00:00:00.000 --> 00:00:04.080
 Okay. It is 9.02 and we do have a quorum,

00:00:04.080 --> 00:00:07.280
 so I'll call to order the public utilities board for

00:00:07.280 --> 00:00:11.300
 the city of Denton on Monday, October 23rd, 2023.

00:00:11.300 --> 00:00:14.320
 The first item is presentations for members of the public,

00:00:14.320 --> 00:00:16.480
 and we do have Mr. Don Murky,

00:00:16.480 --> 00:00:22.320
 who's going to speak on POB 23192 with the contract with Blink.

00:00:22.320 --> 00:00:26.680
 Is he here? Okay. You have three minutes.

00:00:30.280 --> 00:00:34.120
 I'm Don Murky. I live at 2005 Hollyhill Denton.

00:00:34.120 --> 00:00:36.120
 I've lived here since '69.

00:00:36.120 --> 00:00:40.360
 I've been driving EVs for 10 years next month.

00:00:40.360 --> 00:00:47.240
 Became aware of this and was looking at the different things in this.

00:00:47.240 --> 00:00:51.560
 I think there's some emissions and some errors in this proposal.

00:00:51.560 --> 00:00:54.840
 The 110 voltage that they have on there with

00:00:54.840 --> 00:00:58.280
 all these different pieces of equipment to do that.

00:00:58.280 --> 00:01:01.360
 I don't understand the necessity of the 110.

00:01:01.360 --> 00:01:04.760
 It's not viable really for EVs.

00:01:04.760 --> 00:01:07.720
 They require a much higher voltage to charge.

00:01:07.720 --> 00:01:09.760
 240 will work.

00:01:09.760 --> 00:01:12.920
 I charged a 240 at my house.

00:01:12.920 --> 00:01:15.680
 It required a 1450 plug,

00:01:15.680 --> 00:01:18.720
 which is RV-based plug.

00:01:18.720 --> 00:01:21.840
 I have it at 60 amps protection and charge at 30 amps,

00:01:21.840 --> 00:01:23.720
 and it charges my vehicles every night.

00:01:23.720 --> 00:01:26.040
 Cost me less than $100 to put in.

00:01:26.040 --> 00:01:29.520
 I don't need monitoring with software, anything like that.

00:01:29.520 --> 00:01:31.080
 It works very well.

00:01:31.080 --> 00:01:35.880
 In the proposal, I noticed that they don't list what the connectors are,

00:01:35.880 --> 00:01:37.800
 that they're going to be using on the level 2,

00:01:37.800 --> 00:01:40.640
 which is the 240 plugs.

00:01:40.640 --> 00:01:45.320
 Those typically in the old days were CCS,

00:01:45.320 --> 00:01:48.880
 which is what they list for their level 3,

00:01:48.880 --> 00:01:50.160
 which are the superchargers,

00:01:50.160 --> 00:01:53.080
 the 60 and 150 kilowatt ones.

00:01:53.080 --> 00:01:55.240
 This is already obsolete.

00:01:55.240 --> 00:02:04.640
 Every manufacturer that's making a car in North America has adopted the NACS Tesla adapter.

00:02:04.640 --> 00:02:06.760
 It's simpler, it's smaller,

00:02:06.760 --> 00:02:08.640
 it has no moving parts,

00:02:08.640 --> 00:02:11.520
 no switches that frequently break.

00:02:11.520 --> 00:02:16.920
 I tried to run a company here in town using Nissan Leafs,

00:02:16.920 --> 00:02:19.920
 which required using the CCS charger,

00:02:19.920 --> 00:02:22.720
 and I tried to use the blink charging system,

00:02:22.720 --> 00:02:26.640
 and I frequently had issues with their equipment being broken.

00:02:26.640 --> 00:02:29.200
 I've driven a Tesla for 10 years next month.

00:02:29.200 --> 00:02:30.360
 I've got four of them.

00:02:30.360 --> 00:02:34.680
 I have yet to be a Tesla charger that is not functioned.

00:02:34.680 --> 00:02:37.680
 We have Tesla chargers here.

00:02:37.680 --> 00:02:39.760
 They could be used.

00:02:39.760 --> 00:02:43.560
 The level 3 chargers that they're talking about,

00:02:43.560 --> 00:02:50.120
 those are basically used for people that are going from Denton to Austin,

00:02:50.120 --> 00:02:52.000
 and we want to charge on the road.

00:02:52.000 --> 00:02:56.240
 They charge 80 percent usually in 15 to 30 minutes.

00:02:56.240 --> 00:02:58.640
 Being for a city fleet,

00:02:58.640 --> 00:03:01.520
 it doesn't really seem practical for the money.

00:03:01.520 --> 00:03:03.640
 For the amount of money that this is,

00:03:03.640 --> 00:03:09.440
 we're trying to put on the table close to a million dollars for three years to do this,

00:03:09.440 --> 00:03:13.480
 it's obsolete when you even start into the gate.

00:03:13.480 --> 00:03:18.720
 Next year, every car is going to have a different adapter on it.

00:03:18.720 --> 00:03:24.080
 So this needs to be pulled and it needs to be reevaluated.

00:03:24.080 --> 00:03:26.360
 This technology is changing,

00:03:26.360 --> 00:03:28.480
 and I know when this was brought up,

00:03:28.480 --> 00:03:35.560
 it probably wasn't NACS as the prevalent adapter.

00:03:35.560 --> 00:03:41.740
 Now it is, and every manufacturer including Toyota just last week adapted that.

00:03:41.740 --> 00:03:45.960
 So I think there's some errors in this,

00:03:45.960 --> 00:03:48.200
 and I think we're jumping the gun on this.

00:03:48.200 --> 00:03:49.480
 I understand we need to do it.

00:03:49.480 --> 00:03:51.920
 So that's about all I have to say.

00:03:51.920 --> 00:03:53.120
 Thank you.

00:03:53.120 --> 00:03:57.320
 All right.

00:03:57.320 --> 00:03:59.960
 No, there's no one else from the public to speak,

00:03:59.960 --> 00:04:02.160
 so we'll go into the consent agenda.

00:04:02.160 --> 00:04:06.000
 Does any board member wish to pull an items A through G?

00:04:06.000 --> 00:04:09.120
 I know Mr. Rybeck was pulling two.

00:04:09.120 --> 00:04:13.280
 As soon as he gets his mic on.

00:04:13.280 --> 00:04:16.000
 Okay. Yes, I would like to pull items E and G.

00:04:16.000 --> 00:04:19.560
 Okay. Item E and G.

00:04:19.560 --> 00:04:24.720
 Okay. So do we have a motion to approve items A, B, C, D, F?

00:04:24.720 --> 00:04:26.240
 Second.

00:04:26.240 --> 00:04:30.160
 All in favor say aye.

00:04:30.160 --> 00:04:31.320
 Aye.

00:04:31.320 --> 00:04:38.720
 Okay. Item E. That is the blink contract.

00:04:46.760 --> 00:04:49.680
 Madam Chair, board members, Michael Gagne,

00:04:49.680 --> 00:04:52.080
 Director of Environmental Services and Sustainability.

00:04:52.080 --> 00:04:53.680
 I do not have a presentation,

00:04:53.680 --> 00:04:55.600
 but I can answer any questions you have.

00:04:55.600 --> 00:04:58.400
 The primary focus of this contract is to clarify,

00:04:58.400 --> 00:04:59.960
 is for our city fleet,

00:04:59.960 --> 00:05:02.200
 they're not to be made publicly available.

