1 00:00:00,000 --> 00:00:08,679 all the March 26 2018 public utility board meeting to order 2 00:00:08,679 --> 00:00:10,080 we have work 3 00:00:10,080 --> 00:00:16,429 session three items and work session to begin with so let's 4 00:00:16,429 --> 00:00:18,079 go ahead and get 5 00:00:18,079 --> 00:00:21,320 started on those 6 00:00:29,359 --> 00:00:33,380 just item a is going to be to receive a report and hold a 7 00:00:33,380 --> 00:00:34,799 discussion and give 8 00:00:34,799 --> 00:00:39,280 staff direction regarding the use of unbudgeted capital 9 00:00:39,280 --> 00:00:40,719 project funds for 10 00:00:40,719 --> 00:00:45,530 stormwater drainage projects so mr. chairman and pb members 11 00:00:45,530 --> 00:00:46,399 my name is Tony 12 00:00:46,399 --> 00:00:49,549 point I'm the director finance for the city thank you for 13 00:00:49,549 --> 00:00:51,119 having me tonight 14 00:00:51,119 --> 00:00:54,200 first of all let me just say that over the last several 15 00:00:54,200 --> 00:00:55,640 months really beginning 16 00:00:55,640 --> 00:00:59,820 back in August we had a lot of staff internal meetings to 17 00:00:59,820 --> 00:01:01,000 go over all the 18 00:01:01,000 --> 00:01:05,030 city's CIP programs including those that are geo funded and 19 00:01:05,030 --> 00:01:06,319 as a result of many 20 00:01:06,319 --> 00:01:09,569 of those discussions we were able to identify shortfalls as 21 00:01:09,569 --> 00:01:10,260 well as some 22 00:01:10,260 --> 00:01:14,319 savings and a number of other issues throughout the city's 23 00:01:14,319 --> 00:01:15,640 financial system 24 00:01:15,640 --> 00:01:18,930 that allowed us to aggregate dollars from projects they 25 00:01:18,930 --> 00:01:20,040 hadn't been so it 26 00:01:20,040 --> 00:01:22,599 hadn't been completed so there's just been a whole team 27 00:01:22,599 --> 00:01:23,760 effort over the last 28 00:01:23,760 --> 00:01:27,760 several months on that front and so so this particular item 29 00:01:27,760 --> 00:01:28,879 was one of those 30 00:01:28,879 --> 00:01:33,980 items that we were able to identify back in January of this 31 00:01:33,980 --> 00:01:35,560 year late January 32 00:01:35,560 --> 00:01:38,840 30th this year we did meet with the 2014 bond oversight 33 00:01:38,840 --> 00:01:41,519 committee to go over the 34 00:01:41,519 --> 00:01:45,140 specific projects that were included in the 2014 bond 35 00:01:45,140 --> 00:01:46,680 program we also included 36 00:01:46,680 --> 00:01:50,290 projects from the 2012 and even for the 2005 to make some 37 00:01:50,290 --> 00:01:51,400 recommendations to 38 00:01:51,400 --> 00:01:55,150 them regarding the funding for those projects and so what 39 00:01:55,150 --> 00:01:55,959 we're gonna I'm 40 00:01:55,959 --> 00:01:58,730 gonna go over to with you today will be specific to those 41 00:01:58,730 --> 00:02:02,480 drainage projects so 42 00:02:02,480 --> 00:02:05,859 what I want to cover real quick with you is the 2014 geo 43 00:02:05,859 --> 00:02:07,120 bond programs that are 44 00:02:07,120 --> 00:02:11,330 pertaining to drainage projects the shortfall and that we 45 00:02:11,330 --> 00:02:12,800 've identified in 46 00:02:12,800 --> 00:02:16,050 those projects so what it would take to get those projects 47 00:02:16,050 --> 00:02:17,240 fully completed and 48 00:02:17,240 --> 00:02:20,889 fully funded I'm gonna go through also as well through the 49 00:02:20,889 --> 00:02:21,879 history of the 50 00:02:21,879 --> 00:02:25,180 drainage division division and the associated drainage fee 51 00:02:25,180 --> 00:02:26,080 which is really 52 00:02:26,080 --> 00:02:28,319 where some of these proposed the proposal we're gonna make 53 00:02:28,319 --> 00:02:28,879 to you today 54 00:02:28,879 --> 00:02:32,030 where where the money is coming from to get these parts 55 00:02:32,030 --> 00:02:33,460 completed and then 56 00:02:33,460 --> 00:02:37,370 finally just go ahead and discuss with you just the status 57 00:02:37,370 --> 00:02:38,400 of where the money's 58 00:02:38,400 --> 00:02:43,050 coming from which is the channel rehab funds so the 2014 59 00:02:43,050 --> 00:02:44,520 bond program included 60 00:02:44,520 --> 00:02:47,979 a number of projects that are listed here I think many of 61 00:02:47,979 --> 00:02:48,680 those you're 62 00:02:48,680 --> 00:02:52,530 familiar with I will say that the pecan Creek drainage 63 00:02:52,530 --> 00:02:53,960 project is a project that 64 00:02:53,960 --> 00:02:57,210 we feel is fully funded and so there is no shortfall in 65 00:02:57,210 --> 00:02:58,599 that project there is 66 00:02:58,599 --> 00:03:02,490 so an associated project that not listed here for phase 67 00:03:02,490 --> 00:03:03,919 three and four of that 68 00:03:03,919 --> 00:03:07,020 project and we've identified funds previously with the 69 00:03:07,020 --> 00:03:08,000 council to fully 70 00:03:08,000 --> 00:03:10,810 fund that particular project thing the design work on that 71 00:03:10,810 --> 00:03:12,159 is an in in process 72 00:03:12,159 --> 00:03:17,099 this particular project is specific to pecan Creek phase 73 00:03:17,099 --> 00:03:19,159 phase two and that is 74 00:03:19,159 --> 00:03:26,009 located west of Locust to Prairie so again in identifying 75 00:03:26,009 --> 00:03:27,159 these projects with 76 00:03:27,159 --> 00:03:30,430 the bond oversight committee we found that these projects 77 00:03:30,430 --> 00:03:31,360 were there was a 78 00:03:31,360 --> 00:03:35,909 shortfall for mingo and a hinkle drainage as you know that 79 00:03:35,909 --> 00:03:36,680 was a major 80 00:03:36,680 --> 00:03:40,319 project that both the bond oversight committee and also the 81 00:03:40,319 --> 00:03:41,479 associated blue 82 00:03:41,479 --> 00:03:44,849 ribbon committee had identified we and we estimate that the 83 00:03:44,849 --> 00:03:45,800 shortfall for that 84 00:03:45,800 --> 00:03:50,349 project is approximately 1.9 million dollars the following 85 00:03:50,349 --> 00:03:51,000 three projects 86 00:03:51,000 --> 00:03:53,680 you'll see that Oak Street was not a project listed 87 00:03:53,680 --> 00:03:55,599 previously but we've 88 00:03:55,599 --> 00:03:58,060 aggregate we've put together we've combined these three 89 00:03:58,060 --> 00:03:58,960 projects and we've 90 00:03:58,960 --> 00:04:01,710 called them now the drainage downtown drainage projects 91 00:04:01,710 --> 00:04:02,680 felt that that was a 92 00:04:02,680 --> 00:04:05,699 an aspect of that of those projects that need to be 93 00:04:05,699 --> 00:04:07,400 completed as well and that's 94 00:04:07,400 --> 00:04:09,879 to some degree contributed to some of the shortfall but the 95 00:04:09,879 --> 00:04:10,879 shortfall for 96 00:04:10,879 --> 00:04:13,900 those three projects we've estimated at four hundred 97 00:04:13,900 --> 00:04:16,199 seventy thousand dollars the 98 00:04:16,199 --> 00:04:19,449 total shortfall that we want to discuss with you today is 99 00:04:19,449 --> 00:04:20,399 two point three 100 00:04:20,399 --> 00:04:25,839 almost two point four million dollars really quickly the 101 00:04:25,839 --> 00:04:26,879 drainage fee the 102 00:04:26,879 --> 00:04:31,220 drainage fee was adopted actually back in 2002 prior to 103 00:04:31,220 --> 00:04:33,279 that in 2001 the city 104 00:04:33,279 --> 00:04:37,000 had to recognize and adopt the municipal drainage utility 105 00:04:37,000 --> 00:04:38,439 system act in order to 106 00:04:38,439 --> 00:04:42,100 be able to to set that particular fee so that fee was 107 00:04:42,100 --> 00:04:44,160 established by ordinance 108 00:04:44,160 --> 00:04:49,500 2002 019 back in 2002 I will tell you that that fee and the 109 00:04:49,500 --> 00:04:49,959 associated 110 00:04:49,959 --> 00:04:53,220 schedule has not changed since 2002 that has remained and I 111 00:04:53,220 --> 00:04:54,279 've provided in your 112 00:04:54,279 --> 00:04:57,449 backup the establishing ordinance and that has continued 113 00:04:57,449 --> 00:04:59,459 through the 2017 rate 114 00:04:59,459 --> 00:05:02,709 ordinance that was adopted last year in conjunction with 115 00:05:02,709 --> 00:05:04,519 the city's budget and 116 00:05:04,519 --> 00:05:07,910 also with the with the wastewater fund in particular the 117 00:05:07,910 --> 00:05:09,279 intended use of those 118 00:05:09,279 --> 00:05:13,930 drainage dollars was to cover the O&M component of not just 119 00:05:13,930 --> 00:05:15,360 the drainage but 120 00:05:15,360 --> 00:05:19,509 also the watershed protection that was in existence at that 121 00:05:19,509 --> 00:05:21,519 time also associated 122 00:05:21,519 --> 00:05:24,360 general obligation debt that had been issued and was 123 00:05:24,360 --> 00:05:26,920 outstanding and also some 124 00:05:26,920 --> 00:05:29,949 additional debt that was subsequently issued after that 125 00:05:29,949 --> 00:05:30,759 time out of the 126 00:05:30,759 --> 00:05:35,069 wastewater fund as revenue bonds and so I'll be able to 127 00:05:35,069 --> 00:05:36,639 kind of walk you through 128 00:05:36,639 --> 00:05:39,470 any questions you have on that but I will tell you that 129 00:05:39,470 --> 00:05:40,439 this is the final 130 00:05:40,439 --> 00:05:44,399 year of debt service on the geo bond debt we anticipate 131 00:05:44,399 --> 00:05:45,839 that the remaining 132 00:05:45,839 --> 00:05:53,250 wastewater bonds are scheduled they're scheduled to be paid 133 00:05:53,250 --> 00:05:56,360 off in 2022 so what 134 00:05:56,360 --> 00:05:59,360 you've seen and the backup that I provided you you've seen 135 00:05:59,360 --> 00:06:00,079 a decrease in 136 00:06:00,079 --> 00:06:02,699 that annual debt service that has contributed to some of 137 00:06:02,699 --> 00:06:03,439 the money that's 138 00:06:03,439 --> 00:06:06,060 been transferred over to both capital projects and 139 00:06:06,060 --> 00:06:07,879 specifically to the channel 140 00:06:07,879 --> 00:06:11,129 rehab funds the other component as well is that over the 141 00:06:11,129 --> 00:06:12,439 years there's been some 142 00:06:12,439 --> 00:06:15,759 additional work that has that the watershed protection 143 00:06:15,759 --> 00:06:16,399 group has 144 00:06:16,399 --> 00:06:20,689 undertaken one of those is mosquito abatement those are 145 00:06:20,689 --> 00:06:21,639 those costs are 146 00:06:21,639 --> 00:06:23,839 allocated to the general fund so the general fund has 147 00:06:23,839 --> 00:06:24,959 actually increased his 148 00:06:24,959 --> 00:06:28,930 contribution to to that particular operation and that's 149 00:06:28,930 --> 00:06:30,160 also resulted in 150 00:06:30,160 --> 00:06:34,009 some of the additional revenue that has gone into our 151 00:06:34,009 --> 00:06:35,879 capital project program 152 00:06:36,360 --> 00:06:40,240 just really quickly approximately 5.5 million over the last 153 00:06:40,240 --> 00:06:41,519 10 years has been 154 00:06:41,519 --> 00:06:48,370 transferred to to this drainage channel rehab account 1.7 155 00:06:48,370 --> 00:06:49,000 million has been 156 00:06:49,000 --> 00:06:53,839 utilized in various drainage projects and as of February of 157 00:06:53,839 --> 00:06:55,160 this year we had 158 00:06:55,160 --> 00:06:58,769 approximately 4.1 million dollars that 4.1 million dollars 159 00:06:58,769 --> 00:07:01,319 in the 1718 CIP have 160 00:07:01,319 --> 00:07:04,930 not been budgeted there are a number of projects that staff 161 00:07:04,930 --> 00:07:05,800 is anticipating 162 00:07:05,800 --> 00:07:08,959 bringing forward to the PUB and also the City Council for 163 00:07:08,959 --> 00:07:10,279 consideration to be 164 00:07:10,279 --> 00:07:14,160 funded out of that 4.1 million but again we anticipate that 165 00:07:14,160 --> 00:07:15,120 that will continue to 166 00:07:15,120 --> 00:07:20,459 grow even beyond potentially those specific projects and so 167 00:07:20,459 --> 00:07:21,000 what we're 168 00:07:21,000 --> 00:07:26,959 proposing today for you is to to allocate 2.2 million or to 169 00:07:26,959 --> 00:07:28,019 authorize 2.2 170 00:07:28,019 --> 00:07:33,680 million from this drainage channel account that is unbudget 171 00:07:33,680 --> 00:07:34,800 ed to be utilized 172 00:07:34,800 --> 00:07:39,639 to fund the gap of those projects that were included 2014 173 00:07:39,639 --> 00:07:41,240 bond program again 174 00:07:41,240 --> 00:07:43,819 those are drainage projects we feel that they are very 175 00:07:43,819 --> 00:07:45,000 appropriate to be to be 176 00:07:45,000 --> 00:07:48,160 funded from this particular source and again we don't 177 00:07:48,160 --> 00:07:49,560 anticipate that using 178 00:07:49,560 --> 00:07:53,019 these funds in this particular manner will have any 179 00:07:53,019 --> 00:07:54,639 negative impact on any 180 00:07:54,639 --> 00:07:57,889 anticipated projects to be brought forward to you for the 181 00:07:57,889 --> 00:08:00,720 2019 and 2020 CIP 182 00:08:00,720 --> 00:08:06,220 program so just in just in wrapping up we're requesting the 183 00:08:06,220 --> 00:08:07,319 use of 2.2 million 184 00:08:07,319 --> 00:08:13,399 dollars from the drainage rehab fund to be used on these 185 00:08:13,399 --> 00:08:14,360 particular projects 186 00:08:14,360 --> 00:08:17,980 that will be included in a wider budget amendment that we 187 00:08:17,980 --> 00:08:19,319 're anticipating to 188 00:08:19,319 --> 00:08:22,339 bring forward to the council tomorrow that we identify a 189 00:08:22,339 --> 00:08:23,160 number of other 190 00:08:23,160 --> 00:08:26,420 funding sources for a number of other projects beyond these 191 00:08:26,420 --> 00:08:27,560 drainage projects 192 00:08:27,560 --> 00:08:29,910 for council's consideration and so we did want to let you 193 00:08:29,910 --> 00:08:30,800 know we did not bring 194 00:08:30,800 --> 00:08:33,980 that budget amendment to you as an individual item because 195 00:08:33,980 --> 00:08:34,480 it'll be 196 00:08:34,480 --> 00:08:39,649 included in a much wider budget amendment so that really 197 00:08:39,649 --> 00:08:41,840 kind of wraps up my my 198 00:08:41,840 --> 00:08:44,480 presentation to you be happy to answer any questions I know 199 00:08:44,480 --> 00:08:45,320 we have some folks 200 00:08:45,320 --> 00:08:48,090 here from from drainage as well so if you have specific 201 00:08:48,090 --> 00:08:49,320 questions about those 202 00:08:49,320 --> 00:08:53,399 projects be happy to go through that with you. 203 00:08:56,399 --> 00:08:59,840 What accounts for the shortfall in the Magnolia Hinkle 204 00:08:59,840 --> 00:09:02,840 drainage project that's 205 00:09:02,840 --> 00:09:09,080 a significant shortfall? Chad let me ask Chad he's our 206 00:09:09,080 --> 00:09:11,559 drainage engineer. 