WEBVTT

00:00:00.000 --> 00:00:02.760
 - Good evening.

00:00:02.760 --> 00:00:05.480
 Welcome to the Planning and Zoning Commission meeting.

00:00:05.480 --> 00:00:08.260
 It is 5.02 and I call the meeting to order.

00:00:08.260 --> 00:00:09.320
 My name is Tina Fergens

00:00:09.320 --> 00:00:12.040
 and I'm the Deputy Director of Development Services.

00:00:12.040 --> 00:00:14.200
 In light of Chair Pruitt and Vice Chair Pedrone

00:00:14.200 --> 00:00:15.400
 being absent this evening,

00:00:15.400 --> 00:00:16.880
 hence why I'm calling the meeting to order.

00:00:16.880 --> 00:00:18.880
 Our first item of business,

00:00:18.880 --> 00:00:20.640
 I should note that we do have a quorum present,

00:00:20.640 --> 00:00:22.320
 so thank you for that.

00:00:22.320 --> 00:00:24.000
 I should note our first item of business

00:00:24.000 --> 00:00:25.360
 for the work session agenda

00:00:25.360 --> 00:00:28.240
 is under item for individual consideration.

00:00:28.240 --> 00:00:32.280
 Item A, PZ25-132, elect an acting chair

00:00:32.280 --> 00:00:35.360
 for the Planning and Zoning Commission's June 11th meeting.

00:00:35.360 --> 00:00:38.720
 So the person that will serve as the acting chair

00:00:38.720 --> 00:00:40.920
 for this meeting will serve for both work session

00:00:40.920 --> 00:00:42.320
 and the regular meeting.

00:00:42.320 --> 00:00:45.980
 So if there is a motion to nominate a commissioner

00:00:45.980 --> 00:00:48.160
 from those that are present to serve as that acting chair,

00:00:48.160 --> 00:00:49.760
 we'll receive that motion please.

00:00:49.760 --> 00:00:55.860
 Oh, I'm sorry, Commissioner McDuff.

00:00:55.860 --> 00:00:56.700
 - Yes, thank you.

00:00:56.700 --> 00:00:58.760
 - To nominate Commissioner Riggs.

00:00:58.760 --> 00:01:01.420
 - I will second that.

00:01:01.420 --> 00:01:04.680
 - I'll second.

00:01:04.680 --> 00:01:06.440
 - Thank you, Commissioner Dyer as well.

00:01:06.440 --> 00:01:09.760
 So with a motion and a second to nominate Commissioner Riggs

00:01:09.760 --> 00:01:11.880
 to serve as the acting chair, I will take a vote.

00:01:11.880 --> 00:01:13.560
 All in favor, aye.

00:01:13.560 --> 00:01:14.480
 - Aye.

00:01:14.480 --> 00:01:15.320
 - All opposed?

00:01:15.320 --> 00:01:19.000
 (all laughing)

00:01:19.000 --> 00:01:22.080
 Apparently you don't have a choice, so.

00:01:22.080 --> 00:01:22.920
 Well, thank you.

00:01:22.920 --> 00:01:24.240
 So if you wouldn't mind grabbing your name tag

00:01:24.240 --> 00:01:26.680
 and come have a seat next to me, I would appreciate it.

00:01:27.700 --> 00:01:30.200
 a little bit. - I love my partner.

00:01:30.200 --> 00:01:33.200
 - Don't stand there. (laughing)

00:01:33.200 --> 00:01:49.640
 - So we are here for Susan Cometon,

00:01:49.640 --> 00:01:52.060
 consent to the agenda items.

00:01:56.700 --> 00:01:59.580
 So moving on to number two, citizen comments

00:01:59.580 --> 00:02:01.140
 on consent agenda items.

00:02:01.140 --> 00:02:02.740
 Do we have any citizen comments?

00:02:02.740 --> 00:02:07.300
 Okay.

00:02:07.300 --> 00:02:09.940
 Moving on to item three, clarification of agenda items

00:02:09.940 --> 00:02:11.860
 listed on the agenda for this meeting.

00:02:11.860 --> 00:02:23.580
 Okay.

00:02:23.580 --> 00:02:26.840
 So then moving on, we're gonna do consider approval

00:02:26.840 --> 00:02:29.780
 of the Planning and Zoning Commission minutes.

00:02:29.780 --> 00:02:31.620
 There any comments on that?

00:02:31.620 --> 00:02:37.020
 - Any comment, please?

00:02:37.020 --> 00:02:40.860
 Been reading minutes this week,

00:02:40.860 --> 00:02:44.600
 so I was attuned to just a couple things.

00:02:44.600 --> 00:02:49.540
 I don't see a page number, but just some suggestions.

00:02:49.540 --> 00:02:54.540
 And on page one, following discussion,

00:02:54.540 --> 00:02:57.900
 the commission's consensus.

00:02:57.900 --> 00:03:01.380
 I think commissions is missing an apostrophe,

00:03:01.380 --> 00:03:04.880
 and the consensus was as follows.

00:03:04.880 --> 00:03:06.700
 Again, just editorial things.

00:03:06.700 --> 00:03:11.700
 On the second page, I might suggest,

00:03:11.700 --> 00:03:17.900
 we shared items on our Southeast Denton overlay district plan.

00:03:19.740 --> 00:03:22.620
 And we gave input, we offered some suggestions,

00:03:22.620 --> 00:03:26.540
 I might put, of other topics.

00:03:26.540 --> 00:03:30.260
 We talked about other topics such as health and safety.

00:03:30.260 --> 00:03:31.920
 We did talk about that.

00:03:31.920 --> 00:03:36.920
 Eric Chair Pruitt did talk about several things.

00:03:36.920 --> 00:03:40.260
 I'm just not remembering, but I do appreciate that.

00:03:40.260 --> 00:03:43.700
 Encouraged continued public engagement.

00:03:43.700 --> 00:03:46.760
 We did talk about that at length, I think.

00:03:46.760 --> 00:03:49.560
 But we did say health and safety on that.

00:03:49.560 --> 00:03:53.820
 And those would be my suggestions.

00:03:53.820 --> 00:04:00.340
 - So if there's a motion to that effect

00:04:00.340 --> 00:04:04.700
 to make those changes, what I would ask is that maybe allow,

00:04:04.700 --> 00:04:06.760
 actually, I'm thinking out loud.

00:04:06.760 --> 00:04:09.620
 Let us go ahead and work on those further

00:04:09.620 --> 00:04:11.920
 and bring those back to you at the next meeting

00:04:11.920 --> 00:04:13.460
 so that we can update the minutes

00:04:13.460 --> 00:04:14.960
 to include that information.

00:04:14.960 --> 00:04:18.020
 And then we'll have you take action on the minutes

00:04:18.020 --> 00:04:19.380
 at your subsequent meeting

00:04:19.380 --> 00:04:21.300
 so we can get those corrections noted.

00:04:21.300 --> 00:04:26.620
 - Sounds good.

00:04:26.620 --> 00:04:28.940
 Then.

00:04:28.940 --> 00:04:40.020
 Okay, so moving on to the consent agenda.

00:04:40.020 --> 00:04:43.380
 So we have, let's see, one, two, three, four.

00:04:44.660 --> 00:04:45.940
 Five, six, we have six items.

00:04:45.940 --> 00:04:48.500
 Are there any questions on the consent agenda items?

00:04:48.500 --> 00:04:59.500
 Okay, hearing none.

00:04:59.500 --> 00:05:05.140
 Okay.

00:05:05.140 --> 00:05:09.180
 - I submitted some questions on DPP25-0002A.

00:05:13.900 --> 00:05:17.260
 - Was staff gonna talk about those now

00:05:17.260 --> 00:05:19.020
 or are we waiting on that?

00:05:19.020 --> 00:05:20.460
 - We can address those now if you would like.

00:05:20.460 --> 00:05:22.580
 I didn't know if you wanted to frame up your questions

00:05:22.580 --> 00:05:24.780
 and then, and I think Ashley's prepared

00:05:24.780 --> 00:05:25.860
 to be able to address them.

00:05:25.860 --> 00:05:28.860
 - I mean, I'm okay, are we gonna talk about each one

00:05:28.860 --> 00:05:30.640
 and then they can talk about it then?

00:05:30.640 --> 00:05:31.480
 'Cause I'm okay with that.

00:05:31.480 --> 00:05:33.540
 It's gonna be right this second.

00:05:33.540 --> 00:05:35.280
 - So what we can do, if there are no questions

00:05:35.280 --> 00:05:37.380
 on any of the other items on the consent agenda,

00:05:37.380 --> 00:05:39.060
 then we can go ahead and entertain your questions

00:05:39.060 --> 00:05:40.340
 on that particular item D

00:05:40.340 --> 00:05:42.140
 because it is on the consent agenda

00:05:42.140 --> 00:05:44.060
 and Ashley's prepared to be able to address

00:05:44.060 --> 00:05:45.380
 the questions that you had.

00:05:45.380 --> 00:05:46.220
 - Okay, thanks.

00:05:46.220 --> 00:05:47.700
 - You're welcome.

00:05:47.700 --> 00:05:49.680
 Ashley, if you wanna summarize the questions

00:05:49.680 --> 00:05:51.800
 that Commissioner Dyer had provided.

00:05:51.800 --> 00:05:55.180
 - Good evening, Ashley Exit, Associate Planner.

00:05:55.180 --> 00:06:02.620
 So these questions were over PP25-2,

00:06:02.620 --> 00:06:05.700
 which is Churchill East, which is in a mud.

00:06:05.700 --> 00:06:07.220
 To summarize the questions that I did,

00:06:07.220 --> 00:06:09.540
 bring some visuals also.

00:06:09.540 --> 00:06:10.780
 I know one of your questions

00:06:10.780 --> 00:06:14.260
 was whether TCCI Churchill owns this other portion

00:06:14.260 --> 00:06:15.860
 to the West and they do.

00:06:15.860 --> 00:06:17.940
 That will be called Churchill West.

00:06:17.940 --> 00:06:19.300
 So that will also be developed,

00:06:19.300 --> 00:06:20.980
 that will actually be developed first

00:06:20.980 --> 00:06:23.400
 and then they will develop this portion here,

00:06:23.400 --> 00:06:26.940
 which is this plat, which is in the city of Denton's ETJ

00:06:26.940 --> 00:06:29.000
 and this is in Ponder's ETJ.

00:06:29.000 --> 00:06:30.380
 So we won't be platting this

00:06:30.380 --> 00:06:33.380
 and this is not part of the development agreement.

00:06:33.380 --> 00:06:34.780
 And I know your other questions

00:06:34.780 --> 00:06:38.540
 were this proximity to the loop.

00:06:38.540 --> 00:06:41.200
 And let me make this bigger.

00:06:41.200 --> 00:06:43.080
 I've tried to measure it here.

00:06:43.080 --> 00:06:45.460
 So this is the subject property

00:06:45.460 --> 00:06:49.600
 and then this black dotted line will be the future loop.

00:06:49.600 --> 00:06:51.540
 So it's approximately three miles

00:06:51.540 --> 00:06:54.740
 to the loop from this property.

00:06:54.740 --> 00:06:59.320
 And then 2449 is here to the South.

00:06:59.320 --> 00:07:03.980
 And then this portion of 2449, that is in Ponder's ETJ,

00:07:03.980 --> 00:07:06.220
 so that will be shown on the Ponder plat

00:07:06.220 --> 00:07:08.060
 and it will be through them.

00:07:08.060 --> 00:07:09.580
 - 'Cause that's Florence Road, correct?

00:07:09.580 --> 00:07:12.020
 - Yes, so it's Florence to the South

00:07:12.020 --> 00:07:13.660
 and that will continue as Florence

00:07:13.660 --> 00:07:16.980
 as it goes to the North through this development.

00:07:16.980 --> 00:07:20.640
 - So, 'cause just looking at the property

00:07:20.640 --> 00:07:23.580
 when I was looking at all the information

00:07:23.580 --> 00:07:28.500
 is it looks very landlocked, like it's not near a road,

00:07:28.500 --> 00:07:30.860
 but then when you start looking at the plat,

00:07:30.860 --> 00:07:34.140
 you can see that like Churchill's supposed to be there

00:07:34.140 --> 00:07:35.800
 and I don't know if that's the one

00:07:35.800 --> 00:07:38.260
 that's going straight out to 156.

00:07:38.260 --> 00:07:40.560
 But then I saw that some of them butted up again,

00:07:40.560 --> 00:07:44.180
 some of those lots are gonna butt up against Florence.

00:07:44.180 --> 00:07:46.520
 And I didn't know like,

00:07:46.520 --> 00:07:50.000
 it was hard to tell on the map

00:07:50.000 --> 00:07:54.140
 on both that East West Road

00:07:54.140 --> 00:07:58.140
 that goes from the property out to 156.

00:07:58.140 --> 00:08:01.220
 Right now, it looks like it might be a dirt road

00:08:01.220 --> 00:08:05.260
 or a very narrow, if it is asphalt or concrete,

00:08:05.260 --> 00:08:06.740
 it's very narrow.

00:08:06.740 --> 00:08:08.520
 So that's why I was just kind of curious

00:08:08.520 --> 00:08:12.460
 because I wasn't sure how many houses are gonna be in there,

00:08:12.460 --> 00:08:15.060
 but knowing that the property to the West

00:08:15.060 --> 00:08:17.500
 was also part of this development.

00:08:17.500 --> 00:08:19.540
 That's a lot of homes.

00:08:19.540 --> 00:08:23.660
 And we're all talking about the lack of infrastructure

00:08:23.660 --> 00:08:27.060
 for these developments and what it does for the traffic

00:08:27.060 --> 00:08:30.140
 and getting people to and from places

00:08:30.140 --> 00:08:33.380
 and fire and rescue and just all that sorts of stuff.

00:08:33.380 --> 00:08:37.540
 So do you know anything about like the roads?

00:08:37.540 --> 00:08:41.140
 - Yeah, so their TIA is under review now,

00:08:41.140 --> 00:08:42.860
 so it's not approved yet.

00:08:42.860 --> 00:08:47.860
 But in that TIA, they do discuss reconfiguring certain roads,

00:08:47.860 --> 00:08:51.340
 constructing turn lanes at certain roads,

00:08:51.340 --> 00:08:53.060
 installing traffic signals eventually,

00:08:53.060 --> 00:08:55.700
 and also tech stop maybe making improvements out here.

00:08:55.700 --> 00:08:57.020
 The TIA is still under review,

00:08:57.020 --> 00:08:59.100
 so those aren't final recommendations yet.

00:08:59.100 --> 00:09:00.740
 But once those recommendations are final,

00:09:00.740 --> 00:09:02.060
 they will be shown in the civil

00:09:02.060 --> 00:09:03.900
 and that will be approved before the final plaque

00:09:03.900 --> 00:09:05.680
 comes before this body.

00:09:05.680 --> 00:09:08.900
 - Do you know when the Denton side of this development

00:09:08.900 --> 00:09:10.400
 is supposed to get started?

00:09:10.400 --> 00:09:13.980
 I mean, I know you said the Ponder side's happening first,

00:09:13.980 --> 00:09:16.780
 but have they given you a timeline on the Denton side?

00:09:16.780 --> 00:09:19.220
 - It's a 10 to 12 year build out time.

00:09:19.220 --> 00:09:20.060
 - Okay.

00:09:20.060 --> 00:09:29.420
 - Okay, any other questions?

00:09:31.700 --> 00:09:32.540
 - All right, thank you.

00:09:32.540 --> 00:09:33.600
 - Thank you.

00:10:01.860 --> 00:10:04.780
 (faintly speaking)

00:10:04.780 --> 00:10:07.940
 - Okay, I'm getting coached over here, so.

00:10:07.940 --> 00:10:10.260
 Okay, so we're gonna move on

00:10:10.260 --> 00:10:12.380
 and the staff's gonna basically brief us

00:10:12.380 --> 00:10:14.060
 on the different public hearings.

00:10:14.060 --> 00:10:18.620
 And MPA 24-003 has been withdrawn

00:10:18.620 --> 00:10:20.580
 and it'll be brought to us at a future date.

00:10:20.580 --> 00:10:24.280
 So we'll move on to PDA 25-003.

00:10:30.260 --> 00:10:32.760
 - Okay, all right, thank you, Mia.

00:10:32.760 --> 00:10:36.780
 - Good evening.

00:10:36.780 --> 00:10:41.680
 Members of the commission, Mia Hines, senior planner.

00:10:41.680 --> 00:10:43.340
 This item is a plan development amendment

00:10:43.340 --> 00:10:45.280
 to establish some special sign standards

00:10:45.280 --> 00:10:48.140
 within our four-way development located

00:10:48.140 --> 00:10:52.300
 at the southeast corner of Vintage Boulevard and I-35W.

00:10:52.300 --> 00:10:55.540
 The proposed site, site plan for the site

00:10:55.540 --> 00:10:59.860
 and this travel center was approved in 2024.

00:10:59.860 --> 00:11:02.580
 And now they are coming back to do

00:11:02.580 --> 00:11:05.140
 or establish some special sign standards

00:11:05.140 --> 00:11:09.100
 as one of the signs that they are proposing

00:11:09.100 --> 00:11:10.220
 does not meet the code of ordinance

00:11:10.220 --> 00:11:13.660
 and they are proposing to add some limitations

00:11:13.660 --> 00:11:17.980
 that are not, or would otherwise be,

00:11:17.980 --> 00:11:19.580
 for some things that would otherwise be permitted

00:11:19.580 --> 00:11:20.940
 within the didn't sign code.

00:11:20.940 --> 00:11:23.760
 And so staff is recommending approval

00:11:23.760 --> 00:11:27.540
 as the request does meet all the criteria for approval.

00:11:27.540 --> 00:11:30.380
 And I do have a lengthier presentation

00:11:30.380 --> 00:11:31.360
 for the regular session,

00:11:31.360 --> 00:11:33.300
 but I'd be happy to provide any answers

00:11:33.300 --> 00:11:35.500
 to any questions that you have at this time.

00:11:35.500 --> 00:11:39.660
 - Are there any questions?

00:11:39.660 --> 00:11:44.100
 All right, thanks, Mia.

00:11:44.100 --> 00:11:46.260
 - Sorry, I do have one on this.

00:11:46.260 --> 00:11:51.860
 Mia, good work on everything, by the way.

00:11:51.860 --> 00:11:56.420
 Just a question on the public outreach here.

00:11:56.420 --> 00:11:57.340
 - Yes, ma'am.

00:11:57.340 --> 00:12:02.220
 - It seemed to me that all of the public outreaches

00:12:02.220 --> 00:12:05.560
 were done around Memorial Day holiday.

00:12:05.560 --> 00:12:12.340
 How long are we required to do,

00:12:12.340 --> 00:12:14.700
 do we have to do a public outreach?

00:12:14.700 --> 00:12:17.220
 - I believe it's 14 business days

00:12:17.220 --> 00:12:21.040
 for us to publish in the newspaper and post it.

00:12:21.040 --> 00:12:24.620
 That's pretty the pretty standard practice that we have.

00:12:24.620 --> 00:12:28.020
 - Yes, I just did as a comment, a shared comment.

00:12:28.020 --> 00:12:30.820
 I thought that was pretty close to the Memorial Day holiday.

00:12:30.820 --> 00:12:34.900
 And I don't know if folks would be as aware

00:12:34.900 --> 00:12:38.780
 if there were no holiday around.

00:12:38.780 --> 00:12:41.980
 - If I could see clarification,

00:12:41.980 --> 00:12:44.700
 is your concern regarding when the applicant

00:12:44.700 --> 00:12:47.420
 was working to host their public engagement

00:12:47.420 --> 00:12:49.420
 or is your concern regarding

00:12:49.420 --> 00:12:53.580
 when we sent out the various mail notices?

00:12:53.580 --> 00:12:56.740
 - Well, I'm looking under public outreach

00:12:56.740 --> 00:12:58.420
 on the agenda information sheet.

00:12:58.420 --> 00:13:00.500
 And it just, that's my concern

00:13:00.500 --> 00:13:02.140
 when I'm reading this where my note is.

00:13:02.140 --> 00:13:05.620
 - And those dates are related to the public notices

00:13:05.620 --> 00:13:08.220
 that we send out, Tina, to answer your question.

00:13:08.220 --> 00:13:09.420
 - Thank you.

00:13:09.420 --> 00:13:12.100
 It seems they were awful close to Memorial Day

00:13:12.100 --> 00:13:15.140
 when folks aren't maybe necessarily

00:13:15.140 --> 00:13:16.900
 thinking about those things.

00:13:16.900 --> 00:13:20.340
 - And I can understand your concern on that.

00:13:20.340 --> 00:13:22.980
 We actually, our notices go out slightly earlier

00:13:22.980 --> 00:13:26.420
 than what is even provided for by state statute.

00:13:26.420 --> 00:13:28.300
 Did the applicant do any public engagement?

00:13:28.300 --> 00:13:30.900
 Because I know that sometimes we do that direct outreach

00:13:30.900 --> 00:13:32.420
 or that they do that direct outreach.

00:13:32.420 --> 00:13:35.460
 - They did not, that I'm aware of for this site.

00:13:35.460 --> 00:13:37.540
 It's either undeveloped or undeveloping

00:13:37.540 --> 00:13:39.020
 in close proximity around them.

00:13:39.020 --> 00:13:41.380
 So there wasn't, they didn't reach out

00:13:41.380 --> 00:13:43.900
 to a lot of people in my opinion.