00:05:02.200 --> 00:05:04.480
 It's to upgrade the existing locations.

00:05:04.480 --> 00:05:08.520
 We have about five across the city and we have one location we need to add new.

00:05:08.520 --> 00:05:14.440
 The contract right now, we've estimated roughly 228,000 over the first three years.

00:05:14.440 --> 00:05:18.040
 It's just what we've projected, depending on the growth of the fleet, what's available.

00:05:18.040 --> 00:05:22.160
 They have actually in the contract given us the option to change out connectors.

00:05:22.160 --> 00:05:27.000
 So we have options for all different types of connectors within the proposal.

00:05:27.000 --> 00:05:30.360
 To address the DC fast charger or the level three.

00:05:30.360 --> 00:05:34.640
 One of the reasons there is if we start getting into PDs fleet,

00:05:34.640 --> 00:05:43.160
 we will have to have the ability to charge quickly because those vehicles cannot be parked typically for 12 or 14 hours or even six hours.

00:05:43.160 --> 00:05:45.720
 They're used to basically 24/7.

00:05:45.720 --> 00:05:47.040
 So that's the reason that was included.

00:05:47.040 --> 00:05:52.080
 Level one was included because there is a portion of our fleet that averages about 30 miles a day.

00:05:52.080 --> 00:05:59.440
 Those actually at level one done correctly can stay at 100% every week on a regular basis without less demand.

00:05:59.440 --> 00:06:00.960
 So it's just an option in there.

00:06:00.960 --> 00:06:02.800
 Does it mean we're going to choose it?

00:06:02.800 --> 00:06:04.840
 I'll leave it there.

00:06:04.840 --> 00:06:08.200
 Thank you. Miraculously, my microphone is working.

00:06:08.200 --> 00:06:10.040
 I don't know who fixed that, but thank you.

00:06:10.040 --> 00:06:11.280
 Thank you, Mr. Fuente.

00:06:11.280 --> 00:06:18.680
 So, board, just so you know, all the mics are on, so just know that.

00:06:18.680 --> 00:06:19.560
 Interesting.

00:06:19.560 --> 00:06:21.000
 Well, thank you very much.

00:06:21.000 --> 00:06:23.760
 I answered one of my questions.

00:06:23.760 --> 00:06:28.640
 I think our presenter from the public did a nice job of bringing up some things to consider,

00:06:28.640 --> 00:06:33.600
 and I'm glad that this has already been undertaken as part of the plan for this.

00:06:33.600 --> 00:06:38.440
 I'm curious about the total value of this EV installation project.

00:06:38.440 --> 00:06:41.400
 I'm assuming the software is only a part of it?

00:06:41.400 --> 00:06:42.200
 Correct.

00:06:42.200 --> 00:06:42.880
 OK.

00:06:42.880 --> 00:06:51.960
 So do we know what the overall value of this EV charger installation operation is?

00:06:51.960 --> 00:06:53.760
 I'm not sure I'm following the question.

00:06:53.760 --> 00:06:59.280
 This contract is to buy the actual charger itself, kind of like buying an ATM machine as well.

00:06:59.280 --> 00:07:01.720
 It's the product itself with the charging cord.

00:07:01.720 --> 00:07:07.320
 And then we have the option to use their software or their connectivity on a monthly basis as well.

00:07:07.320 --> 00:07:12.560
 So that way our fleet drivers will know if a charging station is available, they can queue in,

00:07:12.560 --> 00:07:16.120
 get alerted, they can be alerted when their car is actually charged, things like that.

00:07:16.120 --> 00:07:17.480
 That's the benefit to the software.

00:07:17.480 --> 00:07:20.800
 So how many chargers are involved in this project?

00:07:20.800 --> 00:07:22.960
 It's built out each year differently.

00:07:22.960 --> 00:07:28.640
 The first year, we're looking between five and seven in year one, mainly level two.

00:07:28.640 --> 00:07:30.440
 Those are different sites we have.

00:07:30.440 --> 00:07:35.440
 In year two, depending on how availability comes on fleet, was the first year we were looking

00:07:35.440 --> 00:07:39.680
 at doing a DC fast charger or a level three charger.

00:07:39.680 --> 00:07:43.240
 That year, we'd probably add in roughly the same five to seven level twos as well,

00:07:43.240 --> 00:07:45.120
 if the fleet grows enough.

00:07:45.120 --> 00:07:47.040
 If not, that would get delayed.

00:07:47.040 --> 00:07:52.040
 And year three is primarily focused on adding an additional level two chargers across the fleet.

00:07:52.040 --> 00:07:58.240
 Currently, we have six full EVs in our fleet, and we do have a few plug-in hybrids as well.

00:07:58.240 --> 00:08:00.920
 But we actually only have six currently in our fleet.

00:08:00.920 --> 00:08:03.240
 OK. But the plan is for that fleet to grow.

00:08:03.240 --> 00:08:06.880
 And therefore, this is to accommodate that expansion?

00:08:06.880 --> 00:08:13.840
 Correct. And to back up one piece, one of Council's priority is to look at EV across the city of Denton.

00:08:13.840 --> 00:08:18.600
 So we're working on a plan to look at how we help out or what we do to assist multifamily.

00:08:18.600 --> 00:08:20.920
 What do we do in the retail restaurant sector?

00:08:20.920 --> 00:08:22.960
 How do we do that across all of Denton?

00:08:22.960 --> 00:08:24.400
 What do we do within our city fleet?

00:08:24.400 --> 00:08:27.160
 What's our five-year plan for upgrading, changing out?

00:08:27.160 --> 00:08:28.480
 How do we make that happen?

00:08:28.480 --> 00:08:30.840
 We're working on that, and that's one of Council priorities.

00:08:30.840 --> 00:08:34.440
 It's out there on our strategic dashboard as well, if you're interested.

00:08:34.440 --> 00:08:36.160
 OK. Well, I did not know that.

00:08:36.160 --> 00:08:39.200
 So I guess that's something I can go look at. Thank you.

00:08:39.200 --> 00:08:44.920
 So do we know overall what the cost of operation of these EV chargers are up to date?

00:08:44.920 --> 00:08:48.080
 And then for the future, do we have any projection of what that's going to cost?

00:08:48.080 --> 00:08:52.760
 Or does DME just provide the power and grant us because it's for the city?

00:08:52.760 --> 00:08:58.040
 We pay DME for the power like we would pay for it for any other part of operating a building.

00:08:58.040 --> 00:09:01.200
 So DME does not provide it for free.

00:09:01.200 --> 00:09:03.000
 I don't have an overall demand on that.

00:09:03.000 --> 00:09:07.680
 It depends on the size of the fleet and where that stands as far as that cost.

00:09:07.680 --> 00:09:17.080
 Do we have a cost comparison between the EV and the charging cost and then the cost of operation of a normal vehicle?

00:09:17.080 --> 00:09:22.560
 What I can say there is typically the payback on an EV can be paid back for the difference in cost,

00:09:22.560 --> 00:09:25.040
 whether it be fuel cost, maintenance cost, everything else.

00:09:25.040 --> 00:09:29.680
 It's usually within that three year period, sometimes as high as five, depending on what you're buying.

00:09:29.680 --> 00:09:37.120
 OK, so after three years, five year period, you've retired the added cost of electric vehicle charging.

