Jul 18, 2019 Special Citizens Bond Advisory Committee on 2019-07-18 5:30 PM
July 18, 2019 Special Citizens Bond Advisory Committee 30224
Meeting Details
| Meeting Date: | July 18, 2019 |
|---|---|
| Board: | Special Citizens Bond Advisory Committee |
| Video ID: | 30224 |
| Has Transcript: | Yes |
|---|---|
| Has Agenda: | Yes |
AI Summary by Dentron 3000
Meeting Summary: Special Citizens Bond Advisory Committee Meeting (July 18, 2019)
1. Administrative Actions - The meeting was called to order by City Secretary Rosa Rios. A motion was made and seconded to appoint Board Member Tim Crouch as Temporary Chair. The motion carried by majority vote.
2. Public Comment - Residents discussed the proposed widening of Brush Creek Road (Hickory Creek Road), expressing concerns about necessity, traffic, property impact, infrastructure alternatives, environmental issues, and requesting clarification on project specifics.
3. Financial Presentation and Assumptions - David Gaines, Director of Finance, presented financial considerations for the proposed 2019 bond program: - Assumed a 5% assessed value growth rate for future years (motion passed unanimously). - Reviewed funding levels and their impact on debt service tax rates: - $235 million program: up to 5-cent increase. - $210 million program: up to 4-cent increase. - $180 million program: up to 3-cent increase. - $100 million program: no increase, with later rate decreases. - Discussed the new state legislation reducing the rollback rate for Maintenance & Operations to 3.5%.
4. Street Rehabilitation Program - Todd Estes, City Engineer, detailed a $70 million allocation for street rehabilitation using a hybrid approach: - Neighborhood approach focusing on holistic reconstruction of specific neighborhoods with low Overall Condition Index (OCI) scores. - Low OCI approach addressing remaining citywide streets with OCI of 20 or less. - Distribution of funds across council districts.
5. Ryan Road Project - Staff compared two funding scenarios for Ryan Road improvements: - $10 million option: includes intersection improvements and a three-lane roadway in select segments. - $19–$25 million option: includes a three-lane roadway for the entire length, comprehensive drainage improvements, sidewalks, street lighting, and trees.
6. Hickory Creek Road (Brush Creek Road) Discussion - Todd Estes addressed questions regarding the proposed six-lane facility: - Alignment options favor Hickory Creek over Ryan Road due to safety and connectivity. - Design flexibility includes narrower rural segments and phased construction. - $34 million bond contribution intended to leverage additional state/county funds for a total project cost of ~$160 million. - Project aims to eliminate at-grade railroad crossings and improve safety.
Next Steps - The committee took a short break to prepare for the prioritization of specific projects within the bond package.
Meeting Summary: Bond Committee Discussion on Hickory Creek Extension and Project Prioritization
1. Hickory Creek Road Extension Discussion - Project Scope: $34 million bond portion covers construction from River Pass to FM 1830, including design for the full route to I-35W, with two three-lane bridges and drainage infrastructure. - Alignment Options: Recommended Hickory Creek over Ryan Road due to safety concerns and connectivity. - Lane Width: Six-lane bridges striped for four lanes; roadway between bridges built with six lanes but striped for four. - Funding Leverage: Hickory Creek identified in the mobility plan, allowing for greater leverage of state/federal matching funds. - Land Use Concerns: Discussion on assumed higher density development versus the Denton 2030 Plan; securing right-of-way now to prevent future condemnation costs. - Decision: No final decision made on the Hickory Creek extension; remains under consideration for prioritization.
2. Prioritization Survey Results - Top 6 Projects: Police Station Renovation, Fire Station 8, Police Substation, Street Rehabilitation Program, Bonnie Brae Street, Hickory Creek Extension. - Lower Priority Items: Sidewalks, Street Lighting, Ryan Road, Robinson Road, and Firing Range. - Dollar Thresholds: Reviewed aggregate costs for various bond totals ($100M, $180M, $210M, $235M).
3. Public Art Policy Debate - Issue: Current policy mandates 2% of vertical construction costs for public art, amounting to approximately $1.3 million. - Discussion: Debate on allocating $1.3 million to public art versus more critical infrastructure needs. - Clarification: Staff clarified that the 2% is calculated based on vertical construction but can be allocated to any proposition. - Motions: Several motions made and withdrawn due to procedural confusion and ongoing discussion.
4. Final Motions and Votes - Motion 1: Recommend items 1 through 10 (totaling $235 million) with no public art funding; failed to gain a second. - Motion 2: Recommend items 1 through 5 (Police Station Renovation, Fire Station 8, Police Substation, Street Rehabilitation Program, Bonnie Brae Street) for inclusion in the bond package. - Amendment: Motion amended to include only items 1 through 5 to allow further discussion on Hickory Creek. - Vote: The amended motion passed unanimously. - Adjournment: Committee adjourned with the understanding that the next meeting will focus on finalizing remaining project selections, the total bond amount, and the public art allocation.
Action Items/Next Steps - Finalize project selections and bond amount at the next meeting. - Address public art policy and allocation in subsequent discussions. - Continue prioritization of Hickory Creek Road extension.