207 00:09:11,559 --> 00:09:18,399 I'm I'm Chad Allen I'm the deputy city engineer I think it 208 00:09:18,399 --> 00:09:19,320 's it was listed in 209 00:09:19,320 --> 00:09:23,379 the AIS there's increased construction costs over the years 210 00:09:23,379 --> 00:09:24,120 we're seeing very 211 00:09:24,120 --> 00:09:26,840 high construction costs more than 10% a year inflation on 212 00:09:26,840 --> 00:09:28,559 construction costs and 213 00:09:28,559 --> 00:09:30,850 when that budget was originally put together they did not 214 00:09:30,850 --> 00:09:32,200 foresee that also 215 00:09:32,200 --> 00:09:36,500 I think previously when establishing those budgets we might 216 00:09:36,500 --> 00:09:37,000 not have been 217 00:09:37,000 --> 00:09:40,639 conservative enough as we should have been so we might not 218 00:09:40,639 --> 00:09:41,759 have used higher 219 00:09:41,759 --> 00:09:44,779 contingency numbers as high as we should we might we may 220 00:09:44,779 --> 00:09:45,720 not have included that 221 00:09:45,720 --> 00:09:49,679 all aspects of the project like design or inspection so we 222 00:09:49,679 --> 00:09:50,360 're much better 223 00:09:50,360 --> 00:09:53,379 nowadays about trying to predict when we're going to go to 224 00:09:53,379 --> 00:09:54,360 construction and 225 00:09:54,360 --> 00:09:56,539 then escalating our costs up to that date and that might 226 00:09:56,539 --> 00:09:57,600 not have been done so 227 00:09:57,600 --> 00:10:07,779 well in the past. Okay thank you. Well I want to follow up 228 00:10:07,779 --> 00:10:08,279 on that is a lot of 229 00:10:08,279 --> 00:10:12,289 concrete in here is that because is that the main material 230 00:10:12,289 --> 00:10:13,879 that you're using for 231 00:10:13,879 --> 00:10:16,039 these drainage projects because I know that's just yes 232 00:10:16,039 --> 00:10:17,759 there's a shortage well 233 00:10:17,759 --> 00:10:20,460 it's not really street concrete that's not really shown on 234 00:10:20,460 --> 00:10:21,360 the AIS and the 235 00:10:21,360 --> 00:10:24,049 numbers you're looking at but there's big concrete box cul 236 00:10:24,049 --> 00:10:25,000 verts that are putting 237 00:10:25,000 --> 00:10:28,200 into Hinkle and all of that storm drain cost has increased 238 00:10:28,200 --> 00:10:29,120 like it's like we 239 00:10:29,120 --> 00:10:31,820 said we've been seeing 10 to 12 percent a year over the 240 00:10:31,820 --> 00:10:33,039 last three to five years 241 00:10:33,039 --> 00:10:39,759 so and the original estimate was put together what year? 242 00:10:39,759 --> 00:10:43,059 Approximately? Not so sure about that. Between 2010 and 243 00:10:43,059 --> 00:10:46,919 2012. Okay all right all right thank you. 244 00:10:46,919 --> 00:10:52,870 Was it a completion time problem? I mean so if it was 245 00:10:52,870 --> 00:10:55,000 budgeted or bid or 246 00:10:55,000 --> 00:10:59,779 estimated in 2012 and approved in a 2014 bond and here it 247 00:10:59,779 --> 00:11:01,759 is 2018 it's not done 248 00:11:01,759 --> 00:11:05,279 so is that that's definitely a part of it. I think that's 249 00:11:05,279 --> 00:11:06,200 fair and one of the 250 00:11:06,200 --> 00:11:09,570 things that we've done over the last six or eight months is 251 00:11:09,570 --> 00:11:10,320 go back all the way 252 00:11:10,320 --> 00:11:14,490 to the 2005 bond package cleaned out all those projects as 253 00:11:14,490 --> 00:11:15,399 well as everything in 254 00:11:15,399 --> 00:11:19,639 2012-14 lifted them up on the spreadsheets in trying to 255 00:11:19,639 --> 00:11:20,200 balance the 256 00:11:20,200 --> 00:11:24,159 remaining bond programs I think we're there on 99% of the 257 00:11:24,159 --> 00:11:25,080 programs now but 258 00:11:25,080 --> 00:11:28,799 you're absolutely correct the time value of money is 259 00:11:28,799 --> 00:11:29,519 definitely been a 260 00:11:29,519 --> 00:11:32,769 major obstacle for us and so a couple of things that we're 261 00:11:32,769 --> 00:11:34,159 doing at this point is 262 00:11:34,159 --> 00:11:36,509 making sure that we're trying to get up to a point where we 263 00:11:36,509 --> 00:11:37,360 've got plans on the 264 00:11:37,360 --> 00:11:40,440 shelf before we meet with the bond committees in the future 265 00:11:40,440 --> 00:11:41,080 and we've also 266 00:11:41,080 --> 00:11:45,429 just recently gone through a pretty exhaustive RFQ process 267 00:11:45,429 --> 00:11:46,159 where we've 268 00:11:46,159 --> 00:11:48,820 pre-qualified a number of engineering firms within seven 269 00:11:48,820 --> 00:11:49,919 different areas so 270 00:11:49,919 --> 00:11:53,080 we're able to get these projects designed and on the street 271 00:11:53,080 --> 00:11:53,799 quickly and 272 00:11:53,799 --> 00:11:58,559 not lose that 1% cost that we're seeing every month in the 273 00:11:58,559 --> 00:11:59,240 escalation of these 274 00:11:59,240 --> 00:12:02,690 projects. Okay and so you feel like those changes will help 275 00:12:02,690 --> 00:12:03,720 us complete the 276 00:12:03,720 --> 00:12:07,440 project with these additional budgeted funds in a time 277 00:12:07,440 --> 00:12:08,320 where we won't have to 278 00:12:08,320 --> 00:12:11,929 come back and ask for more? I mean it's your question is 279 00:12:11,929 --> 00:12:13,639 right on in terms of 280 00:12:13,639 --> 00:12:16,659 having these projects you know estimated and then waiting 281 00:12:16,659 --> 00:12:17,759 four or five six years 282 00:12:17,759 --> 00:12:21,929 to get them constructed you know they've got to go back to 283 00:12:21,929 --> 00:12:23,159 re-engineer 284 00:12:23,159 --> 00:12:26,179 everything make sure the designs are up to speed and with 285 00:12:26,179 --> 00:12:27,360 the construction 286 00:12:27,360 --> 00:12:30,000 estimate the cost that we're seeing escalating right now 287 00:12:30,000 --> 00:12:30,679 many of our 288 00:12:30,679 --> 00:12:33,299 projects have been you know several hundred thousand 289 00:12:33,299 --> 00:12:35,559 dollars short plus so I 290 00:12:35,559 --> 00:12:38,580 do think that the improvements that Chad and Todd Estes our 291 00:12:38,580 --> 00:12:39,279 city engineer 292 00:12:39,279 --> 00:12:43,019 working on are gonna have a major impact moving forward. 293 00:12:43,019 --> 00:12:49,240 Thank you. Other questions? 294 00:12:49,799 --> 00:12:59,740 This is for Tony I guess. So the drainage fees that we see 295 00:12:59,740 --> 00:13:00,320 on our utility 296 00:13:00,320 --> 00:13:06,159 bill have been funding this account that this money is 297 00:13:06,159 --> 00:13:07,639 going coming out of is that 298 00:13:07,639 --> 00:13:12,639 correct? That's correct. And I notice you said there's no 299 00:13:12,639 --> 00:13:15,360 impact on 2019-2020 300 00:13:15,360 --> 00:13:20,519 capital improvement programs for drainage what about 301 00:13:20,519 --> 00:13:21,879 because we normally 302 00:13:21,879 --> 00:13:25,980 look five years out on that is that do we anticipate other 303 00:13:25,980 --> 00:13:26,960 debt are we gonna 304 00:13:26,960 --> 00:13:29,570 have enough money to fund these out of fees going forward 305 00:13:29,570 --> 00:13:30,759 do you think? Well I 306 00:13:30,759 --> 00:13:34,570 think that you know there's certainly some opportunities 307 00:13:34,570 --> 00:13:35,440 here now with with 308 00:13:35,440 --> 00:13:39,289 this capacity to potentially fund some additional bond 309 00:13:39,289 --> 00:13:40,720 issues if we wanted to 310 00:13:40,720 --> 00:13:44,279 do that and maybe get some of these additional projects out 311 00:13:44,279 --> 00:13:44,679 the door 312 00:13:44,679 --> 00:13:46,840 certainly I think over the next couple of months we'll be 313 00:13:46,840 --> 00:13:47,399 having those 314 00:13:47,399 --> 00:13:50,690 discussions coming back to you with a recommendation in 315 00:13:50,690 --> 00:13:51,399 that area in 316 00:13:51,399 --> 00:13:56,240 conjunction with the wastewater budget. 317 00:13:57,039 --> 00:14:02,669 Okay I guess at some point in time we'll determine if we've 318 00:14:02,669 --> 00:14:04,879 done all the all the 319 00:14:04,879 --> 00:14:08,340 drainage projects and wastewater projects we need that day 320 00:14:08,340 --> 00:14:09,080 ever comes I 321 00:14:09,080 --> 00:14:14,250 don't know. Pretty staggering numbers. Yeah you know at 322 00:14:14,250 --> 00:14:15,960 some point in time I 323 00:14:15,960 --> 00:14:22,450 know this was when this was in act put in place in 2002 I 324 00:14:22,450 --> 00:14:24,440 know it was kind of 325 00:14:24,440 --> 00:14:27,809 first time it ever been done so it's not first of all it's 326 00:14:27,809 --> 00:14:28,879 nice to see that it's 327 00:14:28,879 --> 00:14:33,240 actually going towards projects as opposed to debt service 328 00:14:33,240 --> 00:14:34,600 that's that's 329 00:14:34,600 --> 00:14:40,809 good to see so hopefully these things can be we can manage 330 00:14:40,809 --> 00:14:41,639 it where there's a 331 00:14:41,639 --> 00:14:46,830 lot of revenue funded projects in the future for these 332 00:14:46,830 --> 00:14:49,840 things. Any other 333 00:14:49,840 --> 00:14:56,460 questions comments? So Mr. Chairman we are asking for for 334 00:14:56,460 --> 00:14:58,600 direction from the PUB to 335 00:14:58,600 --> 00:15:01,840 move forward again we are planning to have this same 336 00:15:01,840 --> 00:15:03,840 discussion with the City 337 00:15:03,840 --> 00:15:07,080 Council tomorrow night not just specific to these drainage 338 00:15:07,080 --> 00:15:07,960 projects but all the 339 00:15:07,960 --> 00:15:13,169 projects that are included in the in the bond program. Okay 340 00:15:13,169 --> 00:15:14,080 so everybody 341 00:15:14,080 --> 00:15:20,090 understand the request? Do we need a motion? It's not 342 00:15:20,090 --> 00:15:20,759 actually an action item. 343 00:15:20,759 --> 00:15:24,080 It's not an action motion you just need direction. I'm 344 00:15:24,080 --> 00:15:27,960 comfortable in using those funds to finish these projects. 345 00:15:27,960 --> 00:15:32,509 Me too. All right I think you've you've got our all the 346 00:15:32,509 --> 00:15:37,279 head nods. Thank you. 347 00:15:37,279 --> 00:15:42,769 Okay item B is to receive a report, hold a discussion and 348 00:15:42,769 --> 00:15:44,440 give staff direction 349 00:15:44,440 --> 00:15:48,639 regarding a proposed rate reduction for residential solid 350 00:15:48,639 --> 00:15:50,779 waste customers. So Mr. 351 00:15:50,779 --> 00:15:55,620 Chairman and members of the PUB a lot of good news tonight 352 00:15:55,620 --> 00:15:57,639 for you. First of all 353 00:15:57,639 --> 00:16:00,919 before I begin I do want to acknowledge you know all the 354 00:16:00,919 --> 00:16:02,120 hard work that our 355 00:16:02,120 --> 00:16:05,360 staff at the solid waste department have done over the last 356 00:16:05,360 --> 00:16:06,960 several months in 357 00:16:06,960 --> 00:16:10,240 particular you know Mr. Ethan Cox is our director over that 358 00:16:10,240 --> 00:16:11,559 area and also you know 359 00:16:11,559 --> 00:16:15,440 Dr. Kenny Banks both as well as a number of financial staff 360 00:16:15,440 --> 00:16:16,120 members that have been 361 00:16:16,120 --> 00:16:18,870 involved throughout that process have been doing a lot of 362 00:16:18,870 --> 00:16:20,039 work. You've seen 363 00:16:20,039 --> 00:16:22,799 over the last several months a number of items that have 364 00:16:22,799 --> 00:16:24,360 come through you to you. 365 00:16:24,360 --> 00:16:26,899 Changes that we've made to specifically the capital 366 00:16:26,899 --> 00:16:28,240 improvement program but also 367 00:16:28,240 --> 00:16:32,149 some operating changes as well. I think all of that has 368 00:16:32,149 --> 00:16:33,399 been a culmination in 369 00:16:33,399 --> 00:16:36,169 getting us to where we are today and and the recommendation 370 00:16:36,169 --> 00:16:36,919 that we want to 371 00:16:36,919 --> 00:16:43,889 discuss with you this evening. So just really quickly you 372 00:16:43,889 --> 00:16:44,240 know our 373 00:16:44,240 --> 00:16:48,059 recommendation to you will be to decrease the residential 374 00:16:48,059 --> 00:16:49,039 rates an amount 375 00:16:49,039 --> 00:16:54,039 of 12%. They're listed there for you you can see that both 376 00:16:54,039 --> 00:16:55,440 the standard and large 377 00:16:55,440 --> 00:16:59,320 carts will be reduced by that amount and just request that 378 00:16:59,320 --> 00:17:01,480 come in. We anticipate 379 00:17:01,480 --> 00:17:05,140 that that if approved tomorrow by the City Council tonight 380 00:17:05,140 --> 00:17:05,960 by you and tomorrow 381 00:17:05,960 --> 00:17:11,269 by the City Council that that will go into effect for those 382 00:17:11,269 --> 00:17:11,920 for those meters 383 00:17:11,920 --> 00:17:14,960 that are actually rare actually for the billings that go 384 00:17:14,960 --> 00:17:16,279 out on the 28th of 385 00:17:16,279 --> 00:17:20,150 March so those will be kind of the first cycle we call 386 00:17:20,150 --> 00:17:22,960 cycle 19. So the bills that 387 00:17:22,960 --> 00:17:26,099 are due April 1st will be the bills that will actually have 388 00:17:26,099 --> 00:17:28,440 that reduced rate. Just 389 00:17:28,440 --> 00:17:32,160 really quickly for a standard cart if you know if this is 390 00:17:32,160 --> 00:17:33,359 approved and goes 391 00:17:33,359 --> 00:17:37,910 into effect we anticipate about a $20 savings in total for 392 00:17:37,910 --> 00:17:38,960 that six six month 393 00:17:38,960 --> 00:17:42,920 period. That's about $40 per year on a standard cart. If 394 00:17:42,920 --> 00:17:44,519 you're on a large cart 395 00:17:44,519 --> 00:17:49,069 service that's going to be about 23 almost $24 over that 396 00:17:49,069 --> 00:17:49,759 six month period or 397 00:17:49,759 --> 00:17:54,599 about $47 almost $48 that our residential customers will 398 00:17:54,599 --> 00:17:56,000 see. And again 399 00:17:56,000 --> 00:18:00,140 that will be an immediate impact. So I do want to cover 400 00:18:00,140 --> 00:18:01,839 with you some of the 401 00:18:01,839 --> 00:18:04,480 staff efforts that have gone on that resulted in this 402 00:18:04,480 --> 00:18:05,920 recommendation today as 403 00:18:05,920 --> 00:18:09,880 well as changes to our capital plan and debt service. What 404 00:18:09,880 --> 00:18:11,400 that means for the 405 00:18:11,400 --> 00:18:14,480 particular funds reserves and working capital and what the 406 00:18:14,480 --> 00:18:15,720 budget impact will 407 00:18:15,720 --> 00:18:21,670 be for this for the rest this year for 17-18. Finally we'll 408 00:18:21,670 --> 00:18:22,599 cover just cover 409 00:18:22,599 --> 00:18:25,750 quickly some next steps and also just what the general 410 00:18:25,750 --> 00:18:26,880 impact is of this of 411 00:18:26,880 --> 00:18:30,690 this rate decrease in the context of our of our projections 412 00:18:30,690 --> 00:18:33,480 . So speaking about 413 00:18:33,480 --> 00:18:37,650 staff efforts over the last several months so we've done a 414 00:18:37,650 --> 00:18:38,740 business unit 415 00:18:38,740 --> 00:18:43,039 realignment in preparation for a new management study and 416 00:18:43,039 --> 00:18:44,000 also cost of 417 00:18:44,000 --> 00:18:47,109 service. We'll talk a little bit more about that with you 418 00:18:47,109 --> 00:18:48,559 to just better align 419 00:18:48,559 --> 00:18:53,589 what those service streams and revenues are as well as the 420 00:18:53,589 --> 00:18:53,599 expenditure 421 00:18:53,599 --> 00:18:58,940 expenditures. We've revised a capital program and and also 422 00:18:58,940 --> 00:18:59,720 the budget process 423 00:18:59,720 --> 00:19:03,529 and so there's a multi-step review through the department 424 00:19:03,529 --> 00:19:04,200 that was a 425 00:19:04,200 --> 00:19:07,250 recommendation if you remember from one of the consultants 426 00:19:07,250 --> 00:19:08,359 we're trying to make 427 00:19:08,359 --> 00:19:11,650 sure that our staff out there are involved and engaged in 428 00:19:11,650 --> 00:19:12,480 the review of 429 00:19:12,480 --> 00:19:15,779 programs and costs that are happening out in the solid 430 00:19:15,779 --> 00:19:17,200 waste department so that 431 00:19:17,200 --> 00:19:20,220 so that we can appropriately vet those programs and efforts 432 00:19:20,220 --> 00:19:21,000 that may be going 433 00:19:21,000 --> 00:19:24,970 on. I want to make sure that we strengthen our business 434 00:19:24,970 --> 00:19:25,720 case and 435 00:19:25,720 --> 00:19:28,329 financial analysis that goes on with this particular 436 00:19:28,329 --> 00:19:29,319 programs one of the 437 00:19:29,319 --> 00:19:33,400 changes that was made recently this was before mr. Springer 438 00:19:33,400 --> 00:19:34,440 left all the 439 00:19:34,440 --> 00:19:37,549 finance all the finance individuals staff members that are 440 00:19:37,549 --> 00:19:38,400 in the utilities 441 00:19:38,400 --> 00:19:41,519 now report to the city's director finance and so there is 442 00:19:41,519 --> 00:19:42,519 that additional 443 00:19:42,519 --> 00:19:45,710 layer and oversight that really hadn't been there 444 00:19:45,710 --> 00:19:47,640 previously. Again we continue 445 00:19:47,640 --> 00:19:50,680 to work very closely with with our staff members in the 446 00:19:50,680 --> 00:19:52,519 operating department but 447 00:19:52,519 --> 00:19:57,319 many of those discussions happen in tandem with our finance 448 00:19:57,319 --> 00:19:58,480 group as well. 449 00:19:58,960 --> 00:20:03,079 So for the CIP over the next five years that's CIP and you 450 00:20:03,079 --> 00:20:04,680 'll see that coming to 451 00:20:04,680 --> 00:20:08,490 you as well as part of the proposed budget for you when we 452 00:20:08,490 --> 00:20:09,640 come back to you 453 00:20:09,640 --> 00:20:13,960 we've been able to reduce that over the five years by 12.2 454 00:20:13,960 --> 00:20:14,680 million dollars. 