00:09:37.120 --> 00:09:44.360
 Correct. Well, and the upcharge of the vehicle itself, because most EVs are slightly higher priced currently.

00:09:44.360 --> 00:09:48.840
 They're projected to come down to be almost cost neutral closer to 2030.

00:09:48.840 --> 00:09:50.600
 Just depends on the growth.

00:09:50.600 --> 00:09:52.400
 Well, that's great. It's going to get some idea of this.

00:09:52.400 --> 00:09:56.720
 You came to us and asked for money and I was looking at it, OK, where's the rest of it?

00:09:56.720 --> 00:10:02.200
 And the reason we're here is, you know, we do have vehicles within solid waste fleet and within DME's fleet.

00:10:02.200 --> 00:10:05.360
 So we want to make sure that the public utility board is aware of this action.

00:10:05.360 --> 00:10:16.480
 OK, excellent. My last question has to do with the fact this is third party software that we'll be taking into the city, into its operations.

00:10:16.480 --> 00:10:18.360
 Actually, no, they'll operate independently.

00:10:18.360 --> 00:10:22.760
 We will have access to their cloud, so it won't actually integrate within our network system.

00:10:22.760 --> 00:10:28.480
 It'll be similar to what currently we have some publicly facing chargers that are done through ChargePoint.

00:10:28.480 --> 00:10:31.440
 ChargePoint manages all that and then provides the data back to us.

00:10:31.440 --> 00:10:38.080
 They don't actually integrate. OK, so there won't be any of the operator information,

00:10:38.080 --> 00:10:44.920
 city information, city client information like us, the users of DME.

00:10:44.920 --> 00:10:47.160
 No, they will not have access to anything on the city side.

00:10:47.160 --> 00:10:50.920
 We would actually set up with them like any other account within it all.

00:10:50.920 --> 00:10:54.880
 It would be for our users within the blank system.

00:10:54.880 --> 00:11:00.360
 Once they get their log in, they'll be able to use that in our system as well as go outside the system.

00:11:00.360 --> 00:11:03.600
 If we put basically a P card or a mechanism behind it.

00:11:03.600 --> 00:11:09.400
 So if they go to Austin or if they go to Fort Worth or they go to Dallas, they can charge while they're there as well.

00:11:09.400 --> 00:11:13.960
 Under one system, like a fuel card does right now for us under the fuel main gas cards.

00:11:13.960 --> 00:11:24.400
 Well, one of the reasons I asked about this is every data breach that has occurred in our world has been third party software without failure, every one of them.

00:11:24.400 --> 00:11:32.600
 So I saw this and I said, OK, we're going to have users, we're going to have data, we're going to have client information, we're going to have billing information.

00:11:32.600 --> 00:11:35.200
 So hence my concern.

00:11:35.200 --> 00:11:36.800
 This should be fairly simple.

00:11:36.800 --> 00:11:41.400
 And since it would identify a unit and a user number, which would be unique to those two things,

00:11:41.400 --> 00:11:47.160
 which would probably be meaningless to anybody in the public if I quoted off some vehicle numbers to y'all.

00:11:47.160 --> 00:11:51.280
 I don't think y'all would know it probably wouldn't know our employee ID numbers either.

00:11:51.280 --> 00:11:52.960
 That's really what will be in there.

00:11:52.960 --> 00:11:55.920
 OK. Well, getting back to our guest's question.

00:11:55.920 --> 00:12:03.200
 So how many charges do we currently have an operation for the city fleet for the city fleet?

00:12:03.200 --> 00:12:07.040
 We have six locations.

00:12:07.040 --> 00:12:16.520
 Most of those are dual port. One is a single port, two or single ports, meaning the plug connections to one has only two sites.

00:12:16.520 --> 00:12:19.400
 You can connect one vehicle at a time for sites.

00:12:19.400 --> 00:12:26.640
 You can connect up to two vehicles, dual port, dual outlets, dual whips, dual connections.

00:12:26.640 --> 00:12:28.600
 I know, Mr. Oh, I'm sorry. Go ahead.

00:12:28.600 --> 00:12:31.880
 No, please. No, no, no. I was just going to follow on this question.

00:12:31.880 --> 00:12:38.840
 So what about this issue that you brought up about the connectors and the types of plugs and the within the contract?

00:12:38.840 --> 00:12:45.160
 We have the ability to choose which ones we want to deploy and we have a cost in there to change those out if we ever need to as well.

00:12:45.160 --> 00:12:51.440
 So they've given us a cost for repair. If one gets broken, cut damage, we have that ability within that.

00:12:51.440 --> 00:12:57.960
 And they've said they can they can use all every universal port available is what they've told us we can choose from.

00:12:57.960 --> 00:13:07.400
 OK, so the current half dozen locations that we have, what kinds of plugs are they currently using or do you know?

00:13:07.400 --> 00:13:14.200
 I don't want to misspeak. They're all the older one. And I don't I don't remember which exact unit number it is.

00:13:14.200 --> 00:13:17.880
 But we have a multitude of weird ones out there. I'll leave it at that.

00:13:17.880 --> 00:13:21.200
 OK. Do you know what your newest ones are? OK.

00:13:21.200 --> 00:13:30.080
 Well, it's it to our guest question then. So are there plans to update them, modernize them, make them more uniform and universal?

00:13:30.080 --> 00:13:34.320
 That's what's phase one of the year. The first contract. Yes, yes.

00:13:34.320 --> 00:13:38.320
 Is we're going to go in and change those because those are all some aren't in the best location anymore.

00:13:38.320 --> 00:13:41.680
 We've done some facility upgrades, different things are not as accessible.

00:13:41.680 --> 00:13:45.480
 We do have one site with a fleet that doesn't have a charger.

00:13:45.480 --> 00:13:48.600
 We've done some upgrades over fleet services and that one's not as accessible.

00:13:48.600 --> 00:13:53.640
 So we'll probably move that out towards more accessible to people going in and out of there as well.

00:13:53.640 --> 00:13:56.800
 Well, I would like to thank our guests for coming and make presentation.

00:13:56.800 --> 00:13:59.920
 Those are some things I certainly hadn't thought about or been aware of.

00:13:59.920 --> 00:14:02.640
 If anybody else has any questions, feel free to dive in.

00:14:02.640 --> 00:14:07.880
 I know Mr. Reiner had a couple and thank you for your time.

00:14:07.880 --> 00:14:10.360
 Thank you for giving the same questions that I have.

00:14:10.360 --> 00:14:14.880
 And I had a couple of others that came up as you talk about those six locations.

00:14:14.880 --> 00:14:19.720
 Are those exclusive to the city of Denton for our fleet?

00:14:19.720 --> 00:14:23.120
 Yes, they're only accessible by city of debt and fleet customers.

00:14:23.120 --> 00:14:30.040
 We do have publicly accessible charge point sites that are generally only open to the public.

00:14:30.040 --> 00:14:34.040
 So we have those at a couple of libraries, a couple of park sites as well as development services.

00:14:34.040 --> 00:14:44.240
 So the stations that are on private properties, buckies or wherever, are those accessible to the city as well?

00:14:44.240 --> 00:14:49.160
 I mean, do you have, when you said you had a charge card, could you go use those as well if needed be?

00:14:49.160 --> 00:14:53.280
 If you're going to Austin, I would think you would have to use some kind of credit card.

