WEBVTT

00:00:00.000 --> 00:00:05.940
Okay, we do have a quorum, so let's call the December 11th

00:00:05.940 --> 00:00:07.559
Public Utilities Board to order.

00:00:07.559 --> 00:00:11.189
The first item on the agenda is to receive a report and

00:00:11.189 --> 00:00:13.279
hold a discussion of the energy

00:00:13.279 --> 00:00:15.560
management organization by Deloitte.

00:00:15.560 --> 00:00:17.800
Good morning.

00:00:17.800 --> 00:00:19.039
Brian Langley, Deputy City Manager.

00:00:19.039 --> 00:00:21.489
I want to take a few minutes to provide a brief

00:00:21.489 --> 00:00:23.239
introduction on this item.

00:00:23.239 --> 00:00:26.019
As you know, we've hired Deloitte on a couple of different

00:00:26.019 --> 00:00:27.559
occasions to help us work through

00:00:27.559 --> 00:00:30.600
our energy management organization.

00:00:30.600 --> 00:00:33.240
They've done a couple of different scopes of work for us.

00:00:33.240 --> 00:00:35.329
On today's presentation, they're going to be talking to you

00:00:35.329 --> 00:00:36.439
about the benchmarking work

00:00:36.439 --> 00:00:40.710
that they did for FY 2016-17 and also the review that they

00:00:40.710 --> 00:00:42.520
had of the energy management

00:00:42.520 --> 00:00:45.250
organization and all of the procedures and policies

00:00:45.250 --> 00:00:46.560
associated with that.

00:00:46.560 --> 00:00:48.700
Stephen Engler and Tim Metz are here, and so at this point,

00:00:48.700 --> 00:00:50.000
I'll turn over the presentation

00:00:50.000 --> 00:00:51.000
to them.

00:00:51.000 --> 00:00:57.759
Thank you, Brian.

00:00:57.759 --> 00:00:59.359
Good morning, everybody.

00:00:59.359 --> 00:01:01.280
Good morning, members of the board.

00:01:01.280 --> 00:01:03.630
My name is Steve Engler, and I'm with Deloitte's energy

00:01:03.630 --> 00:01:05.519
risk advisory practice, and my colleague

00:01:05.519 --> 00:01:07.760
Tim Metz is here with me as well.

00:01:07.760 --> 00:01:10.209
And we're here to talk about risk management, and Tim could

00:01:10.209 --> 00:01:11.359
talk to you about the risks

00:01:11.359 --> 00:01:14.359
of carrying a sleeping seven-year-old down the stairs.

00:01:14.359 --> 00:01:16.840
So if he hobbles around a little bit, it's because he's got

00:01:16.840 --> 00:01:18.000
a bit of an ankle issue.

00:01:18.000 --> 00:01:21.200
So thank you for having us here this morning.

00:01:21.200 --> 00:01:23.640
Happy to walk through our prepared remarks, but please feel

00:01:23.640 --> 00:01:24.840
free to ask questions at any

00:01:24.840 --> 00:01:28.719
time or save them to the end or both.

00:01:28.719 --> 00:01:30.879
All right.

00:01:30.879 --> 00:01:32.640
Okay.

00:01:32.640 --> 00:01:36.079
I won't read the legal caveats.

00:01:36.079 --> 00:01:38.719
Just to talk quickly on what we're going to discuss here,

00:01:38.719 --> 00:01:40.040
the objectives of today, we're

00:01:40.040 --> 00:01:43.069
going to kind of reframe the question that was asked to us

00:01:43.069 --> 00:01:44.439
the last time we spoke to

00:01:44.439 --> 00:01:45.439
you all.

00:01:45.439 --> 00:01:48.170
We're going to talk a little bit about risk uncertainty and

00:01:48.170 --> 00:01:49.879
how that relates to capabilities

00:01:49.879 --> 00:01:53.200
or expectations of capabilities in an organization.

00:01:53.200 --> 00:01:55.170
And then we'll go right into the results of the risk

00:01:55.170 --> 00:01:56.159
assessment itself.