00:13:43.900 --> 00:13:45.940
 - Okay, so they will, Commissioner MacDuff,

00:13:45.940 --> 00:13:47.660
 they do receive a letter from us

00:13:47.660 --> 00:13:49.740
 that is sent directly to the property owners

00:13:49.740 --> 00:13:51.100
 within 200 feet.

00:13:51.100 --> 00:13:54.260
 There is also a postcard that we send out to all residents

00:13:54.260 --> 00:13:56.340
 based on our utility records,

00:13:56.340 --> 00:13:58.380
 because we realize some residents

00:13:58.380 --> 00:13:59.860
 may not own their properties.

00:13:59.860 --> 00:14:01.580
 So in the overlap area,

00:14:01.580 --> 00:14:03.460
 they would have gotten two notifications from us.

00:14:03.460 --> 00:14:05.580
 And then beyond the 200 feet,

00:14:05.580 --> 00:14:08.500
 those within the balance of that additional 300 feet,

00:14:08.500 --> 00:14:09.780
 we get the postcard.

00:14:09.780 --> 00:14:11.180
 So if they were interested,

00:14:11.180 --> 00:14:12.500
 they would have reached out to us

00:14:12.500 --> 00:14:14.220
 with both of those notifications.

00:14:14.220 --> 00:14:16.660
 The newspaper notice, I realize not everybody may read

00:14:16.660 --> 00:14:18.620
 the Dent Record Chronicle,

00:14:18.620 --> 00:14:21.180
 but hence why we do the two mail notices to help

00:14:21.180 --> 00:14:23.020
 with notifying those property owners.

00:14:23.020 --> 00:14:27.380
 - Can you point out which property owners

00:14:27.380 --> 00:14:28.220
 were actually notified?

00:14:28.220 --> 00:14:29.180
 'Cause I see it's only five.

00:14:29.180 --> 00:14:30.020
 - It's not, yeah.

00:14:30.020 --> 00:14:33.260
 Again, within the proximity of this property,

00:14:33.260 --> 00:14:37.100
 there really is that developing multifamily property

00:14:37.100 --> 00:14:38.900
 to the south that is within there.

00:14:38.900 --> 00:14:42.020
 Other properties are undeveloped parcels

00:14:42.020 --> 00:14:45.380
 within 200 and 300 or 500 feet.

00:14:48.380 --> 00:14:50.460
 So it looks like three of those properties

00:14:50.460 --> 00:14:53.740
 fell within that 200 and then two additional

00:14:53.740 --> 00:14:54.780
 fell within the 500.

00:14:54.780 --> 00:15:02.940
 - Okay, thank you.

00:15:02.940 --> 00:15:03.760
 Thanks, Mia.

00:15:03.760 --> 00:15:05.820
 Okay.

00:15:05.820 --> 00:15:08.820
 Moving on, then we're gonna go to MPA 25001.

00:15:08.820 --> 00:15:16.460
 Sarah?

00:15:16.460 --> 00:15:17.300
 - Sorry.

00:15:17.300 --> 00:15:18.300
 - Sure, sorry.

00:15:18.300 --> 00:15:29.060
 - Good evening, commissioners.

00:15:29.060 --> 00:15:31.020
 My name is Sahar Svandieri,

00:15:31.020 --> 00:15:34.380
 Senior Transportation Planner, Development Services.

00:15:34.380 --> 00:15:36.340
 Tonight, I would like to speak with you

00:15:36.340 --> 00:15:38.540
 about the Mobility Plan amendments.

00:15:38.540 --> 00:15:43.140
 And this one is for MPA 24-001A

00:15:43.140 --> 00:15:47.580
 for Underwood Road, Springside, and Corbyn Road.

00:15:47.580 --> 00:15:49.980
 But before I go any further,

00:15:49.980 --> 00:15:53.300
 let me explain a little bit about the Mobility Plan.

00:15:53.300 --> 00:15:55.960
 Mobility Plan, just like Comprehensive Plan,

00:15:55.960 --> 00:15:57.620
 is a long-range plan.

00:15:57.620 --> 00:15:59.540
 And the current Mobility Plan

00:15:59.540 --> 00:16:03.540
 was adopted by the city council back in March 2022.

00:16:03.540 --> 00:16:12.040
 But right now, as part of the Comprehensive Plan of 2040,

00:16:13.380 --> 00:16:16.220
 generally, the Mobility Plan establishes

00:16:16.220 --> 00:16:20.620
 the future roadways, pedestrian, and bicyclist network

00:16:20.620 --> 00:16:25.180
 to ensure the connectivity and efficient movements.

00:16:25.180 --> 00:16:27.460
 However, we should keep in our mind

00:16:27.460 --> 00:16:29.580
 that Mobility Plan is not intended

00:16:29.580 --> 00:16:33.180
 to provide detailed design of roads or plans.

00:16:33.180 --> 00:16:36.900
 It is more intended to provide general policies

00:16:36.900 --> 00:16:39.180
 and broad roadway alignments.

00:16:39.180 --> 00:16:42.620
 But it can be further refined as needed

00:16:42.620 --> 00:16:44.900
 based on the new development project

00:16:44.900 --> 00:16:48.020
 or new capital improvement project.

00:16:48.020 --> 00:16:52.380
 Also, this Mobility Plan has three major elements.

00:16:52.380 --> 00:16:54.980
 First is the roadway alignment.

00:16:54.980 --> 00:16:57.700
 Second is needed right away.

00:16:57.700 --> 00:16:59.580
 It refers to the width of the road

00:16:59.580 --> 00:17:01.700
 and the speed limit on the roads.

00:17:01.700 --> 00:17:05.140
 And the third is the roadway design standard.

00:17:05.140 --> 00:17:10.020
 So back to our amendments.

00:17:10.020 --> 00:17:14.180
 This amendment has four proposals.

00:17:14.180 --> 00:17:16.540
 The reason that they have all these proposals

00:17:16.540 --> 00:17:19.540
 under one amendment is that they are all located

00:17:19.540 --> 00:17:22.540
 in a very close proximity of each other.

00:17:22.540 --> 00:17:25.220
 So, and they are somehow interconnected.

00:17:25.220 --> 00:17:26.380
 That's why.

00:17:26.380 --> 00:17:28.500
 So it gets a little bit complicated,

00:17:28.500 --> 00:17:31.780
 but I will go one by one and explain the reasons

00:17:31.780 --> 00:17:34.580
 for each of these requests.

00:17:34.580 --> 00:17:36.740
 The general area of these requests

00:17:36.740 --> 00:17:41.740
 located at west, south of the city, east of airport.

00:17:41.740 --> 00:17:46.060
 And the first request is for Underwood Road.

00:17:46.060 --> 00:17:49.700
 As you can see in this map, Underwood Road

00:17:49.700 --> 00:17:52.300
 also identified as road number one.

00:17:52.300 --> 00:17:56.020
 This is the future northern extension of Underwood Road,

00:17:56.020 --> 00:17:58.460
 which means it's not existed yet.

00:17:58.460 --> 00:18:00.940
 Staff proposed to remove this section.

00:18:00.940 --> 00:18:05.660
 The second request is to remove the eastern,

00:18:05.660 --> 00:18:10.380
 the western extension of East-West Corbyn Road here.

00:18:10.380 --> 00:18:14.900
 The road that has been identified as number two.

00:18:14.900 --> 00:18:18.580
 The third request is to extend the roadway classification

00:18:18.580 --> 00:18:21.300
 of North-South Corbyn Road.

00:18:21.300 --> 00:18:24.020
 And the fourth request is about unifying

00:18:24.020 --> 00:18:26.900
 the roadway classification of a spring side road.

00:18:26.900 --> 00:18:29.780
 Thank you, any questions?

00:18:34.820 --> 00:18:38.060
 - Do you have a diagram of what,

00:18:38.060 --> 00:18:40.580
 when you remove Underwood,

00:18:40.580 --> 00:18:43.980
 remove that number two, the little East-West,

00:18:43.980 --> 00:18:46.860
 the little swoop up of Corbyn and make it the north?

00:18:46.860 --> 00:18:52.220
 Is that what, you're basically taking one and two out

00:18:52.220 --> 00:18:53.900
 and replacing it with three?

00:18:53.900 --> 00:18:56.820
 Is that how I'm understanding this?

00:18:56.820 --> 00:18:59.260
 - We are not replacing, but we are going to,

00:18:59.260 --> 00:19:02.020
 the north-south Corbyn Road is existed.

00:19:02.020 --> 00:19:05.940
 We are just extending the roadway classification.

00:19:05.940 --> 00:19:08.020
 But yes, the road is existed.

00:19:08.020 --> 00:19:08.860
 - Oh, okay.

00:19:08.860 --> 00:19:13.700
 - But we are going to re-align the southern section

00:19:13.700 --> 00:19:17.780
 of Underwood here to connect to West Corp.

00:19:17.780 --> 00:19:21.820
 - If you look at exhibit six,

00:19:21.820 --> 00:19:23.660
 that has a graphic depiction

00:19:23.660 --> 00:19:26.700
 of what our mobility plan would look like

00:19:26.700 --> 00:19:28.780
 if this amendment is approved.

00:19:28.780 --> 00:19:31.940
 So in your attachments, in your agenda packet materials,

00:19:31.940 --> 00:19:33.700
 again, exhibit six helps kind of show

00:19:33.700 --> 00:19:36.540
 what that end result would be, as Sahar was explaining.

00:19:36.540 --> 00:19:52.020
 - Thank you. - Any other questions?

00:19:52.020 --> 00:19:52.900
 Maryann?

00:19:52.900 --> 00:19:57.140
 - Yes, question and a comment, just a comment for you.

00:19:57.140 --> 00:20:01.780
 On the background on this mobility plan,

00:20:01.780 --> 00:20:06.780
 I appreciate the acknowledgement that we're moving this

00:20:06.780 --> 00:20:12.260
 to mitigate potential environmental impacts

00:20:12.260 --> 00:20:14.380
 and to improve accessibility.

00:20:14.380 --> 00:20:16.380
 And I will say that back in the day,

00:20:16.380 --> 00:20:18.740
 we used to drive these roads and hot rod.

00:20:18.740 --> 00:20:20.340
 And so I know right where you're talking

00:20:20.340 --> 00:20:23.380
 about the beautiful, some very beautiful...

00:20:23.380 --> 00:20:25.580
 - Creek.

00:20:25.580 --> 00:20:28.380
 - Creek and resources, natural resources.

00:20:28.380 --> 00:20:33.380
 So I appreciate being aware of this and moving the road.

00:20:33.380 --> 00:20:34.420
 - Yes, sure.

00:20:34.420 --> 00:20:41.620
 - Okay, thank you.

00:20:41.620 --> 00:20:42.460
 - Thank you.

00:20:42.460 --> 00:20:43.300
 - Sure.

00:20:43.300 --> 00:20:46.700
 - And you have the next item.

00:20:46.700 --> 00:20:47.540
 - Yes.

00:20:47.540 --> 00:20:48.740
 - All right, well, you're up.

00:20:48.740 --> 00:20:56.860
 - Good evening, Sahar Espandier,

00:20:56.860 --> 00:20:59.540
 Senior Transportation Planner.

00:20:59.540 --> 00:21:01.460
 This mobility plan amendment

00:21:01.460 --> 00:21:04.700
 is about removing a future collector.

00:21:04.700 --> 00:21:08.100
 As you can see, this collector located

00:21:08.100 --> 00:21:10.140
 on the west side of the city,

00:21:10.140 --> 00:21:12.980
 located between I-35 and western,

00:21:12.980 --> 00:21:16.700
 south of US-380 and north of Jim Crystal.

00:21:16.700 --> 00:21:19.500
 Staff proposes to remove this part of the,

00:21:19.500 --> 00:21:22.100
 this future collector.

00:21:22.100 --> 00:21:25.060
 It means that this road is not existed yet,

00:21:26.140 --> 00:21:27.860
 but because of the...

00:21:27.860 --> 00:21:32.100
 I'm going to explain it more after the next session,

00:21:32.100 --> 00:21:34.740
 but there is a railroad crossing here.

00:21:34.740 --> 00:21:37.140
 Also there is a flood pain to the north.

00:21:37.140 --> 00:21:40.100
 So, and there's enough road capacity around.

00:21:40.100 --> 00:21:42.340
 So after a detailed study,

00:21:42.340 --> 00:21:45.300
 staff proposes to remove this future collector.

00:21:45.300 --> 00:21:50.420
 - And Sahar, did you want to correct for the record,

00:21:50.420 --> 00:21:52.220
 it's the Kansas City Southern Railroad?

00:21:52.220 --> 00:21:53.380
 - It's the Kansas City.

00:21:54.620 --> 00:21:57.180
 I believe your staff report acknowledged the Union Pacific

00:21:57.180 --> 00:21:58.900
 and we realized we had an incorrect name.

00:21:58.900 --> 00:22:01.260
 So we'll make sure it's corrected for council.

00:22:01.260 --> 00:22:06.900
 - Okay, any questions?

00:22:06.900 --> 00:22:09.940
 No?

00:22:09.940 --> 00:22:11.900
 Okay, all right, thank you very much.

00:22:11.900 --> 00:22:19.100
 So we'll go back to the work session portion

00:22:19.100 --> 00:22:19.940
 of our agenda.

00:22:24.620 --> 00:22:27.540
 (faintly speaking)

00:22:27.540 --> 00:22:31.180
 - Okay, we're going to receive some work session reports.

00:22:31.180 --> 00:22:35.780
 So up first, we have PZ 25-123.

00:22:35.780 --> 00:22:37.860
 Julie.

00:22:37.860 --> 00:22:40.300
 - Good evening, Julie Wyatt.

00:22:40.300 --> 00:22:41.900
 Let me pull up my presentation.

00:22:41.900 --> 00:22:50.340
 All right, good evening.

00:22:50.340 --> 00:22:52.740
 I'm Julie Wyatt and I am a principal planner

00:22:52.740 --> 00:22:54.060
 with the city of Denton.

00:22:54.060 --> 00:22:56.580
 And I'm presenting a bootcamp to you tonight

00:22:56.580 --> 00:23:00.220
 regarding area planning and zoning district overlays.

00:23:00.220 --> 00:23:07.060
 So just go over what we're going to talk about first.

00:23:07.060 --> 00:23:09.220
 We're going to start off with area planning,

00:23:09.220 --> 00:23:11.420
 talk about what they are, why we do them,

00:23:11.420 --> 00:23:15.460
 how we create them, talk about how we implement them,

00:23:15.460 --> 00:23:17.420
 what our prioritized areas are,

00:23:17.420 --> 00:23:19.180
 and then some adopted area plans

00:23:19.180 --> 00:23:21.140
 that we have within the city.

00:23:21.140 --> 00:23:23.620
 And then we're going to shift to overlay districts.

00:23:23.620 --> 00:23:25.900
 And we're going to, again, talk about what they are

00:23:25.900 --> 00:23:27.940
 and how they're created.

00:23:27.940 --> 00:23:29.900
 What our Denton Development Code says

00:23:29.900 --> 00:23:34.220
 about overlay districts are some existing overlays we have,

00:23:34.220 --> 00:23:35.660
 and then a brief overview

00:23:35.660 --> 00:23:38.340
 of some upcoming overlay districts.

00:23:38.340 --> 00:23:43.100
 So first, we're going to start with area planning.

00:23:43.100 --> 00:23:48.340
 So before we talk about specific area planning,

00:23:48.340 --> 00:23:50.900
 I thought it would be best to kind of set the table

00:23:50.900 --> 00:23:55.500
 about how they fit within our hierarchy of documents.

00:23:55.500 --> 00:23:58.500
 We start off with our policy documents.

00:23:58.500 --> 00:24:03.420
 And the big policy document we have in the city of Denton

00:24:03.420 --> 00:24:05.540
 is our comprehensive plan.

00:24:05.540 --> 00:24:07.420
 It's Denton Plan 2040.

00:24:07.420 --> 00:24:10.060
 It was adopted in 2022.

00:24:10.060 --> 00:24:14.620
 And it is a broad document that covers the entire city

00:24:14.620 --> 00:24:17.820
 and all aspects related to the city.

00:24:17.820 --> 00:24:22.820
 You hear us say from time to time here on zoning cases

00:24:22.820 --> 00:24:25.420
 and other items that come before you,

00:24:25.420 --> 00:24:28.020
 the comprehensive plan is the 30,000-foot view.

00:24:28.020 --> 00:24:31.140
 So if you're in an airplane looking down on the city,

00:24:31.140 --> 00:24:33.320
 that's what that comprehensive plan is.

00:24:33.320 --> 00:24:37.340
 We have other plans nested within the comprehensive plan.

00:24:37.340 --> 00:24:39.620
 And Sahar just talked about the mobility plan,

00:24:39.620 --> 00:24:41.060
 and that's one of them.

00:24:41.060 --> 00:24:45.580
 Those specific plans are, they're citywide,

00:24:45.580 --> 00:24:47.340
 so they cover the entire city,

00:24:47.340 --> 00:24:49.820
 but they are related to a specific subject.

00:24:49.820 --> 00:24:53.180
 So think mobility, think about capital projects,

00:24:53.180 --> 00:24:55.860
 maybe economic development, drainage.

00:24:55.860 --> 00:25:00.380
 So we have some of those citywide plans

00:25:00.380 --> 00:25:03.220
 that are nested within our comprehensive plan,

00:25:03.220 --> 00:25:06.300
 but they are just subject-specific.

00:25:06.300 --> 00:25:07.820
 And then we get to area plans.

00:25:07.820 --> 00:25:09.980
 And those are a little bit closer to the ground.

00:25:09.980 --> 00:25:13.500
 We say they're about 5,000 feet above ground.

00:25:13.500 --> 00:25:17.140
 Area plans allow us to take a deep dive

00:25:17.140 --> 00:25:22.140
 into a particular area, so a geographic boundary.

00:25:22.140 --> 00:25:25.700
 And so if the comp plan looks at the population,

00:25:25.700 --> 00:25:28.500
 in total population of the city,

00:25:28.500 --> 00:25:30.900
 an area plan will look at it at the block level

00:25:30.900 --> 00:25:32.180
 or the neighborhood level.

00:25:32.180 --> 00:25:36.300
 We're looking at things like demographics, area needs,

00:25:36.300 --> 00:25:39.460
 land uses, parks, all of that

00:25:39.460 --> 00:25:43.260
 at a very detailed, specific scale.

00:25:47.380 --> 00:25:49.620
 And then, so we've got these policy documents.

00:25:49.620 --> 00:25:54.620
 And then those then inform our regulatory documents.

00:25:54.620 --> 00:25:56.980
 And that's where the rubber hits the road.

00:25:56.980 --> 00:25:58.500
 And that's at the ground level.

00:25:58.500 --> 00:26:00.900
 That's things like our debt and development code,

00:26:00.900 --> 00:26:04.940
 our zoning map, our capital projects, construction,

00:26:04.940 --> 00:26:06.380
 things that are being built.

00:26:06.380 --> 00:26:09.620
 So all of those policies really should inform

00:26:09.620 --> 00:26:12.460
 what our laws are and what we build within the city.

00:26:14.420 --> 00:26:17.500
 So now I'll talk specifically about area plans

00:26:17.500 --> 00:26:20.460
 in relationship to the comprehensive plan.

00:26:20.460 --> 00:26:24.980
 Denton 2040 does recommend a variety of area plans

00:26:24.980 --> 00:26:28.580
 in order to achieve the community's overall vision.

00:26:28.580 --> 00:26:31.500
 It's both mentioned in our land use element

00:26:31.500 --> 00:26:35.860
 as well as our community character in urban design element.

00:26:35.860 --> 00:26:39.180
 So area plans are a part of our comprehensive plan.

00:26:42.620 --> 00:26:45.300
 So what are specifically area plans?

00:26:45.300 --> 00:26:47.940
 If it's done right, you end up with a document.

00:26:47.940 --> 00:26:51.140
 And we have several of them,

00:26:51.140 --> 00:26:52.740
 and we'll talk about them tonight.

00:26:52.740 --> 00:26:55.220
 But they should be forward-looking.

00:26:55.220 --> 00:26:59.660
 And they allow stakeholders, residents,

00:26:59.660 --> 00:27:01.500
 to determine what their community,

00:27:01.500 --> 00:27:04.380
 their specific neighborhood should look and feel like

00:27:04.380 --> 00:27:05.860
 in 10 to 20 years.

00:27:05.860 --> 00:27:10.140
 As I mentioned, they are specific to a particular area.

00:27:10.140 --> 00:27:14.980
 So it is looking, once again, at a specific neighborhood,

00:27:14.980 --> 00:27:19.340
 or maybe it's a district, maybe it's a corridor.

00:27:19.340 --> 00:27:23.420
 But they are particular to one part of the city.

00:27:23.420 --> 00:27:27.940
 The public engagement should be really focused

00:27:27.940 --> 00:27:31.860
 on an area plan to refine that community's vision,

00:27:31.860 --> 00:27:34.460
 to figure out what it is that they want to see

00:27:34.460 --> 00:27:37.260
 in terms of land uses and parks

00:27:37.260 --> 00:27:40.260
 and mobility within their community.

00:27:40.260 --> 00:27:41.900
 And ultimately, they point the way.

00:27:41.900 --> 00:27:44.860
 They give us a roadmap on how to achieve that vision.

00:27:44.860 --> 00:27:52.500
 We have a variety of reasons as to why we do area plans.