00:14:53.280 --> 00:14:59.720
 To clarify there, there are certain stations out there that are limited to the model or manufacturer you're driving.

00:14:59.720 --> 00:15:02.080
 So the Teslas are driven for Teslas.

00:15:02.080 --> 00:15:02.680
 Yes.

00:15:02.680 --> 00:15:06.160
 Then we have limited use ones such as embassy suites.

00:15:06.160 --> 00:15:10.440
 That site has a charger, but it's for their overnight guests.

00:15:10.440 --> 00:15:13.280
 For their guests get to use that, it's not just for the general public.

00:15:13.280 --> 00:15:20.560
 Whereas a lot of the ones over by Walmart, Kroger, those things on University or 380, anybody can use them.

00:15:20.560 --> 00:15:27.000
 And within these networks, once you establish an account, you can basically use everybody else's sites,

00:15:27.000 --> 00:15:34.320
 except for Tesla or if they're restricted to whether it be residents at the apartment complex or guests or things like that.

00:15:34.320 --> 00:15:42.480
 And then the additional five to seven, the first year, are they specific?

00:15:42.480 --> 00:15:49.880
 Seven or five different locations or just additional power towers, I'll call it, in the current locations.

00:15:49.880 --> 00:15:52.680
 It's actually kind of like we did in this room before you got here.

00:15:52.680 --> 00:15:54.680
 We're going to refresh the current sites.

00:15:54.680 --> 00:15:59.320
 We're only going to add one new charging site in year one, which would be development services.

00:15:59.320 --> 00:16:04.000
 We have two vehicles there that do not have overnight access to a charger.

00:16:04.000 --> 00:16:05.600
 They're going to other locations currently.

00:16:05.600 --> 00:16:09.840
 And then one other question, I think.

00:16:09.840 --> 00:16:15.000
 Presently, we have about six EV vehicles in the fleet, is that correct?

00:16:15.000 --> 00:16:22.120
 And I did not realize this, but you're saying that the council wants us to expand that, which I can understand.

00:16:22.120 --> 00:16:26.360
 Do you have a projection on what we're looking at as to what additional?

00:16:26.360 --> 00:16:29.680
 How large is the fleet going to be next year, let's say, if that's possible?

00:16:29.680 --> 00:16:31.360
 And what kind of vehicles are we?

00:16:31.360 --> 00:16:33.760
 How big does it go as far as the vehicles?

00:16:33.760 --> 00:16:38.160
 Is it just a sedan or does it go up to past pickups, whatever?

00:16:38.160 --> 00:16:40.480
 And is it a question that I can ask in public?

00:16:40.480 --> 00:16:43.120
 You can. We're not quite there yet.

00:16:43.120 --> 00:16:45.080
 We've had some change outs, different things.

00:16:45.080 --> 00:16:48.240
 We're working closely with fleet services to build that plan.

00:16:48.240 --> 00:16:50.080
 That's part of that overall council direction.

00:16:50.080 --> 00:16:54.080
 One piece of that is for us to be looking heavily at a five year cost replacement.

00:16:54.080 --> 00:16:57.720
 And so how we can look at how we transition the fleet to EV.

00:16:57.720 --> 00:17:03.200
 Currently on the market, you do have vehicles ranging anywhere from a small sedan up to at least a light duty pickup.

00:17:03.200 --> 00:17:05.360
 There are some medium duties. They're just not quite there.

00:17:05.360 --> 00:17:10.240
 There's very limited heavy duty, but our primary focus initially be the light duty fleet,

00:17:10.240 --> 00:17:14.600
 which would be anything from a sedan up through a pickup truck, just depending on availability.

00:17:14.600 --> 00:17:17.440
 Again, the supply chain issue has been part of our challenge.

00:17:17.440 --> 00:17:20.280
 We try to do some orders a year and a half ago.

00:17:20.280 --> 00:17:24.200
 They haven't processed. We're still trying to do five new orders currently.

00:17:24.200 --> 00:17:28.720
 And I've been told now those may not go in go in until January.

00:17:28.720 --> 00:17:33.280
 And if they go in in January, I don't know when they'll deliver.

00:17:33.280 --> 00:17:43.120
 OK. So when the when the fleet is expanded, is that is that an issue that will be brought before us before it's done?

00:17:43.120 --> 00:17:45.840
 Or is that already carte blanche done?

00:17:45.840 --> 00:17:49.120
 I wouldn't say it's carte blanche. That's part of what fleet services works on.

00:17:49.120 --> 00:17:55.520
 And depending on which purchases are going on and which funds are paying for those pieces of that may come back through.

00:17:55.520 --> 00:17:59.720
 But again, if it's more general fund driven, those kind of things, it wouldn't come back to this board.

00:17:59.720 --> 00:18:04.040
 So no. All right. Thank you. Thank you, Madam Chair. All right.

00:18:04.040 --> 00:18:07.720
 Oh, go ahead. Go ahead. Good morning. How are you doing?

00:18:07.720 --> 00:18:10.640
 I knew you had to have one. Yeah.

00:18:10.640 --> 00:18:15.160
 So I think I have two questions in the price evaluation.

00:18:15.160 --> 00:18:18.320
 The level three charger prices weren't included.

00:18:18.320 --> 00:18:25.480
 And it seems like that could be a significant cost, like one might be 20 times as expensive as a level two charger.

00:18:25.480 --> 00:18:32.680
 Funny you use that number. It's about it is about that procurement as we work through that, we've got prices on everything.

00:18:32.680 --> 00:18:39.360
 The list in there, I'm looking, I don't know, I don't see Laurie in the room.

00:18:39.360 --> 00:18:44.520
 We cleaned it up to make sure that we had a clear basis to make sure we were comparing apples to apples.

00:18:44.520 --> 00:18:50.800
 So the primary cost comparison was focused in on the level two, which would be the primary use across the city.

00:18:50.800 --> 00:19:01.640
 The level threes did come in. My memory on blink as a manufacturer, they were actually lower on the level DC fast chargers level threes.

00:19:01.640 --> 00:19:11.760
 Now, the challenge there to speak to my predecessor speaking earlier, there's about seven or eight different tiers of DC fast charging out there.

00:19:11.760 --> 00:19:21.160
 So I'd have to go back and look and each proposal to make sure that specifically they were cheaper on what we're what we tried to compare against within that.

00:19:21.160 --> 00:19:27.560
 OK, and then I'm following on Commissioner Rybeck's question about cost.

00:19:27.560 --> 00:19:40.160
 I know personally, I have an E.V. and, you know, two gas powered vehicles and the the cost to run it, the cost to operate and maintain it is like a small fraction.

00:19:40.160 --> 00:19:43.160
 Ten or 20 percent of the cost of a conventional vehicle.

00:19:43.160 --> 00:19:55.920
 But I know in a fleet, it's different. So I'd I'd love to see in a year or two just to kind of an update on, you know, what's the difference in fleet cost for maintenance and fueling effectively.

00:19:55.920 --> 00:19:59.000
 And to add to that, that's one thing fleets really focused on.

00:19:59.000 --> 00:20:08.080
 Currently, we're trying to put GPS units and all of our fleet to get really accurate information to know the use and demand on those vehicles to be able to do that comparison back.

00:20:08.080 --> 00:20:20.800
 Thank you. Madam Chair, I'll just ask Devin if you could bring that up at our management when we get to our management section and then we can make sure that there's there's agreement that for us to do that and we can add it to our future agenda items.