455 00:20:14,680 --> 00:20:17,029 There's a number of projects one of those projects that 456 00:20:17,029 --> 00:20:18,160 comes to mind is the 457 00:20:18,160 --> 00:20:21,180 mining project if you remember that project was discontin 458 00:20:21,180 --> 00:20:21,920 ued and so that 459 00:20:21,920 --> 00:20:28,029 contributes to this 2.2 million dollars. In addition these 460 00:20:28,029 --> 00:20:28,519 changes 461 00:20:28,519 --> 00:20:32,329 have resulted in no debt issuances for 17-18 for the 462 00:20:32,329 --> 00:20:34,720 current year or 18-19 and 463 00:20:34,720 --> 00:20:38,799 so there's associated annual debt service savings from that 464 00:20:38,799 --> 00:20:39,640 that are now 465 00:20:39,640 --> 00:20:42,789 being stripped out of the financial forecast for that 466 00:20:42,789 --> 00:20:45,000 particular fund. So the 467 00:20:45,000 --> 00:20:47,809 reduced debt service expense over the next six years we 468 00:20:47,809 --> 00:20:49,119 anticipate that that 469 00:20:49,119 --> 00:20:52,599 would be 13.4 million dollars based on what we know today 470 00:20:52,599 --> 00:20:53,440 and what's being 471 00:20:53,440 --> 00:20:56,690 planned and what will come forward to you and you can see 472 00:20:56,690 --> 00:20:58,440 that over that that 473 00:20:58,440 --> 00:21:01,000 time horizon that I've listed up here where those savings 474 00:21:01,000 --> 00:21:01,880 are and what those 475 00:21:01,880 --> 00:21:06,220 in those years and so those are associated reduced debt 476 00:21:06,220 --> 00:21:07,160 services that's 477 00:21:07,160 --> 00:21:12,190 the annual debt service. So again this is an immediate rate 478 00:21:12,190 --> 00:21:13,960 decrease you see right 479 00:21:13,960 --> 00:21:19,309 here on the right hand side my left your right that we 480 00:21:19,309 --> 00:21:21,079 think that this reduction 481 00:21:21,079 --> 00:21:24,750 this total percent reduction still keeps this fund very 482 00:21:24,750 --> 00:21:26,680 very healthy. We have 483 00:21:26,680 --> 00:21:30,220 minimum fund balance requirements of 14 percent of budget 484 00:21:30,220 --> 00:21:31,519 expenses and a 485 00:21:31,519 --> 00:21:36,240 maximum of 18 and we're well above those those reserves 486 00:21:36,240 --> 00:21:38,279 even even today. Again 487 00:21:38,279 --> 00:21:40,289 we'll be coming back to you with some additional 488 00:21:40,289 --> 00:21:41,519 recommendations in the near 489 00:21:41,519 --> 00:21:46,250 future. So the growth in reserves is due to decrease debt 490 00:21:46,250 --> 00:21:47,759 service again you go 491 00:21:47,759 --> 00:21:49,910 had already echoed that for you. There'll be some 492 00:21:49,910 --> 00:21:51,880 additional savings from some 493 00:21:51,880 --> 00:21:56,819 operating changes that we're making certainly as we get 494 00:21:56,819 --> 00:21:58,240 back our cost of 495 00:21:58,240 --> 00:22:00,480 service and our management study there may be some 496 00:22:00,480 --> 00:22:01,799 additional changes as well 497 00:22:01,799 --> 00:22:06,980 that they have O&M impacts for that particular fund. So 498 00:22:06,980 --> 00:22:08,759 just here just side 499 00:22:08,759 --> 00:22:12,339 by side we've provided to you what the adopted budget was 500 00:22:12,339 --> 00:22:13,640 when it was adopted 501 00:22:13,640 --> 00:22:17,759 at the end of last year and then what the what we currently 502 00:22:17,759 --> 00:22:18,759 project would be 503 00:22:18,759 --> 00:22:22,390 that particular budget or what we anticipate spending at 504 00:22:22,390 --> 00:22:23,200 the year of eight 505 00:22:23,200 --> 00:22:28,920 fiscal year 17-18. You'll see that we do as a result of 506 00:22:28,920 --> 00:22:30,240 some of the changes that 507 00:22:30,240 --> 00:22:32,980 we've made in the capital program in particular the mining 508 00:22:32,980 --> 00:22:33,720 we didn't just 509 00:22:33,720 --> 00:22:36,960 strip out those related expenses but there were also some 510 00:22:36,960 --> 00:22:37,640 assumptions on 511 00:22:37,640 --> 00:22:40,819 revenues that we've also had to pull out and so that so 512 00:22:40,819 --> 00:22:42,359 there's been changes on 513 00:22:42,359 --> 00:22:46,319 both sides of this equation and then the total expenses 514 00:22:46,319 --> 00:22:47,759 have been reduced by about 515 00:22:47,759 --> 00:22:52,450 four point three million dollars again we anticipate some 516 00:22:52,450 --> 00:22:53,759 drawdown in in that 517 00:22:53,759 --> 00:22:57,509 fund balance but again staying well above the even the 18 518 00:22:57,509 --> 00:22:58,680 percent maximum 519 00:22:58,680 --> 00:23:03,170 that set for that particular fund. This 12 percent 520 00:23:03,170 --> 00:23:05,359 translates to approximately a 521 00:23:05,359 --> 00:23:09,559 six hundred thousand dollar revenue so about 1.2 million 522 00:23:09,559 --> 00:23:11,160 full years that's six 523 00:23:11,160 --> 00:23:17,190 hundred thousand for if it was implemented now mid-year. 524 00:23:17,190 --> 00:23:18,119 Some financial 525 00:23:18,119 --> 00:23:20,700 considerations that we just wanted to pose to you that we 526 00:23:20,700 --> 00:23:21,400 've discussed 527 00:23:21,400 --> 00:23:24,440 internally and just let me just quickly say to you that 528 00:23:24,440 --> 00:23:25,720 this we believe that 529 00:23:25,720 --> 00:23:29,519 this is a first step in in in the recommendation that we're 530 00:23:29,519 --> 00:23:30,359 bringing to 531 00:23:30,359 --> 00:23:33,390 you we anticipate over the next three to four months when 532 00:23:33,390 --> 00:23:34,799 we come back to you the 533 00:23:34,799 --> 00:23:38,279 possibility of some additional rate reductions potentially 534 00:23:38,279 --> 00:23:38,720 both in 535 00:23:38,720 --> 00:23:43,269 residential but also in some of our other classes. So in 536 00:23:43,269 --> 00:23:44,839 doing this 12 percent 537 00:23:44,839 --> 00:23:47,619 reduction again major consideration is to make sure that we 538 00:23:47,619 --> 00:23:48,559 're staying within 539 00:23:48,559 --> 00:23:52,359 those reserve targets of 14 to 18 percent. We also wanted 540 00:23:52,359 --> 00:23:53,359 to make sure that 541 00:23:53,359 --> 00:23:57,450 we safeguarded that fund we do have our wholesale revenue 542 00:23:57,450 --> 00:23:58,559 that makes about two 543 00:23:58,559 --> 00:24:02,420 million dollars we want to make sure that we that that we 544 00:24:02,420 --> 00:24:03,279 have a better 545 00:24:03,279 --> 00:24:07,250 understanding through our cost of service of what potential 546 00:24:07,250 --> 00:24:08,480 impacts could 547 00:24:08,480 --> 00:24:11,750 come to that particular source again two point two million 548 00:24:11,750 --> 00:24:12,559 dollars is a 549 00:24:12,559 --> 00:24:17,500 significant amount for that fund and then finally we've not 550 00:24:17,500 --> 00:24:18,319 made any 551 00:24:18,319 --> 00:24:21,339 recommendations to you today regarding commercial rates we 552 00:24:21,339 --> 00:24:22,599 do anticipate that 553 00:24:22,599 --> 00:24:25,359 there may be some changes there as well it's the largest 554 00:24:25,359 --> 00:24:26,559 revenue stream for that 555 00:24:26,559 --> 00:24:29,349 particular fund and so we want to be cognizant of the fact 556 00:24:29,349 --> 00:24:30,160 that that we're 557 00:24:30,160 --> 00:24:33,529 providing to you a conservative reduction today and and 558 00:24:33,529 --> 00:24:34,440 come back to you 559 00:24:34,440 --> 00:24:37,589 with a much more in-depth discussion about rates in total 560 00:24:37,589 --> 00:24:38,599 once we have more 561 00:24:38,599 --> 00:24:41,970 information from our cost of service and also our 562 00:24:41,970 --> 00:24:45,240 management study. So next steps 563 00:24:45,240 --> 00:24:49,480 is again we'll staff will be reviewing this management 564 00:24:49,480 --> 00:24:51,799 study in addition to 565 00:24:51,799 --> 00:24:54,819 that we'll be conducting a market study for all our rates 566 00:24:54,819 --> 00:24:55,599 to make sure we 567 00:24:55,599 --> 00:24:58,619 understand what we're able to do with those rates in 568 00:24:58,619 --> 00:25:00,279 particular wholesale and 569 00:25:00,279 --> 00:25:04,240 some of these large commercial rates that we have and then 570 00:25:04,240 --> 00:25:05,440 finally we'll be 571 00:25:05,440 --> 00:25:07,859 bringing back to you as part of the proposed budget 572 00:25:07,859 --> 00:25:09,039 potential additional 573 00:25:09,039 --> 00:25:12,789 rate decreases associated with with all these efforts we 574 00:25:12,789 --> 00:25:14,079 anticipate that first 575 00:25:14,079 --> 00:25:17,369 presentation to be for the PAB and the council be in early 576 00:25:17,369 --> 00:25:18,880 summer so you know 577 00:25:18,880 --> 00:25:24,640 we're just around the corner. You know council members of 578 00:25:24,640 --> 00:25:26,160 the PAB that's that 579 00:25:26,160 --> 00:25:28,930 wraps up my presentation I've covered a lot I'd be happy to 580 00:25:28,930 --> 00:25:30,000 stand for any 581 00:25:30,000 --> 00:25:33,019 questions again we have Ethan Cox here and if there's any 582 00:25:33,019 --> 00:25:34,079 specific questions on 583 00:25:34,079 --> 00:25:37,099 that operation we'll be able to provide those responses to 584 00:25:37,099 --> 00:25:39,119 you. I don't have a 585 00:25:39,119 --> 00:25:42,369 question but I have a comment I applaud you for going 586 00:25:42,369 --> 00:25:43,640 through and doing cost 587 00:25:43,640 --> 00:25:47,759 reductions and saying to have a rate decrease now not 588 00:25:47,759 --> 00:25:49,440 waiting until next year 589 00:25:49,440 --> 00:25:52,809 because it's our citizens money and it's not our money so I 590 00:25:52,809 --> 00:25:54,039 applaud you for doing 591 00:25:54,039 --> 00:25:56,160 that. 592 00:25:58,759 --> 00:26:05,000 Questions? I mean I'll second that. That's pretty 593 00:26:05,000 --> 00:26:06,640 incredible I mean 12% 594 00:26:06,640 --> 00:26:12,720 decrease in rates is pretty incredible to find that kind of 595 00:26:12,720 --> 00:26:13,720 operating 596 00:26:13,720 --> 00:26:17,710 efficiency and that's that you're gonna be applauded for 597 00:26:17,710 --> 00:26:20,920 that so and I'm gonna 598 00:26:20,920 --> 00:26:24,450 I'm gonna hold you to it that there's more reductions to 599 00:26:24,450 --> 00:26:26,279 come right? I guess I 600 00:26:26,279 --> 00:26:29,319 do have a question you didn't reduce it even more because 601 00:26:29,319 --> 00:26:31,240 the reserves are like 602 00:26:31,240 --> 00:26:35,539 you said significantly above the 18% but I think that's pr 603 00:26:35,539 --> 00:26:36,640 udent because you're 604 00:26:36,640 --> 00:26:39,390 you're going through this whole commercial review too and 605 00:26:39,390 --> 00:26:39,880 then once 606 00:26:39,880 --> 00:26:42,630 you're done with that I think we'll have a more 607 00:26:42,630 --> 00:26:45,400 comprehensive picture to then 608 00:26:45,400 --> 00:26:48,519 tighten that up even a little bit better too. Yes ma'am 609 00:26:48,519 --> 00:26:50,359 that is the plan. Thank you. 610 00:26:50,359 --> 00:26:57,200 Any other questions? So you're I guess you're basing some 611 00:26:57,200 --> 00:26:57,960 of the future 612 00:26:57,960 --> 00:27:00,650 reductions on that the cost of service study for the 613 00:27:00,650 --> 00:27:02,160 commercial rates will come 614 00:27:02,160 --> 00:27:05,799 in and we will be able to reduce those as well I mean you 615 00:27:05,799 --> 00:27:06,960 're not foreseeing 616 00:27:06,960 --> 00:27:10,500 that we're undercharging them and somehow we won't be able 617 00:27:10,500 --> 00:27:11,400 to offer that 618 00:27:11,400 --> 00:27:16,759 reduction to our residential. Yeah our preliminary review 619 00:27:16,759 --> 00:27:18,519 of those rates is 620 00:27:18,519 --> 00:27:23,660 that there is opportunities to potentially lower those as 621 00:27:23,660 --> 00:27:24,119 well. 622 00:27:26,319 --> 00:27:31,440 Very good. I don't think anybody's gonna be against 623 00:27:31,440 --> 00:27:34,799 reducing rates. Well and just 624 00:27:34,799 --> 00:27:37,819 let me say to you Mr. Chairman that we do have you know 625 00:27:37,819 --> 00:27:38,759 this particular 626 00:27:38,759 --> 00:27:42,579 discussion as well with the City Council tomorrow there is 627 00:27:42,579 --> 00:27:44,000 a an agenda item for 628 00:27:44,000 --> 00:27:49,799 you tonight in individual consideration to amend the 629 00:27:49,799 --> 00:27:50,759 current rate ordinance 630 00:27:50,759 --> 00:27:57,079 and reflect these particular reductions now. Good very good 631 00:27:57,079 --> 00:27:58,559 . Thank you Tony. 632 00:27:58,559 --> 00:28:05,839 Appreciate it. Okay item C is to receive a report, hold a 633 00:28:05,839 --> 00:28:06,599 discussion and give 634 00:28:06,599 --> 00:28:10,809 staff direction regarding current city facilities and how 635 00:28:10,809 --> 00:28:12,079 to proceed with 636 00:28:12,079 --> 00:28:15,099 planning for future space needs regarding the Denton 637 00:28:15,099 --> 00:28:15,960 Service Center 638 00:28:15,960 --> 00:28:20,579 traffic operations building and storage facility located at 639 00:28:20,579 --> 00:28:22,839 651 Mayhill Road. 640 00:28:22,839 --> 00:28:26,289 Thank you Mr. Chairman, members of the PUB Mario Kanazaris, 641 00:28:26,289 --> 00:28:27,480 assistant city manager. 642 00:28:27,480 --> 00:28:30,220 I wanted to present some information to you that was given 643 00:28:30,220 --> 00:28:31,200 to City Council back 644 00:28:31,200 --> 00:28:34,650 in mid February about some existing space needs that we had 645 00:28:34,650 --> 00:28:35,440 our service 646 00:28:35,440 --> 00:28:39,250 center along with our transportation operations building 647 00:28:39,250 --> 00:28:40,359 and some solutions 648 00:28:40,359 --> 00:28:44,390 that we were proposing to utilize to help offset some of 649 00:28:44,390 --> 00:28:45,640 those space needs 650 00:28:45,640 --> 00:28:49,069 and the reason we're bringing it to to the PUB is because 651 00:28:49,069 --> 00:28:50,039 it does affect 652 00:28:50,039 --> 00:28:52,559 utility operations along with solid waste and so I'm going 653 00:28:52,559 --> 00:28:53,240 to go through a 654 00:28:53,240 --> 00:28:55,799 number of slides and let you see what we're proposing and 655 00:28:55,799 --> 00:28:56,680 the assumptions 656 00:28:56,680 --> 00:29:00,740 behind those proposals. So to give you a brief overview 657 00:29:00,740 --> 00:29:02,240 with the presentation just 658 00:29:02,240 --> 00:29:05,279 to give you some history of why we're here some of the 659 00:29:05,279 --> 00:29:06,559 issues that were being 660 00:29:06,559 --> 00:29:09,039 addressed again the space needs that we have in our 661 00:29:09,039 --> 00:29:10,400 operations at the service 662 00:29:10,400 --> 00:29:13,730 center and also at traffic operations. The assumptions that 663 00:29:13,730 --> 00:29:14,279 were used 664 00:29:14,279 --> 00:29:19,039 originally through our previous analysis, some of the 665 00:29:19,039 --> 00:29:19,799 options that we're 666 00:29:19,799 --> 00:29:22,490 utilizing to solve some of the issues that are being 667 00:29:22,490 --> 00:29:24,079 presented, the financial 668 00:29:24,079 --> 00:29:27,539 implications and Mr. Puente is here to to be able to answer 669 00:29:27,539 --> 00:29:28,079 some of the 670 00:29:28,079 --> 00:29:31,799 specifics if the PUB has those questions and then what we 671 00:29:31,799 --> 00:29:32,599 believe will help 672 00:29:32,599 --> 00:29:36,319 improve our overall overall operations along with customer 673 00:29:36,319 --> 00:29:37,559 service that it 674 00:29:37,559 --> 00:29:41,740 affects our community and our constituents and then some 675 00:29:41,740 --> 00:29:42,559 next steps. 676 00:29:42,559 --> 00:29:46,119 To give you an overview of the service center campus I've 677 00:29:46,119 --> 00:29:47,000 outlined here in 678 00:29:47,000 --> 00:29:51,559 yellow the campus itself is approximately 46 acres in size 679 00:29:51,559 --> 00:29:52,599 it's an 680 00:29:52,599 --> 00:29:56,210 industrial area off at Mingo Road I believe the PUB before 681 00:29:56,210 --> 00:29:56,640 before I started 682 00:29:56,640 --> 00:29:59,890 with the organization I had its meetings over there so you 683 00:29:59,890 --> 00:30:00,920 should be relatively 684 00:30:00,920 --> 00:30:06,700 familiar with with this building and and then the overall 685 00:30:06,700 --> 00:30:07,480 campus. 