00:27:52.500 --> 00:27:57.500
 And they can be very unique to a specific area.

00:27:57.500 --> 00:28:01.700
 But generally, they are intended to refine that vision.

00:28:01.700 --> 00:28:04.460
 It's also looking for areas of protection.

00:28:04.460 --> 00:28:06.220
 So if there is a neighborhood

00:28:06.220 --> 00:28:08.740
 that really wants to protect a certain resource

00:28:08.740 --> 00:28:09.980
 within their community,

00:28:09.980 --> 00:28:12.460
 area plans are a good way to determine that

00:28:12.460 --> 00:28:14.140
 and determine how to protect it.

00:28:14.140 --> 00:28:17.260
 They're good at identifying areas of change.

00:28:17.260 --> 00:28:19.980
 Maybe a community wants to see some redevelopment

00:28:19.980 --> 00:28:24.780
 or a change in the particular land uses.

00:28:24.780 --> 00:28:28.220
 They help us understand and respond to community,

00:28:28.220 --> 00:28:31.140
 to specific issues or needs.

00:28:31.140 --> 00:28:32.580
 They plan for opportunities.

00:28:32.580 --> 00:28:35.180
 We're gonna talk about the Design Downtown Denton Plan

00:28:35.180 --> 00:28:36.020
 in a few minutes.

00:28:36.020 --> 00:28:40.300
 And one facet of that plan is the area south of downtown

00:28:40.300 --> 00:28:42.260
 has recently come out of the floodplain.

00:28:42.260 --> 00:28:44.580
 So how are we gonna plan for that opportunity

00:28:44.580 --> 00:28:46.700
 for that part of the community?

00:28:46.700 --> 00:28:49.420
 Identify infrastructure needs,

00:28:49.420 --> 00:28:53.220
 maybe mobility challenges and how to address those.

00:28:53.220 --> 00:28:56.260
 And provide the community an opportunity

00:28:56.260 --> 00:28:59.660
 to provide input in future land use decisions.

00:28:59.660 --> 00:29:04.500
 Our comprehensive plan has this map within it.

00:29:04.500 --> 00:29:08.020
 And it identifies certain focus areas,

00:29:08.020 --> 00:29:10.860
 centers, corridors and gateways within our community.

00:29:10.860 --> 00:29:14.420
 And those are really suggested areas for those area plans

00:29:14.420 --> 00:29:17.620
 because the comprehensive plan recognizes

00:29:17.620 --> 00:29:20.020
 they need more detailed planning.

00:29:20.020 --> 00:29:25.220
 So how are our area plans created?

00:29:25.220 --> 00:29:28.420
 While there is not one right way to do it,

00:29:28.420 --> 00:29:33.140
 there is a framework that most area plans do follow.

00:29:33.140 --> 00:29:35.500
 And we'll just go over these briefly.

00:29:35.500 --> 00:29:37.260
 So first we've got pre-planning.

00:29:37.260 --> 00:29:39.140
 That's identifying the purpose.

00:29:39.140 --> 00:29:41.620
 Maybe what are those opportunities or challenges

00:29:41.620 --> 00:29:42.940
 for a community?

00:29:42.940 --> 00:29:45.060
 Also, before you kick off the plan,

00:29:45.060 --> 00:29:47.980
 you wanna start identifying stakeholders.

00:29:47.980 --> 00:29:52.100
 Maybe create a work plan of what you wanna achieve

00:29:52.100 --> 00:29:53.580
 with the area plan.

00:29:53.580 --> 00:29:56.500
 And then if necessary, retain a consultant.

00:29:56.500 --> 00:29:59.460
 Once you've done your pre-planning,

00:29:59.460 --> 00:30:00.500
 you kick off the plan

00:30:00.500 --> 00:30:02.260
 and that really is the start date, right?

00:30:02.260 --> 00:30:06.140
 You're starting to discover key issues within the community.

00:30:06.140 --> 00:30:11.500
 Appoint a steering or advisory committee

00:30:11.500 --> 00:30:15.100
 to help validate any findings

00:30:15.100 --> 00:30:17.380
 and keep you on the right track.

00:30:17.380 --> 00:30:20.340
 The biggest part of any area plan,

00:30:20.340 --> 00:30:22.540
 or at least that we've had recently

00:30:22.540 --> 00:30:23.980
 within the city of Denton,

00:30:23.980 --> 00:30:26.300
 is that vision and existing conditions.

00:30:26.300 --> 00:30:30.020
 And that's really two parts within that section.

00:30:30.020 --> 00:30:33.340
 It is a whole lot of public engagement,

00:30:33.340 --> 00:30:34.860
 talking to the community,

00:30:34.860 --> 00:30:37.380
 understanding what their concerns are

00:30:37.380 --> 00:30:39.820
 and what their vision and their hopes and dreams

00:30:39.820 --> 00:30:41.080
 for their neighborhoods.

00:30:41.080 --> 00:30:44.620
 So that intensive public engagement,

00:30:44.620 --> 00:30:46.500
 but also getting an understanding

00:30:46.500 --> 00:30:47.940
 of the existing conditions.

00:30:47.940 --> 00:30:49.660
 And that really is a lot of research.

00:30:49.660 --> 00:30:51.860
 So you've got either a city staff

00:30:51.860 --> 00:30:54.020
 or a project team or consultant

00:30:54.020 --> 00:30:56.100
 looking at things like demographics,

00:30:56.980 --> 00:31:00.220
 understanding what those existing land uses are.

00:31:00.220 --> 00:31:04.420
 What is our infrastructure?

00:31:04.420 --> 00:31:08.420
 What are our public facilities within that community?

00:31:08.420 --> 00:31:10.920
 And then we also look at those demographics.

00:31:10.920 --> 00:31:15.100
 So we can understand what the population is.

00:31:15.100 --> 00:31:17.740
 What is the market demand for housing

00:31:17.740 --> 00:31:21.700
 or for other services or facilities within the area?

00:31:21.700 --> 00:31:23.020
 What's the tax base?

00:31:23.020 --> 00:31:25.900
 So looking at all of this data,

00:31:25.900 --> 00:31:29.540
 all of this information goes into writing the plan.

00:31:29.540 --> 00:31:34.620
 So we write, the project team writes the plan,

00:31:34.620 --> 00:31:37.300
 reviews it, and then it goes to the community

00:31:37.300 --> 00:31:39.460
 and policymakers for validation,

00:31:39.460 --> 00:31:41.780
 for response, for feedback.

00:31:41.780 --> 00:31:44.060
 And then that starts all over again.

00:31:44.060 --> 00:31:47.900
 So the drafting plan is a real iterative process

00:31:47.900 --> 00:31:50.420
 in that we go with little sections and say,

00:31:50.420 --> 00:31:51.340
 does this sound right?

00:31:51.340 --> 00:31:53.500
 Is this what we wanna see?

00:31:53.500 --> 00:31:56.660
 Get that validation and then go back and refine.

00:31:56.660 --> 00:32:00.820
 Ultimately, you hopefully end up with a plan

00:32:00.820 --> 00:32:04.300
 that when it's presented to the community,

00:32:04.300 --> 00:32:09.300
 it is accurately reflects what the community wants to see.

00:32:09.300 --> 00:32:10.920
 It goes through public hearing

00:32:10.920 --> 00:32:14.220
 and then adopted by city council.

00:32:14.220 --> 00:32:16.660
 That process takes about 12 months,

00:32:16.660 --> 00:32:18.200
 maybe a little bit longer.

00:32:18.200 --> 00:32:19.140
 With an area plan,

00:32:19.140 --> 00:32:21.160
 you don't wanna get an analysis paralysis.

00:32:21.160 --> 00:32:25.660
 You wanna get in and move forward and get momentum going.

00:32:25.660 --> 00:32:28.860
 Area planning does not stop there, however.

00:32:28.860 --> 00:32:30.380
 Then you have implementation.

00:32:30.380 --> 00:32:31.980
 And there's two parts to implementation

00:32:31.980 --> 00:32:32.920
 the way I think of it.

00:32:32.920 --> 00:32:34.460
 First, you've got the land use policy.

00:32:34.460 --> 00:32:38.260
 You've got that directive within the plan.

00:32:38.260 --> 00:32:40.020
 And that's where the community is saying,

00:32:40.020 --> 00:32:42.040
 look, this is what we wanna preserve.

00:32:42.040 --> 00:32:43.920
 This is what we want to change.

00:32:43.920 --> 00:32:47.260
 And those really inform some of those decisions

00:32:47.260 --> 00:32:50.060
 that you make or that the analysis that staff does

00:32:50.060 --> 00:32:52.820
 in terms of things like zoning decisions

00:32:52.820 --> 00:32:56.900
 or those types of projects that you see before you.

00:32:56.900 --> 00:33:00.060
 It also can include some design elements

00:33:00.060 --> 00:33:01.500
 that the community would like to see,

00:33:01.500 --> 00:33:03.020
 some additional protections

00:33:03.020 --> 00:33:07.980
 or community character that they wanna protect.

00:33:07.980 --> 00:33:09.320
 So that's that policy side.

00:33:09.320 --> 00:33:11.820
 We've also got the action steps.

00:33:11.820 --> 00:33:16.580
 And these are these tasks that staff would carry out

00:33:16.580 --> 00:33:17.900
 or community members,

00:33:17.900 --> 00:33:20.500
 and that would carry out a policy or a project.

00:33:20.500 --> 00:33:25.500
 These should be steps to help us achieve the goals

00:33:25.500 --> 00:33:27.980
 that the community has set forth.

00:33:27.980 --> 00:33:30.860
 One thing that we wanna do in our area planning

00:33:30.860 --> 00:33:34.140
 is make sure that our steps and our tasks are attainable.

00:33:34.140 --> 00:33:37.500
 We wanna make sure we can achieve the promises that we make

00:33:37.500 --> 00:33:40.460
 and those elements that we put in the plan.

00:33:40.460 --> 00:33:42.020
 They should include a timeframe.

00:33:42.020 --> 00:33:46.380
 When we think we can accomplish this task,

00:33:46.380 --> 00:33:48.280
 identify the responsible agencies

00:33:48.280 --> 00:33:50.360
 and then how to pay for it.

00:33:50.360 --> 00:33:55.620
 In 2022, when the city council adopted

00:33:55.620 --> 00:33:58.360
 the current comprehensive plan,

00:33:58.360 --> 00:34:01.260
 they also prioritize some areas

00:34:01.260 --> 00:34:03.140
 that they would like to see some area plans.

00:34:03.140 --> 00:34:07.980
 So they talked through 10 areas.

00:34:07.980 --> 00:34:12.140
 They recommended three, four area plans.

00:34:12.140 --> 00:34:13.700
 The first one was the Northeast Denton

00:34:13.700 --> 00:34:16.100
 that's at Loop 288 and Sherman.

00:34:16.100 --> 00:34:18.940
 That plan did go forward with analysis

00:34:18.940 --> 00:34:20.760
 and some drafting of the plan.

00:34:20.760 --> 00:34:23.340
 It was paused to allow the community members

00:34:23.340 --> 00:34:26.460
 to explore opportunities for funding

00:34:26.460 --> 00:34:27.980
 for a future state part.

00:34:27.980 --> 00:34:30.340
 So that's on pause right now.

00:34:30.340 --> 00:34:33.180
 But the other two prioritize area,

00:34:33.180 --> 00:34:36.100
 Southeast Denton and Downtown Denton,

00:34:36.100 --> 00:34:38.760
 those plans have been adopted.

00:34:38.760 --> 00:34:41.180
 They were adopted last summer.

00:34:41.180 --> 00:34:43.500
 We'll hit them just briefly.

00:34:43.500 --> 00:34:45.940
 So Southeast Denton, I know Mia talked about it.

00:34:45.940 --> 00:34:47.820
 I think it was last meeting.

00:34:47.820 --> 00:34:51.660
 And we had a specific purpose

00:34:51.660 --> 00:34:54.660
 of why we went forward with that plan.

00:34:54.660 --> 00:34:56.260
 And that was first to acknowledge

00:34:56.260 --> 00:34:58.060
 the generational trauma associated

00:34:58.060 --> 00:35:00.980
 with the displacement of Quaker Town families,

00:35:00.980 --> 00:35:03.620
 but also to address residents' concerns

00:35:03.620 --> 00:35:08.620
 of current concerns, places that they wanted to protect,

00:35:08.620 --> 00:35:11.460
 places that they wanted to see change.

00:35:12.660 --> 00:35:16.260
 The process for the Southeast Denton area plan

00:35:16.260 --> 00:35:20.940
 included a tremendous amount of public engagement,

00:35:20.940 --> 00:35:24.660
 over 40 engagement activities, and it ran the gamut.

00:35:24.660 --> 00:35:29.660
 We did standard neighborhood meetings all the way to,

00:35:29.660 --> 00:35:32.340
 there's a picture here in the middle of your screen,

00:35:32.340 --> 00:35:34.420
 man on the street interviews

00:35:34.420 --> 00:35:36.900
 in front of local businesses and parks.

00:35:36.900 --> 00:35:40.940
 And so we wanted to talk to as many people as possible.

00:35:40.940 --> 00:35:44.100
 Ultimately, it was adopted by city council

00:35:44.100 --> 00:35:48.220
 and with a vision

00:35:48.220 --> 00:35:53.220
 that the community wanted to make sure

00:35:53.220 --> 00:35:57.380
 that cherished history and that black culture

00:35:57.380 --> 00:35:58.860
 was protected and preserved,

00:35:58.860 --> 00:36:00.780
 but also to create a community

00:36:00.780 --> 00:36:03.620
 where all were welcome for the future.

00:36:03.620 --> 00:36:07.100
 So it was a really great experience.

00:36:08.020 --> 00:36:11.340
 And then we had the design downtown Denton plan.

00:36:11.340 --> 00:36:13.100
 And that purpose was to ensure

00:36:13.100 --> 00:36:15.940
 that downtown remains relevant for the future.

00:36:15.940 --> 00:36:20.380
 And they did a lot of public engagement as well.

00:36:20.380 --> 00:36:23.980
 It also followed kind of that planning process.

00:36:23.980 --> 00:36:27.620
 And that one was unique in that

00:36:27.620 --> 00:36:30.060
 the stakeholders were extremely diverse.

00:36:30.060 --> 00:36:32.740
 They had business owners all the way to visitors

00:36:32.740 --> 00:36:34.940
 who just came to, who don't necessarily live

00:36:34.940 --> 00:36:39.220
 in the community, but come to the downtown square for events.

00:36:39.220 --> 00:36:42.420
 So they had a lot of really engaging

00:36:42.420 --> 00:36:45.060
 and innovative ways to talk to the community.

00:36:45.060 --> 00:36:49.540
 They used the internet really well in social media.

00:36:49.540 --> 00:36:51.580
 Looking at Cameron, she did a great job.

00:36:51.580 --> 00:36:55.900
 And they just, they really reached out

00:36:55.900 --> 00:37:00.740
 in really interesting ways to get that feedback.

00:37:00.740 --> 00:37:02.740
 We also have older adopted plans.

00:37:02.740 --> 00:37:05.780
 We have a Fry Street area plan, Edenia area plan,

00:37:05.780 --> 00:37:08.020
 and an Oak gateway area plan.

00:37:08.020 --> 00:37:10.020
 A couple of these plans are pretty old.

00:37:10.020 --> 00:37:12.700
 And just to let you know, kind of like comprehensive plan,

00:37:12.700 --> 00:37:15.300
 they should be updated regularly

00:37:15.300 --> 00:37:16.900
 in order to make sure that they stay current

00:37:16.900 --> 00:37:19.780
 and that we inaccurate and that we are

00:37:19.780 --> 00:37:22.420
 accurately reflecting the community's vision.

00:37:22.420 --> 00:37:25.580
 So now we're gonna leave area plans

00:37:25.580 --> 00:37:27.260
 and we're gonna go where the rubber hits the road,

00:37:27.260 --> 00:37:29.660
 and that is overlay districts.

00:37:29.660 --> 00:37:31.140
 So what are they?

00:37:31.140 --> 00:37:34.100
 They are zoning tools to implement area plans

00:37:34.100 --> 00:37:35.860
 or to address localized needs

00:37:35.860 --> 00:37:38.420
 or to achieve other policy goals.

00:37:38.420 --> 00:37:39.620
 So there's a variety of reasons

00:37:39.620 --> 00:37:41.900
 of why we have overlay districts.

00:37:41.900 --> 00:37:44.060
 They actually sit on top of the zoning

00:37:44.060 --> 00:37:46.940
 and they can modify the regulations where they're needed,

00:37:46.940 --> 00:37:50.020
 but that underlying zoning stays in place.

00:37:50.020 --> 00:37:52.580
 They often require substantial coordination

00:37:52.580 --> 00:37:56.980
 between property owners, staff, stakeholders,

00:37:57.900 --> 00:38:01.860
 and the process to put a overlay district in place

00:38:01.860 --> 00:38:03.700
 or to amend it is the same as zoning.

00:38:03.700 --> 00:38:06.660
 So when the live work overlay comes before you,

00:38:06.660 --> 00:38:10.540
 it will function very much like a zoning public hearing

00:38:10.540 --> 00:38:13.100
 where there's notification and a public hearing

00:38:13.100 --> 00:38:15.220
 ultimately approval by city council.

00:38:15.220 --> 00:38:19.180
 The Denton Development Code Subtractor Four

00:38:19.180 --> 00:38:24.060
 outlines how we need to structure our overlays

00:38:24.060 --> 00:38:27.060
 in the city of Denton and approve them.

00:38:27.060 --> 00:38:30.500
 And there are three parts.

00:38:30.500 --> 00:38:33.660
 There is the statement of purpose, the why,

00:38:33.660 --> 00:38:36.140
 a boundary map, and then the regulations.

00:38:36.140 --> 00:38:38.540
 And those regulations should provide that protection

00:38:38.540 --> 00:38:40.580
 of features that the community has said

00:38:40.580 --> 00:38:43.940
 that they wanna protect or that are of special concern.

00:38:43.940 --> 00:38:47.340
 It can change the levels of permission for land uses.

00:38:47.340 --> 00:38:50.620
 It can have special design standards, performance standards,

00:38:50.620 --> 00:38:54.660
 or other standards related to different uses,

00:38:54.660 --> 00:38:57.340
 and then any other matters of importance.

00:38:57.340 --> 00:39:01.900
 I think we have seven overlay districts.

00:39:01.900 --> 00:39:02.860
 I may have miscounted,

00:39:02.860 --> 00:39:05.900
 but just gonna briefly touch on them.

00:39:05.900 --> 00:39:08.140
 So we have the Fry Street overlay

00:39:08.140 --> 00:39:10.820
 that is an orange on your screen.

00:39:10.820 --> 00:39:14.100
 The purpose of that was to protect the public peace,

00:39:14.100 --> 00:39:16.940
 safety, cleanliness, and general welfare.

00:39:16.940 --> 00:39:21.940
 This actually came out of the Fry Street small area plan.

00:39:21.980 --> 00:39:25.980
 And so it regulates things like parking,

00:39:25.980 --> 00:39:29.140
 solid waste containers, signs, setbacks,

00:39:29.140 --> 00:39:31.540
 and then residential and commercial density.

00:39:31.540 --> 00:39:34.620
 We have the Denton Square District.

00:39:34.620 --> 00:39:36.860
 That was intended to make sure that we preserve

00:39:36.860 --> 00:39:39.500
 this cherished community asset.

00:39:39.500 --> 00:39:43.260
 And so it establishes design standards,

00:39:43.260 --> 00:39:47.300
 demolition approvals, and also approvals

00:39:49.740 --> 00:39:53.140
 and certificate of design consistency procedure.

00:39:53.140 --> 00:39:58.220
 We have three historic districts in the city of Denton

00:39:58.220 --> 00:40:03.220
 that Cameron manages as our historic preservation officer.

00:40:03.220 --> 00:40:06.540
 These historic districts are intended to protect,

00:40:06.540 --> 00:40:11.540
 enhance, and preserve these structures within the community.

00:40:11.540 --> 00:40:15.700
 And the regulations include things like

00:40:15.700 --> 00:40:18.860
 architectural standards specific to those areas

00:40:18.860 --> 00:40:22.580
 and approval procedure, the certificate of appropriateness.

00:40:22.580 --> 00:40:28.820
 And then three overlay districts we don't see very much.

00:40:28.820 --> 00:40:31.900
 Well, you see the Razor Ranch District quite a bit,

00:40:31.900 --> 00:40:34.580
 but the municipal airport overlay,

00:40:34.580 --> 00:40:37.500
 that really is related to the functioning of the airport.

00:40:37.500 --> 00:40:40.620
 It is really specific to that area.

00:40:40.620 --> 00:40:43.020
 It regulates things like the height of structures,

00:40:43.020 --> 00:40:46.380
 also limits the uses because you don't wanna build a house

00:40:46.380 --> 00:40:47.780
 next to a runway, right?

00:40:47.780 --> 00:40:49.660
 There are noise implications.

00:40:49.660 --> 00:40:54.660
 So provides those regulations specific

00:40:54.660 --> 00:40:56.820
 to the functioning of that airport.

00:40:56.820 --> 00:41:01.820
 Unicorn Lake Overlay District, that is mainly residential.

00:41:01.820 --> 00:41:06.700
 There's a little bit of piece that is commercial within it,

00:41:06.700 --> 00:41:10.540
 but it was intended to provide

00:41:10.540 --> 00:41:12.660
 kind of that variety of housing type.