00:20:20.800 --> 00:20:25.800
 OK. All right. Any further questions?

00:20:25.800 --> 00:20:39.320
 I move approval of agenda item. Thank you. You'd be twenty three one ninety two. Do we have a second second. All in favor say aye.

00:20:39.320 --> 00:20:55.880
 Carries. Next is twenty three one ninety four contract with S.E.A. Towers Limited for some transmission. And Mr. Ryback pulled that one off. Yes, I'm the guilty party.

00:20:55.880 --> 00:21:00.240
 More code, it's an already engineering answer. Any questions regarding still poles?

00:21:00.240 --> 00:21:08.360
 Yes, sir. Thank you for joining us this morning. I appreciate it. I don't really have any problem with the purchase of this equipment, but it brought some questions to mind.

00:21:08.360 --> 00:21:21.080
 Sure. Which are this is obviously part of a larger effort to put in this new service line. So I was curious if we at this time know the total project value.

00:21:21.080 --> 00:21:27.800
 And my other question is, so what's driving this upgrade to this particular service line?

00:21:27.800 --> 00:21:41.880
 Well, as far as value, we have the cost. I'm not sure if that's what you're asking for. The total cost of the project. The total cost will be around five point six million dollars for this contract.

00:21:41.880 --> 00:21:54.200
 For this contract, for just the material. Yes, sir. Just the material. That part I see. I'm asking no, sir. I do not know. I do not have that. OK, I can look into it and get back with you.

00:21:54.200 --> 00:22:04.120
 I would appreciate that. That's kind of my question. I understand we're buying all this hardware to make this project possible to increase the size of the service line. I get that.

00:22:04.120 --> 00:22:12.520
 So something's driving that and that total cost of the project. There must be some number out there. And I'd just like to know what it is.

00:22:12.520 --> 00:22:19.080
 I think Jerry. Mark Zimmer is going to come up here and give you a response to that. Thank you.

00:22:19.080 --> 00:22:29.400
 Yes, sir. Mark Zimmer, DME Engineering. Total project cost for this is about 14 million. About 14 million. And what is driving the upgrade to this service line?

00:22:29.400 --> 00:22:37.320
 Our studies have shown that this line is overloaded. It's currently overloaded. By the year 2025.

00:22:37.320 --> 00:22:44.440
 Could you tell us what area it currently serves? Well, it's part of the transmission system, so it generally serves a large area.

00:22:44.440 --> 00:22:52.840
 I couldn't pinpoint an exact area, but it generally serves the industrial side of town. So the west side of 35.

00:22:52.840 --> 00:22:57.320
 OK, so Peterbilt, Touchback, all those customers on the west. All right.

00:22:57.320 --> 00:23:02.920
 And the good news, Mr. Rebecca and for the board, this is part of our transmission cost of service.

00:23:02.920 --> 00:23:14.360
 So we do earn a rate of return on that as well. So we'll be seeing a large portion of that project will be basically reimbursed back to DME over the course of a number of years.

00:23:14.360 --> 00:23:21.400
 As part of that uplift program that it's done through the ERCOT grid. Well, thank you. Appreciate that.

00:23:21.400 --> 00:23:28.440
 OK, so got a rough total value of the project. Know where it's going. And those are my questions. Thank you very much.

00:23:28.440 --> 00:23:34.680
 Do we have other questions? OK, seeing none, do we have a motion to approve? So moved.

00:23:34.680 --> 00:23:47.480
 Moved. Do we have a second? Mr. Rayner, second. All in favor say aye. Aye. That carries. Next is approval of the October 9th, 2023 minute meeting.

00:23:47.480 --> 00:23:54.120
 Meeting minutes. Did anybody see any changes or corrections?

00:23:54.120 --> 00:24:02.600
 Seeing none, do we have a motion to approve the minutes? So moved. Mr. Rayner. I'll take second. OK, Mr. Black moved in. Mr. Rayner takes second.

00:24:02.600 --> 00:24:15.240
 All in favor say aye. Aye. Next is item PUB 23135, General Capital Program Expenditures for Bonds. Certificates.

00:24:15.240 --> 00:24:22.440
 See if I can get this out of my eyesight a little bit there. Good morning. Randy Klingle, Treasury Manager with the Finance Department.

00:24:22.440 --> 00:24:31.520
 I have a short presentation today, maybe. There it goes for me. Ma'am, could you speak more into the microphone? Thank you.

00:24:31.520 --> 00:24:38.120
 How's this? This better? Better. OK. Much. I'm a little height challenged here, but I'll make it work.

00:24:38.120 --> 00:24:44.200
 I have an annual reimbursement ordinance that we bring to you every year before we start the bond process.

00:24:44.200 --> 00:24:48.480
 And the reason for the reimbursement ordinance is because it's required by the IRS.

00:24:48.480 --> 00:24:56.240
 It shows that our intent that we're going to reimburse ourselves later with bond proceeds that come through the bond sale later this summer.

00:24:56.240 --> 00:25:03.760
 Normally we do the bond sale 12 months after this ordinance is executed. We do like to finish it by the end of the fiscal year.

00:25:03.760 --> 00:25:12.240
 So we will have this done by by September always so we can receive the proceeds of the same fiscal year that we have this reimbursement ordinance.

00:25:12.240 --> 00:25:19.880
 And our debt policy that governs our debt and our bond sale items do include the opportunity to have this ordinance.

00:25:19.880 --> 00:25:26.560
 So today we are only covering the utility project items for this board to oversee, and I will not be going through the project items.

00:25:26.560 --> 00:25:30.360
 They are exactly the same as you saw September 26 go through council.

00:25:30.360 --> 00:25:34.360
 So nothing has changed there, but we will be just covering the utilities.

00:25:34.360 --> 00:25:44.720
 So the first utility we have for today is solid waste, which their capital improvement plan project budget for this fiscal year is just a little bit over seven million dollars.

00:25:44.720 --> 00:25:54.240
 And in your back up, you have a couple of little narrative sentences about each fund program that kind of gives you an overall narrative of what these projects will do for them this fiscal year.

00:25:54.240 --> 00:26:07.600
 But you also have this presentation, which will give you the line item detail water project for the this fiscal year is eighty two point seven million dollars for their fund for the projects for this year.

00:26:07.600 --> 00:26:13.080
 Wastewater's budget is fifty five point nine million dollars.

00:26:13.080 --> 00:26:20.520
 And last, we have the electric fund with eighty two point five million dollars for their capital improvement, but budget for the reimbursement ordinance.

00:26:20.520 --> 00:26:33.160
 So in summary, for just the utilities, solid waste water, wastewater, electric, we have two hundred and twenty eight million three hundred and forty one thousand one hundred and fifty seven dollars in their capital improvement plan budget.

00:26:33.160 --> 00:26:47.080
 So our next steps, I'll come back to you guys in April for the notice of intent, which I'll bring the same list to you, possibly reduced depending on how things go as they look at their project timelines or cost and what their availability of projects are.

00:26:47.080 --> 00:26:56.600
 And then in May, we'll come back with the bond parameter ordinance, which will be our our final push with our final numbers on this list, and they will have a projected sell in June.

00:26:56.600 --> 00:27:06.800
 And then we'll receive our proceeds in July, and that's kind of the annual process that we have for this. And we kind of maintain that same timeline year over year.