686 00:30:07,480 --> 00:30:11,289 Procurement materials management is housed there our fleet 687 00:30:11,289 --> 00:30:11,960 services 688 00:30:11,960 --> 00:30:15,950 operations are housed there we also have a number of areas 689 00:30:15,950 --> 00:30:17,279 where we continue we 690 00:30:17,279 --> 00:30:20,720 where we house our our fill and dirt materials so that can 691 00:30:20,720 --> 00:30:21,759 be utilized for 692 00:30:21,759 --> 00:30:24,880 our drainage and our street operations so again just to 693 00:30:24,880 --> 00:30:26,119 keep kind of give you 694 00:30:26,119 --> 00:30:29,930 an overview of the location which we're talking about the 695 00:30:29,930 --> 00:30:31,079 two areas the two 696 00:30:31,079 --> 00:30:33,029 buildings that we're covering this evening and it was 697 00:30:33,029 --> 00:30:33,759 covered with City 698 00:30:33,759 --> 00:30:36,779 Council was the the the first one we're going to be 699 00:30:36,779 --> 00:30:38,799 covering is a service center 700 00:30:38,799 --> 00:30:43,900 here in the on the I guess your top top left my right here 701 00:30:43,900 --> 00:30:45,559 on the screen on the 702 00:30:45,559 --> 00:30:48,069 on the left side and then the traffic operations here on 703 00:30:48,069 --> 00:30:49,039 the opposite side of 704 00:30:49,039 --> 00:30:53,000 of the screen there and again to give you some history the 705 00:30:53,000 --> 00:30:54,240 service center was 706 00:30:54,240 --> 00:30:58,880 built back in 1980 the traffic operations was the building 707 00:30:58,880 --> 00:30:59,400 itself was 708 00:30:59,400 --> 00:31:03,950 built in the 60s over time the the service center has been 709 00:31:03,950 --> 00:31:04,559 renovated or 710 00:31:04,559 --> 00:31:08,009 expanded slightly over the last number of years to give you 711 00:31:08,009 --> 00:31:09,079 some statistics 712 00:31:09,079 --> 00:31:11,809 about the city of Denton it was much smaller back then back 713 00:31:11,809 --> 00:31:13,000 in 1980 when it 714 00:31:13,000 --> 00:31:16,019 was constructed and as you can see the sizes of our 715 00:31:16,019 --> 00:31:17,240 community now and it's 716 00:31:17,240 --> 00:31:21,210 certainly much larger these numbers were from 2016 and as 717 00:31:21,210 --> 00:31:22,240 you can also see just 718 00:31:22,240 --> 00:31:24,440 the amount of square mileage that the city has expanded 719 00:31:24,440 --> 00:31:25,720 over the years we we've 720 00:31:25,720 --> 00:31:29,569 expanded three three times the size of our community since 721 00:31:29,569 --> 00:31:30,440 this facility was 722 00:31:30,440 --> 00:31:33,819 opened and then the most glaring issue is a fact that back 723 00:31:33,819 --> 00:31:35,319 in 1980 we house a 724 00:31:35,319 --> 00:31:38,130 little over a hundred employees and now we're certainly 725 00:31:38,130 --> 00:31:39,599 double that 250 somewhat 726 00:31:39,599 --> 00:31:43,700 employees now are our house there and and I would imagine 727 00:31:43,700 --> 00:31:44,839 that as during 728 00:31:44,839 --> 00:31:47,200 seasonal activity or during the summer months there's 729 00:31:47,200 --> 00:31:48,039 probably additional 730 00:31:48,039 --> 00:31:50,710 employees there especially at the parks department because 731 00:31:50,710 --> 00:31:51,440 of the amount of 732 00:31:51,440 --> 00:31:54,690 activities happening in and around the summer months of the 733 00:31:54,690 --> 00:31:58,359 calendar year the 734 00:31:58,359 --> 00:32:00,859 first facility wanted to cover was a service center as 735 00:32:00,859 --> 00:32:02,039 again I was mentioned 736 00:32:02,039 --> 00:32:05,410 it was built in 1980 it's been updated over the last number 737 00:32:05,410 --> 00:32:07,440 of years 250 738 00:32:07,440 --> 00:32:12,039 employees operate from that location it's very cramped 739 00:32:12,039 --> 00:32:13,160 there's no room for 740 00:32:13,160 --> 00:32:17,190 growth in existing configuration it's somewhat poorly 741 00:32:17,190 --> 00:32:18,759 configured you all 742 00:32:18,759 --> 00:32:21,589 familiar with it when you walk into the lobby it's not the 743 00:32:21,589 --> 00:32:22,720 most user-friendly 744 00:32:22,720 --> 00:32:27,039 location there's no one to greet you if you look behind the 745 00:32:27,039 --> 00:32:28,160 the first wall 746 00:32:28,160 --> 00:32:32,400 behind the stairs there's restroom facilities there it's 747 00:32:32,400 --> 00:32:33,799 also it also has 748 00:32:33,799 --> 00:32:36,569 shower facilities so if you can imagine the public walks in 749 00:32:36,569 --> 00:32:37,480 and we don't have a 750 00:32:37,480 --> 00:32:40,210 lot of public that utilize that facility but we do have 751 00:32:40,210 --> 00:32:40,960 contractors 752 00:32:40,960 --> 00:32:44,809 consultants that come in to do business there to have 753 00:32:44,809 --> 00:32:46,559 meetings etc and so when 754 00:32:46,559 --> 00:32:50,119 you walk in if you use restroom facilities you're greeted 755 00:32:50,119 --> 00:32:50,920 with you know 756 00:32:50,920 --> 00:32:53,730 your traditional restroom facilities also shower facilities 757 00:32:53,730 --> 00:32:54,359 and so it does 758 00:32:54,359 --> 00:32:58,529 create some awkwardness if field employees are utilizing 759 00:32:58,529 --> 00:32:59,000 those 760 00:32:59,000 --> 00:33:02,019 facilities if been out in the field working in a very muddy 761 00:33:02,019 --> 00:33:02,400 dirty 762 00:33:02,400 --> 00:33:05,420 environment and they're needing to clean off rinse off and 763 00:33:05,420 --> 00:33:06,400 you're also 764 00:33:06,400 --> 00:33:09,920 intermingling with folks from the public utilizing restroom 765 00:33:09,920 --> 00:33:11,240 so not the ideal 766 00:33:11,240 --> 00:33:17,130 situation so if so again just the current configurations of 767 00:33:17,130 --> 00:33:18,519 spaces it's 768 00:33:18,519 --> 00:33:23,640 not the most configured appropriately some previous 769 00:33:23,640 --> 00:33:24,680 assumptions that we use 770 00:33:24,680 --> 00:33:30,119 that to do some space needs back in 2015 2016 the city had 771 00:33:30,119 --> 00:33:30,599 hired a 772 00:33:30,599 --> 00:33:33,910 consultant to do a series of space needs analysis for the 773 00:33:33,910 --> 00:33:35,200 entire organization 774 00:33:35,200 --> 00:33:39,779 from City Hall to City Hall East to City Hall West our fire 775 00:33:39,779 --> 00:33:41,079 stations etc 776 00:33:41,079 --> 00:33:44,099 and one of these was for a service center and one of the 777 00:33:44,099 --> 00:33:45,079 considerations 778 00:33:45,079 --> 00:33:49,269 that was discussed was potentially having an annexed a 779 00:33:49,269 --> 00:33:51,000 service center annex 780 00:33:51,000 --> 00:33:56,980 on the southwest side of town close to fire station 7 near 781 00:33:56,980 --> 00:33:58,519 Bonnie Bray and in 782 00:33:58,519 --> 00:34:02,809 vintage and the idea behind it was to help move some of the 783 00:34:02,809 --> 00:34:03,920 operations to that 784 00:34:03,920 --> 00:34:08,090 location again as a city continued to grow but the cost of 785 00:34:08,090 --> 00:34:09,079 those of that 786 00:34:09,079 --> 00:34:13,110 facility was in a neighborhood of 21 to 22 million dollars 787 00:34:13,110 --> 00:34:14,480 for 40,000 square feet 788 00:34:14,480 --> 00:34:19,030 and so that would require bond issuance it would be years 789 00:34:19,030 --> 00:34:20,500 in the making and so 790 00:34:20,500 --> 00:34:24,500 at that time through a change of administration with the 791 00:34:24,500 --> 00:34:25,480 new city manager 792 00:34:25,480 --> 00:34:28,889 coming on board late in January the conversation was 793 00:34:28,889 --> 00:34:30,679 resurrected as to what 794 00:34:30,679 --> 00:34:36,079 options could we utilize to allow for better utilization of 795 00:34:36,079 --> 00:34:36,960 our existing 796 00:34:36,960 --> 00:34:41,079 space but also try to meet the needs of our staff as it 797 00:34:41,079 --> 00:34:42,960 continues to grow and 798 00:34:42,960 --> 00:34:47,309 again so here the last number of months we viewed a lot we 799 00:34:47,309 --> 00:34:49,000 've analyzed all the 800 00:34:49,000 --> 00:34:52,289 spaces that we have in the city knowing that trying to 801 00:34:52,289 --> 00:34:54,719 build a 21 to 22 million 802 00:34:54,719 --> 00:35:00,500 dollar facility or potentially more depending on as as mr. 803 00:35:00,500 --> 00:35:01,360 Allen mentioned 804 00:35:01,360 --> 00:35:04,139 about the cost of inflation would be higher in current 805 00:35:04,139 --> 00:35:05,920 dollars what could we 806 00:35:05,920 --> 00:35:09,239 do to better utilize existing spaces and some of that space 807 00:35:09,239 --> 00:35:10,239 may be hiding in 808 00:35:10,239 --> 00:35:12,730 plain sight so what we decided to do is look at the 809 00:35:12,730 --> 00:35:15,199 existing service center and 810 00:35:15,199 --> 00:35:19,010 I'll show you a slide here of what we decided to do and is 811 00:35:19,010 --> 00:35:20,159 look utilizing the 812 00:35:20,159 --> 00:35:23,179 existing service center and looking at materials management 813 00:35:23,179 --> 00:35:24,079 as an opportunity 814 00:35:24,079 --> 00:35:27,360 where if we have the option of moving materials management 815 00:35:27,360 --> 00:35:28,280 out of the service 816 00:35:28,280 --> 00:35:32,000 center could we utilize that vacant space and reconfigure 817 00:35:32,000 --> 00:35:33,039 it into office 818 00:35:33,039 --> 00:35:38,860 space and so what you have here before you basically are a 819 00:35:38,860 --> 00:35:41,039 snapshot of the the 820 00:35:41,039 --> 00:35:44,320 site layout the interior site layout of the service center 821 00:35:44,320 --> 00:35:45,440 the first and second 822 00:35:45,440 --> 00:35:47,960 floor and the bottom floor where it says materials 823 00:35:47,960 --> 00:35:49,280 management is just under 824 00:35:49,280 --> 00:35:53,000 30,000 square feet and again that is a warehouse operations 825 00:35:53,000 --> 00:35:54,360 that is where where 826 00:35:54,360 --> 00:35:59,880 departments are issued supplies from just from poles and 827 00:35:59,880 --> 00:36:01,800 equipment for P for 828 00:36:01,800 --> 00:36:10,219 DME and other types of cable to pipe fittings pipes blue 829 00:36:10,219 --> 00:36:11,840 jeans it depends I 830 00:36:11,840 --> 00:36:14,550 mean it's a it's a variety of things that are issued and 831 00:36:14,550 --> 00:36:15,599 distributed at our 832 00:36:15,599 --> 00:36:19,320 materials management warehouse but it does occupy about 40% 833 00:36:19,320 --> 00:36:19,920 of our square 834 00:36:19,920 --> 00:36:23,199 footage of the first floor of the service center and so 835 00:36:23,199 --> 00:36:25,280 knowing that we 836 00:36:25,280 --> 00:36:29,829 have some operations or some facilities and DME or excuse 837 00:36:29,829 --> 00:36:31,039 me a DME at solid 838 00:36:31,039 --> 00:36:33,769 waste we felt like we could potentially move that 839 00:36:33,769 --> 00:36:36,280 operations over and just 840 00:36:36,280 --> 00:36:39,070 wanted to show you here some photos of the existing service 841 00:36:39,070 --> 00:36:39,960 center and just to 842 00:36:39,960 --> 00:36:44,190 cramp nature in which our operations are being housed in 843 00:36:44,190 --> 00:36:45,760 and and I don't need to 844 00:36:45,760 --> 00:36:48,780 go through every single one of these pictures but but so 845 00:36:48,780 --> 00:36:49,760 some of you that are 846 00:36:49,760 --> 00:36:53,050 familiar with with the facility we have some of our parks 847 00:36:53,050 --> 00:36:54,360 facilities and all the 848 00:36:54,360 --> 00:36:57,730 other operations facility where they've been very been very 849 00:36:57,730 --> 00:36:58,639 creative and 850 00:36:58,639 --> 00:37:01,960 incorporating every single nook and cranny so they can 851 00:37:01,960 --> 00:37:03,639 whether it's having 852 00:37:03,639 --> 00:37:09,000 staff meetings or break room areas that also is 853 00:37:09,000 --> 00:37:10,840 incorporated locker room area 854 00:37:10,840 --> 00:37:13,610 locker room areas our restroom facilities that I'd 855 00:37:13,610 --> 00:37:14,920 mentioned earlier on 856 00:37:14,920 --> 00:37:17,579 the on the bottom right hand corner of the screen we 857 00:37:17,579 --> 00:37:18,719 utilize some of our 858 00:37:18,719 --> 00:37:22,679 equipment bays for staff meetings or areas for our staff to 859 00:37:22,679 --> 00:37:23,699 to have lunch or 860 00:37:23,699 --> 00:37:29,429 have breaks in our parks area which is in the top middle is 861 00:37:29,429 --> 00:37:31,079 is is has equipment 862 00:37:31,079 --> 00:37:34,650 and other supplies where they utilize to to maintain our 863 00:37:34,650 --> 00:37:36,480 park system and so every 864 00:37:36,480 --> 00:37:39,880 single bit of the space is utilized and so really it doesn 865 00:37:39,880 --> 00:37:41,199 't create the necessary 866 00:37:41,199 --> 00:37:45,559 work environment for our staff to have the space they need 867 00:37:45,559 --> 00:37:46,920 to to meet during 868 00:37:46,920 --> 00:37:50,570 the morning when they when they get when they begin their 869 00:37:50,570 --> 00:37:52,380 shift to have a variety 870 00:37:52,380 --> 00:37:54,869 of private conversations when it requires supervisor to 871 00:37:54,869 --> 00:37:55,480 employee top 872 00:37:55,480 --> 00:38:00,199 issues it just makes it very inconvenient very difficult to 873 00:38:00,199 --> 00:38:01,519 have those 874 00:38:01,519 --> 00:38:04,940 kinds of conversations and operate out of that cramped 875 00:38:04,940 --> 00:38:06,280 space and so just wanted 876 00:38:06,280 --> 00:38:11,090 to show you some of those current conditions so the thought 877 00:38:11,090 --> 00:38:12,039 was with with 878 00:38:12,039 --> 00:38:15,599 moving materials management out of that space would free up 879 00:38:15,599 --> 00:38:16,800 quite a bit of space 880 00:38:16,800 --> 00:38:19,940 at the service center and and I know we brought this 881 00:38:19,940 --> 00:38:21,840 information before you to 882 00:38:21,840 --> 00:38:25,079 the pub before but the thought was if we could utilize an 883 00:38:25,079 --> 00:38:26,280 existing location 884 00:38:26,280 --> 00:38:30,360 existing space 651 Mayhill is the one that came to mind 885 00:38:30,360 --> 00:38:31,679 that's a space that is 886 00:38:31,679 --> 00:38:36,639 owned by the city it's a solid waste facility over at the 887 00:38:36,639 --> 00:38:38,320 Mayhill location 888 00:38:38,320 --> 00:38:43,280 it's 81,000 square feet as a former Department of Defense 889 00:38:43,280 --> 00:38:44,280 warehouse 890 00:38:44,280 --> 00:38:48,599 location where as troops were were deployed overseas 891 00:38:48,599 --> 00:38:49,840 depending on whatever 892 00:38:49,840 --> 00:38:53,030 the theater of operation they were they would they would 893 00:38:53,030 --> 00:38:54,000 maintain their 894 00:38:54,000 --> 00:38:57,159 equipment their vehicles or personal vehicles in this space 895 00:38:57,159 --> 00:38:58,599 and so as you can 896 00:38:58,599 --> 00:39:02,039 see by the pictures it's very rectangular in size for the 897 00:39:02,039 --> 00:39:02,639 most part 898 00:39:02,639 --> 00:39:06,699 it's it's a very open space it's it's basically a blank 899 00:39:06,699 --> 00:39:09,400 canvas we do house 900 00:39:09,400 --> 00:39:14,949 some solid waste carts and I know DME has some of their 901 00:39:14,949 --> 00:39:17,800 equipment there but 902 00:39:17,800 --> 00:39:20,469 we'll leave that we can utilize that space and move 903 00:39:20,469 --> 00:39:22,119 materials management over 904 00:39:22,119 --> 00:39:27,219 into into this location and so the thought was if we can 905 00:39:27,219 --> 00:39:28,559 move approximately 906 00:39:28,559 --> 00:39:31,400 30,000 square feet of materials management out of the 907 00:39:31,400 --> 00:39:32,159 service center and 908 00:39:32,159 --> 00:39:35,880 put them into this 81,000 square feet it really would open 909 00:39:35,880 --> 00:39:36,679 up quite a bit of 910 00:39:36,679 --> 00:39:40,889 space we're looking at potentially doubling the size of 911 00:39:40,889 --> 00:39:41,880 materials management 912 00:39:41,880 --> 00:39:45,760 their footprint because some of this equipment that 913 00:39:45,760 --> 00:39:46,880 materials management 914 00:39:46,880 --> 00:39:50,519 houses over at service center is under awnings so it is 915 00:39:50,519 --> 00:39:51,719 protected by the 916 00:39:51,719 --> 00:39:55,570 elements but not completely and so the thought is if we can 917 00:39:55,570 --> 00:39:56,679 move most of not 918 00:39:56,679 --> 00:40:01,869 all of that material under a roof a would protect it would 919 00:40:01,869 --> 00:40:03,159 protect the asset 920 00:40:03,159 --> 00:40:06,409 and really give materials management the space they need to 921 00:40:06,409 --> 00:40:07,599 to fully function in 922 00:40:07,599 --> 00:40:11,320 that location it still provides some additional space for 923 00:40:11,320 --> 00:40:12,199 future expansion 924 00:40:12,199 --> 00:40:16,369 which I'll show you here in some subsequent slides it would 925 00:40:16,369 --> 00:40:17,400 provide for 926 00:40:17,400 --> 00:40:21,159 about just under five acres of a laydown yard as well 927 00:40:21,159 --> 00:40:22,760 employee spaces parking 928 00:40:22,760 --> 00:40:28,539 spaces for this location and so we believe that that would 929 00:40:28,539 --> 00:40:29,940 again free up 930 00:40:29,940 --> 00:40:34,230 some of the space and so as a result there is an investment 931 00:40:34,230 --> 00:40:35,480 to be made what 932 00:40:35,480 --> 00:40:41,150 we were thinking is if we could working with our architects 933 00:40:41,150 --> 00:40:42,559 we believe we have 934 00:40:42,559 --> 00:40:45,320 developed some at least high-level planning estimates on 935 00:40:45,320 --> 00:40:46,239 probable costs on 936 00:40:46,239 --> 00:40:51,000 this construction project to to allocate about a million 937 00:40:51,000 --> 00:40:52,239 six for moving 938 00:40:52,239 --> 00:40:54,710 materials management there is an investment to be made on 939 00:40:54,710 --> 00:40:55,280 the laydown 940 00:40:55,280 --> 00:40:59,019 yard and other parking that's required for that location so 941 00:40:59,019 --> 00:40:59,760 all in with 942 00:40:59,760 --> 00:41:02,019 construction it'd be right at two point five million 943 00:41:02,019 --> 00:41:03,760 dollars we would require 944 00:41:03,760 --> 00:41:06,909 some additional furniture fixtures and equipment to out 945 00:41:06,909 --> 00:41:08,159 outfit that facility 946 00:41:08,159 --> 00:41:11,179 some design fees would be incorporated into that and then 947 00:41:11,179 --> 00:41:11,800 some minor 948 00:41:11,800 --> 00:41:15,519 development fees cost that we pay for the city for as part 949 00:41:15,519 --> 00:41:16,519 of its development 950 00:41:16,519 --> 00:41:19,250 of that of that location and working with the finance 951 00:41:19,250 --> 00:41:20,639 department we believe 952 00:41:20,639 --> 00:41:25,000 we could utilize excess certificates of obligation in the 953 00:41:25,000 --> 00:41:26,400 solid waste fund to 