00:01:56.159 --> 00:01:59.299
We'll tell you how we did the work and some of the outcomes

00:01:59.299 --> 00:02:00.040
of that.

00:02:00.040 --> 00:02:03.099
This presentation is kind of a summary of a more detailed

00:02:03.099 --> 00:02:04.739
report that's been prepared

00:02:04.739 --> 00:02:07.840
and presented to you all.

00:02:07.840 --> 00:02:10.860
Then the next piece we'll talk about will be some

00:02:10.860 --> 00:02:13.300
discussion of the benchmark and some

00:02:13.300 --> 00:02:17.129
recommendations there, an idea for an alternative benchmark

00:02:17.129 --> 00:02:19.680
, and then we'll talk about recommended

00:02:19.680 --> 00:02:20.680
next steps.

00:02:20.680 --> 00:02:23.719
So if that's clear, then we will move along.

00:02:23.719 --> 00:02:27.349
So just to reframe and remind everybody what we were asked,

00:02:27.349 --> 00:02:29.240
essentially one question that

00:02:29.240 --> 00:02:32.460
came to us the last time we spoke was, what are the risks

00:02:32.460 --> 00:02:34.120
that we've kind of taken on

00:02:34.120 --> 00:02:37.750
as an organization by bringing the EMO activities in-house

00:02:37.750 --> 00:02:40.060
where prior they were outsourced?

00:02:40.060 --> 00:02:42.680
So that was the first part of the analysis was to frame,

00:02:42.680 --> 00:02:44.080
and we'll talk about here in

00:02:44.080 --> 00:02:48.050
a minute, what risks existed before and are there any new

00:02:48.050 --> 00:02:50.120
or changing -- any changes to

00:02:50.120 --> 00:02:55.300
that set of risks since the EMO go live.

00:02:55.300 --> 00:02:58.520
Based on those risks identified and what's been brought in-

00:02:58.520 --> 00:03:00.000
house and being managed by

00:03:00.000 --> 00:03:05.939
DME, we then used that to form the basis of our assessment

00:03:05.939 --> 00:03:08.780
and our benchmark analysis

00:03:08.780 --> 00:03:13.479
and then following that, our recommendations.

00:03:13.479 --> 00:03:16.419
And then I said the last piece of this was to take a look

00:03:16.419 --> 00:03:18.199
at some different approaches

00:03:18.199 --> 00:03:21.849
for establishing a new benchmark going forward and make

00:03:21.849 --> 00:03:24.120
some recommendations as to how to

00:03:24.120 --> 00:03:25.120
proceed.

00:03:25.120 --> 00:03:26.120
Okay?

00:03:26.120 --> 00:03:27.120
All right.

00:03:27.120 --> 00:03:30.240
Let's talk a little bit about risks.

00:03:30.240 --> 00:03:34.969
Kind of a very consulting-y slide, but I think it's good to

00:03:34.969 --> 00:03:36.439
set the stage.

00:03:36.439 --> 00:03:39.439
We sometimes mix up the words risk and uncertainty, and I

00:03:39.439 --> 00:03:41.599
think it's important to understand kind

00:03:41.599 --> 00:03:44.879
of the differences, but also how they interrelate.

00:03:44.879 --> 00:03:48.889
A risk is really the possibilities of suffering an adverse

00:03:48.889 --> 00:03:51.599
outcome, higher rates, higher fuel

00:03:51.599 --> 00:03:55.680
prices, market changes, and the impact of that on the

00:03:55.680 --> 00:03:57.080
organization.

00:03:57.080 --> 00:04:00.080
Uncertainty while similar, it really refers to unknown

00:04:00.080 --> 00:04:01.879
events where the probability is

00:04:01.879 --> 00:04:03.680
difficult to quantify.

00:04:03.680 --> 00:04:08.539
So the risk of prices falling is related to the uncertainty

00:04:08.539 --> 00:04:11.080
of how much they could fall.