00:27:06.800 --> 00:27:21.120
 Yes, wrong way. There we go. Any questions? Yes, ma'am. So this is a bond obligation or bond sale for this year to cover the next two fiscal years.

00:27:21.120 --> 00:27:28.840
 Well, we will get the proceeds this year and then they will allocate them and use them as it comes up and necessary for their contracts with the future.

00:27:28.840 --> 00:27:34.000
 OK, so this is for this year. Do we do this essentially every year?

00:27:34.000 --> 00:27:41.440
 Essentially every year. Yes, we have a lot of capital projects. So we do do this becomes an annual annual annual chunks, if you will.

00:27:41.440 --> 00:27:45.800
 Yes. OK, thank you. And this isn't actually the bond sale.

00:27:45.800 --> 00:27:54.000
 It's just authorizing us to go ahead and go ahead and do the reimbursement right and then reimburse ourselves when we get the proceeds.

00:27:54.000 --> 00:28:02.360
 Just want to clear that up. Yes, ma'am. Other questions? Do we have a motion to approve this item?

00:28:02.360 --> 00:28:16.160
 So, Mr. Do we have a second second and seconds? All in favor say aye. Aye. Next item is P.B. twenty three one eighty three wholesale transmission charges.

00:28:32.360 --> 00:28:51.520
 Where'd it go? That's what he's thinking.

00:28:51.520 --> 00:28:57.200
 You're just trying to make us feel good. Yeah, I don't see my presentation.

00:28:57.200 --> 00:29:12.040
 In my packet, it's called presentation dash five, if that helps you.

00:29:12.040 --> 00:29:18.240
 You may want to go to the Web site and just pull it off of there. OK, yeah, that might be quicker.

00:29:18.240 --> 00:29:39.240
 Apologize. No, no problem.

00:29:39.240 --> 00:30:08.400
 Need some help is yes, sir. Is it over here?

00:30:08.400 --> 00:30:15.000
 All right. Yes. Good morning, Madam Chairman and board member of P.B.

00:30:15.000 --> 00:30:20.520
 I'm here today to discuss transmission cost of service expense.

00:30:20.520 --> 00:30:27.080
 These are routine expenses that the electric fund incurs every single year, basically.

00:30:27.080 --> 00:30:38.280
 We're bringing this to the board for transparency purposes, and these expenses has already been approved in the budget.

00:30:38.280 --> 00:30:52.520
 So this slide right here just represents some of the external vendors that will be paying or external providers that will be paying.

00:30:52.520 --> 00:30:57.240
 And this is going to come around about seven point one million dollars.

00:30:57.240 --> 00:31:07.160
 So this is the cost that the city will pay for using other providers transmission assets pretty much.

00:31:07.160 --> 00:31:21.840
 And this next slide is just we're just listing some of the other providers that will be using that is basically under the fifty thousand dollars just for transparency purposes.

00:31:21.840 --> 00:31:26.120
 Any questions or comments? Go ahead.

00:31:26.120 --> 00:31:32.440
 Thank you, Madam Chair. So I have I have a general understanding of transmission cost of service.

00:31:32.440 --> 00:31:37.720
 We and this is just a kind of required payment within our code.

00:31:37.720 --> 00:31:48.160
 Everybody pays to use the shared grid that moves power from the various generators to the various consumers.

00:31:48.160 --> 00:31:56.880
 But I'd like to just understand a little bit more about these the individual transactions here are.

00:31:56.880 --> 00:32:07.080
 I've always seen transmission cost of service just kind of summed up as kind of a fee based on four CP peak.

00:32:07.080 --> 00:32:21.800
 Is that then just allocated out based on some other factor and every load serving entity in ERCOT pays the same kind of fractions out to the various vendors?

00:32:21.800 --> 00:32:28.320
 Or are these like individual kind of bilateral transactions for the different vendors?

00:32:28.320 --> 00:32:33.560
 Kind of a technical question, but I'm just trying to understand how this works in a little more detail.

00:32:33.560 --> 00:32:39.840
 Yes. So let me summarize. So basically all these all these service providers.

00:32:39.840 --> 00:32:43.560
 This is a dollar amount that is calculated, like you said, from the four CPs.

00:32:43.560 --> 00:32:49.400
 And then basically this is our cost to using basically their transmission assets.

00:32:49.400 --> 00:32:52.360
 And this is for the new fiscal year that's coming up.

00:32:52.360 --> 00:32:57.000
 So I hope that answer your questions or maybe Tony can help.

00:32:57.000 --> 00:32:59.640
 It looks like yes. So so you're exactly right.

00:32:59.640 --> 00:33:03.800
 It's based on your load ratio share. Right.

00:33:03.800 --> 00:33:08.800
 Both in how you charge other providers and in how you pay other providers as well.

00:33:08.800 --> 00:33:16.840
 So it's all distributed based on that four CP is calculated every year, June, July, August and September.

00:33:16.840 --> 00:33:21.560
 It's kind of it's the average of that. And so that applies to every utility out there.

00:33:21.560 --> 00:33:24.280
 And so there's some utilities where we net out.

00:33:24.280 --> 00:33:31.400
 And so we ended up having to pay because because we owe them more that they owe us or or they owe us more than than we owe them.

00:33:31.400 --> 00:33:38.720
 And so so that's how that's done across across all the TSP's transmission service providers in the state.

00:33:38.720 --> 00:33:42.960
 That was my other question. These are already netted of our transmission.

00:33:42.960 --> 00:33:50.360
 Yes. And going back to that transmission ROI from that transmission project that was being discussed earlier,

00:33:50.360 --> 00:33:59.120
 that transmission ROI would would lower these net outs in the future in future years.

00:33:59.120 --> 00:34:09.960
 Yes, correct. And so a high level currently we pay out in a single fiscal year about twenty five, twenty eight million dollars total.

00:34:09.960 --> 00:34:14.800
 This is only a portion of that. There'll be others that will come to you.

00:34:14.800 --> 00:34:23.200
 What we've been earning prior to our latest TCO case was over 60 million dollars just for comparison purposes.

00:34:23.200 --> 00:34:27.520
 As you know, we recently had a filing. There was a final order.

00:34:27.520 --> 00:34:32.400
 We anticipate that that revenue that we get is going to come down to about 30 million dollars a year.

00:34:32.400 --> 00:34:37.200
 So we're still we're still getting a little bit more than what we're paying out.

00:34:37.200 --> 00:34:41.400
 Not quite the calculation, right. But but just for comparison purposes.

00:34:41.400 --> 00:34:45.000
 So you have all the information. Thank you for that question.

00:34:45.000 --> 00:34:48.200
 Oh, go ahead, sir. You're closer. You go. Oh, you're too kind.

00:34:48.200 --> 00:34:52.640
 Could you go back a slide or two? I was just curious. Another one.

00:34:52.640 --> 00:34:54.800
 The first one. No, go back to go back where you were.

00:34:54.800 --> 00:34:58.240
 Yes. Yes. It's just like I'm at my house and they don't.

00:34:58.240 --> 00:35:04.120
 It's OK. It works. So all of these description, is this what we're paying or is this what they're paying?

00:35:04.120 --> 00:35:07.120
 Is this where we're getting additional? So what is that?

00:35:07.120 --> 00:35:11.720
 So basically, these are the dollar amounts that the city is paying out.

00:35:11.720 --> 00:35:16.480
 So this is our cost for using transmission assets from other providers.

00:35:16.480 --> 00:35:23.240
 And these are all. Now, is this a is this generally the same characters that we use?

