WEBVTT

00:00:00.000 --> 00:00:11.560
 good morning it's 9 a.m. and we have a quorum present so let's call the Monday

00:00:11.560 --> 00:00:19.480
 January 14th 2019 meeting of the public utility board to order we're going to

00:00:19.480 --> 00:00:24.960
 move the first item the closed meeting item to the end of the meeting and so

00:00:24.960 --> 00:00:34.200
 let's start with a regular meeting item 1 the consent agenda does any public

00:00:34.200 --> 00:00:44.360
 utility board member want to pull item a B C or D for any further discussion so

00:00:44.360 --> 00:00:51.360
 we're gonna pull item C any other items would like to be pulled for any further

00:00:51.360 --> 00:01:01.080
 clarification or discussion so pulling item C do we have a motion to approve

00:01:01.080 --> 00:01:08.000
 consent consent agenda items a B and D do we have a motion for approval

00:01:08.000 --> 00:01:15.120
 recommend approval second so we have a motion and a second any further

00:01:15.120 --> 00:01:23.260
 discussion on any of those items without hearing any all those in favor of

00:01:23.260 --> 00:01:33.560
 approving items a B and D say aye aye those against nay motion to approve

00:01:33.560 --> 00:01:47.800
 consent agenda items a B and D passes how are these purchases of the recycling

00:01:47.800 --> 00:01:54.960
 bins treated on the books are they assets that are depreciated or my

00:01:54.960 --> 00:01:57.640
 understanding right now is we actually move this to an operating expense since

00:01:57.640 --> 00:02:01.400
 these are fairly low cost items I think they're about 40 some odd dollars each

00:02:01.400 --> 00:02:05.200
 depending on the size and so we just kind of treat those as an operational

00:02:05.200 --> 00:02:09.640
 expense which comes in as a one-year expense okay that's correct all right

00:02:09.640 --> 00:02:20.760
 thank you I'll second we have a motion and second to approve item C of the

00:02:20.760 --> 00:02:28.320
 consent agenda any further discussion clarification no all those in favor of

00:02:28.320 --> 00:02:38.520
 approving item C of the consent agenda say aye aye those against nay the item C

00:02:38.520 --> 00:02:47.120
 passes number two items for individual consideration the first item is a the

00:02:47.120 --> 00:02:52.280
 consider approval of the Public Utility Board meetings from December 10th 2018

00:02:52.280 --> 00:02:57.080
 those minutes have been distributed prior to this meeting does any member

00:02:57.080 --> 00:03:04.440
 have any amendments clarifications that they'd like to make to those minutes

00:03:04.440 --> 00:03:08.760
 hearing none do we have a motion for approval of the Public Utility Board

00:03:08.760 --> 00:03:16.600
 meeting minutes from December 10th 2018 so moved second second all those in

00:03:16.600 --> 00:03:24.280
 favor of approval say aye aye those against nay the Public Utility Board

00:03:24.280 --> 00:03:31.760
 meeting minutes from December 10th 2018 are approved item B under items for

00:03:31.760 --> 00:03:36.200
 individual individual consideration consider recommending adoption of an

00:03:36.200 --> 00:03:40.760
 ordinance of the city of Denton a Texas home rule municipal corporation

00:03:40.760 --> 00:03:45.680
 authorizing the city manager to execute a contract with Thale Construction

00:03:45.680 --> 00:03:50.320
 Company incorporated for the construction of the north-south phase 2

00:03:50.320 --> 00:03:57.240
 36 inch 42 inch water transmission line project for the city of Denton providing

00:03:57.240 --> 00:04:05.760
 for the expenditures of fund therefore and providing an effective date in the

00:04:05.760 --> 00:04:10.240
 not to exceed amount of seven million seven hundred ninety eight thousand

00:04:10.240 --> 00:04:14.760
 eight hundred seven dollars good morning board my name is Lee Perry I'm program

00:04:14.760 --> 00:04:18.440
 manager for capital project delivery I'm here today talking about the north

00:04:18.440 --> 00:04:25.280
 south water main phase 2 36 inches 42 42 inch water main project so we've got