954 00:41:26,400 --> 00:41:32,130 help offset the cost of that process on that project so I 955 00:41:32,130 --> 00:41:34,280 'll let that digest for 956 00:41:34,280 --> 00:41:43,670 the minute so in turn what what does that do for us by 957 00:41:43,670 --> 00:41:44,639 moving materials 958 00:41:44,639 --> 00:41:47,670 management out of the service center what we believe it'll 959 00:41:47,670 --> 00:41:48,559 do is it'll free 960 00:41:48,559 --> 00:41:52,409 up quite a bit of space and to allow our parks operations 961 00:41:52,409 --> 00:41:53,519 streets electric 962 00:41:53,519 --> 00:41:58,070 communications water distribution utility safety training 963 00:41:58,070 --> 00:41:58,880 it would allow 964 00:41:58,880 --> 00:42:02,119 us to expand further into that vacant footprint of the 965 00:42:02,119 --> 00:42:04,559 facility so before this 966 00:42:04,559 --> 00:42:07,929 future this the space here where it says future expansion 967 00:42:07,929 --> 00:42:09,440 again it showed 968 00:42:09,440 --> 00:42:12,550 twenty nine thousand it allows for a future expansion of 969 00:42:12,550 --> 00:42:13,760 our facility so what 970 00:42:13,760 --> 00:42:17,840 I decided what I provided here is a table of the current 971 00:42:17,840 --> 00:42:19,000 configuration of 972 00:42:19,000 --> 00:42:22,760 the square footage and again these are how these are high 973 00:42:22,760 --> 00:42:23,840 level planning 974 00:42:23,840 --> 00:42:26,860 estimates of the square footage nothing has been designed 975 00:42:26,860 --> 00:42:27,519 these are just 976 00:42:27,519 --> 00:42:30,960 conversations that have been had with our architect at a 977 00:42:30,960 --> 00:42:32,320 planning level from 978 00:42:32,320 --> 00:42:35,340 a planning level estimate and just what could happen if 979 00:42:35,340 --> 00:42:36,559 this space were vacated 980 00:42:36,559 --> 00:42:40,110 so what I wanted to show you here is just the current 981 00:42:40,110 --> 00:42:41,639 square footage and our 982 00:42:41,639 --> 00:42:44,389 current operations and the proposed square footage with 983 00:42:44,389 --> 00:42:45,480 materials management 984 00:42:45,480 --> 00:42:48,349 moving out of the service center on the first floor so you 985 00:42:48,349 --> 00:42:48,960 can see the 986 00:42:48,960 --> 00:42:52,130 difference and this is then what would happen on the second 987 00:42:52,130 --> 00:42:52,960 floor it would 988 00:42:52,960 --> 00:42:56,150 allow for engineering to expand water wastewater 989 00:42:56,150 --> 00:42:58,159 administration to to to be 990 00:42:58,159 --> 00:43:03,099 reconfigured in a much more holistic fashion purchasing 991 00:43:03,099 --> 00:43:04,119 administration the 992 00:43:04,119 --> 00:43:07,639 actual purchasing manager along with her staff would stay 993 00:43:07,639 --> 00:43:09,000 at the service center 994 00:43:09,000 --> 00:43:11,510 at this point it was just be the materials management staff 995 00:43:11,510 --> 00:43:12,159 that would be 996 00:43:12,159 --> 00:43:17,190 moving over to the service center so as you can see it does 997 00:43:17,190 --> 00:43:18,559 allow room for 998 00:43:18,559 --> 00:43:22,409 expansion on the previous slide so as our staff continues 999 00:43:22,409 --> 00:43:23,380 to grow we have 1000 00:43:23,380 --> 00:43:27,380 about 18,000 square feet to move into that over time and so 1001 00:43:27,380 --> 00:43:28,760 in essence it 1002 00:43:28,760 --> 00:43:32,139 would forego the need having to build a second service 1003 00:43:32,139 --> 00:43:33,400 center or a service 1004 00:43:33,400 --> 00:43:40,340 center annex in the near future for us to make that happen 1005 00:43:40,340 --> 00:43:42,360 it would be just 1006 00:43:42,360 --> 00:43:46,079 under a nine million dollar investment to make that change 1007 00:43:46,079 --> 00:43:48,079 to to renovate the 1008 00:43:48,079 --> 00:43:50,460 service center we're talking about five point eight million 1009 00:43:50,460 --> 00:43:51,039 dollars some 1010 00:43:51,039 --> 00:43:53,320 additional side improvements that would be necessary there 1011 00:43:53,320 --> 00:43:54,159 at the service center 1012 00:43:54,159 --> 00:43:57,469 so all in construction and hard costs would be just under 1013 00:43:57,469 --> 00:43:58,480 six point eight 1014 00:43:58,480 --> 00:44:01,320 million dollars along with furniture fixtures and equipment 1015 00:44:01,320 --> 00:44:02,980 to add into the 1016 00:44:02,980 --> 00:44:05,820 additional footprint that would be moving into that vacant 1017 00:44:05,820 --> 00:44:06,559 space what the 1018 00:44:06,559 --> 00:44:10,039 design fees and the development development fees for that 1019 00:44:10,039 --> 00:44:10,760 project so 1020 00:44:10,760 --> 00:44:13,780 we're talking right under nine million dollars for that 1021 00:44:13,780 --> 00:44:15,119 entire project to be 1022 00:44:15,119 --> 00:44:20,599 completed and on the opposite side our funding sources that 1023 00:44:20,599 --> 00:44:21,519 we've been working 1024 00:44:21,519 --> 00:44:25,239 with the finance department to to at least from a high- 1025 00:44:25,239 --> 00:44:27,119 level perspective from 1026 00:44:27,119 --> 00:44:30,559 an allocation of if we were to move forward with this 1027 00:44:30,559 --> 00:44:31,840 project what would be 1028 00:44:31,840 --> 00:44:34,610 estimated that those respective funds and those areas of 1029 00:44:34,610 --> 00:44:35,599 funding would come 1030 00:44:35,599 --> 00:44:43,070 from so from a service center perspective we believe that 1031 00:44:43,070 --> 00:44:43,480 moving 1032 00:44:43,480 --> 00:44:47,699 purchasing from the service center to 651 Mayhill makes 1033 00:44:47,699 --> 00:44:49,239 sense we believe that 1034 00:44:49,239 --> 00:44:53,130 it allow us to to allow us to utilize some existing space 1035 00:44:53,130 --> 00:44:54,440 that city already 1036 00:44:54,440 --> 00:44:58,610 owns no need to purchase anything else allowed us allows us 1037 00:44:58,610 --> 00:45:00,000 to expand into the 1038 00:45:00,000 --> 00:45:04,320 existing space and fully utilize all the space areas that 1039 00:45:04,320 --> 00:45:06,440 we have to date we 1040 00:45:06,440 --> 00:45:09,539 believe it will meet the shortages that we have at the 1041 00:45:09,539 --> 00:45:11,400 service center again it 1042 00:45:11,400 --> 00:45:15,579 would allows us to from a standpoint from a construction to 1043 00:45:15,579 --> 00:45:16,320 be minimal amounts of 1044 00:45:16,320 --> 00:45:18,739 construction because you're not having to build new 1045 00:45:18,739 --> 00:45:20,360 foundations you're utilizing 1046 00:45:20,360 --> 00:45:23,469 existing footprints of existing facility so a lot of it's 1047 00:45:23,469 --> 00:45:24,679 just renovation and 1048 00:45:24,679 --> 00:45:28,400 retrofitting into existing into an existing facility it's 1049 00:45:28,400 --> 00:45:29,320 scalable allows 1050 00:45:29,320 --> 00:45:32,570 for future growth we believe that it does provide some 1051 00:45:32,570 --> 00:45:33,760 efficiencies for city 1052 00:45:33,760 --> 00:45:39,190 staff it would must be a much more inviting environment for 1053 00:45:39,190 --> 00:45:40,039 our for the 1054 00:45:40,039 --> 00:45:43,289 visiting public that comes in to see and visit with city 1055 00:45:43,289 --> 00:45:44,559 staff when it comes to 1056 00:45:44,559 --> 00:45:47,579 doing business it would be coder it would meet code 1057 00:45:47,579 --> 00:45:48,519 requirements because we 1058 00:45:48,519 --> 00:45:50,650 would have to add additional restroom facilities at the 1059 00:45:50,650 --> 00:45:51,519 service center which 1060 00:45:51,519 --> 00:45:56,070 were highly needed and so overall we believe that it's a 1061 00:45:56,070 --> 00:45:57,360 good option for the 1062 00:45:57,360 --> 00:45:59,889 staff to consider and for the and then the way it was 1063 00:45:59,889 --> 00:46:01,360 presented to City Council 1064 00:46:01,360 --> 00:46:05,469 we're in the process of in fact we just closed your request 1065 00:46:05,469 --> 00:46:06,519 for qualifications 1066 00:46:06,519 --> 00:46:10,369 for architectural services so just to kind of keep in mind 1067 00:46:10,369 --> 00:46:11,480 that we have not 1068 00:46:11,480 --> 00:46:15,389 spent any money on any of these projects these are all high 1069 00:46:15,389 --> 00:46:16,760 level high level 1070 00:46:16,760 --> 00:46:19,420 planning estimates but we have done a request for 1071 00:46:19,420 --> 00:46:20,599 qualifications for 1072 00:46:20,599 --> 00:46:24,849 architectural services that has closed and so what would we 1073 00:46:24,849 --> 00:46:25,760 be doing and as 1074 00:46:25,760 --> 00:46:29,719 this as staff reviews these requests for qualifications 1075 00:46:29,719 --> 00:46:31,280 once an architect is 1076 00:46:31,280 --> 00:46:35,099 selected and we begin contract negotiations we would bring 1077 00:46:35,099 --> 00:46:35,400 that 1078 00:46:35,400 --> 00:46:39,420 contract to the PUB for your consideration and then if 1079 00:46:39,420 --> 00:46:40,400 voted favorably 1080 00:46:40,400 --> 00:46:43,590 would it then be presented to City Council at a subsequent 1081 00:46:43,590 --> 00:46:45,119 meeting any 1082 00:46:45,119 --> 00:46:48,530 questions about about the service center so far because 1083 00:46:48,530 --> 00:46:49,760 there are some more slides 1084 00:46:49,760 --> 00:46:56,570 but it's about the traffic operations. Just a question 1085 00:46:56,570 --> 00:46:56,599 about you were saying 1086 00:46:56,599 --> 00:47:01,940 that these buildings were old 1960 1980 well the service 1087 00:47:01,940 --> 00:47:03,880 centers 1980s but but 1088 00:47:03,880 --> 00:47:06,570 the traffic operations which I'll show you here in just a 1089 00:47:06,570 --> 00:47:07,679 moment that was built 1090 00:47:07,679 --> 00:47:11,760 in the 1960s okay what you've said is so far so it's it's 1091 00:47:11,760 --> 00:47:13,840 stable as far as you 1092 00:47:13,840 --> 00:47:20,340 know as far as you know it's stable to you know redesign 1093 00:47:20,340 --> 00:47:21,519 okay all right so 1094 00:47:21,519 --> 00:47:23,809 we're talking about the difference between eight or nine 1095 00:47:23,809 --> 00:47:24,559 million dollars 1096 00:47:24,559 --> 00:47:28,659 and thank you to 21 million dollars before start from 1097 00:47:28,659 --> 00:47:32,320 scratch. And we're 1098 00:47:32,320 --> 00:47:37,550 using a building that wasn't being used. I just wanted to 1099 00:47:37,550 --> 00:47:38,519 make sure that the 1100 00:47:38,519 --> 00:47:43,960 existing building was stable. Yes ma'am it's safe and sound 1101 00:47:43,960 --> 00:47:44,760 . Okay. I think this is the 1102 00:47:44,760 --> 00:47:53,050 building that was being used. 1960 isn't that old. Yes they 1103 00:47:53,050 --> 00:47:54,800 've been vacated from there. 1104 00:47:54,800 --> 00:48:00,809 Yes. How does it work from a location standpoint for 1105 00:48:00,809 --> 00:48:02,360 materials management to 1106 00:48:02,360 --> 00:48:08,929 be on Mayhill for all the I don't know I'm assuming at some 1107 00:48:08,929 --> 00:48:10,000 point in time 1108 00:48:10,000 --> 00:48:14,940 everybody has to go there to get something. Correct. Well 1109 00:48:14,940 --> 00:48:16,360 it is change so 1110 00:48:16,360 --> 00:48:19,989 that is it is I guess a con in the standpoint of the pros 1111 00:48:19,989 --> 00:48:21,000 and cons of that 1112 00:48:21,000 --> 00:48:24,719 facility but it will be an adjustment and we were working 1113 00:48:24,719 --> 00:48:25,320 with materials 1114 00:48:25,320 --> 00:48:28,559 management to make sure that that operations that are 1115 00:48:28,559 --> 00:48:29,679 maintained at the 1116 00:48:29,679 --> 00:48:32,119 service center that they have the adequate supplies they 1117 00:48:32,119 --> 00:48:32,840 need to make sure 1118 00:48:32,840 --> 00:48:36,559 they can leave from their location and work in a very 1119 00:48:36,559 --> 00:48:38,880 efficient manner but but 1120 00:48:38,880 --> 00:48:42,010 certainly it will be a change and it is the service center 1121 00:48:42,010 --> 00:48:43,159 where it's located 1122 00:48:43,159 --> 00:48:46,340 now in the central part of town moving it over to to May 1123 00:48:46,340 --> 00:48:47,559 hill will be a change 1124 00:48:47,559 --> 00:48:50,619 so there'll be an adjustment that will need to be made and 1125 00:48:50,619 --> 00:48:51,599 and we think we can 1126 00:48:51,599 --> 00:48:56,579 work through that. How many issues do you have during the 1127 00:48:56,579 --> 00:48:59,360 day? Sir. How many visitors do you have in and out 1128 00:48:59,360 --> 00:49:02,079 during a day? Of the service center? Material management. 1129 00:49:02,079 --> 00:49:04,360 Oh goodness I would 1130 00:49:04,360 --> 00:49:07,380 imagine just about every single operation probably comes in 1131 00:49:07,380 --> 00:49:07,880 and out of 1132 00:49:07,880 --> 00:49:11,760 materials management they just walk across and so it'll be 1133 00:49:11,760 --> 00:49:12,480 a lot of them 1134 00:49:12,480 --> 00:49:15,909 there'll be a lot more coordination that's needed. We're 1135 00:49:15,909 --> 00:49:17,199 not utilizing the 1136 00:49:17,199 --> 00:49:20,579 train for shipping right there are we because the train 1137 00:49:20,579 --> 00:49:21,619 goes right by the 1138 00:49:21,619 --> 00:49:32,239 existing location. Mostly it's all dropped by truck. So 1139 00:49:32,239 --> 00:49:33,000 moving on to 1140 00:49:33,000 --> 00:49:36,159 traffic operation this is the building that was built in 1141 00:49:36,159 --> 00:49:38,079 the 60s this is a one 1142 00:49:38,079 --> 00:49:41,260 of the entrances to the service center and that building 1143 00:49:41,260 --> 00:49:42,519 there is our traffic 1144 00:49:42,519 --> 00:49:46,840 operations facility. It was built in the 1960s is 1145 00:49:46,840 --> 00:49:48,519 approximately 4,000 square foot 1146 00:49:48,519 --> 00:49:54,079 it's the former former animal shelter facility. It's been 1147 00:49:54,079 --> 00:49:55,519 utilized by our 1148 00:49:55,519 --> 00:49:59,480 traffic operations folks since the mid 80s and again some 1149 00:49:59,480 --> 00:50:00,119 of the same 1150 00:50:00,119 --> 00:50:03,210 statistics that I showed you earlier about the size of Dent 1151 00:50:03,210 --> 00:50:04,719 on over the years 1152 00:50:04,719 --> 00:50:08,039 and again if you can imagine the amount of signals that we 1153 00:50:08,039 --> 00:50:09,199 've added over the 1154 00:50:09,199 --> 00:50:12,219 years and the amount of rows that are maintained stop signs 1155 00:50:12,219 --> 00:50:13,360 etc it's quite a bit 1156 00:50:13,360 --> 00:50:15,710 that's happened and they've been utilizing that same 1157 00:50:15,710 --> 00:50:17,440 footprint for for 1158 00:50:17,440 --> 00:50:23,130 30 plus years. Currently non full-time full-time equival 1159 00:50:23,130 --> 00:50:25,639 ents FTEs are housed at 1160 00:50:25,639 --> 00:50:28,840 our traffic operations building. While it does show no 1161 00:50:28,840 --> 00:50:30,119 vehicle bays I mean there 1162 00:50:30,119 --> 00:50:33,559 is a garage door but if you'll see a photo here in a minute 1163 00:50:33,559 --> 00:50:34,440 it does not act 1164 00:50:34,440 --> 00:50:38,400 as a base basically just another storage area for our folks 1165 00:50:38,400 --> 00:50:39,000 and so it's 1166 00:50:39,000 --> 00:50:43,550 very cramped there is no room for expansion and again it is 1167 00:50:43,550 --> 00:50:44,079 the former 1168 00:50:44,079 --> 00:50:49,880 animal control facility so it's time it's time to to 1169 00:50:49,880 --> 00:50:51,639 upgrade our facilities 1170 00:50:51,639 --> 00:50:54,389 for this for the staff and quite honestly they're really it 1171 00:50:54,389 --> 00:50:55,079 's not designed 1172 00:50:55,079 --> 00:50:58,610 for new technology as we replace several of our aging 1173 00:50:58,610 --> 00:51:01,679 traffic signals they are in 1174 00:51:01,679 --> 00:51:04,860 essence smart signals they can be worked remotely and 1175 00:51:04,860 --> 00:51:06,199 things that nature you can 1176 00:51:06,199 --> 00:51:08,940 operate those from a centralized location this facility 1177 00:51:08,940 --> 00:51:09,719 doesn't really 1178 00:51:09,719 --> 00:51:12,460 house it doesn't really lends itself for that type of 1179 00:51:12,460 --> 00:51:13,960 operation so it's very 1180 00:51:13,960 --> 00:51:17,480 manually oriented when it comes to working a traffic signal 1181 00:51:17,480 --> 00:51:18,239 for our staff 1182 00:51:18,239 --> 00:51:22,519 so any type of remote locate remote login to to to work 1183 00:51:22,519 --> 00:51:23,760 through these 1184 00:51:23,760 --> 00:51:27,420 signals it just doesn't happen at this location. So again 1185 00:51:27,420 --> 00:51:28,960 some photos so you can 1186 00:51:28,960 --> 00:51:31,980 see the location this is basically some of the control 1187 00:51:31,980 --> 00:51:33,199 centers that we have for 1188 00:51:33,199 --> 00:51:36,750 our traffic operations here and then here's some of our 1189 00:51:36,750 --> 00:51:37,880 staff areas where we 1190 00:51:37,880 --> 00:51:41,349 work in and and again that's that bay door area where we 1191 00:51:41,349 --> 00:51:42,480 have some of our 1192 00:51:42,480 --> 00:51:45,659 equipment and supplies and signs and that are that are 1193 00:51:45,659 --> 00:51:46,960 housed there so it's 1194 00:51:46,960 --> 00:51:51,659 it's a very cramped space it's very small and again doesn't 1195 00:51:51,659 --> 00:51:53,159 really allow for 1196 00:51:53,159 --> 00:51:58,949 our staff to work in the most in a good area for it for 1197 00:51:58,949 --> 00:52:00,360 what they need to do in 1198 00:52:00,360 --> 00:52:03,929 the amount of work that they have to do. To give you an 1199 00:52:03,929 --> 00:52:05,639 idea there was a bond 1200 00:52:05,639 --> 00:52:10,289 package item back in 2014 where the citizens voted to to 1201 00:52:10,289 --> 00:52:11,639 have the city build 1202 00:52:11,639 --> 00:52:17,889 a traffic operations facility and there had been some some 1203 00:52:17,889 --> 00:52:18,159 some planning 1204 00:52:18,159 --> 00:52:21,449 documents put together some planning level estimates that 1205 00:52:21,449 --> 00:52:22,079 were put together 1206 00:52:22,079 --> 00:52:25,619 of building a 10,000 square foot facility actually on the 1207 00:52:25,619 --> 00:52:26,239 service center 1208 00:52:26,239 --> 00:52:29,780 campus and so but one of the options that was going to 1209 00:52:29,780 --> 00:52:31,199 happen with that with 1210 00:52:31,199 --> 00:52:35,400 that process was to they were gonna the thought was to real 1211 00:52:35,400 --> 00:52:37,079 ign Roodale Road in 1212 00:52:37,079 --> 00:52:42,019 that location along with some other interior streets to to 1213 00:52:42,019 --> 00:52:42,960 to configure to 1214 00:52:42,960 --> 00:52:47,210 be reconfigured for traffic operations along with just just 1215 00:52:47,210 --> 00:52:48,239 the alignment of 1216 00:52:48,239 --> 00:52:52,579 Roodale Road for the ease of traffic through that location. 