00:35:23.240 --> 00:35:27.640
 Pardon the pun throughout the history of it? Yes, exactly.

00:35:27.640 --> 00:35:31.560
 And so if I understand then, Madam Chair, this was approved by the budget. Yes.

00:35:31.560 --> 00:35:36.640
 So the city council's already approved this. So is this just more or less this is what we're doing and hope you like it?

00:35:36.640 --> 00:35:41.040
 Because there's not really any changes we're making, is it? Just for transparency. Exactly.

00:35:41.040 --> 00:35:44.960
 Thank you. Transparency important. Transparency purpose. Thank you for your time.

00:35:44.960 --> 00:35:48.360
 My question is, you mentioned these ratios that we pay out on.

00:35:48.360 --> 00:35:52.600
 Where do those come from? Are those from the PUCT or?

00:35:52.600 --> 00:35:57.840
 Yeah. So so they're calculated based on what's called the four CP of the four coincident peaks.

00:35:57.840 --> 00:36:01.240
 It's the highest use in June, July, August and September.

00:36:01.240 --> 00:36:10.360
 That's average. And that that load share is what's what all these are based off of for everybody in the ERCOT market.

00:36:10.360 --> 00:36:13.200
 Thank you. All right.

00:36:13.200 --> 00:36:21.320
 Further questions. Do we have a motion to approve? So move seconded.

00:36:21.320 --> 00:36:25.120
 All in favor say aye. Aye.

00:36:25.120 --> 00:36:35.760
 OK. Next item is PUB one ninety five. Consider a contract with Felix Felix Construction Company for the ropes and ranch water reclamation plant lift station.

00:36:35.760 --> 00:36:56.280
 Oh, excuse me. Good morning. How are y'all?

00:36:56.280 --> 00:36:59.160
 My name is David Brown. I'm water utilities project manager.

00:36:59.160 --> 00:37:03.880
 Today, I'm going to bring to you ropes and ranch plant lift station improvement.

00:37:03.880 --> 00:37:07.080
 This is a phase one of the improvements out there.

00:37:07.080 --> 00:37:12.320
 As you know, ropes and ranch community south on 35 going towards Fort Worth.

00:37:12.320 --> 00:37:22.120
 So 20 years ago, they actually installed a wastewater plant out there that actually treats water on site, the wastewater.

00:37:22.120 --> 00:37:26.760
 And so they have a permit out there. And this was put in in play about 20 years ago.

00:37:26.760 --> 00:37:34.680
 They have permit out there of close to one M.G.D. per day. And right now they have reached 90 percent of that T.C.Q. permitted flows.

00:37:34.680 --> 00:37:40.680
 So T.C.Q. has a rule 75 90 rule at 75 percent of the permitted flows.

00:37:40.680 --> 00:37:45.720
 You're being designed and at 90 percent, we're being construction.

00:37:45.720 --> 00:37:56.120
 So with this, this plan of action is to convert the existing east lift station over to convert it over to it's going to be a lift station,

00:37:56.120 --> 00:38:05.040
 but it's going to pump into directly into connection that capital projects delivered that actually go into our Pecan Creek water reclamation plant.

00:38:05.040 --> 00:38:09.560
 So we're utilizing a new gravity and a force made that's been recently put in.

00:38:09.560 --> 00:38:14.000
 We're going to connect that over. What this does is it relieves 40 percent of those flows.

00:38:14.000 --> 00:38:19.320
 We're going to take 40 percent of those flows and put it into our regular treatment over at Pecan Creek.

00:38:19.320 --> 00:38:24.640
 Like I said, the east lift station pumps will be upgraded and also the piping will be upgraded.

00:38:24.640 --> 00:38:30.400
 What this does is twofold. It splits the flows up basically east and west.

00:38:30.400 --> 00:38:33.200
 On the west side, it'll go over to the plant like we do now.

00:38:33.200 --> 00:38:40.600
 There'll be a little bit of improvements on the SBR plant with disinfection.

00:38:40.600 --> 00:38:44.360
 At the same time, we'll split our flows and go east, we'll go over to our Pecan Creek.

00:38:44.360 --> 00:38:48.640
 So that'll increase the capacity over there at ropes and at this time.

00:38:48.640 --> 00:38:52.640
 And like I said, this is phase one. There are other opportunities. We'll go into phase two.

00:38:52.640 --> 00:38:58.800
 There's other opportunities which may be upgrading the plant or making a lift station connected to a gravity.

00:38:58.800 --> 00:39:05.080
 Of course, we want to try to get away from lift stations and plants. We want to go to gravity on that.

00:39:05.080 --> 00:39:08.760
 So with that, we have a contract.

00:39:08.760 --> 00:39:16.280
 We'd like to have approved for contract with Felix Construction at two point nine million dollars, three hundred ten days for construction.

00:39:16.280 --> 00:39:23.400
 Like I said, this is phase one and ropes and has we entered an agreement with ropes in the 2019 to help fund this.

00:39:23.400 --> 00:39:30.800
 So a lot of the funding is coming from ropes and community be glad to answer any questions.

00:39:30.800 --> 00:39:38.360
 Yes. So the current water treatment plant on the west side of the community that was built by the community.

00:39:38.360 --> 00:39:42.120
 Yes, sir. It's owned, owned, operated by the city.

00:39:42.120 --> 00:39:50.200
 That's all it is. So it is a city. We do have an operator over there. The city operates it, but ropes and community built it.

00:39:50.200 --> 00:39:52.560
 Yes. OK. So the city operates it.

00:39:52.560 --> 00:40:11.280
 So the city, in order to meet these T.E.C.Q. requirements is going to put this project, take a large percentage of the effluent flow and move it over towards the new Concrete treatment facility.

00:40:11.280 --> 00:40:15.240
 Well, it's not the new. It's our existing concrete so upgraded.

00:40:15.240 --> 00:40:28.400
 I apologize. What they the CIP group delivered a project as far as a force main to this lift station and then gravity along ropes and when under thirty five and connects over to the country lakes addition.

00:40:28.400 --> 00:40:33.360
 And then, of course, that actually leads into our concrete plant over there off of Mayhill.

00:40:33.360 --> 00:40:37.040
 Yes, sir. OK. Makes perfectly good sense. Thank you.

00:40:37.040 --> 00:40:39.560
 So I have a question. Thank you.

00:40:39.560 --> 00:40:44.040
 Obviously, we realize there's so much growth out there and more houses coming and such.

00:40:44.040 --> 00:40:52.120
 I was curious with that last comment you made as that gravity fed goes underneath thirty five and is connected to that other large subdivision.

00:40:52.120 --> 00:41:04.240
 Is this line going to be potentially being connected with other are you planning on having being connected with other subdivision developments going on or will they be parallel?

00:41:04.240 --> 00:41:16.040
 When you said phase one, do you see another potential lift station or such on that side of the west of thirty five for covering all of these?

00:41:16.040 --> 00:41:23.200
 The thought process with the initial project was to make that plant into a lift station, which can be converted.

00:41:23.200 --> 00:41:28.520
 The plant right now actually treats wastewater, just doesn't pump it, treats and discharges into a creek.

00:41:28.520 --> 00:41:46.880
 The plan is is to be able to make that a lift station because you already have the capacity, their lift station and float and actually pump reverse flow to this lift station that we're going to convert right now and and basically pump it into our conventional system that we have now.