00:41:12.660 --> 00:41:15.420
 It also has private streets within it.

00:41:15.420 --> 00:41:17.180
 And then those dimensional standards.

00:41:17.180 --> 00:41:19.260
 And then we have the Razor Ranch Overlay District.

00:41:19.260 --> 00:41:20.860
 That is one you're very familiar with.

00:41:20.860 --> 00:41:24.500
 And that it was intended to provide that combination

00:41:24.500 --> 00:41:28.500
 of land uses to encourage that real commercial district.

00:41:28.500 --> 00:41:32.460
 And then you've got three proposed overlay districts

00:41:32.460 --> 00:41:35.300
 you are gonna see in the near future.

00:41:35.300 --> 00:41:37.620
 We have the Southeast Denton Residential Overlay.

00:41:37.620 --> 00:41:38.460
 Let me back up.

00:41:38.460 --> 00:41:40.500
 These stem from the Southeast Denton Area Plan.

00:41:40.500 --> 00:41:42.340
 So these were a recommendation within that.

00:41:42.340 --> 00:41:45.260
 So this is one of those action steps

00:41:45.260 --> 00:41:47.940
 where we're creating the regulations.

00:41:47.940 --> 00:41:51.100
 So the residential overlay community really wanted

00:41:51.100 --> 00:41:53.660
 to make sure that the neighborhoods

00:41:53.660 --> 00:41:55.820
 within Southeast Denton were protected.

00:41:55.820 --> 00:41:57.180
 Not only in terms of use,

00:41:57.180 --> 00:41:59.220
 but in terms of scale and character.

00:41:59.220 --> 00:42:02.700
 And so that residential overlay is intended

00:42:02.700 --> 00:42:07.700
 to make sure that we protect those neighborhoods.

00:42:07.700 --> 00:42:10.740
 We also have a height limitation overlay

00:42:10.740 --> 00:42:13.460
 and that will be coming forward.

00:42:13.460 --> 00:42:17.860
 And that is area in blue on your screen.

00:42:17.860 --> 00:42:20.060
 And that is just intended to make sure

00:42:20.060 --> 00:42:22.700
 that any commercial development

00:42:22.700 --> 00:42:27.380
 near residential areas is compatible.

00:42:27.380 --> 00:42:31.020
 And then the Southeast Denton Live Work Overlay.

00:42:31.020 --> 00:42:33.500
 I know you heard about that last meeting.

00:42:33.500 --> 00:42:35.660
 So I won't go into detail with that.

00:42:35.660 --> 00:42:37.420
 And that's the area in pink.

00:42:37.420 --> 00:42:40.740
 That concludes my presentation.

00:42:40.740 --> 00:42:42.700
 Sorry if it went along, but a little long,

00:42:42.700 --> 00:42:44.940
 but I'm happy to answer any questions if you have them.

00:42:44.940 --> 00:42:48.220
 Or Tina might jump in if I can't answer it.

00:42:48.220 --> 00:42:56.260
 - What if a resident wanted to talk

00:42:56.260 --> 00:42:59.780
 about an area plan for their community?

00:42:59.780 --> 00:43:02.900
 I mean, is it the city that prompts these

00:43:02.900 --> 00:43:04.940
 or is it residents that kind of says,

00:43:04.940 --> 00:43:07.260
 "Hey, can we have an area plan over here?"

00:43:07.260 --> 00:43:09.580
 - I'm gonna let Tina answer that.

00:43:09.580 --> 00:43:12.300
 (laughing)

00:43:12.300 --> 00:43:14.100
 I guess technically it could be both.

00:43:14.100 --> 00:43:18.980
 You know, with the work that we've done here in Denton,

00:43:18.980 --> 00:43:20.580
 I think it's, well, I think we've probably had

00:43:20.580 --> 00:43:23.500
 kind of a combination because wasn't,

00:43:23.500 --> 00:43:25.460
 not Price Street, the Oak Hickory Gateway,

00:43:25.460 --> 00:43:28.700
 wasn't that really resident driven?

00:43:28.700 --> 00:43:29.620
 It predates me.

00:43:29.620 --> 00:43:31.020
 So I'm just trying to...

00:43:31.020 --> 00:43:35.460
 I think, let's put it this way.

00:43:35.460 --> 00:43:37.900
 I know Northeast, well, Northeast Denton's a great example.

00:43:37.900 --> 00:43:39.500
 I know the residents in Northeast Denton

00:43:39.500 --> 00:43:43.140
 were interested in having an area plan adopted

00:43:43.140 --> 00:43:44.580
 for the area of the community.

00:43:44.580 --> 00:43:47.420
 In fact, they drafted their own area plan.

00:43:47.420 --> 00:43:50.980
 And as a result of some of the work they did,

00:43:50.980 --> 00:43:53.740
 coupled with the timing coming out of our adoption

00:43:53.740 --> 00:43:55.660
 of the comprehensive plan where we were prioritizing

00:43:55.660 --> 00:43:59.460
 our future area plans, that is what kind of helped

00:43:59.460 --> 00:44:03.260
 probably move that area up to number one on the list,

00:44:03.260 --> 00:44:05.900
 not to mention, you know, some of the other development

00:44:05.900 --> 00:44:07.460
 interests we were seeing within the area.

00:44:07.460 --> 00:44:11.100
 But that was truly, I would say driven by residents,

00:44:11.100 --> 00:44:14.460
 but also staff and elected officials in that case.

00:44:14.460 --> 00:44:18.380
 So it's possible that residents could put forth,

00:44:18.380 --> 00:44:20.420
 you know, we've come up with this list

00:44:20.420 --> 00:44:21.820
 when we did the comprehensive plan.

00:44:21.820 --> 00:44:23.340
 As Julie mentioned earlier, you know,

00:44:23.340 --> 00:44:24.940
 we would probably revisit this list

00:44:24.940 --> 00:44:27.060
 and see if those priority areas, you know,

00:44:27.060 --> 00:44:28.740
 a four through 10 are still in the correct order

00:44:28.740 --> 00:44:32.460
 if we were to do any future area plan.

00:44:32.460 --> 00:44:35.220
 But also we'd take into consideration

00:44:35.220 --> 00:44:36.980
 what we're hearing from the community.

00:44:38.420 --> 00:44:40.100
 Sorry, that was kind of long-winded.

00:44:40.100 --> 00:44:42.180
 I was thinking through that one.

00:44:42.180 --> 00:44:43.020
 - No, it's okay.

00:44:43.020 --> 00:44:44.820
 I just feel like my little neck of the woods,

00:44:44.820 --> 00:44:46.580
 like it's like the forgotten stepchild.

00:44:46.580 --> 00:44:49.060
 Like there's nothing happening over where I live.

00:44:49.060 --> 00:44:50.860
 I don't even think it's on that map.

00:44:50.860 --> 00:44:53.900
 - I think you raise a great question.

00:44:53.900 --> 00:44:58.460
 So, I mean, if that's an area that the commission feels

00:44:58.460 --> 00:45:02.540
 needs to be studied, you can make that recommendation.

00:45:02.540 --> 00:45:04.460
 We could also work it through council's

00:45:04.460 --> 00:45:05.740
 two minute pitch process.

00:45:05.740 --> 00:45:06.980
 I'd have to give a little more thought to it,

00:45:06.980 --> 00:45:11.260
 but if we were to go through and identify

00:45:11.260 --> 00:45:14.100
 future area plans that would need to be done,

00:45:14.100 --> 00:45:16.260
 we would look for that kind of feedback.

00:45:16.260 --> 00:45:18.140
 - We just, we have a lot going on there.

00:45:18.140 --> 00:45:22.340
 And because we're the very southern most part of Denton

00:45:22.340 --> 00:45:26.500
 where it has a border with North Lake,

00:45:26.500 --> 00:45:29.100
 like there's a lot of stuff happening there

00:45:29.100 --> 00:45:32.340
 and a lot of concerns by current residents.

00:45:32.340 --> 00:45:36.300
 And I'm sure once landmark starts opening up sales

00:45:36.300 --> 00:45:38.940
 and we're gonna have residents there,

00:45:38.940 --> 00:45:41.500
 there are also going to be some future concerns

00:45:41.500 --> 00:45:45.460
 that I think people just don't even realize yet.

00:45:45.460 --> 00:45:46.780
 - Yeah, I can understand why you say that.

00:45:46.780 --> 00:45:50.220
 And, you know, it probably really hasn't crossed our minds

00:45:50.220 --> 00:45:51.860
 in the past really to focus on the year

00:45:51.860 --> 00:45:54.220
 because with the ropes and ranch zoning

00:45:54.220 --> 00:45:56.740
 that was customized and put in place for that area,

00:45:56.740 --> 00:45:59.780
 then you couple that with all of the work that was done

00:45:59.780 --> 00:46:03.540
 with the formerly known as Hunter landmark development

00:46:03.540 --> 00:46:06.100
 and coal ranch with the municipal management districts,

00:46:06.100 --> 00:46:07.660
 the master plan community zoning

00:46:07.660 --> 00:46:09.220
 that's already in place there.

00:46:09.220 --> 00:46:14.420
 We might've felt like we had checked the box and moved on,

00:46:14.420 --> 00:46:17.340
 but you're right, there's, you know,

00:46:17.340 --> 00:46:20.860
 because it's already has the zoning entitlements in place,

00:46:20.860 --> 00:46:24.900
 we probably haven't viewed that area as much of a priority,

00:46:24.900 --> 00:46:28.140
 but it could definitely find itself resonating

00:46:28.140 --> 00:46:30.620
 near the top of the list sooner or later.

00:46:30.620 --> 00:46:32.860
 - Maybe this is a great conversation to have

00:46:32.860 --> 00:46:35.780
 with Councilman Hall and myself and staff

00:46:35.780 --> 00:46:38.260
 about what's happening over there

00:46:38.260 --> 00:46:42.860
 and what are some potential immediate needs.

00:46:42.860 --> 00:46:46.220
 - Yeah, I think that's fine.

00:46:46.220 --> 00:46:47.620
 I would definitely love to sit down

00:46:47.620 --> 00:46:49.020
 and visit with you further on it.

00:46:49.020 --> 00:46:52.020
 And then we could, and then if you feel it's necessary

00:46:52.020 --> 00:46:54.140
 to go to Councilman Hall and we can definitely talk

00:46:54.140 --> 00:46:55.700
 about what those next steps might be

00:46:55.700 --> 00:46:57.060
 or if that's a subsequent conversation

00:46:57.060 --> 00:46:58.780
 with the planning and zoning commission,

00:46:58.780 --> 00:46:59.860
 but we could look into that.

00:46:59.860 --> 00:47:02.020
 I think Hillary has an idea too.

00:47:02.020 --> 00:47:03.740
 - Oh, my idea is to take this offline

00:47:03.740 --> 00:47:05.620
 so we stay to posting.

00:47:05.620 --> 00:47:06.980
 - Oh, okay, all right.

00:47:06.980 --> 00:47:11.180
 Thank you for putting me in check.

00:47:11.180 --> 00:47:16.180
 - No, you could finish the, you got to the right place.

00:47:16.180 --> 00:47:17.580
 - Okay, very good point.

00:47:17.580 --> 00:47:18.660
 Any other questions?

00:47:18.660 --> 00:47:22.700
 - I noticed on one of the slides you said

00:47:22.700 --> 00:47:24.820
 as part of the planning is that the city

00:47:24.820 --> 00:47:26.580
 hires a consultant.

00:47:26.580 --> 00:47:29.060
 So a consultant usually writes

00:47:29.060 --> 00:47:31.980
 the small area plans for the city.

00:47:31.980 --> 00:47:34.940
 - You know, the city and Tina may wanna correct me

00:47:34.940 --> 00:47:38.500
 or weigh in, but the city has done it both ways.

00:47:38.500 --> 00:47:41.100
 They've done them in house.

00:47:41.100 --> 00:47:43.380
 You know, they're pretty big projects

00:47:43.380 --> 00:47:44.860
 and there are some communities

00:47:44.860 --> 00:47:46.500
 that are called small area plans,

00:47:46.500 --> 00:47:50.660
 but in Denton, we make them, we supersize our area plans.

00:47:50.660 --> 00:47:54.460
 And so they're often so large

00:47:54.460 --> 00:47:56.580
 that additional help is needed,

00:47:56.580 --> 00:47:58.220
 but Tina may wanna weigh in.

00:47:58.220 --> 00:47:59.460
 - Julie's right.

00:47:59.460 --> 00:48:01.500
 We don't necessarily have to retain a consultant.

00:48:01.500 --> 00:48:02.740
 On these area plans we did

00:48:02.740 --> 00:48:04.900
 because of their size and scale,

00:48:04.900 --> 00:48:08.780
 also with the size of our staff, we were limited, right?

00:48:08.780 --> 00:48:10.900
 When we hire a consultant team,

00:48:10.900 --> 00:48:13.780
 we really view them as an extension of our team, right?

00:48:13.780 --> 00:48:16.020
 We are one project team.

00:48:16.020 --> 00:48:18.420
 They just help provide an additional level of expertise

00:48:18.420 --> 00:48:20.940
 that we may not necessarily have in house.

00:48:20.940 --> 00:48:24.460
 And then, so we, you know, bring them to the table

00:48:24.460 --> 00:48:26.660
 to be able to help us accomplish the effort.

00:48:26.660 --> 00:48:31.620
 There are consultants who, in the case of Southeast Denton,

00:48:31.620 --> 00:48:34.300
 one of the sub-consultants on that team

00:48:34.300 --> 00:48:35.620
 has made it his life career

00:48:35.620 --> 00:48:38.580
 working with communities that have experienced past harm.

00:48:38.580 --> 00:48:40.940
 And so he really brought unique perspective

00:48:40.940 --> 00:48:42.420
 in helping our team work with that

00:48:42.420 --> 00:48:44.900
 'cause no one else on our team had that experience.

00:48:44.900 --> 00:48:46.900
 And so we'll bring those consultants in

00:48:46.900 --> 00:48:48.900
 for those levels of specialty experience.

00:48:48.900 --> 00:48:50.940
 Our design downtown Denton plan,

00:48:50.940 --> 00:48:54.220
 Zach and his team that we brought on, super helpful.

00:48:54.220 --> 00:48:56.300
 They've done numerous downtown plans

00:48:56.300 --> 00:48:58.180
 and really can speak to

00:48:58.180 --> 00:49:00.060
 some successful implementation efforts

00:49:00.060 --> 00:49:01.980
 'cause they've been involved in that as well.

00:49:01.980 --> 00:49:05.220
 And so they, again, we're an extension of our team

00:49:05.220 --> 00:49:07.060
 to allow us to be able to partner with them

00:49:07.060 --> 00:49:08.620
 to help us create a plan

00:49:08.620 --> 00:49:11.540
 that is most appropriate for our community.

00:49:11.540 --> 00:49:13.600
 I viewed it also as an opportunity for my team

00:49:13.600 --> 00:49:15.180
 to learn from those experts

00:49:15.180 --> 00:49:17.900
 because then, you know, we've got great talent

00:49:17.900 --> 00:49:20.460
 on our staff as well who, you know,

00:49:20.460 --> 00:49:22.140
 depending upon the type of area plan

00:49:22.140 --> 00:49:22.980
 that we were working on,

00:49:22.980 --> 00:49:25.620
 it's possible we could accomplish it all in house.

00:49:25.620 --> 00:49:27.940
 It's possible we might need to bring somebody on

00:49:27.940 --> 00:49:29.300
 to help us with the effort.

00:49:29.300 --> 00:49:31.020
 So it's not a must.

00:49:31.020 --> 00:49:33.100
 It is definitely was a huge benefit for us

00:49:33.100 --> 00:49:34.700
 on those particular two projects.

00:49:34.700 --> 00:49:37.360
 And even on the Northeast Denton plan,

00:49:37.360 --> 00:49:39.140
 just given the level of public engagement

00:49:39.140 --> 00:49:40.500
 that we were doing also on that plan

00:49:40.500 --> 00:49:42.500
 and the complexities associated with it.

00:49:42.500 --> 00:49:47.540
 - Just a comment.

00:49:47.540 --> 00:49:50.600
 Can you go back to your slide that had frustrate on it?

00:49:50.600 --> 00:49:55.100
 - The area plan or the overlay?

00:49:55.100 --> 00:49:59.100
 - Well, which it has frustrated, is it the overlay?

00:49:59.100 --> 00:50:01.180
 Where it gives us the date that was updated.

00:50:01.180 --> 00:50:04.120
 That was the plan, I guess, the area plan.

00:50:04.120 --> 00:50:08.620
 1999, gosh, that might need to be looked at

00:50:08.620 --> 00:50:09.980
 just as a comment.

00:50:09.980 --> 00:50:12.140
 I know it's not a priority and, you know,

00:50:12.140 --> 00:50:14.500
 we've moved a lot of our businesses

00:50:14.500 --> 00:50:19.420
 and activity from Fry Street to downtown.

00:50:19.420 --> 00:50:21.800
 Not sure how long that's been in place,

00:50:21.800 --> 00:50:26.800
 but just speaking for my area of representation.

00:50:27.900 --> 00:50:32.900
 - Yes, and so we adopted the Oak gateway area plan,

00:50:32.900 --> 00:50:37.580
 those recommendations and vision.

00:50:37.580 --> 00:50:40.380
 That one kind of enveloped Fry Street.

00:50:40.380 --> 00:50:43.800
 I don't think it was necessarily focused on Fry Street.

00:50:43.800 --> 00:50:47.180
 So I think it kind of maybe split both,

00:50:47.180 --> 00:50:50.740
 but yeah, it's something we'll take note of

00:50:50.740 --> 00:50:54.380
 'cause they should be updated regularly.

00:50:54.380 --> 00:50:57.460
 - Keep in mind, we have not, as I've understood it

00:50:57.460 --> 00:51:00.420
 and I looked at Haley and Julie many times and Sean,

00:51:00.420 --> 00:51:03.820
 because they have the most tenure here compared to myself.

00:51:03.820 --> 00:51:08.440
 But we have done those area plans from time to time,

00:51:08.440 --> 00:51:11.120
 but we have not had like staff fully dedicated

00:51:11.120 --> 00:51:12.280
 to be able to do those efforts.

00:51:12.280 --> 00:51:14.460
 A lot of times those area plans are done

00:51:14.460 --> 00:51:16.420
 from a reactive point of view as well,

00:51:16.420 --> 00:51:18.300
 just because of issues that are going on

00:51:18.300 --> 00:51:19.900
 in a particular area of the community.

00:51:19.900 --> 00:51:23.500
 And so we were able to allocate the resources

00:51:23.500 --> 00:51:25.780
 to be able to do so.

00:51:25.780 --> 00:51:28.860
 We're fortunate now with the size of the staff that we have

00:51:28.860 --> 00:51:31.200
 and especially having kind of a small

00:51:31.200 --> 00:51:32.940
 long range planning team.

00:51:32.940 --> 00:51:33.780
 They're still responsible

00:51:33.780 --> 00:51:35.460
 for doing development review as well.

00:51:35.460 --> 00:51:38.220
 But we're a little better positioned for us

00:51:38.220 --> 00:51:40.860
 to be able to do projects of this nature.

00:51:40.860 --> 00:51:45.500
 So if it requires additional budgetary financial resources,

00:51:45.500 --> 00:51:48.780
 then the projects are gonna be paused for the time being.

00:51:48.780 --> 00:51:51.500
 But we definitely have the talent in-house

00:51:51.500 --> 00:51:53.700
 where we can visit certain areas.

00:51:53.700 --> 00:51:56.060
 And like I said, a lot of our effort,

00:51:56.060 --> 00:51:59.300
 we're responsive to what is the Mesa or the foremost need,

00:51:59.300 --> 00:52:01.580
 which the statutory requirements are the plats

00:52:01.580 --> 00:52:02.700
 and the zoning compliance plans

00:52:02.700 --> 00:52:03.800
 and the civil engineering plans.

00:52:03.800 --> 00:52:05.880
 But we do try to make sure that we have more of a focus

00:52:05.880 --> 00:52:07.740
 with our long range planning now,

00:52:07.740 --> 00:52:09.380
 just because we have not fully benefited

00:52:09.380 --> 00:52:10.540
 from that in the past.

00:52:10.540 --> 00:52:16.940
 - Well, it takes time, right?

00:52:16.940 --> 00:52:19.060
 - Thank you. - Thank you, Julie.

00:52:19.060 --> 00:52:22.600
 So since y'all voted me as temporary chair,

00:52:22.600 --> 00:52:25.620
 I have to go ahead and say, I missed something already.

00:52:25.620 --> 00:52:28.700
 So we're gonna go back and review the regular agenda

00:52:28.700 --> 00:52:30.900
 and we're gonna go to item four,

00:52:30.900 --> 00:52:33.540
 items for individual consideration.

00:52:33.540 --> 00:52:36.140
 Now we're gonna talk about, to start off,

00:52:36.140 --> 00:52:41.140
 plat FP25-0018, Mia?

00:52:41.140 --> 00:52:42.580
 - Yes, sir.

00:52:42.580 --> 00:52:45.100
 Oh, I'm not trying to go to Zoom.

00:52:45.100 --> 00:52:47.740
 That's gonna pop up, so, so sorry.

00:52:47.740 --> 00:52:51.500
 Okay, combined plots.