00:04:11.080 --> 00:04:12.080
Okay?

00:04:12.080 --> 00:04:15.150
While they both talk about expectations in the future, it's

00:04:15.150 --> 00:04:16.680
important to remember that

00:04:16.680 --> 00:04:18.600
risk can be mitigated.

00:04:18.600 --> 00:04:21.319
On the other hand, uncertainty will always exist.

00:04:21.319 --> 00:04:24.490
So it's that risk--it's that management or the mitigation

00:04:24.490 --> 00:04:25.959
of the risks that really is

00:04:25.959 --> 00:04:30.720
one of the charges of the EMO or DME more broadly.

00:04:30.720 --> 00:04:34.029
And so that's, again, a very important underlying concept

00:04:34.029 --> 00:04:36.000
for how we proceed, not just here,

00:04:36.000 --> 00:04:39.639
but when we do this work at peer organizations as well.

00:04:39.639 --> 00:04:41.529
And then related to that, and we're going to--you know,

00:04:41.529 --> 00:04:42.920
there's been a lot of talk about hedging

00:04:42.920 --> 00:04:46.180
and kind of optimization around the assets.

00:04:46.180 --> 00:04:49.500
It's important to note that managing or mitigating a risk

00:04:49.500 --> 00:04:51.639
does not necessarily mean forgoing

00:04:51.639 --> 00:04:53.480
an opportunity.

00:04:53.480 --> 00:04:56.089
And it's the infrastructure that enables all that, which is

00:04:56.089 --> 00:04:57.199
really what we took a look

00:04:57.199 --> 00:04:59.199
at as part of DME.

00:04:59.199 --> 00:05:01.639
Does that make sense?

00:05:01.639 --> 00:05:02.639
Okay.

00:05:02.639 --> 00:05:06.839
So another consulting slide, if you will.

00:05:06.839 --> 00:05:10.189
When we do an assessment like this at an organization, it's

00:05:10.189 --> 00:05:12.480
important for us to understand what's

00:05:12.480 --> 00:05:15.790
the objective, what's the transacting mandate is a phrase

00:05:15.790 --> 00:05:18.000
we like to use a lot of the organization

00:05:18.000 --> 00:05:22.839
because that helps us kind of frame the recommendations.

00:05:22.839 --> 00:05:25.439
Just to explain this chart a little bit, if you look at the

00:05:25.439 --> 00:05:26.800
x-axis on the bottom, we've

00:05:26.800 --> 00:05:31.000
got price taker, asset optimizer, and proprietary trader.

00:05:31.000 --> 00:05:33.800
And then the y-axis talks about the capabilities.

00:05:33.800 --> 00:05:37.129
And the capabilities in this context would be things around

00:05:37.129 --> 00:05:38.959
risk oversight, reporting,

00:05:38.959 --> 00:05:42.120
governance, systems, people.

00:05:42.120 --> 00:05:45.509
As you move on the x-axis from the left to the right, what

00:05:45.509 --> 00:05:47.319
we always try to keep in mind

00:05:47.319 --> 00:05:49.959
is that the risks really for all those organizations are

00:05:49.959 --> 00:05:51.800
very similar, the types of risks that

00:05:51.800 --> 00:05:54.740
they're--that organization is exposed to.

00:05:54.740 --> 00:05:57.639
It's the implication on what that means in terms of where

00:05:57.639 --> 00:05:59.199
do your capabilities need to

00:05:59.199 --> 00:06:01.000
be will vary.

00:06:01.000 --> 00:06:04.230
So if I'm all the way on the left as a price taker, meaning

00:06:04.230 --> 00:06:05.879
that I've got a commodity to

00:06:05.879 --> 00:06:08.649
sell or a commodity to buy, I'm just taking what the market

00:06:08.649 --> 00:06:10.240
offers me in terms of prices.

00:06:10.240 --> 00:06:13.199
And I'm not trying to do too much around that.

00:06:13.199 --> 00:06:15.310
All the way on the right hand side, we're a proprietary

00:06:15.310 --> 00:06:15.800
trader.