00:41:46.880 --> 00:41:51.480
 And it's a boy. Sorry. Avoid running a plant out there at Robson.

00:41:51.480 --> 00:42:02.760
 So it is you have and I'm thinking phase two, phase three and such that will just be further expansion of that plan to take care of the additional demands that will be coming on that side.

00:42:02.760 --> 00:42:12.080
 Yes, sir. Right now, this is kind of this is a alleviate and helps right now to be able to split that flow so you can have more capacity on that west side.

00:42:12.080 --> 00:42:27.080
 And then it gives us some time in order to plan. If a developer comes in and puts in a gravity line on that north side of that plant, you know, a hundred coal addition can put a gravity line and then we can tie into that.

00:42:27.080 --> 00:42:35.240
 So and with that effect, the capacity where we would need to come back to do another seventy ninety that you were talking about, not that we know of.

00:42:35.240 --> 00:42:43.840
 It's been studied that not we know of that gravity line will alleviate a lot of that course. There's plans for another plant.

00:42:43.840 --> 00:42:51.320
 So we have, you know, that that wastewater mass plant spells out a lot of that to take care of those that growth on that west side of thirty five.

00:42:51.320 --> 00:42:54.960
 Thank you for your time. Thank you, Madam Chair. The question. Go ahead.

00:42:54.960 --> 00:43:11.560
 Well, I have another question for me. It's curiosity. It's outside the scope of this project. I recognize. But we have those two new Hunter and coal ranch developments going in basically between ropes and ranch and the thirty five W.

00:43:11.560 --> 00:43:17.440
 So are they also going to tie into this new east connector that you're building?

00:43:17.440 --> 00:43:23.240
 Not that we know of there. They're as far as I know, they're going to build their own interceptors on that side.

00:43:23.240 --> 00:43:27.520
 And they're also going to flow to Pecan Creek as of now, as of now.

00:43:27.520 --> 00:43:33.480
 OK, thank you. Oh, I don't want to think the master plan for the wastewater can test somewhere.

00:43:33.480 --> 00:43:40.920
 We can see that on the city website. I don't know if it's all been if it's been we haven't approved it yet.

00:43:40.920 --> 00:43:49.840
 It's under review. The wastewater plants will see that coming to us coming to us at a future date soon.

00:43:49.840 --> 00:43:52.200
 Thank you very much. All right.

00:43:52.200 --> 00:43:59.440
 Other questions. Or do we have a motion to approve?

00:43:59.440 --> 00:44:01.400
 So moved. Thank you, Mr. Pluck.

00:44:01.400 --> 00:44:05.600
 And do we have a second, Mr. Rybeck?

00:44:05.600 --> 00:44:10.520
 I'm going to abstain from voting since I'm employed by ropes and ranch HOA.

00:44:10.520 --> 00:44:15.840
 So. All in favor, I'm abstaining.

00:44:15.840 --> 00:44:21.640
 Thank you. Last item is management reports.

00:44:21.640 --> 00:44:25.840
 Madam Chair, members of the board, a couple of few items that we have for you.

00:44:25.840 --> 00:44:32.360
 One, we had a response to a question Mr. Rybeck had asked regarding the Spencer generation station.

00:44:32.360 --> 00:44:37.960
 And what I'll say about this is that just remember that the Spencer generation station,

00:44:37.960 --> 00:44:43.960
 even though it's next door to DME's campus, is not owned owned by DME nor the city of Denton,

00:44:43.960 --> 00:44:46.600
 actually owned by Garland Power and Light.

00:44:46.600 --> 00:44:50.960
 But we did provide some information back to Mr. Rybeck, hopefully, to answer your question.

00:44:50.960 --> 00:44:54.520
 If not, I'm happy to answer anything else you may have on that.

00:44:54.520 --> 00:44:57.360
 No, I thank you. I did read this prior to coming to the meeting.

00:44:57.360 --> 00:45:00.200
 So thank you very much. Appreciate it.

00:45:00.200 --> 00:45:03.520
 It was just curiosity. Obviously, it used to be our asset.

00:45:03.520 --> 00:45:06.280
 It's right next to our op center.

00:45:06.280 --> 00:45:13.040
 See, we have this big resource here and it's obviously in close proximity to our transmission system.

00:45:13.040 --> 00:45:17.040
 So it seemed like something would be good to know about. So thank you.

00:45:17.040 --> 00:45:25.880
 And feature agenda items. So December 11th, we have on schedule the Wastewater Master Plan

00:45:25.880 --> 00:45:30.880
 that will be coming to you by that department. They're still working on that.

00:45:30.880 --> 00:45:35.760
 And we'll begin that over to you and certainly be a work session with you.

00:45:35.760 --> 00:45:38.400
 And then new business action items.

00:45:38.400 --> 00:45:42.320
 The one item that we had was a request from Mr. Rybeck on the Spencer station.

00:45:42.320 --> 00:45:48.640
 So we've provided a response to that. Happy to answer any other questions or if there's any other requests.

00:45:48.640 --> 00:45:58.560
 I would like to make a request, as I stated earlier, regarding what information the fleet fleet has on

00:45:58.560 --> 00:46:03.520
 EV operation versus conventional ICE vehicles.

00:46:03.520 --> 00:46:06.400
 And I understand that it might take a while to gather data.

00:46:06.400 --> 00:46:10.560
 So if this is appropriate in six months or a year, that's fine.

00:46:10.560 --> 00:46:19.680
 I just wanted to just kind of begin to get an understanding for fleet at the fleet level, what the cost difference is.

00:46:19.680 --> 00:46:25.720
 Yeah, well, we'll get it added. And I'll talk to Tom Gremer, who's the director of fleet operations and make him aware of it.

00:46:25.720 --> 00:46:32.000
 Thank you. I do have a question for a future agenda, which is my third party software question.

00:46:32.000 --> 00:46:39.120
 It really occurred to me that we've talked a lot about various and sundry software systems and automated billing and things of that nature.

00:46:39.120 --> 00:46:49.280
 So I'd like to know what steps the city is taking to protect our information from data breach from via third party software vendors.

00:46:49.280 --> 00:46:53.360
 Yeah, let me let me visit with our technology department about that.

00:46:53.360 --> 00:47:00.200
 Also, our legal department to make sure that that's something that can come to the border and how how it would come to the board.

00:47:00.200 --> 00:47:03.240
 But certainly, I'll get back to you in response to that.

00:47:03.240 --> 00:47:13.000
 Thank you. And again, this blink system and then the software and I got to thinking about all the third party software breaches that our data has suffered.

00:47:13.000 --> 00:47:21.840
 So I would be curious to know what steps the city is taking since we're obviously in the business of adding more vendor software to our universal systems.

00:47:21.840 --> 00:47:29.760
 Yeah, certainly a high priority item for us as a matter of fact, that tomorrow several of us are attending a cybersecurity training down in Rowlett.

00:47:29.760 --> 00:47:38.360
 So it is something that is high on everybody's mind as we deal with a multitude of data and information.

00:47:38.360 --> 00:47:43.640
 So. And we're on to concluding items.

00:47:43.640 --> 00:47:51.320
 Does any board member wish to say anything to the public or have something put on a future agenda?

00:47:51.320 --> 00:47:56.520
 OK, seeing none, do we have a motion to adjourn?

00:47:56.520 --> 00:47:59.400
 Thank you. Thank you, Mr. Taylor. We're adjourned.