00:52:52.600 --> 00:52:55.340
 (mouse clicking)

00:52:55.340 --> 00:53:02.020
 Okay, Mia Hines, senior planner.

00:53:02.020 --> 00:53:05.740
 This item is a final plat for Hickory Grove, phase four.

00:53:05.740 --> 00:53:08.700
 The Hickory Grove subdivision is located

00:53:08.700 --> 00:53:11.100
 within a municipal utility district

00:53:11.100 --> 00:53:13.900
 located just north of West University Drive

00:53:13.900 --> 00:53:18.540
 with the previous phases sort of moving north, northwest.

00:53:18.540 --> 00:53:22.900
 This phase, phase four, is approximately 80 feet east

00:53:22.900 --> 00:53:25.420
 of Nail and Jackson Road,

00:53:25.420 --> 00:53:28.080
 or the intersection of Nail and Jackson Road

00:53:28.080 --> 00:53:32.240
 and includes approximately 115 acres.

00:53:32.240 --> 00:53:34.860
 At this time, the plat is not ready,

00:53:34.860 --> 00:53:36.940
 or does not meet all the criteria for approval

00:53:36.940 --> 00:53:40.540
 as presented in the DDC, so staff is recommending denial.

00:53:40.540 --> 00:53:43.500
 However, we have no objection to the requested extension,

00:53:43.500 --> 00:53:47.500
 which could be granted to June 25th, 2025.

00:53:47.500 --> 00:53:48.460
 Any questions?

00:53:48.460 --> 00:53:56.260
 - So what exactly is not meeting the requirements right now?

00:53:56.260 --> 00:53:58.660
 - I believe with this one, it's some minor things.

00:53:58.660 --> 00:54:00.340
 I know that they have some notes.

00:54:00.340 --> 00:54:03.340
 It's provided in the backup for sure on the staff analysis,

00:54:03.340 --> 00:54:06.380
 but there are some notes related to gas wells,

00:54:06.380 --> 00:54:09.740
 and then there's some minor sort of detailed things

00:54:09.740 --> 00:54:11.300
 on the plat that they need to address.

00:54:11.300 --> 00:54:13.700
 For the most part, lot sizes, the orientation,

00:54:13.700 --> 00:54:15.640
 it's in line with the phasing plan

00:54:15.640 --> 00:54:16.640
 that was adopted for this,

00:54:16.640 --> 00:54:18.740
 so the bigger picture stuff there, they're ready,

00:54:18.740 --> 00:54:23.300
 and I suspect that they should have it ready for approval

00:54:23.300 --> 00:54:24.820
 by that next extension date,

00:54:24.820 --> 00:54:27.820
 if that works out with the submittal calendar,

00:54:27.820 --> 00:54:29.580
 which I believe it does.

00:54:29.580 --> 00:54:31.080
 - Okay, any other questions?

00:54:31.080 --> 00:54:38.500
 - Excuse me, so is the applicant asking for the extension?

00:54:38.500 --> 00:54:40.580
 - Yes, ma'am. - Thank you.

00:54:40.580 --> 00:54:42.960
 - And that is provided as exhibit six,

00:54:42.960 --> 00:54:45.500
 or five, I believe, in your backup.

00:54:47.340 --> 00:54:50.060
 - And we tend to get a lot of these each meeting,

00:54:50.060 --> 00:54:52.580
 so, okay, well, thank you.

00:54:52.580 --> 00:54:53.700
 - Yes, sir.

00:54:53.700 --> 00:54:58.700
 - We'll move on then to item 4B, FP25-0020.

00:54:58.700 --> 00:55:00.860
 Matt.

00:55:00.860 --> 00:55:08.660
 - Good evening, commission.

00:55:08.660 --> 00:55:11.420
 Matt Bodine, assistant planner,

00:55:11.420 --> 00:55:15.860
 here to present a final plat

00:55:16.660 --> 00:55:21.620
 located approximately 610 feet west of Teesley Lane

00:55:21.620 --> 00:55:24.300
 along Hickory Creek Road.

00:55:24.300 --> 00:55:26.700
 This is about a 10 and a half acre tract

00:55:26.700 --> 00:55:30.940
 for the development of a self-service storage facility.

00:55:30.940 --> 00:55:33.940
 At this time, the plat does not yet meet

00:55:33.940 --> 00:55:35.940
 our criteria for approval,

00:55:35.940 --> 00:55:38.940
 though they are requesting an extension of the review time

00:55:38.940 --> 00:55:41.380
 to a date certain of June 25th,

00:55:41.380 --> 00:55:45.420
 and staff has no objection to their extension request.

00:55:45.420 --> 00:55:47.480
 Here to answer any questions.

00:55:47.480 --> 00:55:51.020
 - Okay, any questions?

00:55:51.020 --> 00:55:55.640
 All right, Matt, thanks. - All right.

00:55:55.640 --> 00:56:00.340
 - Okay, that being said,

00:56:00.340 --> 00:56:02.700
 we'll jump back over into our work session mode.

00:56:15.080 --> 00:56:16.100
 - Okay, well, I've just been told

00:56:16.100 --> 00:56:17.500
 there's a very important notice.

00:56:17.500 --> 00:56:19.100
 Dinner is here, so we're gonna pause,

00:56:19.100 --> 00:56:20.380
 let everybody get some dinner,

00:56:20.380 --> 00:56:21.260
 and then we'll come back

00:56:21.260 --> 00:56:24.580
 and we'll go back into our work session, so.

00:56:24.580 --> 00:56:27.300
 - Okay, I'm gonna call back to order our work session.

00:56:27.300 --> 00:56:30.940
 The time is 616, and to move on,

00:56:30.940 --> 00:56:33.940
 we're going to our work session item 4B.

00:56:33.940 --> 00:56:38.880
 Oh, no, I'm sorry.

00:56:42.580 --> 00:56:47.580
 Yep, 4B, PZ25-131.

00:56:47.580 --> 00:56:50.220
 All right, Mia.

00:56:50.220 --> 00:56:54.780
 Oh, also, before you get started, Mia,

00:56:54.780 --> 00:56:56.020
 for the sake of time,

00:56:56.020 --> 00:56:58.920
 let's just hold all questions until the very end,

00:56:58.920 --> 00:57:00.700
 and that way we can make sure that we get through it.

00:57:00.700 --> 00:57:02.100
 - Cool. - Yeah, thank you.

00:57:02.100 --> 00:57:05.900
 - Mia Hines, senior planner.

00:57:05.900 --> 00:57:10.340
 This item or this work session bootcamp presentation

00:57:10.340 --> 00:57:13.100
 is essentially all other applications.

00:57:13.100 --> 00:57:15.320
 This is everything but the kitchen sink, a little bit.

00:57:15.320 --> 00:57:16.500
 Of all other applications

00:57:16.500 --> 00:57:18.380
 that the Planning and Zoning Commission considers

00:57:18.380 --> 00:57:21.180
 that doesn't necessarily fall in line with

00:57:21.180 --> 00:57:23.220
 or fall into the categories of like plats

00:57:23.220 --> 00:57:24.300
 and other things that we've covered

00:57:24.300 --> 00:57:27.180
 within this bootcamp series.

00:57:27.180 --> 00:57:30.100
 So, so far, I just want to show this slide

00:57:30.100 --> 00:57:33.100
 because so far, to remind you all what we've covered,

00:57:33.100 --> 00:57:34.540
 Julie just did a great presentation

00:57:34.540 --> 00:57:37.260
 over the area plans and zoning overlays.

00:57:37.260 --> 00:57:39.940
 Earlier this year, I did that planning one-on-one bootcamp

00:57:39.940 --> 00:57:40.820
 that talked a little bit about

00:57:40.820 --> 00:57:43.860
 comprehensive planning process as well as the overview

00:57:43.860 --> 00:57:45.340
 of some of the development applications

00:57:45.340 --> 00:57:47.220
 and process that you all see.

00:57:47.220 --> 00:57:50.020
 We've also done zoning and PDs,

00:57:50.020 --> 00:57:53.420
 SUPs, annexations, platting, and subdivision variances,

00:57:53.420 --> 00:57:55.820
 and today's presentation,

00:57:55.820 --> 00:57:59.140
 we are gonna be talking about alternative ESA plans,

00:57:59.140 --> 00:58:03.500
 historic landmarks and district designations,

00:58:03.500 --> 00:58:06.840
 DDC tax amendments, policy plan amendments a little bit,

00:58:06.840 --> 00:58:10.540
 and then some special zoning compliance plan applications

00:58:10.540 --> 00:58:14.140
 that the commission is responsible for reviewing.

00:58:14.140 --> 00:58:17.660
 So we'll start with those alternative

00:58:17.660 --> 00:58:22.660
 environmentally sensitive area plans or the AESA plans.

00:58:22.660 --> 00:58:27.380
 For a little overview about what we're talking about here

00:58:27.380 --> 00:58:29.300
 are those environmentally sensitive areas,

00:58:29.300 --> 00:58:32.300
 specifically cross timbers upland habitat,

00:58:32.300 --> 00:58:35.020
 riparian buffer or water-related habitat areas,

00:58:35.020 --> 00:58:36.580
 and undeveloped floodplain.

00:58:36.580 --> 00:58:38.780
 Those cross timber upland habitat areas

00:58:38.780 --> 00:58:41.740
 are those remnants of eastern cross timber forests

00:58:41.740 --> 00:58:42.700
 within the city.

00:58:42.700 --> 00:58:46.340
 That riparian buffer area is the area within 50 to 100 feet

00:58:46.340 --> 00:58:48.180
 of the centerline of a stream,

00:58:48.180 --> 00:58:50.900
 just depending on the watershed size,

00:58:50.900 --> 00:58:52.980
 and then the undeveloped floodplain is that area

00:58:52.980 --> 00:58:55.060
 within the FEMA 100-year floodplain.

00:58:55.060 --> 00:58:58.860
 And essentially, the DDC has different ways

00:58:58.860 --> 00:59:00.940
 that these areas are to be preserved

00:59:00.940 --> 00:59:05.940
 or if developed in how they are to be treated.

00:59:06.100 --> 00:59:08.900
 The alternative ESA plan provides an opportunities

00:59:08.900 --> 00:59:13.300
 for developers to offer things outside

00:59:13.300 --> 00:59:15.980
 of what the DDC would allow for,

00:59:15.980 --> 00:59:17.780
 but still within certain limits

00:59:17.780 --> 00:59:21.500
 that ultimately yield to a higher quality engineered plan

00:59:21.500 --> 00:59:25.220
 and mitigation for environmentally sensitive areas

00:59:25.220 --> 00:59:27.500
 in relation to developments.

00:59:27.500 --> 00:59:30.540
 So typically, Christy Upton is usually the one

00:59:30.540 --> 00:59:33.900
 that presents alternative ESA plans to you all,

00:59:33.900 --> 00:59:36.740
 and she'll come to you with a little bit of information

00:59:36.740 --> 00:59:37.780
 similar to this.

00:59:37.780 --> 00:59:41.140
 Well, she'll start off with the ESA field assessment

00:59:41.140 --> 00:59:42.700
 sort of site inventory,

00:59:42.700 --> 00:59:45.900
 letting you all know what environmentally sensitive areas

00:59:45.900 --> 00:59:48.980
 specifically are on the site of the proposed development.

00:59:48.980 --> 00:59:50.500
 She'll also provide some information

00:59:50.500 --> 00:59:52.100
 on the proposed development itself,

00:59:52.100 --> 00:59:54.380
 what land uses are being proposed,

00:59:54.380 --> 00:59:59.380
 as well as sort of how the environmentally sensitive areas

00:59:59.380 --> 01:00:01.300
 are to be disturbed.

01:00:01.300 --> 01:00:03.700
 And then she'll provide you with a mitigation plan

01:00:03.700 --> 01:00:05.900
 that the engineering or the developers

01:00:05.900 --> 01:00:07.780
 provides the city staff for review

01:00:07.780 --> 01:00:11.620
 that lists how the development proposes

01:00:11.620 --> 01:00:14.460
 with their disturbance

01:00:14.460 --> 01:00:16.420
 of these environmentally sensitive areas,

01:00:16.420 --> 01:00:18.940
 how they propose to sort of mitigate for that

01:00:18.940 --> 01:00:22.460
 and ultimately develop a higher quality product.

01:00:22.460 --> 01:00:25.340
 So that's ESAs.

01:00:25.340 --> 01:00:29.100
 Next is historic landmarks and districts.

01:00:29.100 --> 01:00:32.860
 I start with this slide to make sure we're sort of all clear

01:00:32.860 --> 01:00:35.300
 on the difference between a historic landmark

01:00:35.300 --> 01:00:38.220
 and a conservation or historic district.

01:00:38.220 --> 01:00:40.820
 Notably, historic landmarks are those buildings,

01:00:40.820 --> 01:00:44.060
 districts, objects, sites, or structures

01:00:44.060 --> 01:00:46.820
 that are recognized by the state or the US nationally.

01:00:46.820 --> 01:00:48.420
 They come with a plaque of some sort.

01:00:48.420 --> 01:00:50.340
 And those conservation and historic districts

01:00:50.340 --> 01:00:52.060
 are more like zoning overlays

01:00:52.060 --> 01:00:53.780
 that we just sort of learned about

01:00:53.780 --> 01:00:55.260
 that are recognized at a city level

01:00:55.260 --> 01:00:58.220
 and passed locally at a city level.

01:00:58.220 --> 01:01:01.700
 So here's some examples of some of those landmarks

01:01:01.700 --> 01:01:03.460
 and districts that we have in the city.

01:01:03.460 --> 01:01:05.900
 Landmarks are included in those images on the left.

01:01:05.900 --> 01:01:09.300
 The courthouse, for example, is one of those landmarks.

01:01:09.300 --> 01:01:11.780
 The districts, like I said, are more like an overlay.

01:01:11.780 --> 01:01:14.300
 So those maps that you see there to the right,

01:01:14.300 --> 01:01:17.180
 we have that Oak Hickory Historic District,

01:01:17.180 --> 01:01:18.660
 that Belle Avenue Historic District,

01:01:18.660 --> 01:01:20.740
 and that West Oak Historic District

01:01:20.740 --> 01:01:23.820
 that all come with, as Julie stated,

01:01:23.820 --> 01:01:25.900
 some additional design requirements and standards

01:01:25.900 --> 01:01:29.980
 to sort of preserve the historic character in that area.

01:01:29.980 --> 01:01:31.820
 Where this body comes into play

01:01:31.820 --> 01:01:37.940
 is after the Historic Landmark Commission reviews

01:01:37.940 --> 01:01:41.220
 these applications for historic significance.

01:01:41.220 --> 01:01:43.540
 This body provides a recommendation to the city council

01:01:43.540 --> 01:01:46.220
 and then they ultimately make a decision.

01:01:46.220 --> 01:01:48.980
 This is a little bit different,

01:01:48.980 --> 01:01:51.340
 not too many applications that this body sees

01:01:51.340 --> 01:01:54.140
 also is seen by other boards.

01:01:54.140 --> 01:01:55.980
 So Cameron typically provides,

01:01:55.980 --> 01:01:57.540
 she's our historic preservation officer,

01:01:57.540 --> 01:01:59.260
 she typically provides an overview

01:01:59.260 --> 01:02:02.220
 of those presentations when that comes forward.

01:02:02.220 --> 01:02:06.980
 And then this, once those items are passed,

01:02:06.980 --> 01:02:11.980
 is a map showing all of the city's historic districts

01:02:11.980 --> 01:02:15.980
 as well as all the historic landmarks.

01:02:15.980 --> 01:02:18.780
 So those dots are the historic landmark points

01:02:18.780 --> 01:02:19.740
 that we have throughout the city,

01:02:19.740 --> 01:02:23.220
 and then the sort of shaded area are those districts.

01:02:23.220 --> 01:02:25.780
 And this is available on the city's website as well.

01:02:27.340 --> 01:02:30.220
 Okay, so the next category or the next type of application

01:02:30.220 --> 01:02:34.900
 and I wanna talk about is the DDC text amendments.

01:02:34.900 --> 01:02:36.940
 These are simply what they are.

01:02:36.940 --> 01:02:39.340
 They are amendments to the regulations

01:02:39.340 --> 01:02:41.740
 as provided in the DIN development code.

01:02:41.740 --> 01:02:46.060
 And this body is a recommendation body for that,

01:02:46.060 --> 01:02:48.380
 and then city council approves it ultimately.

01:02:48.380 --> 01:02:54.700
 DDC amendments are initiated

01:02:54.700 --> 01:02:56.660
 through various different reasons.

01:02:56.660 --> 01:02:58.420
 Sometimes it's city direction,

01:02:58.420 --> 01:03:02.740
 city council has asked staff to take up a specific task.

01:03:02.740 --> 01:03:05.220
 Or sometimes there's industry changes or challenges

01:03:05.220 --> 01:03:07.340
 that we as staff have noticed

01:03:07.340 --> 01:03:08.700
 throughout the development process

01:03:08.700 --> 01:03:10.180
 or something along those lines.

01:03:10.180 --> 01:03:12.020
 And we sort of feel that there is a need

01:03:12.020 --> 01:03:14.780
 to take the initiative and update the code

01:03:14.780 --> 01:03:17.620
 to meet those challenges.

01:03:17.620 --> 01:03:20.300
 And then sometimes it's legislative challenges and changes.

01:03:20.300 --> 01:03:23.700
 So I know we're, excuse me, in a session right now

01:03:23.700 --> 01:03:25.060
 where we're gonna probably have to develop

01:03:25.060 --> 01:03:27.140
 or update our DIN development code

01:03:27.140 --> 01:03:29.620
 with one of these DDC amendments

01:03:29.620 --> 01:03:32.740
 or a few of these DDC amendment text

01:03:32.740 --> 01:03:35.940
 because of we're having to respond to legislative changes

01:03:35.940 --> 01:03:37.740
 and things at the state level.

01:03:37.740 --> 01:03:40.980
 Once that idea starts for DDC text amendments,

01:03:40.980 --> 01:03:43.580
 we move on to staff research and analysis.

01:03:43.580 --> 01:03:45.380
 That's done throughout the whole process,

01:03:45.380 --> 01:03:47.420
 but a part of that research and analysis

01:03:47.420 --> 01:03:50.260
 is community engagement as well as sometimes,

01:03:50.260 --> 01:03:51.140
 depending on the topic,

01:03:51.140 --> 01:03:54.340
 taking it forward to the development code review committee,

01:03:54.340 --> 01:03:56.020
 which is made up of some of this body

01:03:56.020 --> 01:03:57.780
 and some of city council.

01:03:57.780 --> 01:03:59.980
 Once we've done all that research and analysis back and forth,

01:03:59.980 --> 01:04:02.140
 staff will form a recommendation on the topic

01:04:02.140 --> 01:04:03.540
 and those amendment changes.

01:04:03.540 --> 01:04:06.020
 And then it'll come before this body.

01:04:06.020 --> 01:04:07.540
 This body will make a recommendation.

01:04:07.540 --> 01:04:10.500
 City council will make a final decision

01:04:10.500 --> 01:04:13.860
 and then it'll be added to the DDC as an update.

01:04:13.860 --> 01:04:20.660
 The next class of application that I wanna talk about

01:04:20.660 --> 01:04:23.260
 is comprehensive plan amendments.

01:04:23.260 --> 01:04:25.420
 Like I said, we did that comprehensive planning process

01:04:25.420 --> 01:04:26.860
 overview in February.

01:04:26.860 --> 01:04:28.420
 Julie just gave a good presentation

01:04:28.420 --> 01:04:30.860
 over area planning and that nature,

01:04:30.860 --> 01:04:33.460
 but I just wanted to just a little bit talk about

01:04:33.460 --> 01:04:37.500
 or mention that this application process

01:04:37.500 --> 01:04:39.060
 does come before this body.

01:04:39.060 --> 01:04:42.420
 And of course, in the event that any of the codes

01:04:42.420 --> 01:04:46.020
 that Julie mentioned needs to be amended,

01:04:46.020 --> 01:04:49.220
 you all would be a part of that process.

01:04:49.220 --> 01:04:52.020
 This is that future land use map

01:04:52.020 --> 01:04:56.860
 that's adopted with the Denton 2040 comprehensive plan.

01:04:56.860 --> 01:04:59.180
 Typically when a cop plan amendments

01:04:59.180 --> 01:05:01.140
 just plain come before you all,

01:05:01.140 --> 01:05:05.260
 it is to amend a future land use designation on this map.

01:05:05.260 --> 01:05:07.780
 So it's to change one color to another,

01:05:07.780 --> 01:05:11.060
 and of course what that color represents.

01:05:11.060 --> 01:05:13.540
 An example could be one of the things

01:05:13.540 --> 01:05:16.140
 that we're considering I think is the 380 corridor area,

01:05:16.140 --> 01:05:18.580
 potentially doing a comprehensive plan amendment

01:05:18.580 --> 01:05:20.460
 in that area that would ultimately change

01:05:20.460 --> 01:05:23.300
 what that future land use designation is for that area.

01:05:23.300 --> 01:05:26.340
 Similarly, you have a mobility plan amendment

01:05:26.340 --> 01:05:28.260
 on your agenda this evening.

01:05:28.260 --> 01:05:31.660
 And typically it is a request to change one of the colors

01:05:31.660 --> 01:05:33.140
 on this map essentially.

01:05:33.140 --> 01:05:37.580
 And that's either reclassifying one of the roadways

01:05:37.580 --> 01:05:44.580
 shown on this map or adjusting the structure of those.