00:06:15.800 --> 00:06:18.019
That's where you're taking probably more speculative

00:06:18.019 --> 00:06:18.680
positions.

00:06:18.680 --> 00:06:19.680
You're in the market.

00:06:19.680 --> 00:06:23.079
You're--you know, an example would be large banks or the

00:06:23.079 --> 00:06:24.959
very large integrated oil and

00:06:24.959 --> 00:06:28.959
gas companies that really are, to use the word, trading.

00:06:28.959 --> 00:06:31.769
So they've got some assets but they don't even necessarily

00:06:31.769 --> 00:06:33.319
trade around those assets.

00:06:33.319 --> 00:06:35.540
In the middle is where we find a lot of the clients that we

00:06:35.540 --> 00:06:36.160
work with.

00:06:36.160 --> 00:06:40.560
And that's probably where DME is or requires to be.

00:06:40.560 --> 00:06:44.019
And that's to optimize around the assets and the positions

00:06:44.019 --> 00:06:45.000
that you own.

00:06:45.000 --> 00:06:49.379
So somewhere in between price taker and proprietary trader

00:06:49.379 --> 00:06:52.199
is where we see your organization and

00:06:52.199 --> 00:06:56.800
that's the context that we completed the assessment on.

00:06:56.800 --> 00:06:58.680
Okay.

00:06:58.680 --> 00:07:03.350
So now let's talk about the first question which is what

00:07:03.350 --> 00:07:05.879
risks existed before the EMO

00:07:05.879 --> 00:07:10.120
is established and what risks exist post.

00:07:10.120 --> 00:07:12.939
And the takeaway to this slide, I apologize, it's a little

00:07:12.939 --> 00:07:13.600
bit busy.

00:07:13.600 --> 00:07:16.629
The takeaway to this slide is that from our perspective and

00:07:16.629 --> 00:07:18.319
looking at the business before

00:07:18.319 --> 00:07:23.240
and now, there really are no net new risks in our opinion

00:07:23.240 --> 00:07:25.759
as to what the company or the

00:07:25.759 --> 00:07:28.019
utility has been exposed to.

00:07:28.019 --> 00:07:31.439
The difference is where were those risks managed.

00:07:31.439 --> 00:07:35.329
And prior to establishing the EMO, a lot of the risks were

00:07:35.329 --> 00:07:37.139
managed by the third party

00:07:37.139 --> 00:07:40.680
through that contract that was established.

00:07:40.680 --> 00:07:43.649
First go live or in the current state, those risks while

00:07:43.649 --> 00:07:45.519
they existed before are now being

00:07:45.519 --> 00:07:48.920
actively managed by DME.

00:07:48.920 --> 00:07:51.220
All of the risks down the left-hand side, if you look in

00:07:51.220 --> 00:07:52.399
kind of the bold or the big

00:07:52.399 --> 00:07:55.699
categories and then some specifics underneath it, these are

00:07:55.699 --> 00:07:57.439
very common to any company that's

00:07:57.439 --> 00:08:00.279
exposed to the commodity markets, particularly the energy

00:08:00.279 --> 00:08:01.399
commodity markets.

00:08:01.399 --> 00:08:05.189
So when we look at a company or utility such as DME, it

00:08:05.189 --> 00:08:07.800
could be bigger or smaller, those

00:08:07.800 --> 00:08:09.199
risks are fairly common.

00:08:09.199 --> 00:08:11.670
We have market risk in the sense of what's the price of the

00:08:11.670 --> 00:08:13.279
commodity, what's the liquidity

00:08:13.279 --> 00:08:16.959
of the products and the commodities that are out there.

00:08:16.959 --> 00:08:21.060
Do we have to deal with congestion risk and does that have

00:08:21.060 --> 00:08:22.879
an impact on pricing?