00:04:25.280 --> 00:04:30.320
 about 10,000 feet of water me we're going to install between Rose Lawn and I-35

00:04:30.320 --> 00:04:36.280
 this is the second phase of this project it's going to follow along Bonnie Bray

00:04:36.280 --> 00:04:43.080
 from Rose Lawn it's on the city's master plan this is one of the top five

00:04:43.080 --> 00:04:50.120
 projects there oh sorry

00:04:50.120 --> 00:05:08.800
 so this is on the city's water master plan it's one of the top five projects

00:05:08.800 --> 00:05:14.580
 water projects that we need to that we need to get done the construction time

00:05:14.580 --> 00:05:17.880
 frame is about a year

00:05:17.880 --> 00:05:27.760
 so our bid results we got six bids in thali construction was a little better

00:05:27.760 --> 00:05:32.560
 at just under 7.8 million our engineers estimate was 8.4 million and the high

00:05:32.560 --> 00:05:37.560
 bid was at 9.8 million so our estimate was was sitting right in the middle of

00:05:37.560 --> 00:05:43.080
 the the six bid so we feel pretty good about our our bidder that we got our

00:05:43.080 --> 00:05:46.760
 consultant recommended approval they've this contractor hasn't worked for the

00:05:46.760 --> 00:05:49.920
 city of Denton in the past but our our consultant has worked with them on other

00:05:49.920 --> 00:05:58.640
 projects and so they recommended them for approval and so we are here

00:05:58.640 --> 00:06:03.480
 recommending that y'all recommend approval for the construction contract

00:06:03.480 --> 00:06:11.520
 without any construction set just under 7.8 million if you have any questions

00:06:11.520 --> 00:06:18.000
 does this project have anything to do will it have anything to do with the 377

00:06:18.000 --> 00:06:25.720
 extension is it no there will be a third phase which is the final phase of this

00:06:25.720 --> 00:06:30.800
 project which goes from I-35 up to McKenna Park along Bonnie Bray as well

00:06:30.800 --> 00:06:35.080
 and that will complete the loop or I'll say the loop but that will complete the

00:06:35.080 --> 00:06:40.880
 link between Ray Roberts and then Rose Lawn the transmission main at Rose Lawn

00:06:40.880 --> 00:06:47.240
 are they gonna have to dig up Bonnie Bray yes so related question is it

00:06:47.240 --> 00:06:51.440
 connected to the expansion of Bonnie Bray this will go ahead of the roadway

00:06:51.440 --> 00:06:55.480
 project okay yes this will be constructed this year and then the

00:06:55.480 --> 00:07:00.380
 roadway project will begin towards the beginning of next of 2020 are they

00:07:00.380 --> 00:07:06.160
 dependent on each other schedule-wise yes yeah we need to get the water line in

00:07:06.160 --> 00:07:09.800
 first this is such a big project we want to get this out of the way before we

00:07:09.800 --> 00:07:20.240
 start the roadway does this replace existing transmission lines or are they

00:07:20.240 --> 00:07:26.520
 is this all additional capacity this is new this is right now there's kind of a

00:07:26.520 --> 00:07:31.360
 bottleneck between Rose Lawn and McKenna Park we got a 42 inch down to a 16 inch

00:07:31.360 --> 00:07:40.000
 so this is to increase that okay capacity okay yeah any further questions

00:07:40.000 --> 00:07:42.640
 or discussion

00:07:52.720 --> 00:07:57.320
 yeah the feedback that I received was that they did a pretty good job at

00:07:57.320 --> 00:08:01.800
 completing their projects on time and so we don't have any reason to think

00:08:01.800 --> 00:08:15.760
 otherwise I know I've I've worked with SJ Lewis construction personally in

00:08:15.760 --> 00:08:22.440
 another city but the other contractors I didn't recognize them Tim might might

00:08:22.440 --> 00:08:30.240
 have some this is just a loose yeah just okay okay I actually have one more

00:08:30.240 --> 00:08:36.840
 question okay maybe just general assumption but we see a lot of projects

00:08:36.840 --> 00:08:42.280
 and and I guess my assumption all along although it doesn't come up much I don't