01:05:44.580 --> 01:05:48.380
 And then lastly, one of the other things

01:05:48.380 --> 01:05:49.980
 or the other thing that I wanted to mention

01:05:49.980 --> 01:05:53.060
 was those special sort of one-off site plan applications

01:05:53.060 --> 01:05:56.940
 that this body has to review every once in a while.

01:05:56.940 --> 01:05:58.340
 And typically in the past,

01:05:58.340 --> 01:06:00.700
 our plan development districts require the adoption

01:06:00.700 --> 01:06:04.020
 of a detailed site plan prior to development

01:06:04.020 --> 01:06:05.420
 being allowed to develop.

01:06:05.420 --> 01:06:07.820
 And so those will come back before this body.

01:06:07.820 --> 01:06:09.740
 The plan development amendment actually

01:06:09.740 --> 01:06:13.540
 that I have on tonight's agenda came before this body,

01:06:13.540 --> 01:06:15.460
 I believe in July of last year,

01:06:15.460 --> 01:06:18.220
 with a detailed site plan for that to be adopted.

01:06:18.220 --> 01:06:20.420
 So you'll see cases like that.

01:06:20.420 --> 01:06:21.500
 And then one of the other cases,

01:06:21.500 --> 01:06:24.140
 I think that I'll have one of these next month

01:06:24.140 --> 01:06:26.900
 is a razor ranch overlay site plan

01:06:26.900 --> 01:06:28.580
 or zoning compliance plan,

01:06:28.580 --> 01:06:30.580
 which per that overlay standards,

01:06:30.580 --> 01:06:33.340
 all site plans for development south of 380

01:06:33.340 --> 01:06:36.020
 has to come before this body for final approval.

01:06:36.020 --> 01:06:38.060
 So typically if it's a site plan

01:06:38.060 --> 01:06:39.580
 as a part of a plan development amendment

01:06:39.580 --> 01:06:41.380
 or something along those lines,

01:06:41.380 --> 01:06:43.660
 that comes to this body for recommendation.

01:06:43.660 --> 01:06:45.700
 And then because it's an ordinance and a zoning change,

01:06:45.700 --> 01:06:48.940
 it does have to get approved, final approval by city council.

01:06:48.940 --> 01:06:50.460
 Those razor ranch applications,

01:06:50.460 --> 01:06:53.840
 this body is the final recommending or approval body.

01:06:53.840 --> 01:06:57.240
 And this is an example of that.

01:06:57.240 --> 01:06:59.620
 This one is for that Razor Town Center.

01:06:59.620 --> 01:07:03.540
 That's a multifamily development south of 380,

01:07:03.540 --> 01:07:04.820
 located in Razor.

01:07:04.820 --> 01:07:07.860
 And typically I'll present the basic facts

01:07:07.860 --> 01:07:09.180
 of what the development is proposing,

01:07:09.180 --> 01:07:11.300
 the site plans, landscape plans,

01:07:11.300 --> 01:07:13.660
 elevations and things of that nature.

01:07:13.660 --> 01:07:17.340
 And then how it stacks up against the criteria for approval.

01:07:17.340 --> 01:07:21.700
 That pretty much concludes my presentation.

01:07:21.700 --> 01:07:24.580
 I know that was a lot of different topic areas,

01:07:24.580 --> 01:07:27.220
 but I'll happily take any questions or comments

01:07:27.220 --> 01:07:28.740
 that you have at this time.

01:07:28.740 --> 01:07:34.540
 - Okay, any questions?

01:07:34.540 --> 01:07:37.360
 All right, good job.

01:07:37.360 --> 01:07:38.200
 Thank you.

01:07:43.660 --> 01:07:44.500
 Thank you.

01:07:44.500 --> 01:07:50.580
 - Okay, well, with that being said, that's all we have.

01:07:50.580 --> 01:07:54.460
 So I'm gonna adjourn the work session at 6.27 PM.

01:07:54.460 --> 01:08:00.100
 - Good evening.

01:08:00.100 --> 01:08:01.780
 Welcome to the Planning and Zoning Commission

01:08:01.780 --> 01:08:03.220
 meeting tonight.

01:08:03.220 --> 01:08:04.840
 I'll be acting chair tonight,

01:08:04.840 --> 01:08:08.460
 and I will call this meeting to order at 6.42.

01:08:08.460 --> 01:08:12.800
 And with that being said, we do have a quorum present.

01:08:12.800 --> 01:08:14.860
 So the next order of business is to move on

01:08:14.860 --> 01:08:17.500
 to the Pledge of Allegiance to the U.S. flag, Texas flag.

01:08:17.500 --> 01:08:19.100
 So please stand and join me.

01:08:19.100 --> 01:08:21.060
 Pledge of Allegiance.

01:08:21.060 --> 01:08:26.300
 - I pledge allegiance to the flag

01:08:26.300 --> 01:08:28.620
 of the United States of America,

01:08:28.620 --> 01:08:31.420
 and to the republic for which it stands,

01:08:31.420 --> 01:08:34.980
 one nation under God, indivisible,

01:08:34.980 --> 01:08:37.140
 with liberty and justice for all.

01:08:37.140 --> 01:08:42.700
 - On the Texas flag, I pledge allegiance to the city

01:08:42.700 --> 01:08:47.700
 of Texas, one state, under God, one indivisible.

01:08:47.700 --> 01:08:53.920
 - Okay.

01:08:53.920 --> 01:08:57.620
 Moving on, I just wanted to make an order of business.

01:08:57.620 --> 01:09:02.000
 So item 5A on the public,

01:09:02.000 --> 01:09:05.980
 on the, yeah, it's on the public hearing portion

01:09:05.980 --> 01:09:07.620
 has been withdrawn.

01:09:07.620 --> 01:09:09.340
 So that will not be considered tonight.

01:09:09.340 --> 01:09:12.000
 We will move on to the next items.

01:09:12.740 --> 01:09:17.740
 So that takes us moving on to item 2A.

01:09:17.740 --> 01:09:21.700
 Basically consider approval of planning

01:09:21.700 --> 01:09:24.220
 and zoning minutes from the last meeting.

01:09:24.220 --> 01:09:26.180
 Commissioner McDuff during the work session

01:09:26.180 --> 01:09:28.660
 pointed out that there were some errors,

01:09:28.660 --> 01:09:30.700
 mainly editorial, clerical errors.

01:09:30.700 --> 01:09:32.660
 So we're actually gonna push that,

01:09:32.660 --> 01:09:35.380
 and we will consider that at the next meeting.

01:09:35.380 --> 01:09:38.660
 And then that takes us on to the consent agenda.

01:09:38.660 --> 01:09:42.020
 And so if there are no questions on the consent agenda,

01:09:42.020 --> 01:09:43.580
 I will entertain a motion.

01:09:43.580 --> 01:09:53.980
 Commissioner Dyer.

01:09:53.980 --> 01:09:56.980
 - I make a motion that we approve the consent agenda

01:09:56.980 --> 01:09:58.540
 as presented.

01:09:58.540 --> 01:09:59.380
 - Okay.

01:09:59.380 --> 01:10:00.500
 Commissioner McDade.

01:10:00.500 --> 01:10:01.880
 - I'll second the motion.

01:10:01.880 --> 01:10:03.820
 - Okay, let's vote.

01:10:11.460 --> 01:10:14.580
 Okay, with that, the consent agenda item passes.

01:10:14.580 --> 01:10:20.580
 And that moves us on to items for individual consideration.

01:10:20.580 --> 01:10:26.940
 Item 4A, FP25-0018, Mia.

01:10:26.940 --> 01:10:37.940
 - Good evening, members of the commission.

01:10:37.940 --> 01:10:39.580
 Mia Hines, senior planner.

01:10:40.700 --> 01:10:44.180
 This item is a final plat of Hickory Grove, phase four.

01:10:44.180 --> 01:10:45.820
 This property is located

01:10:45.820 --> 01:10:47.460
 within a municipal utility district

01:10:47.460 --> 01:10:49.980
 located just north of West University,

01:10:49.980 --> 01:10:53.720
 or between West University, US 380, and Jackson Road.

01:10:53.720 --> 01:10:58.060
 This phase, phase four, is approximately 80 miles east

01:10:58.060 --> 01:11:02.220
 of Jackson Road and FM 156 North.

01:11:02.220 --> 01:11:03.860
 At this time, the plat is not meeting

01:11:03.860 --> 01:11:05.220
 all of our criteria for approval,

01:11:05.220 --> 01:11:06.780
 so we are recommending denial.

01:11:06.780 --> 01:11:08.740
 However, we have no objection

01:11:08.740 --> 01:11:11.020
 to the applicant-requested extension

01:11:11.020 --> 01:11:14.360
 to a date certain of June 25th, 2025.

01:11:14.360 --> 01:11:16.420
 At this time, I will take any questions.

01:11:16.420 --> 01:11:20.580
 - Okay, are there any questions for Mia?

01:11:20.580 --> 01:11:23.820
 I'm gonna entertain a motion.

01:11:23.820 --> 01:11:24.660
 Thanks, Mia.

01:11:24.660 --> 01:11:37.580
 Commissioner McDuff.

01:11:38.940 --> 01:11:41.040
 - Motion to approve the extension.

01:11:41.040 --> 01:11:47.140
 - Okay, to the date certain of June 25th, okay, okay.

01:11:47.140 --> 01:11:50.780
 - I'll second the motion.

01:11:50.780 --> 01:11:53.380
 - Okay, let's vote.

01:11:53.380 --> 01:12:05.620
 Okay, and the item passes.

01:12:05.620 --> 01:12:10.620
 That takes us on to item 4B, FP25-0020.

01:12:10.620 --> 01:12:15.560
 Matt.

01:12:15.560 --> 01:12:18.300
 - Good evening, Commission.

01:12:18.300 --> 01:12:20.340
 Matt Bodine, Assistant Planner,

01:12:20.340 --> 01:12:22.460
 here to present a request for approval

01:12:22.460 --> 01:12:24.420
 of the final plat of lot one,

01:12:24.420 --> 01:12:27.740
 block B, Hickory Creek Center addition.

01:12:27.740 --> 01:12:30.220
 The approximately 10 and a half acre track

01:12:30.220 --> 01:12:33.140
 is located on the south side of Hickory Street,

01:12:33.140 --> 01:12:36.660
 about 610 feet west of Teesley Lane,

01:12:36.660 --> 01:12:38.860
 and this is for the purpose of developing

01:12:38.860 --> 01:12:41.740
 a self-service storage facility.

01:12:41.740 --> 01:12:43.980
 At this time, the final plat does not meet

01:12:43.980 --> 01:12:47.340
 our criteria for approval, so we cannot recommend approval.

01:12:47.340 --> 01:12:50.300
 However, we have no objection to the requested

01:12:50.300 --> 01:12:54.020
 plat review extension to a date certain of June 25th.

01:12:54.020 --> 01:12:59.980
 - Okay, are there any questions for Matt?

01:12:59.980 --> 01:13:01.580
 If not, I'll entertain a motion.

01:13:03.580 --> 01:13:05.580
 - Okay, Commissioner McDuff.

01:13:05.580 --> 01:13:09.260
 - Motion to approve this first extension.

01:13:09.260 --> 01:13:19.260
 - To the date certain June 25th?

01:13:19.260 --> 01:13:21.780
 - To a date certain of June 25th.

01:13:21.780 --> 01:13:23.200
 - Okay, Commissioner McDade.

01:13:23.200 --> 01:13:25.520
 - I'll second the motion.

01:13:25.520 --> 01:13:28.460
 - Okay, let's vote.

01:13:33.140 --> 01:13:38.140
 - Okay, motion passes.

01:13:38.140 --> 01:13:43.220
 That takes us, moves us on to item five, public hearings.

01:13:43.220 --> 01:13:48.220
 And as a reminder, item 5A, MPA 24-003 has been withdrawn,

01:13:48.220 --> 01:13:52.000
 and so it will not be considered tonight.

01:13:52.000 --> 01:13:57.000
 That takes us on to item 5B, PDA 25-0003.

01:13:57.000 --> 01:14:01.980
 It is a public hearing,

01:14:01.980 --> 01:14:04.620
 so I'm gonna open the public hearing at this time.

01:14:04.620 --> 01:14:12.620
 - Chair, acting chair, I am concerned that I have a conflict

01:14:12.620 --> 01:14:16.700
 of interest on this item and would need to recuse myself

01:14:16.700 --> 01:14:20.520
 if I hear the merits of this case.

01:14:20.520 --> 01:14:22.500
 Therefore, I'd like to make a motion

01:14:22.500 --> 01:14:24.820
 to continue this public hearing

01:14:24.820 --> 01:14:29.820
 to the commissioner's next meeting of June 25th, 2025,

01:14:30.900 --> 01:14:35.220
 to allow more commissioners present to hear this request

01:14:35.220 --> 01:14:40.360
 that would meet a quorum if lost this evening.

01:14:40.360 --> 01:14:46.940
 Excuse me.

01:14:46.940 --> 01:14:47.980
 - Okay, we have a motion.

01:14:47.980 --> 01:14:48.980
 Do we have a second?

01:14:48.980 --> 01:15:00.460
 - Can I ask a question first

01:15:00.460 --> 01:15:02.140
 before we second?

01:15:02.140 --> 01:15:05.180
 Will there be enough time to get notice out?

01:15:05.180 --> 01:15:07.020
 Do you have to send another notice out

01:15:07.020 --> 01:15:08.620
 before the next meeting?

01:15:08.620 --> 01:15:11.540
 - Since her motion is to a date certain of June 25th,

01:15:11.540 --> 01:15:12.380
 no, we would not.

01:15:12.380 --> 01:15:17.340
 So this serves, if this request is approved

01:15:17.340 --> 01:15:18.940
 by the commission, that serves as notice

01:15:18.940 --> 01:15:20.660
 to the applicant and anybody that's here

01:15:20.660 --> 01:15:21.980
 that might be interested in it,

01:15:21.980 --> 01:15:24.340
 that it's being continued to the 25th.

01:15:24.340 --> 01:15:26.020
 - Okay, I'll go ahead and second.

01:15:29.220 --> 01:15:31.980
 - Okay, we have a motion and a second to continue.

01:15:31.980 --> 01:15:32.800
 Let's vote.

01:15:32.800 --> 01:15:45.580
 Okay, motion unanimously passes to hold this,

01:15:45.580 --> 01:15:48.340
 basically to push it to the next meeting.

01:15:48.340 --> 01:15:53.340
 Okay, that takes us on to item 5C, MPA 250001.

01:15:53.340 --> 01:15:58.860
 Well, actually, let me close the public hearing

01:15:58.860 --> 01:16:01.260
 for item 5B, that item.

01:16:01.260 --> 01:16:02.420
 - Actually, you're gonna leave it open

01:16:02.420 --> 01:16:03.540
 since we continued it.

01:16:03.540 --> 01:16:06.060
 - Oh, well, nevermind, I'll correct it again.

01:16:06.060 --> 01:16:08.020
 We're leaving that open.

01:16:08.020 --> 01:16:09.220
 So we'll leave that one open

01:16:09.220 --> 01:16:12.700
 and we will open item 5C, MPA 250001.

01:16:12.700 --> 01:16:24.700
 - Good evening, commissioners.

01:16:24.700 --> 01:16:26.380
 My name is Saharis Van Yeri,

01:16:26.380 --> 01:16:28.060
 Senior Transportation Planner,

01:16:28.060 --> 01:16:29.780
 Development Services.

01:16:29.780 --> 01:16:33.340
 Tonight, I'd like to discuss about a mobility plan amendment

01:16:33.340 --> 01:16:37.140
 for Underwood, Springside, and Corbyn Road.

01:16:37.140 --> 01:16:39.060
 But before I go any further,

01:16:39.060 --> 01:16:42.400
 let me talk a little bit about the mobility plan.

01:16:42.400 --> 01:16:45.320
 Mobility plan, just like a comprehensive plan,

01:16:45.320 --> 01:16:46.980
 is a long-range plan.

01:16:46.980 --> 01:16:49.740
 And the current mobility plan was adopted

01:16:49.740 --> 01:16:54.580
 by the city council on March 22nd

01:16:54.580 --> 01:16:58.900
 as a part of the comprehensive plan for 2040.

01:16:58.900 --> 01:17:02.740
 So the mobility plan establishes future roadways,

01:17:02.740 --> 01:17:06.460
 pedestrian, and bicyclists network

01:17:06.460 --> 01:17:10.480
 to enhance connectivity and efficient movement.

01:17:10.480 --> 01:17:13.020
 This plan is not intended

01:17:13.020 --> 01:17:17.940
 to provide detailed roadway design or plans.

01:17:17.940 --> 01:17:20.940
 Rather, it is about general policies

01:17:20.940 --> 01:17:23.660
 and broad roadway alignment.

01:17:23.660 --> 01:17:26.300
 But it can be further refined as needed

01:17:26.300 --> 01:17:28.820
 as part of a new development project

01:17:28.820 --> 01:17:31.960
 or new capital improvement project.

01:17:31.960 --> 01:17:36.960
 Basically, this mobility plan has three major elements.

01:17:36.960 --> 01:17:39.940
 First is roadway alignment.

01:17:39.940 --> 01:17:42.140
 And second is right-of-way,

01:17:42.140 --> 01:17:44.080
 which refers to the width of the road

01:17:44.080 --> 01:17:46.660
 and speed limit on the roads.

01:17:46.660 --> 01:17:49.360
 And also the roadway design standards.

01:17:51.140 --> 01:17:56.140
 So this mobility plan amendment has four requests.

01:17:56.140 --> 01:17:59.800
 The reason that I have all these proposals

01:17:59.800 --> 01:18:02.780
 under one amendment is that they are all located

01:18:02.780 --> 01:18:05.060
 in a very close distance from each other,

01:18:05.060 --> 01:18:07.620
 and they are almost interconnected.

01:18:07.620 --> 01:18:10.600
 So going towards all of them one by one,

01:18:10.600 --> 01:18:13.140
 and I will explain all of these

01:18:13.140 --> 01:18:16.500
 in more details in later slides.

01:18:16.500 --> 01:18:19.340
 So the first request is to remove

01:18:19.340 --> 01:18:23.280
 the future northern extension of Underwood Road.

01:18:23.280 --> 01:18:26.340
 As you can see in the map to the right,

01:18:26.340 --> 01:18:31.340
 which is about located south of Airport Road or 15,

01:18:31.340 --> 01:18:38.100
 or FM 1515, and to the south, a terminus at Springside.

01:18:38.100 --> 01:18:42.660
 But I should mention that the general area

01:18:42.660 --> 01:18:47.660
 of these requests located at southwest of the city of Denton,

01:18:49.380 --> 01:18:51.780
 and like east of airport.

01:18:51.780 --> 01:18:54.680
 So the second road and second request

01:18:54.680 --> 01:18:57.060
 is about removing the future

01:18:57.060 --> 01:19:00.880
 western extension of Corbin Road.

01:19:00.880 --> 01:19:02.980
 The third request is about extending

01:19:02.980 --> 01:19:07.200
 the functional classification of north-south Corbin Road.

01:19:07.200 --> 01:19:13.060
 Also, the fourth road is Springside Road,

01:19:13.060 --> 01:19:15.060
 which we are requesting to unifying

01:19:15.060 --> 01:19:19.060
 the roadway classification to a collector

01:19:19.060 --> 01:19:21.820
 as the roadway classification for a Springside.

01:19:21.820 --> 01:19:26.260
 So now Underwood Road.

01:19:26.260 --> 01:19:29.660
 Existing Underwood Road located

01:19:29.660 --> 01:19:33.060
 between Springside to the north,

01:19:33.060 --> 01:19:36.860
 and FM 2449 to the south.

01:19:36.860 --> 01:19:39.940
 However, according to the mobility plan,

01:19:39.940 --> 01:19:42.860
 the northern part of Underwood is extended

01:19:42.860 --> 01:19:46.060
 to FM 1515 or Airport Road.

01:19:46.060 --> 01:19:49.540
 The staff requesting to remove this portion of Underwood

01:19:49.540 --> 01:19:51.700
 because of the following reasons.

01:19:51.700 --> 01:19:56.340
 First, as you can see on the map to the left and up,

01:19:56.340 --> 01:20:00.820
 this road located inside a riparian buffer and floodplain.

01:20:00.820 --> 01:20:02.700
 Therefore, in order to avoid

01:20:02.700 --> 01:20:05.020
 any adverse environmental impact

01:20:05.020 --> 01:20:09.140
 and disturbing the bottomland hardwood and local wildlife,

01:20:09.140 --> 01:20:12.980
 staff request to remove this portion of road.

01:20:12.980 --> 01:20:16.540
 Also, as you can see, this road is located between

01:20:16.540 --> 01:20:19.500
 West Court as a secondary arterial

01:20:19.500 --> 01:20:21.820
 and Corbin Road to the right.

01:20:21.820 --> 01:20:24.420
 So in the absence of this road,

01:20:24.420 --> 01:20:26.300
 there will be enough road capacity

01:20:26.300 --> 01:20:29.620
 to take care of the traffic movement in this area.

01:20:29.620 --> 01:20:34.540
 The map to the left-hand bottom of the page

01:20:34.540 --> 01:20:37.260
 shows the final configuration of this road.

01:20:37.260 --> 01:20:42.260
 So as you can see, the northern section of Underwood

01:20:42.380 --> 01:20:44.740
 will be connected to the West Court

01:20:44.740 --> 01:20:48.060
 by re-aligning to the left with the care.

