreciated and no longer in use.

00:22:59.360 --> 00:23:06.720
 Now, we're talking about components of the DEC, in total, the plan has more of a 30-to-50-year

00:23:06.720 --> 00:23:07.720
 life on it, right?

00:23:07.720 --> 00:23:13.320
 And so the reason we do these things is to continue to expand the life of the overall

00:23:13.320 --> 00:23:14.320
 facility.

00:23:14.320 --> 00:23:18.960
 So we don't anticipate another five years financing another X million dollars for 10

00:23:18.960 --> 00:23:19.960
 more years?

00:23:19.960 --> 00:23:20.960
 No, probably not.

00:23:20.960 --> 00:23:23.560
 I mean, I'd have to go back and look at our CFP where we program it, but that's probably

00:23:23.560 --> 00:23:25.520
 outside of that next 10-year window.

00:23:25.520 --> 00:23:26.520
 Okay.

00:23:26.520 --> 00:23:27.520
 Thank you.

00:23:27.520 --> 00:23:30.160
 I do have one question.

00:23:30.160 --> 00:23:35.960
 The original recommendation was 16,000 hours and 2,500 cycles.

00:23:35.960 --> 00:23:43.920
 We're only at 13,000 hours and 3,500 cycles, our cycles are way up.

00:23:43.920 --> 00:23:50.040
 Now that we have this experience, moving forward, do we have strategies to try to limit all

00:23:50.040 --> 00:23:51.040
 that uptime down time?

00:23:51.040 --> 00:23:56.080
 I guess that's when the components are that susceptible, right?

00:23:56.080 --> 00:24:00.200
 Getting hot, cooling off and things like that, or is it just is what it is and that's the

00:24:00.200 --> 00:24:01.200
 way it's going to be?

00:24:01.200 --> 00:24:06.160
 I mean, Arthur's job out in the plant and the guy's plant is to be ready to go whenever

00:24:06.160 --> 00:24:07.160
 we need them, right?

00:24:07.160 --> 00:24:10.560
 So whenever we get that price single, it needs to be ready to go, right?

00:24:10.560 --> 00:24:14.000
 And so we put a lot of pressure, unfortunately, on those guys out there.

00:24:14.000 --> 00:24:24.400
 But yeah, so the goal is to try to have this facility ready to go at a moment's notice.

00:24:24.400 --> 00:24:29.680
 And so following those bulletins, if they've changed, it's part of that strategy, right?

00:24:29.680 --> 00:24:33.200
 And so we were based on hours.

00:24:33.200 --> 00:24:39.160
 Now there's these hours and this 2,500 measure that it was before, 3,500.

00:24:39.160 --> 00:24:46.980
 And so now of the two, which one's going to have this plan ready to go sooner?

00:24:46.980 --> 00:24:50.320
 One more question, if I may.

00:24:50.320 --> 00:24:54.000
 So was the Acceleron, was that the lowest bidder?

00:24:54.000 --> 00:24:56.880
 Or do we use the bidding process for something like this?

00:24:56.880 --> 00:24:58.840
 Yes, we did use the bidding process.

00:24:58.840 --> 00:25:00.800
 They were the lowest.

00:25:00.800 --> 00:25:02.760
 How many bids did we ask?

00:25:02.760 --> 00:25:05.840
 I believe we had three come in.

00:25:05.840 --> 00:25:12.840
 Was it two?

00:25:12.840 --> 00:25:16.480
 Uh-oh.

00:25:16.480 --> 00:25:18.000
 Lori Hill, Purchasing Manager.

00:25:18.000 --> 00:25:20.040
 They evaluated two vendors for this.

00:25:20.040 --> 00:25:22.080
 Familiar with both of them?

00:25:22.080 --> 00:25:23.080
 Yes.

00:25:23.080 --> 00:25:24.080
 Yes, they were.

00:25:24.080 --> 00:25:27.240
 And this was the only vendor that actually bid all lines and could provide all products.

00:25:27.240 --> 00:25:28.240
 Thank you.

00:25:28.240 --> 00:25:29.240
 That's what I was going to say.

00:25:29.240 --> 00:25:32.240
 When I looked at the evaluation, the other one didn't really fill it out.

00:25:32.240 --> 00:25:33.240
 Thank you, Mr. Chair.

00:25:33.240 --> 00:25:34.240
 Any other comments?

00:25:34.240 --> 00:25:35.240
 Do you want to undertake a motion?

00:25:35.240 --> 00:25:36.240
 We have a motion and a second.

00:25:36.240 --> 00:25:37.240
 All in favor?

00:25:37.240 --> 00:25:38.240
 Aye.

00:25:38.240 --> 00:25:39.240
 Any opposed?

00:25:39.240 --> 00:25:53.680
 Passes.

00:25:53.680 --> 00:25:58.840
 With that, we'll move on to Item C, Tony, Management Reports.

00:25:58.840 --> 00:25:59.840
 Yes, sir, Mr. Chair.

00:25:59.840 --> 00:26:03.760
 I'm a member of the PB, so I don't have a lot for you.

00:26:03.760 --> 00:26:06.400
 No changes to the future agenda items.

00:26:06.400 --> 00:26:09.920
 Obviously, I'm going to keep just talking about reminding you about budget items.

00:26:09.920 --> 00:26:11.400
 Budget items are those that are going to be coming to you.

00:26:11.400 --> 00:26:16.480
 Make sure you make note of those specific dates.

00:26:16.480 --> 00:26:23.720
 And then for new business action items, you know, we hope to provide the right information

00:26:23.720 --> 00:26:26.400
 that was requested at your next meeting in April.

00:26:26.400 --> 00:26:31.560
 I think given the fact that we had our Chair and Vice Chair out today, that probably makes

00:26:31.560 --> 00:26:32.560
 sense for that.

00:26:32.560 --> 00:26:36.040
 So it was not planned that way, but certainly worked out that way.

00:26:36.040 --> 00:26:41.840
 And the Water Wastewater Department on April 13th will also be bringing to you a work session

00:26:41.840 --> 00:26:42.840
 item.

00:26:42.840 --> 00:26:48.640
 And the only thing that I'll mention as well, DME is also looking at maybe adding some type

00:26:48.640 --> 00:26:53.160
 of quarterly type of update for you as well, kind of the way that the Water Wastewater

00:26:53.160 --> 00:26:54.160
 has done this.

00:26:54.160 --> 00:26:58.120
 We're still kind of working through that internally, but my hope is that by the next meeting, we'll

00:26:58.120 --> 00:27:03.680
 add that to your calendar as well and just, you know, bring you information on items that

00:27:03.680 --> 00:27:04.680
 may be of interest.

00:27:04.680 --> 00:27:10.480
 So if you have thoughts on things that you want to know about within DME or even Solid

00:27:10.480 --> 00:27:12.040
 Waste, please let us know.

00:27:12.040 --> 00:27:14.640
 We can try to get those items scheduled.

00:27:14.640 --> 00:27:15.640
 Fantastic.

00:27:15.640 --> 00:27:17.840
 Appreciate your help on that.

00:27:17.840 --> 00:27:20.440
 I know that getting those updates is going to be important.

00:27:20.440 --> 00:27:23.480
 I think we've all been looking forward to it.

00:27:23.480 --> 00:27:26.760
 And with that, we're adjourned.

00:27:26.760 --> 00:27:30.740
 So it shall be.

00:27:30.740 --> 00:27:32.280
 We are adjourned.