00:08:42.280 --> 00:08:51.200
 think is that the city requires that all of these companies like this are bonded

00:08:51.200 --> 00:09:09.000
 yeah great no further discussion do we have a motion for approval of me second

00:09:09.000 --> 00:09:17.760
 and a second any further discussion or comments all those in favor of approving

00:09:17.760 --> 00:09:25.040
 item B for individual consideration say aye aye those against nay motion approved

00:09:25.040 --> 00:09:34.680
 is approved item C is the ACM update sure yes mr. vice chair members of the

00:09:34.680 --> 00:09:39.800
 board a few things to report in your in your packet you'll see a memo from

00:09:39.800 --> 00:09:45.920
 Kenny banks to me about a water system fee for 2018 typically we would bring

00:09:45.920 --> 00:09:50.600
 those things to the PUB to get approved and then paid unfortunately with the

00:09:50.600 --> 00:09:55.000
 fact that the PUB did not meet at the end of December the invoice was sent by

00:09:55.000 --> 00:10:00.560
 Lee was TCEQ and they needed a 30-day turnaround on that annual payment so we

00:10:00.560 --> 00:10:04.800
 went ahead and and process that through our finance department but wanted to

00:10:04.800 --> 00:10:09.200
 provide just a little bit of an overview for you all to let you know that that

00:10:09.200 --> 00:10:13.640
 payment went ahead so that we would not be behind on that payment the other

00:10:13.640 --> 00:10:17.840
 thing that you have other items you have in your packet are presentation

00:10:17.840 --> 00:10:22.960
 material that was presented by PS Aurora late last year the fourth quarter

00:10:22.960 --> 00:10:26.280
 financial report if you have any questions I believe David Gaines is here

00:10:26.280 --> 00:10:30.960
 to answer any specifics that you have and then the future agenda list was a

00:10:30.960 --> 00:10:36.740
 few items up for your meeting next next time at the end of January and then if

00:10:36.740 --> 00:10:40.040
 you have any questions be happy to answer

00:10:43.640 --> 00:10:50.800
 I do have a question for you I went through most of the fourth quarter

00:10:50.800 --> 00:11:03.160
 financial report and then I noticed on the matrix that my request for the CIP

00:11:03.160 --> 00:11:08.520
 and bomb projects some information on those it looked like it was that with is

00:11:08.520 --> 00:11:14.640
 that that information or are we going to discuss that at the 24 no sir my

00:11:14.640 --> 00:11:20.800
 intentions if we can get everything put together is to have is to have a verbal

00:11:20.800 --> 00:11:27.440
 report to the PUB on on CIP so just present that information to the board

00:11:27.440 --> 00:11:31.480
 hopefully it meets the needs of the board and then if so then we'll continue

00:11:31.480 --> 00:11:43.240
 that process on a quarterly basis okay okay thank you so item three for

00:11:43.240 --> 00:11:48.040
 concluding items under section five five one zero four two of the Texas Open

00:11:48.040 --> 00:11:52.760
 Meetings Act would respond to inquiries from the public identity board or the

00:11:52.760 --> 00:11:58.200
 public with specific factual information of recitation of policy or accept a

00:11:58.200 --> 00:12:02.880
 proposal to place the matter on the agenda for an upcoming meeting I'm not

00:12:02.880 --> 00:12:06.120
 going to read the rest of that but does anybody like would like anything brought

00:12:06.120 --> 00:12:14.360
 up on the agenda or anything to add to the new business matrix nobody was

00:12:14.360 --> 00:12:19.360
 requesting any additional information or items for future so I guess we need a

00:12:19.360 --> 00:12:32.080
 motion to adjourn this meeting so we can proceed I think we need a motion to

00:12:32.080 --> 00:12:44.360
 adjourn is that correct but do we need a motion to close it okay all right so at

00:12:44.360 --> 00:12:48.680
 this moment then we're going to close the public the public portion of the

00:12:48.680 --> 00:12:54.120
 public utility board meeting and go into our closed session if everybody will

00:12:54.120 --> 00:12:57.520
 turn off their microphones please