01:20:48.060 --> 01:20:55.380
 The second request is for East-West Corbin Road.

01:20:55.380 --> 01:20:56.780
 As you can see in this map,

01:20:56.780 --> 01:21:00.780
 the East-West Corbin Road started from east of I-35

01:21:00.780 --> 01:21:03.900
 from Bonnie Bray Street, crosses I-35.

01:21:03.900 --> 01:21:06.300
 Of course, the crossing is now closed,

01:21:06.300 --> 01:21:08.700
 but the focus of this request

01:21:08.700 --> 01:21:11.620
 is located inside this orange loop.

01:21:11.620 --> 01:21:15.460
 As you can see, according to the mobility plan,

01:21:15.460 --> 01:21:18.460
 this future extension of Corbin Road

01:21:18.460 --> 01:21:20.700
 crosses three properties.

01:21:20.700 --> 01:21:22.460
 So after a detailed study,

01:21:22.460 --> 01:21:25.700
 staff recommends to remove this portion of road

01:21:25.700 --> 01:21:28.860
 to avoid disturbing the surrounding properties.

01:21:28.860 --> 01:21:31.020
 Also, the absence of this road

01:21:31.020 --> 01:21:34.060
 will have no impact on traffic flow

01:21:34.060 --> 01:21:36.580
 because of the existing Corbin Road

01:21:36.580 --> 01:21:39.340
 and a Springside Road in a very close distance

01:21:39.340 --> 01:21:41.340
 of this target road.

01:21:41.340 --> 01:21:43.020
 There will be enough road capacity

01:21:43.020 --> 01:21:45.100
 to take care of the traffic movement.

01:21:45.100 --> 01:21:49.420
 The third request is about

01:21:49.420 --> 01:21:52.540
 extending the roadway classification.

01:21:52.540 --> 01:21:56.900
 Currently, the Corbin Road existing between Airport Road

01:21:56.900 --> 01:21:59.860
 all the way south to the East-West,

01:21:59.860 --> 01:22:03.100
 connecting to the East-West Corbin Road.

01:22:03.100 --> 01:22:05.900
 But mobility plan only identify

01:22:05.900 --> 01:22:11.180
 these roads from airport to Springside as a collector.

01:22:11.180 --> 01:22:14.940
 Staff recommend to extend this roadway classification

01:22:14.940 --> 01:22:16.860
 to provide better connectivity

01:22:16.860 --> 01:22:20.500
 and improved access for residents around this area.

01:22:20.500 --> 01:22:26.540
 The fourth request is for Springside Road.

01:22:26.540 --> 01:22:28.700
 As you can see in this map,

01:22:28.700 --> 01:22:33.620
 Springside Road, which is located in the orange circle,

01:22:33.620 --> 01:22:37.220
 is located between West Court Road and Corbin Road.

01:22:37.220 --> 01:22:39.700
 The western section of Springside

01:22:39.700 --> 01:22:42.740
 has been identified as secondary arteriole,

01:22:42.740 --> 01:22:45.180
 whereas the eastern section is identified

01:22:45.180 --> 01:22:47.700
 as a collector in the mobility plan.

01:22:47.700 --> 01:22:51.100
 Staff recommends to unify this roadway classification

01:22:51.100 --> 01:22:52.780
 as a collector

01:22:52.780 --> 01:22:57.340
 to provide the unifying roadway classification.

01:22:57.340 --> 01:23:01.500
 Just for some background about this roadway classification,

01:23:01.500 --> 01:23:04.980
 this roadway classification refers to the width of the road

01:23:04.980 --> 01:23:06.060
 and the speed limit.

01:23:06.060 --> 01:23:09.820
 As a collector, the roadway should have 65 feet

01:23:09.820 --> 01:23:11.740
 of total right-of-way,

01:23:11.740 --> 01:23:16.740
 and the speed limit will be from 30 to 35 miles per hour.

01:23:16.740 --> 01:23:19.340
 However, as a secondary arteriole,

01:23:19.340 --> 01:23:21.860
 the right-of-way will be 110,

01:23:21.860 --> 01:23:26.500
 and the speed limit will be 35 to 40 miles per hour.

01:23:26.500 --> 01:23:30.780
 So we recommend to downgrade this roadway classification

01:23:30.780 --> 01:23:34.500
 to a collector, especially because this area,

01:23:34.500 --> 01:23:37.900
 located in a complex kind of land use,

01:23:37.900 --> 01:23:42.900
 the mix of rural residential and heavy industrial area,

01:23:42.900 --> 01:23:46.580
 this road is going to be used by passenger cars

01:23:46.580 --> 01:23:49.380
 and heavy commercial trucks.

01:23:49.380 --> 01:23:51.620
 So by lowering the classification

01:23:51.620 --> 01:23:53.420
 and lowering the speed limit,

01:23:53.420 --> 01:23:58.420
 we are providing a safer passage for all the road users.

01:23:58.420 --> 01:24:03.340
 And of course, because it is very close to the airport road,

01:24:03.340 --> 01:24:05.380
 there will be enough road capacity,

01:24:05.380 --> 01:24:08.060
 because airport road is a primary arteriole,

01:24:08.060 --> 01:24:11.060
 so they can take care of the traffic flow in the area.

01:24:11.060 --> 01:24:16.260
 So as you can see, the map on the right

01:24:16.260 --> 01:24:20.580
 shows the final configuration of these proposed changes.

01:24:20.580 --> 01:24:26.140
 All these proposals meet the criteria for approval,

01:24:26.140 --> 01:24:28.420
 especially regarding to the comprehensive plan,

01:24:28.420 --> 01:24:30.540
 future land use and mobility plan.

01:24:32.260 --> 01:24:36.100
 We have done the public outreach for this area.

01:24:36.100 --> 01:24:39.700
 We had an in-person meeting back in May 7th with residents,

01:24:39.700 --> 01:24:41.540
 and we addressed the questions

01:24:41.540 --> 01:24:44.340
 and explained the process for them.

01:24:44.340 --> 01:24:49.020
 We had newspaper ad, website announcement, property signs,

01:24:49.020 --> 01:24:50.900
 and we have also made the notices

01:24:50.900 --> 01:24:54.660
 to 200 and 500 buffer around the target roads,

01:24:54.660 --> 01:24:57.460
 and we have received one written letter

01:24:57.460 --> 01:24:59.220
 in favor of this request.

01:25:01.900 --> 01:25:04.660
 Staff recommends approval of this proposal,

01:25:04.660 --> 01:25:09.660
 as it complies with the criteria in section 271D of the DDC.

01:25:09.660 --> 01:25:12.100
 The next step will be a public hearing

01:25:12.100 --> 01:25:14.620
 at City Council on June 17th.

01:25:14.620 --> 01:25:16.380
 Thank you.

01:25:16.380 --> 01:25:25.380
 - Okay, are there any questions from the commission?

01:25:25.380 --> 01:25:27.620
 - I do.

01:25:27.620 --> 01:25:30.900
 First, just commending the city staff

01:25:30.900 --> 01:25:34.620
 on recognizing that this is going to help the environment

01:25:34.620 --> 01:25:36.300
 and all the wildlife there.

01:25:36.300 --> 01:25:41.300
 I have to assume, as well, that Underwood,

01:25:41.300 --> 01:25:44.820
 by taking that out, I would assume

01:25:44.820 --> 01:25:47.460
 there would have to be a bridge going over there,

01:25:47.460 --> 01:25:49.940
 over the creek, so that's also a money saver

01:25:49.940 --> 01:25:51.740
 for the city as well.

01:25:51.740 --> 01:25:56.740
 So way to go to save the city some money, so thank you.

01:25:56.740 --> 01:25:57.780
 - Sure.

01:25:59.620 --> 01:26:01.380
 I will say, it does look like this configuration.

01:26:01.380 --> 01:26:05.100
 Obviously, it avoids the wetlands and the,

01:26:05.100 --> 01:26:07.700
 or not the wetlands, the floodplain and the habitat,

01:26:07.700 --> 01:26:09.780
 but it also looks like it ultimately

01:26:09.780 --> 01:26:11.500
 reduces the surrounding residents,

01:26:11.500 --> 01:26:14.660
 and so this seems like a good thing.

01:26:14.660 --> 01:26:15.620
 I'll just say that.

01:26:15.620 --> 01:26:18.940
 That being said, it is a public hearing,

01:26:18.940 --> 01:26:22.000
 so if there's no other questions from the commission,

01:26:22.000 --> 01:26:25.620
 I can take questions.

01:26:25.620 --> 01:26:28.580
 That being said, I have one card,

01:26:28.580 --> 01:26:30.500
 so we'll start with the cards.

01:26:30.500 --> 01:26:33.500
 Mr. Kyle Eaton, please come up,

01:26:33.500 --> 01:26:37.860
 state your name and address, and you have four minutes.

01:26:37.860 --> 01:26:43.940
 - My name is Kyle Eaton, I'm at 2999 Corbin Road.

01:26:43.940 --> 01:26:46.300
 I'm actually on the other side of 35,

01:26:46.300 --> 01:26:48.940
 but this was brought to my attention,

01:26:48.940 --> 01:26:52.740
 and so really kind of what I want to focus on,

01:26:52.740 --> 01:26:56.180
 on this item, is the including but not limited to.

01:26:56.180 --> 01:26:59.880
 So I guess my question, my concern on this,

01:26:59.880 --> 01:27:01.380
 is item number one,

01:27:01.380 --> 01:27:04.620
 which is removing the piece of Underwood,

01:27:04.620 --> 01:27:07.280
 and the concern that I have with that is,

01:27:07.280 --> 01:27:10.460
 I guess the role potentially that,

01:27:10.460 --> 01:27:12.140
 I think it's Walter P. Moore,

01:27:12.140 --> 01:27:15.120
 I think he was the consultant that did the mobility plan,

01:27:15.120 --> 01:27:16.740
 what role he actually played,

01:27:16.740 --> 01:27:19.120
 what role they played in this whole process,

01:27:19.120 --> 01:27:20.900
 because when I look at Underwood,

01:27:20.900 --> 01:27:23.140
 yes, it's in a floodplain,

01:27:23.140 --> 01:27:25.580
 it's not just crossing a floodplain,

01:27:25.580 --> 01:27:30.020
 there's about 2,700 foot of road that's in a floodplain.

01:27:30.020 --> 01:27:31.700
 So my question is,

01:27:31.700 --> 01:27:35.700
 how do you make this recommendation on a mobility plan,

01:27:35.700 --> 01:27:37.660
 and it gets to this stage,

01:27:37.660 --> 01:27:40.780
 where somebody on city staff has to catch it and says,

01:27:40.780 --> 01:27:44.420
 somebody, we can't do this, this is impossible.

01:27:44.420 --> 01:27:46.460
 And I don't think it's limited just to

01:27:46.460 --> 01:27:47.980
 that portion of the road,

01:27:47.980 --> 01:27:50.780
 and my concern is that we've hired these outside consultants

01:27:50.780 --> 01:27:52.260
 to try to save money,

01:27:52.260 --> 01:27:54.360
 and what we've ended up doing is we have people

01:27:54.360 --> 01:27:56.380
 that don't know the city,

01:27:56.380 --> 01:27:57.580
 they don't know the city,

01:27:57.580 --> 01:28:00.260
 and then that has very real consequences

01:28:00.260 --> 01:28:02.100
 for the people that live here,

01:28:02.100 --> 01:28:05.940
 because whenever a developer sees a secondary arterial,

01:28:05.940 --> 01:28:07.700
 I can tell you they are rubbing their hand

01:28:07.700 --> 01:28:10.880
 and say, mixed use, let's put mixed use there,

01:28:10.880 --> 01:28:12.360
 'cause the roads will support it,

01:28:12.360 --> 01:28:14.340
 we're not gonna get pushed back on that.

01:28:14.340 --> 01:28:16.340
 So that's my first concern.

01:28:16.340 --> 01:28:17.820
 My second concern is,

01:28:17.820 --> 01:28:22.620
 why are we stopping on downgrading it

01:28:22.620 --> 01:28:26.420
 on the collector on Corbin Road, just to that one section?

01:28:26.420 --> 01:28:30.300
 I have the I-35 schematics right here,

01:28:30.300 --> 01:28:36.420
 and there is no connection to I-35 for Corbin.

01:28:36.420 --> 01:28:40.560
 And so my question is, on the north south of Corbin,

01:28:40.560 --> 01:28:42.420
 where we're downgrading it to a collector,

01:28:42.420 --> 01:28:43.780
 why does it stop there?

01:28:43.780 --> 01:28:47.580
 Why not take it, the remainder of the way, 235,

01:28:47.580 --> 01:28:49.640
 and make downgrade that as well?

01:28:49.640 --> 01:28:52.100
 That's about 300 foot of road,

01:28:52.100 --> 01:28:55.800
 300 or 400 foot of road, that serves three residents.

01:28:55.800 --> 01:28:58.020
 And so I don't understand why,

01:28:58.020 --> 01:28:59.860
 if you're making these changes already,

01:28:59.860 --> 01:29:01.740
 you just don't go ahead and you finish them out.

01:29:01.740 --> 01:29:04.020
 It doesn't make sense to leave out another portion.

01:29:04.020 --> 01:29:06.940
 That's a secondary arterial in my opinion.

01:29:06.940 --> 01:29:07.780
 Thank you.

01:29:07.780 --> 01:29:12.460
 - Okay, it is a public hearing,

01:29:12.460 --> 01:29:15.260
 so if anybody else would like to speak, please come up.

01:29:15.260 --> 01:29:18.940
 Please state your name and address,

01:29:18.940 --> 01:29:20.400
 and you have four minutes.

01:29:20.400 --> 01:29:24.220
 - Kevin McKinney, and I live at 2057 Underwood Road.

01:29:24.220 --> 01:29:29.220
 And the concern I've got is that we had a plan,

01:29:29.220 --> 01:29:33.240
 then we changed it and came up with a new plan.

01:29:33.240 --> 01:29:36.940
 And then before May 7th, we had a new plan,

01:29:36.940 --> 01:29:40.900
 which is what you are trying to stop.

01:29:40.900 --> 01:29:42.240
 Is that what we're doing?

01:29:42.240 --> 01:29:44.940
 You're trying to change that and go to a new plan?

01:29:44.940 --> 01:29:47.380
 We're Underwood Road, is that correct?

01:29:47.380 --> 01:29:48.740
 Did I read that right?

01:29:48.740 --> 01:29:52.540
 - So currently, Underwood Road runs north of Springside.

01:29:52.540 --> 01:29:53.940
 This would remove that portion.

01:29:53.940 --> 01:29:55.180
 - Right, okay, all right.

01:29:55.180 --> 01:29:59.220
 And the Corbin Road Bridge is not gonna be reopened?

01:29:59.220 --> 01:30:02.340
 Was that, yes, no?

01:30:02.340 --> 01:30:03.820
 - That would be something for staff,

01:30:03.820 --> 01:30:05.660
 but this is really not a back and forth.

01:30:05.660 --> 01:30:06.940
 This is a time for you to--

01:30:06.940 --> 01:30:08.300
 - I'm just asking questions.

01:30:08.300 --> 01:30:10.220
 You asked for any questions, these were the questions.

01:30:10.220 --> 01:30:13.900
 - Okay, we'll let staff answer them when you're done.

01:30:13.900 --> 01:30:18.420
 - Because I had to actually contact the P&Z

01:30:18.420 --> 01:30:21.060
 to get notified of all these meetings.

01:30:21.060 --> 01:30:24.460
 I'm just worried about my piece of property,

01:30:24.460 --> 01:30:27.380
 and from what I remember on Underwood Road,

01:30:27.380 --> 01:30:32.120
 there are four houses, there's four houses.

01:30:32.120 --> 01:30:36.380
 And then on Corbin, there's three residents.

01:30:36.380 --> 01:30:39.740
 And Springside, one.

01:30:39.740 --> 01:30:42.640
 I mean, and we're here.

01:30:42.640 --> 01:30:44.740
 And this is what's affecting us.

01:30:46.980 --> 01:30:49.260
 You're home, nobody wants at your home, your home.

01:30:49.260 --> 01:30:52.740
 Nobody wants coming in and taking roads over, driving down.

01:30:52.740 --> 01:30:54.580
 You're talking about the safety on that road.

01:30:54.580 --> 01:30:56.340
 It's 30 miles an hour now.

01:30:56.340 --> 01:30:58.660
 It's a blacktop road on Underwood.

01:30:58.660 --> 01:31:03.340
 And it says no trucks, no one's enforcing that.

01:31:03.340 --> 01:31:08.100
 Y'all, the city built a bridge to keep it from flooding.

01:31:08.100 --> 01:31:11.540
 And they're just destroying the road

01:31:11.540 --> 01:31:14.460
 and doing 50 miles an hour down that road all day long.

01:31:14.460 --> 01:31:16.580
 So if you've never been down Underwood Road,

01:31:16.580 --> 01:31:18.380
 y'all might want to go take a visit,

01:31:18.380 --> 01:31:21.860
 what you're voting on, okay?

01:31:21.860 --> 01:31:22.700
 That's my point.

01:31:22.700 --> 01:31:31.060
 - Yeah, are there any other public speakers?

01:31:31.060 --> 01:31:35.860
 You'll have to come up to the podium,

01:31:35.860 --> 01:31:37.300
 state your name and address.

01:31:37.300 --> 01:31:46.120
 Okay, is there anyone else?

01:31:47.140 --> 01:31:50.140
 Okay, one more time, anyone else like to speak?

01:31:50.140 --> 01:31:52.940
 Okay.

01:31:52.940 --> 01:32:07.740
 Okay, well, if there's no other public speakers,

01:32:07.740 --> 01:32:10.120
 then I'm going to close the public hearing

01:32:10.120 --> 01:32:12.460
 and open it up for questions.

01:32:12.460 --> 01:32:14.300
 Commissioner, are there any questions?

01:32:16.580 --> 01:32:21.580
 Okay, well, I do have a couple of questions.

01:32:21.580 --> 01:32:30.140
 One, it looks like as if this proposal

01:32:30.140 --> 01:32:32.580
 would ultimately have less of an impact

01:32:32.580 --> 01:32:37.140
 to the residents and to the area around it.

01:32:37.140 --> 01:32:39.260
 It seems to me like this would be less of an impact

01:32:39.260 --> 01:32:40.620
 than the current plan.

01:32:40.620 --> 01:32:42.580
 I'd like staff to kind of come up

01:32:42.580 --> 01:32:45.700
 and talk about their analysis and from a traffic side.

01:32:47.580 --> 01:32:50.760
 - Good evening, Chandra Muruganandam,

01:32:50.760 --> 01:32:52.460
 city traffic engineer, city of Denton,

01:32:52.460 --> 01:32:54.340
 transportation services.

01:32:54.340 --> 01:32:56.260
 So based on the proposal we have,

01:32:56.260 --> 01:32:59.660
 we are actually downgrading some of the roadways,

01:32:59.660 --> 01:33:03.220
 so that should actually be less impact to the residents

01:33:03.220 --> 01:33:05.420
 as what is in the classification right now.

01:33:05.420 --> 01:33:09.860
 We are actually reducing it from a secondary arterials

01:33:09.860 --> 01:33:12.060
 to collectors, so that we'll be having

01:33:12.060 --> 01:33:14.980
 less right of way undertaking in the future

01:33:14.980 --> 01:33:19.220
 when the developments occur on those areas,

01:33:19.220 --> 01:33:20.460
 on those roadways.

01:33:20.460 --> 01:33:29.060
 - Chandra, can you speak to why Corbin Road

01:33:29.060 --> 01:33:33.180
 on the east-west portion was not downgraded as well

01:33:33.180 --> 01:33:35.020
 as part of this request?

01:33:35.020 --> 01:33:38.440
 - So right now as we see, we have to see

01:33:38.440 --> 01:33:42.060
 on the mobility plan what is on the development plan,

01:33:42.060 --> 01:33:44.940
 not right now, what is on the 2040,

01:33:44.940 --> 01:33:48.420
 as per the 2022 adoption of the mobility plan.

01:33:48.420 --> 01:33:52.340
 So as the land area is available for developments,

01:33:52.340 --> 01:33:56.740
 those roadways will be, has to match those classifications.

01:33:56.740 --> 01:34:01.740
 But if the data supports to downgrade it

01:34:01.740 --> 01:34:05.920
 and offer to provide the enough level of service

01:34:05.920 --> 01:34:09.020
 and with the development numbers that showing,

01:34:09.020 --> 01:34:10.700
 then we could downgrade it.

01:34:10.700 --> 01:34:14.980
 But as such, when these studies are done,

01:34:14.980 --> 01:34:19.980
 the models predict how much trips are projected in the 2040

01:34:19.980 --> 01:34:23.140
 and we will be relying on those models

01:34:23.140 --> 01:34:25.540
 to have these classifications done.

01:34:25.540 --> 01:34:30.540
 And as a case by case, these are at a high level maps.

01:34:30.540 --> 01:34:32.020
 We will take a closer look at it

01:34:32.020 --> 01:34:35.940
 as the development comes in to see if it fits the needs,

01:34:35.940 --> 01:34:38.220
 whether it supports downgrading,

01:34:38.220 --> 01:34:40.780
 whether it has alternate capacities to handle

01:34:40.780 --> 01:34:41.760
 the future traffic.

01:34:41.760 --> 01:34:49.420
 - Yeah, Bettina, would you like to add something?