1217 00:52:52,579 --> 00:52:53,320 When those 1218 00:52:53,320 --> 00:52:57,880 planning level estimates were conducted back in 2018 the 1219 00:52:57,880 --> 00:52:58,440 construction 1220 00:52:58,440 --> 00:53:01,599 estimates came in at 2.2 million dollars which obviously is 1221 00:53:01,599 --> 00:53:02,760 higher than the 1.5 1222 00:53:02,760 --> 00:53:07,119 million that was approved by the bond by by the community 1223 00:53:07,119 --> 00:53:08,480 however it did not 1224 00:53:08,480 --> 00:53:10,829 include any furniture fixtures and equipment these high- 1225 00:53:10,829 --> 00:53:11,559 level planning 1226 00:53:11,559 --> 00:53:15,210 estimates and there was and the laid-out yard also was not 1227 00:53:15,210 --> 00:53:16,239 factored into that 1228 00:53:16,239 --> 00:53:20,139 cost so right then and there we were already 700,000 over 1229 00:53:20,139 --> 00:53:21,119 budget plus there 1230 00:53:21,119 --> 00:53:25,960 were other components that were still not not not taken 1231 00:53:25,960 --> 00:53:27,360 into account as part 1232 00:53:27,360 --> 00:53:30,139 of the project so it could very easily have been nearly 1233 00:53:30,139 --> 00:53:31,320 three million dollars 1234 00:53:31,320 --> 00:53:34,340 or twice the amount that was approved by the bond committee 1235 00:53:34,340 --> 00:53:35,880 and by the by the 1236 00:53:35,880 --> 00:53:38,570 community so at the time the thought was let's put the 1237 00:53:38,570 --> 00:53:39,760 project on hold let's 1238 00:53:39,760 --> 00:53:43,809 reassess and see what other options are considered could be 1239 00:53:43,809 --> 00:53:45,360 considered so again 1240 00:53:45,360 --> 00:53:51,039 with new city management we revisited the issue and and and 1241 00:53:51,039 --> 00:53:52,239 felt we needed to 1242 00:53:52,239 --> 00:53:56,289 what can we do to advance the conversation and see what 1243 00:53:56,289 --> 00:53:57,300 options were 1244 00:53:57,300 --> 00:54:01,650 made available and so the thought was again looking at the 1245 00:54:01,650 --> 00:54:03,400 existing facilities 1246 00:54:03,400 --> 00:54:05,869 as we talked about for materials management could we 1247 00:54:05,869 --> 00:54:07,280 incorporate 10,000 1248 00:54:07,280 --> 00:54:13,460 square feet into the into the leftover space for 651 May 1249 00:54:13,460 --> 00:54:15,000 hill and so again the 1250 00:54:15,000 --> 00:54:19,550 thought was could we take that the 10,000 square foot 1251 00:54:19,550 --> 00:54:21,960 facility renovate 1252 00:54:21,960 --> 00:54:25,769 651 Mayhill and incorporate traffic operations into that 1253 00:54:25,769 --> 00:54:27,000 location and so 1254 00:54:27,000 --> 00:54:30,630 that's one of the options that we considered so we we 1255 00:54:30,630 --> 00:54:33,280 believe that we can 1256 00:54:33,280 --> 00:54:36,360 incorporate the 1.5 million dollars retrofit the interior 1257 00:54:36,360 --> 00:54:39,199 of 651 Mayhill this 1258 00:54:39,199 --> 00:54:42,449 information was taken to the bond oversight committee in 1259 00:54:42,449 --> 00:54:43,440 late January and 1260 00:54:43,440 --> 00:54:47,699 they unanimously approved it and so I can show you here 1261 00:54:47,699 --> 00:54:49,519 just a kind of a 1262 00:54:49,519 --> 00:54:54,480 rudimentary site plan of here's materials management or 1263 00:54:54,480 --> 00:54:55,039 incorporating 1264 00:54:55,039 --> 00:54:58,519 their 61,000 square foot facility here's traffic control 1265 00:54:58,519 --> 00:55:00,079 incorporating 10,000 1266 00:55:00,079 --> 00:55:03,360 square foot allows for an additional 10,000 square feet of 1267 00:55:03,360 --> 00:55:04,440 future expansion if 1268 00:55:04,440 --> 00:55:08,400 needed over time and incorporate some additional parking 1269 00:55:08,400 --> 00:55:10,039 for that operation of 1270 00:55:10,039 --> 00:55:16,880 traffic here the financials moving that 1.5 million dollars 1271 00:55:16,880 --> 00:55:19,159 into 651 it would 1272 00:55:19,159 --> 00:55:23,800 include the parking stalls there would be some furniture 1273 00:55:23,800 --> 00:55:25,559 and fixtures cost that 1274 00:55:25,559 --> 00:55:29,000 were needed we would need to do some design elements for 1275 00:55:29,000 --> 00:55:30,039 that so in essence 1276 00:55:30,039 --> 00:55:33,179 all-in for that entire project we're estimating it just 1277 00:55:33,179 --> 00:55:34,480 under 2.2 million 1278 00:55:34,480 --> 00:55:37,789 dollars which is very similar to the previous budget we had 1279 00:55:37,789 --> 00:55:38,599 come in at but 1280 00:55:38,599 --> 00:55:41,750 this is all-in with all cost versus the other one there 1281 00:55:41,750 --> 00:55:43,360 were still some elements 1282 00:55:43,360 --> 00:55:47,739 that were missing so we think this is based on what we've 1283 00:55:47,739 --> 00:55:49,239 in conversations 1284 00:55:49,239 --> 00:55:52,610 with the architect we believe that this is a you know a 1285 00:55:52,610 --> 00:55:53,280 really a good project 1286 00:55:53,280 --> 00:55:57,079 and it would be all-in from the standpoint of moving that 1287 00:55:57,079 --> 00:55:57,699 operation 1288 00:55:57,699 --> 00:56:03,039 over and then again from a financials incorporating the 1.5 1289 00:56:03,039 --> 00:56:03,639 million dollars 1290 00:56:03,639 --> 00:56:07,260 general obligation bonds that were approved by by the 1291 00:56:07,260 --> 00:56:08,599 community and then 1292 00:56:08,599 --> 00:56:13,440 some excess CEOs and solid waste to make up the difference 1293 00:56:13,440 --> 00:56:14,840 so for the 2.2 1294 00:56:14,840 --> 00:56:22,239 million and that's just that doesn't include the technology 1295 00:56:22,239 --> 00:56:23,760 correct for the 1296 00:56:23,760 --> 00:56:27,800 traffic correct correct facility correct it'll include some 1297 00:56:27,800 --> 00:56:28,480 but not the whole 1298 00:56:28,480 --> 00:56:35,460 thing and the excess certificates of obligation if that's 1299 00:56:35,460 --> 00:56:36,519 because we're not 1300 00:56:36,519 --> 00:56:40,079 doing something solid waste that we plan to use this for 1301 00:56:40,079 --> 00:56:42,199 yes ma'am we have about 1302 00:56:42,199 --> 00:56:45,960 4.2 million dollars of excess CEOs that were planned we're 1303 00:56:45,960 --> 00:56:47,119 already issued we're 1304 00:56:47,119 --> 00:56:50,369 planned for something else and so the proposal here is to 1305 00:56:50,369 --> 00:56:51,239 use it for this 1306 00:56:51,239 --> 00:56:54,889 purpose and so then the city's materials management fund 1307 00:56:54,889 --> 00:56:55,960 and also then the general 1308 00:56:55,960 --> 00:56:58,980 fund traffic is housed in the general fund would pay a 1309 00:56:58,980 --> 00:57:00,519 rental back to solid 1310 00:57:00,519 --> 00:57:04,599 waste offset that debt and so it really you know helps 1311 00:57:04,599 --> 00:57:06,239 solid waste fund as 1312 00:57:06,239 --> 00:57:09,380 well the idea would be that that asset would continue to be 1313 00:57:09,380 --> 00:57:10,400 a solid waste asset 1314 00:57:10,400 --> 00:57:14,650 met with a with the city's bond council and we think it's 1315 00:57:14,650 --> 00:57:15,519 an appropriate use 1316 00:57:15,519 --> 00:57:18,800 there is no private activity issue that arises out of this 1317 00:57:18,800 --> 00:57:20,079 it's the city itself 1318 00:57:20,079 --> 00:57:24,059 and so it's an allowable use you read my mind Tony you knew 1319 00:57:24,059 --> 00:57:25,280 what my next question 1320 00:57:25,280 --> 00:57:29,880 was thank you so that that offset was taken into account 1321 00:57:29,880 --> 00:57:31,239 for the previous 1322 00:57:31,239 --> 00:57:36,179 item we had yes sir it's already built into that into that 1323 00:57:36,179 --> 00:57:38,840 forecast yes sir 1324 00:57:40,840 --> 00:57:44,650 so again some of the issues that it solves it does fulfill 1325 00:57:44,650 --> 00:57:45,559 the bond 1326 00:57:45,559 --> 00:57:48,579 commitment that was made to the community it's utilizing 1327 00:57:48,579 --> 00:57:49,239 with with 1328 00:57:49,239 --> 00:57:53,789 existing bond funds as budgeted utilize existing space that 1329 00:57:53,789 --> 00:57:54,440 the city already 1330 00:57:54,440 --> 00:57:58,289 owns allows for future growth it's scalable allows for the 1331 00:57:58,289 --> 00:57:59,000 state of the art 1332 00:57:59,000 --> 00:58:02,659 components that we need to maintain and and expand our 1333 00:58:02,659 --> 00:58:04,400 operations and expand our 1334 00:58:04,400 --> 00:58:07,090 footprint when it comes to replacing our traffic signals 1335 00:58:07,090 --> 00:58:08,599 and our community we 1336 00:58:08,599 --> 00:58:10,989 believe that it provides some efficiencies by centralizing 1337 00:58:10,989 --> 00:58:11,320 a lot of 1338 00:58:11,320 --> 00:58:14,690 these operations that right now are done manually on site 1339 00:58:14,690 --> 00:58:15,400 there at the 1340 00:58:15,400 --> 00:58:18,650 intersection so allows for safety allows for a lot of 1341 00:58:18,650 --> 00:58:19,599 different things to be done 1342 00:58:19,599 --> 00:58:23,889 from a remote location or centralized location again as I 1343 00:58:23,889 --> 00:58:24,920 mentioned earlier 1344 00:58:24,920 --> 00:58:26,949 this information was presented to the bond oversight 1345 00:58:26,949 --> 00:58:27,880 committee back in late 1346 00:58:27,880 --> 00:58:31,409 January it was approved unanimously and then really the 1347 00:58:31,409 --> 00:58:32,320 next steps is we're in 1348 00:58:32,320 --> 00:58:36,489 the process of reviewing architects so again not a single 1349 00:58:36,489 --> 00:58:38,039 penny has been spent 1350 00:58:38,039 --> 00:58:42,039 on any of these projects so again this information was 1351 00:58:42,039 --> 00:58:42,840 presented to council 1352 00:58:42,840 --> 00:58:46,090 back in February we wanted to present it to you tonight to 1353 00:58:46,090 --> 00:58:47,239 keep you informed of 1354 00:58:47,239 --> 00:58:50,030 what we were what we were wanting to do and like to do and 1355 00:58:50,030 --> 00:58:50,639 seek your 1356 00:58:50,639 --> 00:58:54,119 recommendation for moving this process forward and as and 1357 00:58:54,119 --> 00:58:55,679 as mentioned if as we 1358 00:58:55,679 --> 00:58:58,760 go through the process of selecting an architect we'll 1359 00:58:58,760 --> 00:59:00,159 bring that selection to 1360 00:59:00,159 --> 00:59:05,400 the pub with with the requisite funding to get your 1361 00:59:05,400 --> 00:59:06,440 recommendation and if 1362 00:59:06,440 --> 00:59:09,460 recommended favorably that would then be sent to the City 1363 00:59:09,460 --> 00:59:10,400 Council at one of their 1364 00:59:10,400 --> 00:59:21,579 upcoming meetings okay questions we with the technology 1365 00:59:21,579 --> 00:59:22,920 shortcomings that you say 1366 00:59:22,920 --> 00:59:26,530 that the existing traffic operations building has what can 1367 00:59:26,530 --> 00:59:27,599 you touch on what 1368 00:59:27,599 --> 00:59:32,719 those might be and how they'll be alleviated out on Mayhill 1369 00:59:32,719 --> 00:59:33,400 they're just 1370 00:59:33,400 --> 00:59:37,570 metal buildings so there's really not there's really not 1371 00:59:37,570 --> 00:59:38,280 much difference 1372 00:59:38,280 --> 00:59:42,039 between the building on Mayhill off of Mayhill and the 1373 00:59:42,039 --> 00:59:43,119 building that we 1374 00:59:43,119 --> 00:59:47,679 currently have well it in size right well right they're 1375 00:59:47,679 --> 00:59:48,679 they're both metal 1376 00:59:48,679 --> 00:59:52,170 buildings of the the one on Mayhill can be again with 1377 00:59:52,170 --> 00:59:53,800 working with an architect 1378 00:59:53,800 --> 00:59:58,039 will be insulated will be I mean it'll it'll look like an 1379 00:59:58,039 --> 00:59:59,039 office on the 1380 00:59:59,039 --> 01:00:02,559 interior would allow for some bays it'll allow for 1381 01:00:02,559 --> 01:00:06,679 workspace for our our sign 1382 01:00:06,679 --> 01:00:12,019 sign crews so they can create signs and change create stop 1383 01:00:12,019 --> 01:00:13,760 signs and sign blades 1384 01:00:13,760 --> 01:00:19,409 for street signs etc from a technology perspective and some 1385 01:00:19,409 --> 01:00:19,760 of the traffic 1386 01:00:19,760 --> 01:00:23,010 operation facilities I've been in I mean it literally looks 1387 01:00:23,010 --> 01:00:24,239 like NASA and you've 1388 01:00:24,239 --> 01:00:27,730 got all these flat panels and you're able to meet able to 1389 01:00:27,730 --> 01:00:28,840 see your your city 1390 01:00:28,840 --> 01:00:32,969 out your your intersections via cameras etc so while we do 1391 01:00:32,969 --> 01:00:34,000 have have some of 1392 01:00:34,000 --> 01:00:37,380 that technology there at the existing facility it's not to 1393 01:00:37,380 --> 01:00:38,360 the extent it could 1394 01:00:38,360 --> 01:00:41,380 be as we continue to expand our footprint and replacing 1395 01:00:41,380 --> 01:00:41,760 these older 1396 01:00:41,760 --> 01:00:46,340 older intersections with your traffic signals okay I have 1397 01:00:46,340 --> 01:00:47,159 one more question 1398 01:00:47,159 --> 01:00:50,880 it's just some clarification for me so the bond oversight 1399 01:00:50,880 --> 01:00:53,099 committee so they 1400 01:00:53,099 --> 01:00:57,150 meet and they reviewed the original intent of the bond 1401 01:00:57,150 --> 01:00:58,800 committee before and 1402 01:00:58,800 --> 01:01:03,099 they review the intent of the ordinance that the city voted 1403 01:01:03,099 --> 01:01:03,980 on and then 1404 01:01:03,980 --> 01:01:07,230 determined that the funds can be reallocated to a project 1405 01:01:07,230 --> 01:01:08,159 that the voters 1406 01:01:08,159 --> 01:01:12,710 didn't approve I'm just curious how that works so about 1407 01:01:12,710 --> 01:01:13,599 every five years the 1408 01:01:13,599 --> 01:01:16,860 council appoints a blue ribbon committee it's about 50 you 1409 01:01:16,860 --> 01:01:18,840 know citizens I think 1410 01:01:18,840 --> 01:01:21,920 each council member gets about seven that they can appoint 1411 01:01:21,920 --> 01:01:22,719 from that 1412 01:01:22,719 --> 01:01:25,739 generally speaking that that committee will break up into 1413 01:01:25,739 --> 01:01:27,800 subcommittees and so 1414 01:01:27,800 --> 01:01:29,800 once the committee's work's been done and the 1415 01:01:29,800 --> 01:01:31,239 recommendations been made and 1416 01:01:31,239 --> 01:01:35,579 elections been had generally speaking the chairman as there 1417 01:01:35,579 --> 01:01:36,840 's there's co-chairmans 1418 01:01:36,840 --> 01:01:39,480 of the entire committee and then the chairs of the of the 1419 01:01:39,480 --> 01:01:40,599 subcommittees then 1420 01:01:40,599 --> 01:01:43,840 become the bond oversight committee so it's the same 1421 01:01:43,840 --> 01:01:45,320 individuals that were 1422 01:01:45,320 --> 01:01:47,929 involved from the very beginning on what those projects 1423 01:01:47,929 --> 01:01:49,320 were and what was decided 1424 01:01:49,320 --> 01:01:53,039 they're fully in tune believe me on what what the intent 1425 01:01:53,039 --> 01:01:54,000 was for those 1426 01:01:54,000 --> 01:01:57,519 individual projects we do try to meet with them at least 1427 01:01:57,519 --> 01:01:58,559 annually that we have 1428 01:01:58,559 --> 01:02:01,179 been talking about meeting with them I believe quarterly 1429 01:02:01,179 --> 01:02:02,159 now because of some of 1430 01:02:02,159 --> 01:02:06,119 these changes so we do review this and from time to time 1431 01:02:06,119 --> 01:02:07,679 there are reallocations 1432 01:02:07,679 --> 01:02:12,170 that occur from one project to another but generally 1433 01:02:12,170 --> 01:02:13,079 speaking most of those 1434 01:02:13,079 --> 01:02:17,440 projects stay intact unless there's you know some other 1435 01:02:17,440 --> 01:02:20,889 extenuating circumstances and I will tell you in the 2005 1436 01:02:20,889 --> 01:02:22,280 bond program there was a 1437 01:02:22,280 --> 01:02:26,829 couple of projects where the city had issued bonds US 377 1438 01:02:26,829 --> 01:02:28,800 FM 1830 those 1439 01:02:28,800 --> 01:02:32,760 project was subsequently funded by other sources external 1440 01:02:32,760 --> 01:02:34,079 to the city so that 1441 01:02:34,079 --> 01:02:37,690 resulted in some dollars that we had available so you know 1442 01:02:37,690 --> 01:02:38,159 part of our 1443 01:02:38,159 --> 01:02:40,840 recommendation to the council tomorrow will be to reall 1444 01:02:40,840 --> 01:02:42,079 ocate those dollars for 1445 01:02:42,079 --> 01:02:45,480 some other projects that are in existence and so so again 1446 01:02:45,480 --> 01:02:46,320 yeah we have a 1447 01:02:46,320 --> 01:02:49,139 lot of conversations with that committee but generally 1448 01:02:49,139 --> 01:02:50,280 speaking unless there's 1449 01:02:50,280 --> 01:02:52,750 some exchange circumstance those projects that were 1450 01:02:52,750 --> 01:02:53,639 identified for the 1451 01:02:53,639 --> 01:02:56,659 for the citizens are the ones that we work on okay and so 1452 01:02:56,659 --> 01:02:58,559 the current oversight 1453 01:02:58,559 --> 01:03:02,320 committee is made up of the chairpeople from the 2016 bond 1454 01:03:02,320 --> 01:03:03,239 or you actually have 1455 01:03:03,239 --> 01:03:06,280 multiple bond oversight committees that are made up of the 1456 01:03:06,280 --> 01:03:07,280 chairpeople from 1457 01:03:07,280 --> 01:03:11,239 those years that those bonds were presented the the only 1458 01:03:11,239 --> 01:03:12,159 committee that we 1459 01:03:12,159 --> 01:03:16,500 have currently is from the 2014 bond election and as a 1460 01:03:16,500 --> 01:03:17,599 matter of fact the pub 1461 01:03:17,599 --> 01:03:21,679 chairman is the chairman of that committee we do have a 1462 01:03:21,679 --> 01:03:22,599 2000 1463 01:03:26,599 --> 01:03:30,090 just trying to get some clarification now this work we also 1464 01:03:30,090 --> 01:03:31,599 had a an oversight 1465 01:03:31,599 --> 01:03:36,960 committee from the 2012 bond program we did late last year 1466 01:03:36,960 --> 01:03:38,199 attempted to get 1467 01:03:38,199 --> 01:03:40,880 those two committees together unfortunately some of those 1468 01:03:40,880 --> 01:03:41,440 members have 1469 01:03:41,440 --> 01:03:45,340 now moved on and so we've not officially dissolved it so 1470 01:03:45,340 --> 01:03:46,559 what we've asked the 1471 01:03:46,559 --> 01:03:49,579 2014 bond oversight committee because some of the projects 1472 01:03:49,579 --> 01:03:50,280 are very similar 1473 01:03:50,280 --> 01:03:53,440 street reconstruction was 2012 we've asked them to make a 1474 01:03:53,440 --> 01:03:57,159 recommendation on the 2005 projects 2012 projects and the 1475 01:03:57,159 --> 01:03:58,320 14 projects as well 1476 01:03:58,320 --> 01:04:06,239 okay thank you for sure okay I just have one comment and I 1477 01:04:06,239 --> 01:04:07,679 guess it's a concern 1478 01:04:07,679 --> 01:04:11,400 with some lost efficiency and in splitting your material 1479 01:04:11,400 --> 01:04:12,519 management area 1480 01:04:12,519 --> 01:04:16,329 away from your workforce having had some experience with 1481 01:04:16,329 --> 01:04:18,440 that and losing employees 1482 01:04:18,440 --> 01:04:22,550 on a much smaller campus than you guys are working with in 1483 01:04:22,550 --> 01:04:25,039 making those trips I 1484 01:04:25,039 --> 01:04:28,289 think it's something you need to take a deep look at with 1485 01:04:28,289 --> 01:04:29,400 your supervisors 1486 01:04:29,400 --> 01:04:37,739 absolutely we definitely will other comments questions you 1487 01:04:37,739 --> 01:04:38,639 need an 1488 01:04:38,639 --> 01:04:45,090 indication from us then as far as what what the committee's 1489 01:04:45,090 --> 01:04:46,760 preference is I say 1490 01:04:46,760 --> 01:04:56,150 go ahead thank you thanks yeah well on 22 million well yeah 1491 01:04:56,150 --> 01:05:00,000 plus it's the best 1492 01:05:00,000 --> 01:05:04,730 thing I mean you get you get a lot of room to grow if you 1493 01:05:04,730 --> 01:05:07,440 will yeah that you're 1494 01:05:07,440 --> 01:05:14,880 gonna need eventually anyway okay thank you thank you 1495 01:05:16,760 --> 01:05:29,679 okay see what we have we have a closed meeting is the next 1496 01:05:29,679 --> 01:05:32,599 thing on the agenda 1497 01:05:32,599 --> 01:05:39,440 I know we've got some people here that that really deals 1498 01:05:39,440 --> 01:05:41,679 with one one issue one 1499 01:05:41,679 --> 01:05:46,789 matter on the regular agenda yeah I'm thinking we could do 1500 01:05:46,789 --> 01:05:51,239 that and we yeah and 1501 01:05:51,239 --> 01:05:54,400 then come back and pick up the one that deals with closed 1502 01:05:54,400 --> 01:05:55,440 meeting after yeah 1503 01:05:55,440 --> 01:06:02,559 after okay okay trying to make sure buddy gets home in time 1504 01:06:02,559 --> 01:06:03,320 to watch part of 1505 01:06:03,320 --> 01:06:08,260 the North Texas basketball game tonight or listen to it 1506 01:06:08,260 --> 01:06:11,159 anyway okay so we'll 1507 01:06:11,159 --> 01:06:14,769 rather than going to close meeting we'll do the do the 1508 01:06:14,769 --> 01:06:17,199 regular meeting we have a 1509 01:06:17,199 --> 01:06:31,699 consent agenda with let's see five items on the consent 1510 01:06:31,699 --> 01:06:34,039 agenda is there any 1511 01:06:34,039 --> 01:06:39,440 member who would like to have any of those items pulled for 1512 01:06:39,440 --> 01:06:40,639 individual 1513 01:06:40,639 --> 01:06:43,159 consideration 1514 01:06:48,519 --> 01:06:53,489 hearing none then is there a motion to approve the consent 1515 01:06:53,489 --> 01:06:56,559 agenda so moved 1516 01:06:56,559 --> 01:07:01,920 second of a motion second to approve the items item a b c d 1517 01:07:01,920 --> 01:07:03,480 and e on the 1518 01:07:03,480 --> 01:07:09,380 consent agenda is there further discussion all in favor 1519 01:07:09,380 --> 01:07:11,280 then say aye any 1520 01:07:11,280 --> 01:07:18,130 opposed same sign okay consent agenda is approved items for 1521 01:07:18,130 --> 01:07:18,599 individual 1522 01:07:18,599 --> 01:07:24,250 consideration first item a which is to consider approval of 1523 01:07:24,250 --> 01:07:25,199 the public 1524 01:07:25,199 --> 01:07:30,610 utilities board meeting minutes of February 26 2018 are 1525 01:07:30,610 --> 01:07:32,440 there any questions 1526 01:07:32,440 --> 01:07:38,130 additions corrections for to those minutes if not then is 1527 01:07:38,130 --> 01:07:39,639 there a motion to 1528 01:07:39,639 --> 01:07:46,989 approve those as submitted so moved motion second and a 1529 01:07:46,989 --> 01:07:48,679 second discussion 1530 01:07:48,679 --> 01:07:55,320 all in favor say aye any opposed same sign okay item B 1531 01:07:55,320 --> 01:07:57,880 under items for 1532 01:07:57,880 --> 01:08:01,039 individual consideration is to consider recommending 1533 01:08:01,039 --> 01:08:02,280 approval of the watershed 1534 01:08:02,280 --> 01:08:06,320 protection division sponsorship agreement with keep didn't 1535 01:08:06,320 --> 01:08:07,079 beautiful 1536 01:08:07,079 --> 01:08:11,800 incorporated in the amount of $8,000 1537 01:08:18,119 --> 01:08:18,569 good evening pb my name is Deb Rivera I'm with 1538 01:08:18,569 --> 01:08:23,520 environmental services tonight 1539 01:08:23,520 --> 01:08:30,779 staff is requesting the recommendation for expanding $8,000 1540 01:08:30,779 --> 01:08:32,520 for sponsorship 1541 01:08:36,399 --> 01:08:39,500 watershed protection allocate fund annually for this 1542 01:08:39,500 --> 01:08:41,479 purpose and the 1543 01:08:41,479 --> 01:08:44,960 purpose though the reason why we do it is just for 1544 01:08:44,960 --> 01:08:46,619 promoting pollution 1545 01:08:46,619 --> 01:08:50,489 prevention it's on water and water quality awareness and to 1546 01:08:50,489 --> 01:08:51,439 meet the 1547 01:08:51,439 --> 01:08:54,630 requirements of the MS4 permit which is the municipal 1548 01:08:54,630 --> 01:08:56,439 separate sewer site or a 1549 01:08:56,439 --> 01:09:01,779 system I'm sorry separate storm sewer system with the CQ by 1550 01:09:01,779 --> 01:09:04,239 using the KDB 1551 01:09:04,239 --> 01:09:08,720 staff is able to capitalize in the network of contacts that 1552 01:09:08,720 --> 01:09:10,039 KDB already has 1553 01:09:10,039 --> 01:09:15,069 to use the volunteer base over 2,000 people that KDB 1554 01:09:15,069 --> 01:09:16,800 currently has and to 1555 01:09:16,800 --> 01:09:20,649 use establish events that the community would recognize 1556 01:09:20,649 --> 01:09:22,199 already in the last two 1557 01:09:22,199 --> 01:09:24,989 years staff have allocated between nine thousand ninety 1558 01:09:24,989 --> 01:09:27,000 five hundred dollars for 1559 01:09:27,000 --> 01:09:35,300 that purpose we are requesting to spend eight thousand 1560 01:09:35,300 --> 01:09:36,960 dollars for paying into 1561 01:09:36,960 --> 01:09:39,680 the Red One Festival the great American cleanup and the 1562 01:09:39,680 --> 01:09:41,000 environmental grant 1563 01:09:41,000 --> 01:09:45,569 program for a total of 8,000 however due to a rollover 1564 01:09:45,569 --> 01:09:47,720 funds from last year we 1565 01:09:47,720 --> 01:09:51,439 are actually requesting for eighteen I'm sorry fifteen 1566 01:09:51,439 --> 01:09:52,600 hundred dollars to be used 1567 01:09:52,600 --> 01:09:57,329 towards that so we will end up paying sixty five hundreds 1568 01:09:57,329 --> 01:09:58,680 to keep the kid 1569 01:09:58,680 --> 01:10:04,960 that and beautiful at this point the staff is recommending 1570 01:10:04,960 --> 01:10:05,880 on maintaining the 1571 01:10:05,880 --> 01:10:09,920 sponsorship to KDB to approve the requested expenditure of 1572 01:10:09,920 --> 01:10:12,840 sixty five hundred dollars and to adhere the resolution 1573 01:10:12,840 --> 01:10:16,199 passed in 2018 about how to expand 1574 01:10:16,199 --> 01:10:20,750 sponsorship funds that was ordinance I'm sorry resolution 1575 01:10:20,750 --> 01:10:22,479 eighteen zero nine five 1576 01:10:22,479 --> 01:10:31,590 any questions questions yes what is the MS4 MS4 is a permit 1577 01:10:31,590 --> 01:10:32,279 that the city has 1578 01:10:32,279 --> 01:10:38,159 with TCQ and it is for the municipal separate storm sewer 1579 01:10:38,159 --> 01:10:39,920 system and that's 1580 01:10:39,920 --> 01:10:43,640 a permit that the city have to maintain every five years 1581 01:10:43,640 --> 01:10:44,880 with TCQ every 1582 01:10:44,880 --> 01:10:51,340 municipal has to do that across the country and just to be 1583 01:10:51,340 --> 01:10:54,279 clear this is we 1584 01:10:54,279 --> 01:10:57,840 just approve the minutes from last time those were DME 1585 01:10:57,840 --> 01:10:59,840 funds that we looked at 1586 01:10:59,840 --> 01:11:04,390 last time this is a wastewater right watershed watershed 1587 01:11:04,390 --> 01:11:06,520 protection and I'll 1588 01:11:06,520 --> 01:11:10,050 make the same statement I made last time I think it's a 1589 01:11:10,050 --> 01:11:12,520 great way to leverage 1590 01:11:12,520 --> 01:11:16,520 keeping it beautiful is a good good job in leveraging 1591 01:11:16,520 --> 01:11:18,600 public money with private 1592 01:11:18,600 --> 01:11:23,300 donations and private volunteer hours and so they do a good 1593 01:11:23,300 --> 01:11:26,560 job so 1594 01:11:26,560 --> 01:11:33,909 2000 people 2000 people those on the events that we are 1595 01:11:33,909 --> 01:11:34,960 participating in have 1596 01:11:34,960 --> 01:11:38,210 been for 13 years the community already recognized them 1597 01:11:38,210 --> 01:11:39,399 they actually attend 1598 01:11:39,399 --> 01:11:42,770 those on a regular basis so it's definitely a win-win 1599 01:11:42,770 --> 01:11:44,359 situation for both 1600 01:11:44,359 --> 01:11:50,760 KDB and watershed protection okay we have a motion then on 1601 01:11:50,760 --> 01:11:53,880 item B 1602 01:11:53,880 --> 01:12:00,920 much to approve and a second further discussion all in 1603 01:12:00,920 --> 01:12:02,880 favor say aye any 1604 01:12:02,880 --> 01:12:09,960 opposed same sign thank you items passes 1605 01:12:13,920 --> 01:12:22,390 okay we can item C which is to consider recommending 1606 01:12:22,390 --> 01:12:23,399 adoption of an ordinance 1607 01:12:23,399 --> 01:12:29,880 for the city of Denton amending ordinance number 2017 273 1608 01:12:29,880 --> 01:12:31,720 to reduce solid waste 1609 01:12:31,720 --> 01:12:35,529 residential collection service rates and remove certain 1610 01:12:35,529 --> 01:12:36,859 administrative rate 1611 01:12:36,859 --> 01:12:41,199 setting provisions in providing an effective date of course 1612 01:12:41,199 --> 01:12:41,880 this relates 1613 01:12:41,880 --> 01:12:46,640 back to our work session item so Tony 1614 01:12:46,640 --> 01:12:49,920 I'll just want to just react read a right again this is a 1615 01:12:49,920 --> 01:12:52,199 first step stab at 1616 01:12:52,199 --> 01:12:55,350 these rates we will come back to you in the next three or 1617 01:12:55,350 --> 01:12:56,600 four months to have a 1618 01:12:56,600 --> 01:13:00,130 wider discussion about all the rates in solid waste but we 1619 01:13:00,130 --> 01:13:01,560 believe that that we 1620 01:13:01,560 --> 01:13:04,260 can immediately make this change for our residential 1621 01:13:04,260 --> 01:13:06,000 customers so we're here to 1622 01:13:06,000 --> 01:13:09,729 recommend a 12% decrease in those refuge and recycling 1623 01:13:09,729 --> 01:13:11,399 rates standard and large 1624 01:13:11,399 --> 01:13:16,149 carts and be happy to answer any questions that you may 1625 01:13:16,149 --> 01:13:18,439 have this is for 1626 01:13:18,439 --> 01:13:23,539 an effective date of the effective date it will be the 28th 1627 01:13:23,539 --> 01:13:25,760 28 correct you know 1628 01:13:25,760 --> 01:13:33,399 pending councils okay any other questions at Tony is there 1629 01:13:33,399 --> 01:13:34,359 a motion then 1630 01:13:34,359 --> 01:13:40,289 to approve we have a motion to second this time from the 1631 01:13:40,289 --> 01:13:42,079 side of the room 1632 01:13:42,079 --> 01:13:49,039 give them a turn any other discussion all in favor say aye 1633 01:13:49,039 --> 01:13:50,960 any opposed same 1634 01:13:50,960 --> 01:13:57,069 sign thank you item D is to consider recommending adoption 1635 01:13:57,069 --> 01:13:57,640 of an ordinance 1636 01:13:57,640 --> 01:14:01,739 of the city of Denton Texas excuse me authorizing the city 1637 01:14:01,739 --> 01:14:02,840 manager to execute a 1638 01:14:02,840 --> 01:14:07,779 contract for a utility assistance program supporting low- 1639 01:14:07,779 --> 01:14:08,840 income households 1640 01:14:08,840 --> 01:14:12,039 providing for the expenditure of funds therefore and 1641 01:14:12,039 --> 01:14:13,520 providing an effective 1642 01:14:13,520 --> 01:14:19,319 date RFP 6669 awarded to interfaith ministries of Denton 1643 01:14:19,319 --> 01:14:21,359 incorporated in the 1644 01:14:21,359 --> 01:14:24,859 not to exceed amount of three hundred and seventy five 1645 01:14:24,859 --> 01:14:27,159 thousand dollars customer 1646 01:14:27,159 --> 01:14:29,930 service manager I'm happy to report that I did not go to 1647 01:14:29,930 --> 01:14:31,079 the dentist prior to 1648 01:14:31,079 --> 01:14:35,430 this meeting so you should be able to understand me I'm 1649 01:14:35,430 --> 01:14:36,600 here tonight to talk 1650 01:14:36,600 --> 01:14:39,619 about the utility assistance program request for proposal a 1651 01:14:39,619 --> 01:14:40,239 little bit of 1652 01:14:40,239 --> 01:14:43,489 background the prevent loss of utility service also known 1653 01:14:43,489 --> 01:14:44,000 as the plus one 1654 01:14:44,000 --> 01:14:46,520 program helps our customers that are going through a 1655 01:14:46,520 --> 01:14:47,760 financial hardship to be 1656 01:14:47,760 --> 01:14:50,449 able to pay for their utilities and also to be able to 1657 01:14:50,449 --> 01:14:51,880 restore services if they 1658 01:14:51,880 --> 01:14:55,439 encountered an interruption of service I'm also happy to 1659 01:14:55,439 --> 01:14:56,600 let you know that we 1660 01:14:56,600 --> 01:15:00,100 had anticipated not coming back to you until June of this 1661 01:15:00,100 --> 01:15:01,520 year with this RFP so 1662 01:15:01,520 --> 01:15:03,630 we're three months ahead of schedule so we'll be able to 1663 01:15:03,630 --> 01:15:05,079 implement that enhanced 1664 01:15:05,079 --> 01:15:08,319 criteria sooner for our customers pending your approval 1665 01:15:08,319 --> 01:15:09,920 interfaith ministry 1666 01:15:09,920 --> 01:15:13,289 we did send this out to 295 organizations we had one 1667 01:15:13,289 --> 01:15:14,239 response which 1668 01:15:14,239 --> 01:15:17,300 was the incumbent interfaith ministries Inc of Denton the 1669 01:15:17,300 --> 01:15:18,319 contracts going to be 1670 01:15:18,319 --> 01:15:23,260 increasing from 100,000 to 125,000 and the administrative 1671 01:15:23,260 --> 01:15:24,279 costs are going up 1672 01:15:24,279 --> 01:15:29,119 by 26% with this contract proposal the last two contracts 1673 01:15:29,119 --> 01:15:29,920 with interfaith we 1674 01:15:29,920 --> 01:15:32,409 did not see any price increase so this is the first price 1675 01:15:32,409 --> 01:15:33,520 increase with them in 1676 01:15:33,520 --> 01:15:36,640 the last seven years and it's specifically tied to their 1677 01:15:36,640 --> 01:15:37,520 personnel and 1678 01:15:37,520 --> 01:15:41,050 also their technology for their personnel they do spend an 1679 01:15:41,050 --> 01:15:42,159 hour with each of the 1680 01:15:42,159 --> 01:15:44,640 clients that are coming in to offer them a holistic 1681 01:15:44,640 --> 01:15:46,439 solution because usually it 1682 01:15:46,439 --> 01:15:48,920 isn't just a singular issue that that family may be 1683 01:15:48,920 --> 01:15:50,279 experiencing so they spend 1684 01:15:50,279 --> 01:15:53,109 time making sure that the customer knows about additional 1685 01:15:53,109 --> 01:15:54,840 resources and also how 1686 01:15:54,840 --> 01:15:57,310 that they can budget in the future with that so that's one 1687 01:15:57,310 --> 01:15:58,220 of the reasons why 1688 01:15:58,220 --> 01:16:01,939 the personnel expense is going up and then the phone and 1689 01:16:01,939 --> 01:16:03,399 technology they are 1690 01:16:03,399 --> 01:16:07,359 implementing a homeless management information system that 1691 01:16:07,359 --> 01:16:08,199 's going to help 1692 01:16:08,199 --> 01:16:11,220 us with the additional criteria that we're requiring and so 1693 01:16:11,220 --> 01:16:11,880 that is one of 1694 01:16:11,880 --> 01:16:16,180 the reasons why that technology is increasing as well so 1695 01:16:16,180 --> 01:16:17,239 the niche 1696 01:16:17,239 --> 01:16:20,079 criteria for the clients is they're going to be able to get 1697 01:16:20,079 --> 01:16:20,840 assistance on 1698 01:16:20,840 --> 01:16:23,640 security deposits now they'll be able to get assistance up 1699 01:16:23,640 --> 01:16:24,720 to three times a year 1700 01:16:24,720 --> 01:16:27,840 where it was only once a year and then also there's no 1701 01:16:27,840 --> 01:16:29,399 required tenure at that 1702 01:16:29,399 --> 01:16:31,939 address that they have to be there to get assistance those 1703 01:16:31,939 --> 01:16:32,760 are the top three 1704 01:16:32,760 --> 01:16:36,000 things that we pinpointed why our customers were being 1705 01:16:36,000 --> 01:16:37,039 declined to be able 1706 01:16:37,039 --> 01:16:39,670 to get assistance and so that criteria is in the new 1707 01:16:39,670 --> 01:16:41,239 contract in addition to 1708 01:16:41,239 --> 01:16:44,119 that we've updated the reporting criteria so we're going to 1709 01:16:44,119 --> 01:16:44,680 be able to 1710 01:16:44,680 --> 01:16:47,520 get richer data in order to understand what the barriers 1711 01:16:47,520 --> 01:16:48,680 are our customers are 1712 01:16:48,680 --> 01:16:52,000 facing so we know if we need to pull additional levers or 1713 01:16:52,000 --> 01:16:53,159 do the additional 1714 01:16:53,159 --> 01:16:57,260 criteria enhancements going forward and so tonight we are 1715 01:16:57,260 --> 01:16:58,399 asking for your 1716 01:16:58,399 --> 01:17:01,939 recommendation or consideration and improving this contract 1717 01:17:01,939 --> 01:17:02,840 and awarding it 1718 01:17:02,840 --> 01:17:05,680 to interfaith ministries we're going to report back to you 1719 01:17:05,680 --> 01:17:07,680 within one year on the 1720 01:17:07,680 --> 01:17:11,189 impact to our customers that this criteria change has had 1721 01:17:11,189 --> 01:17:12,039 what the data 1722 01:17:12,039 --> 01:17:14,850 results are and then if there's any additional adjustments 1723 01:17:14,850 --> 01:17:15,640 that we may need 1724 01:17:15,640 --> 01:17:19,270 to make with your direction and council's direction do you 1725 01:17:19,270 --> 01:17:20,079 have any 1726 01:17:20,079 --> 01:17:24,050 questions for me you're glad that you're doing this sooner 1727 01:17:24,050 --> 01:17:25,439 I imagine summer is 1728 01:17:25,439 --> 01:17:28,760 when most of these people hurt the most yes absolutely so 1729 01:17:28,760 --> 01:17:29,880 and what the deposits 1730 01:17:29,880 --> 01:17:31,850 being able to assist with the deposit you have a lot of 1731 01:17:31,850 --> 01:17:33,260 customers moving in 1732 01:17:33,260 --> 01:17:37,130 and hey and so I would actually anticipate our our May 1733 01:17:37,130 --> 01:17:38,560 assistance going 1734 01:17:38,560 --> 01:17:41,399 up and September and August are usually our big heavy hit 1735 01:17:41,399 --> 01:17:42,239 ter months because the 1736 01:17:42,239 --> 01:17:44,720 bills are starting to start creeping up a little bit 1737 01:17:44,720 --> 01:17:46,640 contingent on weather with 1738 01:17:46,640 --> 01:17:49,789 that so it'll be interesting how the enhancements and 1739 01:17:49,789 --> 01:17:50,920 criteria what it's 1740 01:17:50,920 --> 01:17:55,479 going to influence on those months for the assistant good 1741 01:17:55,479 --> 01:18:01,319 data so we have we 1742 01:18:01,319 --> 01:18:06,020 did we modify the budget to make it 125 this year this 1743 01:18:06,020 --> 01:18:07,880 fiscal year okay and 1744 01:18:07,880 --> 01:18:13,520 we'll revisit that we have the data back yes by the time we 1745 01:18:13,520 --> 01:18:14,960 adopt a budget for 1746 01:18:14,960 --> 01:18:18,000 next year yes yeah we'll come back here to know if we need 1747 01:18:18,000 --> 01:18:18,439 to make any 1748 01:18:18,439 --> 01:18:22,079 modifications to that but we'll be able to increase that 1749 01:18:22,079 --> 01:18:22,960 funding now with 1750 01:18:22,960 --> 01:18:28,800 savings budget so we're going to be able to absorb that I 1751 01:18:28,800 --> 01:18:31,960 guess I'm I am but I'm 1752 01:18:31,960 --> 01:18:38,159 not amazed at 295 organizations only one response 1753 01:18:41,920 --> 01:18:47,720 it's okay they do a good job so any other questions 1754 01:18:47,720 --> 01:18:51,359 comments do we have a 1755 01:18:51,359 --> 01:18:57,880 motion on the item so I have to approve okay second and a 1756 01:18:57,880 --> 01:19:00,640 second discussion is 1757 01:19:00,640 --> 01:19:05,199 just a point of clarification is this a three-year yes sir 1758 01:19:05,199 --> 01:19:06,039 it's one year and then 1759 01:19:06,039 --> 01:19:12,039 with two years any other discussion all in favor say aye 1760 01:19:12,039 --> 01:19:14,079 any opposed same sign 1761 01:19:14,079 --> 01:19:23,470 motion carries thank you okay I think we've gone as far as 1762 01:19:23,470 --> 01:19:25,439 we can with that 1763 01:19:25,439 --> 01:19:36,090 going into closed meeting so at this time we will go into a 1764 01:19:36,090 --> 01:19:39,119 closed meeting 1765 01:19:39,439 --> 01:19:52,380 to consider okay it is 742 so we'll are back in open 1766 01:19:52,380 --> 01:19:56,079 session and we have a 1767 01:19:56,079 --> 01:20:04,000 couple of items remaining one of which is item E which is 1768 01:20:04,000 --> 01:20:07,079 to consider 1769 01:20:09,439 --> 01:20:13,289 recommending adoption of an ordinance authorizing the city 1770 01:20:13,289 --> 01:20:14,199 manager or his 1771 01:20:14,199 --> 01:20:19,539 designee to sign a notice of extension of the TMPA power 1772 01:20:19,539 --> 01:20:21,880 sales contract for 1773 01:20:21,880 --> 01:20:28,720 seasonal operation from some September 1 2018 to September 1774 01:20:28,720 --> 01:20:32,680 3rd 2018 and then 1775 01:20:32,680 --> 01:20:38,310 for seasonal operation from some September 1 2018 to 1776 01:20:38,310 --> 01:20:41,359 September 30 2018 1777 01:20:41,359 --> 01:20:47,560 pursuant to section 5.1.3 of the TMPA amended joint 1778 01:20:47,560 --> 01:20:50,239 operating agreement and I 1779 01:20:50,239 --> 01:20:56,189 believe George has a presentation on this chairman and 1780 01:20:56,189 --> 01:20:57,399 members of the public 1781 01:20:57,399 --> 01:21:02,960 utility board George Morrow DME general manager as I was 1782 01:21:02,960 --> 01:21:03,920 mentioned I before you 1783 01:21:03,920 --> 01:21:07,640 tonight to talk about a possible 30-day extension of the 1784 01:21:07,640 --> 01:21:09,000 power sales contract 1785 01:21:09,000 --> 01:21:14,720 for the Gibbons Creek power plant presently we we have a 21 1786 01:21:14,720 --> 01:21:15,760 .3 percent 1787 01:21:15,760 --> 01:21:19,039 entitlement or about a hundred megawatts in that plant 1788 01:21:19,039 --> 01:21:21,359 based on a termination 1789 01:21:21,359 --> 01:21:23,880 notice given about two years ago by the city of Greenville 1790 01:21:23,880 --> 01:21:25,239 there's a trigger 1791 01:21:25,239 --> 01:21:29,979 date of September 1 for the other participants to extend 1792 01:21:29,979 --> 01:21:31,000 for an additional 1793 01:21:31,000 --> 01:21:36,710 month if they so desire and so far staff of the three 1794 01:21:36,710 --> 01:21:38,920 entities have shown 1795 01:21:38,920 --> 01:21:42,550 interest just wanted to show you that provision it was 1796 01:21:42,550 --> 01:21:44,399 approved by the utility 1797 01:21:44,399 --> 01:21:47,029 board and City Council I believe or came before you back in 1798 01:21:47,029 --> 01:21:47,920 September of last 1799 01:21:47,920 --> 01:21:53,359 year that did allow for this extension for seasonal 1800 01:21:53,359 --> 01:21:54,680 operation that were 1801 01:21:54,680 --> 01:21:59,779 here today to talk about so I have received an extension 1802 01:21:59,779 --> 01:22:01,680 letter for this 1803 01:22:01,680 --> 01:22:06,340 30-day period it will increase our entitlement from that 21 1804 01:22:06,340 --> 01:22:07,399 .3 percent to 1805 01:22:07,399 --> 01:22:12,520 23.7 because Greenville is departing the project after that 1806 01:22:12,520 --> 01:22:13,640 date and we'll 1807 01:22:13,640 --> 01:22:17,520 proportionally share their remaining entitlement that they 1808 01:22:17,520 --> 01:22:18,520 would have would 1809 01:22:18,520 --> 01:22:24,039 have taken so what I can say to you right now is that we've 1810 01:22:24,039 --> 01:22:24,359 done an 1811 01:22:24,359 --> 01:22:28,170 analysis of that plant operation for the month of September 1812 01:22:28,170 --> 01:22:29,239 and that the value 1813 01:22:29,239 --> 01:22:35,720 exceeds the the cost of operation and it's a one-time thing 1814 01:22:35,720 --> 01:22:37,640 it's only really 1815 01:22:37,640 --> 01:22:41,399 just for that month it has no obligation beyond that and if 1816 01:22:41,399 --> 01:22:43,079 there is a desire to 1817 01:22:43,079 --> 01:22:48,189 discuss possible operation for next year's seasonal then we 1818 01:22:48,189 --> 01:22:49,239 would take that 1819 01:22:49,239 --> 01:22:56,079 up at a later date so there is an ordinance that I'd like 1820 01:22:56,079 --> 01:22:58,079 you to consider 1821 01:22:58,079 --> 01:23:02,689 recommending to the City Council that would extend that 1822 01:23:02,689 --> 01:23:04,439 operation for the 30 1823 01:23:04,439 --> 01:23:06,949 day period we've been talking about and that's my 1824 01:23:06,949 --> 01:23:08,399 recommendation to you this 1825 01:23:08,399 --> 01:23:21,159 evening okay questions so this this is again an extension 1826 01:23:21,159 --> 01:23:22,239 30-day extension of 1827 01:23:22,239 --> 01:23:28,680 our existing contract with with no future obligation to 1828 01:23:28,680 --> 01:23:31,119 just if we want 1829 01:23:31,119 --> 01:23:35,859 correct the plan is still for this plant to be shut down at 1830 01:23:35,859 --> 01:23:38,079 some foreseeable point 1831 01:23:38,079 --> 01:23:46,840 in the future right okay okay any other comments questions 1832 01:23:46,840 --> 01:23:48,560 do we have a motion 1833 01:23:48,560 --> 01:23:54,600 on this item recommend okay we have a motion to approve 1834 01:23:54,600 --> 01:23:57,000 second and a second 1835 01:23:57,000 --> 01:24:06,390 further discussion all in favor say aye any opposed nay one 1836 01:24:06,390 --> 01:24:08,000 nay motion passes 1837 01:24:08,000 --> 01:24:16,880 thank you very much okay item F is ACM update yes mr. 1838 01:24:16,880 --> 01:24:17,640 chairman members of the 1839 01:24:17,640 --> 01:24:20,659 board in your packet you will have you have a number of 1840 01:24:20,659 --> 01:24:21,319 reports that were 1841 01:24:21,319 --> 01:24:25,039 provided by staff first of them is first of them is a first 1842 01:24:25,039 --> 01:24:25,920 quarter financial 1843 01:24:25,920 --> 01:24:29,640 review report the impact fee capital improvements advisory 1844 01:24:29,640 --> 01:24:30,439 committee and dr. 1845 01:24:30,439 --> 01:24:34,250 banked here is here to answer any questions you might have 1846 01:24:34,250 --> 01:24:35,560 as mr. Morrow 1847 01:24:35,560 --> 01:24:39,430 just presented the Gibbons Creek plant closure update so 1848 01:24:39,430 --> 01:24:40,800 that is provided as 1849 01:24:40,800 --> 01:24:44,199 well along with a DME transmission and substation update 1850 01:24:44,199 --> 01:24:45,600 that was requested 1851 01:24:45,600 --> 01:24:49,609 from a previous pub meeting mr. Morrow and mr. banks are 1852 01:24:49,609 --> 01:24:50,439 here to answer any 1853 01:24:50,439 --> 01:24:56,680 questions you may have about those items on your future ag 1854 01:24:56,680 --> 01:24:58,899 endas list we have a 1855 01:24:58,899 --> 01:25:01,920 number of items that are coming forward to you in the near 1856 01:25:01,920 --> 01:25:02,920 future I believe 1857 01:25:02,920 --> 01:25:08,119 there was a minor typo typographical error on the energy 1858 01:25:08,119 --> 01:25:12,479 risk policy it was 1859 01:25:12,479 --> 01:25:15,250 believe on the agenda it was scheduled to be presented 1860 01:25:15,250 --> 01:25:16,199 today that'll be 1861 01:25:16,199 --> 01:25:21,850 presented on April the 9th the the energy risk policy 1862 01:25:21,850 --> 01:25:22,960 update that should be for 1863 01:25:22,960 --> 01:25:27,680 April the 9th so at your next pub meeting not today so make 1864 01:25:27,680 --> 01:25:30,039 that correction 1865 01:25:30,039 --> 01:25:37,359 I think that's been changed it has been okay okay okay and 1866 01:25:37,359 --> 01:25:39,520 then and then for a 1867 01:25:39,520 --> 01:25:43,479 new business matrix believe everything has been covered 1868 01:25:43,479 --> 01:25:45,239 that has been requested 1869 01:25:45,239 --> 01:25:48,659 so far there are a couple of items that were requested as 1870 01:25:48,659 --> 01:25:49,960 far as reconnect fees 1871 01:25:49,960 --> 01:25:53,439 for meters and smart meters along with the revenue 1872 01:25:53,439 --> 01:25:55,319 reconnect fees as they're 1873 01:25:55,319 --> 01:25:57,869 lowered that will be information that will be presented at 1874 01:25:57,869 --> 01:25:59,199 a future meeting 1875 01:25:59,199 --> 01:26:01,829 for your during the budget process so that'll be covered 1876 01:26:01,829 --> 01:26:02,680 during that time 1877 01:26:02,680 --> 01:26:05,760 frame and we'll bring all that forward to you then all the 1878 01:26:05,760 --> 01:26:07,119 remaining items I 1879 01:26:07,119 --> 01:26:12,770 believe were covered tonight okay nothing further questions 1880 01:26:12,770 --> 01:26:13,279 on any of the 1881 01:26:13,279 --> 01:26:23,760 ACM items no hearing none okay if we're concluding items 1882 01:26:23,760 --> 01:26:25,880 under section five five 1883 01:26:25,880 --> 01:26:30,489 one point oh four to the Texas Open Meetings Act any inqu 1884 01:26:30,489 --> 01:26:32,960 iries from the 1885 01:26:32,960 --> 01:26:35,829 Public Utilities Board or the public with specific factual 1886 01:26:35,829 --> 01:26:36,640 information or 1887 01:26:36,640 --> 01:26:40,630 recitation of policy or accept a proposal to place a matter 1888 01:26:40,630 --> 01:26:41,239 on the agenda 1889 01:26:41,239 --> 01:26:44,520 for an upcoming meeting 1890 01:26:47,880 --> 01:26:55,119 hearing none is there a motion to adjourn motion second 1891 01:26:55,119 --> 01:26:57,039 Alan second all in 1892 01:26:57,039 --> 01:27:02,840 favor say aye any opposed thank you