01:34:49.420 --> 01:34:50.740
 - Yeah, I just wanted to add something

01:34:50.740 --> 01:34:53.620
 just to follow up to a comment that Chandra made.

01:34:53.620 --> 01:34:58.620
 So he's right, when we did the update to the mobility plan,

01:34:58.620 --> 01:35:01.580
 these are, there are models that are in,

01:35:01.580 --> 01:35:04.180
 while the city may hire a consultant team to assist us,

01:35:04.180 --> 01:35:07.620
 staff is intimately involved with making recommendations

01:35:07.620 --> 01:35:10.900
 as well as to what the mobility plan map should show.

01:35:10.900 --> 01:35:14.060
 So to his point, you know, we do the analysis

01:35:14.060 --> 01:35:18.620
 that we have at the time, it's a higher level analysis.

01:35:18.620 --> 01:35:21.140
 We do have the ability though to study areas

01:35:21.140 --> 01:35:23.340
 and make amendments to the map as needed

01:35:23.340 --> 01:35:26.180
 because we realize sometimes conditions can change

01:35:26.180 --> 01:35:29.020
 within an area or we're seeing a different

01:35:29.020 --> 01:35:31.620
 development pattern and so it's worthy to go back

01:35:31.620 --> 01:35:34.320
 and do a deeper dive analysis on recommendations

01:35:34.320 --> 01:35:35.920
 associated with the mobility plan.

01:35:35.920 --> 01:35:37.620
 So that's why you have the recommendations

01:35:37.620 --> 01:35:40.420
 that are before you this evening to make those changes.

01:35:40.420 --> 01:35:43.900
 I had one I thought and I just lost it, I'm sorry.

01:35:43.900 --> 01:35:47.500
 But it, oh, the other thing is, keep in mind,

01:35:47.500 --> 01:35:49.340
 when the mobility plan is adopted,

01:35:49.340 --> 01:35:51.360
 and Chandra, you can correct me if I'm wrong on this,

01:35:51.360 --> 01:35:53.220
 but we actually have language in the plan also

01:35:53.220 --> 01:35:55.660
 that acknowledges that the roadway alignments

01:35:55.660 --> 01:35:58.220
 have the ability to shift 1,000 feet in either direction

01:35:58.220 --> 01:36:02.800
 because again, we're looking at locations of roadways,

01:36:02.800 --> 01:36:04.700
 it's a higher level analysis that's done at the time

01:36:04.700 --> 01:36:06.460
 when we're adopting the plan.

01:36:06.460 --> 01:36:10.100
 We realize we may not have gotten it perfect,

01:36:10.100 --> 01:36:12.180
 possibly on alignment or some conditions have changed

01:36:12.180 --> 01:36:13.380
 or we're working with a property owner

01:36:13.380 --> 01:36:15.460
 where that alignment might need to adjust.

01:36:15.460 --> 01:36:18.140
 And so the mobility plan has some level of flexibility

01:36:18.140 --> 01:36:22.340
 built into it regarding where the final road does land,

01:36:22.340 --> 01:36:24.540
 if you will, on the ground.

01:36:24.540 --> 01:36:27.620
 But so we have that flexibility built in there.

01:36:27.620 --> 01:36:30.120
 So again, it's taken into consideration

01:36:30.120 --> 01:36:32.980
 as conditions are evolving whether or not

01:36:32.980 --> 01:36:35.860
 we have the ability to or whether or not it's necessary

01:36:35.860 --> 01:36:37.820
 to make some of those changes.

01:36:37.820 --> 01:36:38.660
 - That's right.

01:36:38.660 --> 01:36:45.020
 - Okay, any other questions from the commission?

01:36:45.020 --> 01:36:49.100
 Yes.

01:36:49.100 --> 01:36:51.300
 - I had a question regarding the comment

01:36:51.300 --> 01:36:54.300
 about the 300 feet of Corbin Road

01:36:54.300 --> 01:36:58.860
 not being completely extended to 35.

01:36:58.860 --> 01:37:00.780
 And I'm sorry if some of what she said,

01:37:00.780 --> 01:37:04.060
 Tina addressed that, but is there some reason

01:37:04.060 --> 01:37:07.340
 why that wasn't considered or is it not in the plan?

01:37:07.340 --> 01:37:11.540
 - As such, we have been told from the design team

01:37:11.540 --> 01:37:13.220
 that is part of the plan.

01:37:13.220 --> 01:37:16.140
 And they are in a schematic stage at this time.

01:37:16.140 --> 01:37:21.200
 And we have to take a look at specifically

01:37:21.200 --> 01:37:23.260
 on what section they are mentioning

01:37:23.260 --> 01:37:26.320
 that portion of 300 feet,

01:37:26.320 --> 01:37:28.220
 they are wanting to take a look at it.

01:37:30.100 --> 01:37:33.740
 And how much distance is it to 35?

01:37:33.740 --> 01:37:35.020
 What's the distance?

01:37:35.020 --> 01:37:36.860
 He mentioned 300.

01:37:36.860 --> 01:37:41.740
 - So on this plan, in the mobility plan amendment,

01:37:41.740 --> 01:37:45.460
 the roadway that the Corbin Road shown on this map,

01:37:45.460 --> 01:37:48.700
 there will be a bridge that's constructed

01:37:48.700 --> 01:37:50.980
 the north-south Corbin that was closed

01:37:50.980 --> 01:37:53.020
 due to a fatality back in 2010.

01:37:53.020 --> 01:37:57.060
 So that portion of the bridge is still intact.

01:37:57.060 --> 01:37:59.140
 That plan is to build it back.

01:38:00.100 --> 01:38:00.940
 - Okay.

01:38:00.940 --> 01:38:07.500
 Any other questions?

01:38:07.500 --> 01:38:12.580
 I know the public hearing has been closed.

01:38:12.580 --> 01:38:13.420
 I'm sorry.

01:38:13.420 --> 01:38:19.940
 Okay, with that, I'll entertain a motion.

01:38:30.100 --> 01:38:30.940
 - Okay.

01:38:30.940 --> 01:38:39.540
 We have a motion and a second.

01:38:39.540 --> 01:38:41.180
 Commissioner Dyer.

01:38:41.180 --> 01:38:43.020
 - I'd like to make a motion to go ahead

01:38:43.020 --> 01:38:47.220
 and move forward on recommending the proposed changes

01:38:47.220 --> 01:38:48.360
 to the city council.

01:38:48.360 --> 01:38:51.580
 - Commissioner MacDuff.

01:38:51.580 --> 01:38:54.860
 - I'd like to second this motion.

01:38:54.860 --> 01:38:58.320
 And may I add something, a comment here?

01:38:58.320 --> 01:38:59.160
 - Sure.

01:38:59.160 --> 01:39:00.000
 - Commissioner MacDuff did before.

01:39:00.000 --> 01:39:01.300
 Commissioner Dyer did before.

01:39:01.300 --> 01:39:03.820
 I want us to move forward with this,

01:39:03.820 --> 01:39:06.860
 but I certainly want us to take into account these comments.

01:39:06.860 --> 01:39:10.420
 - Okay.

01:39:10.420 --> 01:39:11.820
 Well, with that, let's vote.

01:39:27.460 --> 01:39:29.820
 Okay, motion passes four zero.

01:39:29.820 --> 01:39:34.820
 Moving on to item five D, MPA 25-0002.

01:39:34.820 --> 01:39:44.820
 And I will go ahead and open the public hearing at this time.

01:39:57.460 --> 01:39:59.500
 - Good evening, Sahar Isfandiari,

01:39:59.500 --> 01:40:00.980
 senior transportation planner.

01:40:00.980 --> 01:40:05.500
 This is MPA 25-002A,

01:40:05.500 --> 01:40:09.500
 which is about removing a future collector.

01:40:09.500 --> 01:40:11.300
 As you can see in this map,

01:40:11.300 --> 01:40:14.420
 the general area of this future collector

01:40:14.420 --> 01:40:17.620
 located at the west side of the city.

01:40:17.620 --> 01:40:20.180
 To be more specific, it is located

01:40:20.180 --> 01:40:24.180
 between item five D and MPA 25-0002A.

01:40:24.180 --> 01:40:29.180
 It is located between I-35 and Western,

01:40:29.180 --> 01:40:33.420
 south of US-380 and north of Jim Crystal.

01:40:33.420 --> 01:40:39.860
 So, as I mentioned,

01:40:39.860 --> 01:40:44.740
 staff requesting removing this future collector.

01:40:44.740 --> 01:40:48.180
 And the reason behind this request is,

01:40:48.180 --> 01:40:51.340
 first, as you can see this future collector

01:40:51.340 --> 01:40:54.540
 located in the pink circle.

01:40:54.540 --> 01:40:59.180
 There is a railroad, Kansas City Southern Railroad,

01:40:59.180 --> 01:41:02.660
 that crosses this future roadway.

01:41:02.660 --> 01:41:06.180
 So, according to the regulations,

01:41:06.180 --> 01:41:09.140
 we need, in order to open a new crossing,

01:41:09.140 --> 01:41:12.420
 we have to close at least two or more

01:41:12.420 --> 01:41:16.180
 other existing crossing in the city to open a new one.

01:41:16.180 --> 01:41:18.540
 And of course, any new crossing

01:41:18.540 --> 01:41:21.100
 will have its own safety concerns.

01:41:21.860 --> 01:41:24.380
 The second reason is that, as you can see,

01:41:24.380 --> 01:41:26.180
 the northern section of this road

01:41:26.180 --> 01:41:28.980
 located inside a floodplain.

01:41:28.980 --> 01:41:33.980
 So, in order to prevent any adverse environmental impact,

01:41:33.980 --> 01:41:37.820
 we are requesting to remove this future collector

01:41:37.820 --> 01:41:40.500
 from the mobility plan.

01:41:40.500 --> 01:41:44.300
 Also, noticing that this road

01:41:44.300 --> 01:41:47.300
 located between I-35 as a highway

01:41:47.300 --> 01:41:50.860
 and Western Road as a primary arterial,

01:41:50.860 --> 01:41:52.980
 there will be enough road capacity

01:41:52.980 --> 01:41:55.500
 in the absence of this future collector

01:41:55.500 --> 01:41:58.340
 to take care of the traffic movement in the area.

01:41:58.340 --> 01:42:03.860
 To the right, you can see the future

01:42:03.860 --> 01:42:05.620
 or proposed mobility plan.

01:42:05.620 --> 01:42:10.780
 And this proposal meet the criteria for approval,

01:42:10.780 --> 01:42:13.340
 especially regarding to the comprehensive plan,

01:42:13.340 --> 01:42:15.580
 future land use and mobility plan.

01:42:15.580 --> 01:42:20.460
 We've done the public outreach for this request

01:42:20.460 --> 01:42:22.820
 through newspaper ad, website announcement,

01:42:22.820 --> 01:42:26.100
 property signs, we have also mailed the notices

01:42:26.100 --> 01:42:30.020
 to 200 and 500 feet buffer around the target road,

01:42:30.020 --> 01:42:33.060
 and we have received one written letter in response

01:42:33.060 --> 01:42:35.180
 and in favor of this request.

01:42:35.180 --> 01:42:39.980
 Staff recommends approval of this proposal

01:42:39.980 --> 01:42:44.980
 as it complies with the criteria in Section 271D of the DDC.

01:42:44.980 --> 01:42:47.060
 The next step will be a public hearing

01:42:47.060 --> 01:42:49.780
 at City Council on June 17th.

01:42:49.780 --> 01:42:50.620
 Thank you.

01:42:50.620 --> 01:42:53.980
 - Okay, are there any questions for staff

01:42:53.980 --> 01:42:56.780
 from the commission?

01:42:56.780 --> 01:42:59.780
 Okay, this is a public hearing,

01:42:59.780 --> 01:43:02.820
 so if anyone would like to come up and make comments,

01:43:02.820 --> 01:43:04.580
 you are more than welcome to do so.

01:43:04.580 --> 01:43:11.500
 Okay, looks like we don't have anyone,

01:43:11.500 --> 01:43:16.260
 so in that case, I am going to close the public hearing

01:43:16.260 --> 01:43:19.740
 and commission if there's any discussion

01:43:19.740 --> 01:43:22.420
 or if anyone wants to make a motion,

01:43:22.420 --> 01:43:23.620
 I'd entertain a motion.

01:43:23.620 --> 01:43:29.620
 Okay, Commissioner Dyer.

01:43:29.620 --> 01:43:31.300
 - I'll make a motion that we move forward

01:43:31.300 --> 01:43:33.980
 to recommend to the City Council

01:43:33.980 --> 01:43:36.260
 the changes in this proposal.

01:43:36.260 --> 01:43:38.140
 - Commissioner McDonough.

01:43:38.140 --> 01:43:40.860
 - I'll second the motion.

01:43:40.860 --> 01:43:41.900
 - Okay, let's vote.

01:43:48.420 --> 01:43:50.540
 Okay, item passes unanimously.

01:43:50.540 --> 01:43:55.540
 That takes us on to Item 6A, PZ25-022,

01:43:55.540 --> 01:44:00.980
 hold a discussion regarding the planning

01:44:00.980 --> 01:44:02.900
 and zoning project matrix.

01:44:02.900 --> 01:44:10.540
 - Thank you, Chair Riggs.

01:44:10.540 --> 01:44:13.060
 So there were no changes made to the matrix

01:44:13.060 --> 01:44:14.460
 that was included in your packet

01:44:14.460 --> 01:44:17.180
 since there were no requests from the prior meeting.

01:44:17.180 --> 01:44:19.740
 And then also regarding actions

01:44:19.740 --> 01:44:22.460
 that council has taken on development projects

01:44:22.460 --> 01:44:25.820
 that the commission also may have heard previously.

01:44:25.820 --> 01:44:29.620
 Since your meeting on May 28th,

01:44:29.620 --> 01:44:31.700
 the commission only had, or excuse me,

01:44:31.700 --> 01:44:33.820
 the council only had action on one agenda item

01:44:33.820 --> 01:44:36.620
 and that was the Denton-195 project.

01:44:36.620 --> 01:44:38.980
 The applicant had requested that the item B

01:44:38.980 --> 01:44:41.220
 continued indefinitely and to allow them

01:44:41.220 --> 01:44:43.820
 to be able to make some additional refinements

01:44:43.820 --> 01:44:45.220
 to their application.

01:44:45.220 --> 01:44:47.620
 So at such point in time when that application

01:44:47.620 --> 01:44:48.980
 is ready to proceed to council,

01:44:48.980 --> 01:44:51.700
 staff will re-notice for that public hearing

01:44:51.700 --> 01:44:53.740
 and send out the required public notifications

01:44:53.740 --> 01:44:56.180
 to the various property owners and residents

01:44:56.180 --> 01:44:58.220
 at such point in time when that's ready to move forward.

01:44:58.220 --> 01:44:59.940
 And I do not have any date on that,

01:44:59.940 --> 01:45:02.020
 but otherwise that concludes my report.

01:45:02.020 --> 01:45:02.860
 So thank you.

01:45:02.860 --> 01:45:04.900
 - So question on that.

01:45:04.900 --> 01:45:05.740
 - Yes, ma'am.

01:45:05.740 --> 01:45:07.540
 - So if the developer is going back

01:45:07.540 --> 01:45:09.660
 and making changes on the 195 project,

01:45:09.660 --> 01:45:13.380
 will it go back to the PNC before it goes back

01:45:13.380 --> 01:45:15.180
 to the city council or does it just go straight

01:45:15.180 --> 01:45:16.780
 to the city council?

01:45:16.780 --> 01:45:18.100
 - So that depends.

01:45:18.100 --> 01:45:20.620
 Not knowing what changes of any they might make.

01:45:20.620 --> 01:45:22.380
 If they were significant changes,

01:45:22.380 --> 01:45:24.500
 then we would still take the item back to council,

01:45:24.500 --> 01:45:25.780
 but it could be that our recommendation

01:45:25.780 --> 01:45:27.820
 is that it's brought back to the commission.

01:45:27.820 --> 01:45:29.660
 Not wanting to get too off posting

01:45:29.660 --> 01:45:32.460
 before I get the eyebrows again, so.

01:45:32.460 --> 01:45:36.980
 But that's kind of the basic how that would roll.

01:45:36.980 --> 01:45:38.700
 But we don't know.

01:45:38.700 --> 01:45:40.580
 So we'll make that decision

01:45:40.580 --> 01:45:42.700
 once we receive more information.

01:45:42.700 --> 01:45:44.300
 It's a great question.

01:45:44.300 --> 01:45:45.660
 - Thank you.

01:45:45.660 --> 01:45:46.540
 Thank you for answering it,

01:45:46.540 --> 01:45:48.700
 not for the great question comment,

01:45:48.700 --> 01:45:49.860
 but thanks for that too.

01:45:49.860 --> 01:45:50.700
 - No problem.

01:45:50.700 --> 01:45:55.420
 So I know we have some new commissioners.

01:45:55.420 --> 01:45:58.180
 So just, we might not have talked about the matrix

01:45:58.180 --> 01:46:00.380
 in your commissioner training, so that's my fault.

01:46:00.380 --> 01:46:02.620
 But what we use this matrix for

01:46:02.620 --> 01:46:05.900
 is that if there are any particular special topics

01:46:05.900 --> 01:46:08.700
 that you would like staff to bring back to you

01:46:08.700 --> 01:46:11.260
 in the future so that we can have that discussion

01:46:11.260 --> 01:46:13.020
 or more posted for it,

01:46:13.020 --> 01:46:15.700
 this is the time to be able to make that request.

01:46:15.700 --> 01:46:18.980
 So you'll see on the matrix attachment

01:46:18.980 --> 01:46:21.100
 some requests that have been made in the past

01:46:21.100 --> 01:46:23.620
 that we have pending and we've noted

01:46:23.620 --> 01:46:26.300
 that we'll bring forth that at some future date.

01:46:26.300 --> 01:46:27.780
 So we've got a couple of items

01:46:27.780 --> 01:46:29.700
 that are on your matrix for now.

01:46:29.700 --> 01:46:32.380
 And then also we have our PNZ bootcamp presentations

01:46:32.380 --> 01:46:33.780
 that the staff has been doing

01:46:33.780 --> 01:46:35.740
 and we've been scheduling those as needed.

01:46:35.740 --> 01:46:40.060
 But again, if there is a particular request,

01:46:40.060 --> 01:46:41.500
 a special project that you're interested

01:46:41.500 --> 01:46:42.740
 in the staff working on,

01:46:42.740 --> 01:46:45.700
 this would be the appropriate time to make that request.

01:46:45.700 --> 01:46:47.420
 We will add it to our matrix

01:46:47.420 --> 01:46:49.340
 and note the commissioner who requested it,

01:46:49.340 --> 01:46:50.500
 the request date,

01:46:50.500 --> 01:46:52.700
 and then we will get it also programmed

01:46:52.700 --> 01:46:53.980
 into our work program.

01:46:53.980 --> 01:47:02.460
 - Okay, are there any other questions?

01:47:02.460 --> 01:47:06.100
 There is no action to take on this item.

01:47:06.100 --> 01:47:07.780
 - There's no action.

01:47:07.780 --> 01:47:08.700
 - Commissioner McDuff.

01:47:08.700 --> 01:47:10.580
 - So as an addition to the matrix,

01:47:10.580 --> 01:47:13.380
 I just have on my clipboard,

01:47:13.380 --> 01:47:15.300
 I'd like to talk a little bit more

01:47:15.300 --> 01:47:19.300
 about techniques of public engagement,

01:47:19.300 --> 01:47:24.300
 just so we would all know those methodologies.

01:47:24.300 --> 01:47:32.260
 So that's on my clipboard, number one.

01:47:32.260 --> 01:47:34.460
 - So when you say,

01:47:34.460 --> 01:47:35.780
 just to make sure I understand the request,

01:47:35.780 --> 01:47:36.940
 so I know what we bring back.

01:47:36.940 --> 01:47:38.740
 So when you talk about the techniques

01:47:38.740 --> 01:47:40.740
 of public engagement methodologies,

01:47:40.740 --> 01:47:42.740
 you're talking about public engagement

01:47:42.740 --> 01:47:44.660
 that we as staff do?

01:47:44.660 --> 01:47:45.500
 - Yes.

01:47:45.500 --> 01:47:46.340
 - Okay.

01:47:46.340 --> 01:47:47.160
 - Yes, ma'am.

01:47:47.160 --> 01:47:48.380
 - We can add that to the matrix and bring that back.

01:47:48.380 --> 01:47:49.500
 - Thank you so much.

01:47:49.500 --> 01:47:54.860
 And that may be already part of our boot camp training, but.

01:47:54.860 --> 01:47:58.020
 - We'll double check,

01:47:58.020 --> 01:48:00.260
 but nonetheless, we'll make sure we get it added.

01:48:00.260 --> 01:48:01.100
 - Thank you, ma'am.

01:48:06.980 --> 01:48:07.980
 Any other requests?

01:48:07.980 --> 01:48:11.140
 Okay.

01:48:11.140 --> 01:48:11.980
 There are none.

01:48:11.980 --> 01:48:12.940
 Moving to item seven.

01:48:12.940 --> 01:48:14.780
 Are there any concluding items?

01:48:14.780 --> 01:48:17.700
 Okay.

01:48:17.700 --> 01:48:18.540
 There are none.

01:48:18.540 --> 01:48:22.580
 I am going to close this PNZ meeting at 722.