00:08:22.879 --> 00:08:25.889
One of the things to point out here, just in terms of

00:08:25.889 --> 00:08:28.000
changes with the anticipated move

00:08:28.000 --> 00:08:31.629
to 70% renewable and then potentially 100% renewable, it

00:08:31.629 --> 00:08:33.320
creates kind of a different load

00:08:33.320 --> 00:08:35.360
serving risk in our perspective.

00:08:35.360 --> 00:08:38.899
In other words, the availability of the renewable resources

00:08:38.899 --> 00:08:40.960
is something that is different than

00:08:40.960 --> 00:08:43.120
fossil fuel resources.

00:08:43.120 --> 00:08:47.389
And so increasing the footprint of that type of resource in

00:08:47.389 --> 00:08:49.679
your portfolio will probably

00:08:49.679 --> 00:08:53.039
create a different type of maybe even a more complex price

00:08:53.039 --> 00:08:54.799
risk than you've experienced

00:08:54.799 --> 00:08:58.120
before and also load serving.

00:08:58.120 --> 00:09:00.940
Do we know that the sun's going to shine tomorrow or is the

00:09:00.940 --> 00:09:02.519
wind going to blow tonight?

00:09:02.519 --> 00:09:05.129
It'll change a different dynamic for what the utility is

00:09:05.129 --> 00:09:06.879
trying to manage on a day-to-day,

00:09:06.879 --> 00:09:09.480
an hour-to-hour and really minute-to-minute basis.

00:09:09.480 --> 00:09:12.879
So those risks existed before, for sure.

00:09:12.879 --> 00:09:15.149
There's probably a different profile to those risks going

00:09:15.149 --> 00:09:16.399
forward as you move towards the

00:09:16.399 --> 00:09:19.480
more renewable plan.

00:09:19.480 --> 00:09:23.379
We highlight operations risk here and by operations, I don

00:09:23.379 --> 00:09:25.919
't mean running the power plant or the

00:09:25.919 --> 00:09:28.159
transmission lines.

00:09:28.159 --> 00:09:31.419
Really what this means is more the organizational

00:09:31.419 --> 00:09:34.440
activities inside the EMO, forecasting the

00:09:34.440 --> 00:09:37.669
load, forecasting the supply, looking at the market

00:09:37.669 --> 00:09:40.000
dynamics, understanding the impact

00:09:40.000 --> 00:09:44.620
of that on the position on a real-time and go-forward basis

00:09:44.620 --> 00:09:46.960
, executing, entering and

00:09:46.960 --> 00:09:50.500
settling transactions, all those things that have to happen

00:09:50.500 --> 00:09:52.000
to support the EMO and the

00:09:52.000 --> 00:09:53.840
transacting and the risk management activity.

00:09:53.840 --> 00:09:56.720
There's a key focus of our assessment and some of the

00:09:56.720 --> 00:09:58.639
recommendations will relate to

00:09:58.639 --> 00:10:01.639
that as well.

00:10:01.639 --> 00:10:05.759
A couple at the bottom that we think maybe are slightly

00:10:05.759 --> 00:10:08.799
different than before, certainly,

00:10:08.799 --> 00:10:11.850
and I mentioned already the variability risk of the

00:10:11.850 --> 00:10:14.279
renewable resources is going to create

00:10:14.279 --> 00:10:18.679
a different load profile for DME.

00:10:18.679 --> 00:10:22.879
We talked a fair amount with staff around the Givens Creek

00:10:22.879 --> 00:10:25.000
asset and prior to or I guess

00:10:25.000 --> 00:10:28.539
up until this point, this is as we understand an asset that

00:10:28.539 --> 00:10:30.360
's co-owned with three other

00:10:30.360 --> 00:10:31.519
entities.

00:10:31.519 --> 00:10:34.070
So there was, we say it was not actively managed prior to

00:10:34.070 --> 00:10:35.480
go live and that's important to

00:10:35.480 --> 00:10:39.110
point out because all those decisions weren't necessarily

00:10:39.110 --> 00:10:40.679
always in DME's hands.

00:10:40.679 --> 00:10:44.350
There had to be partner agreements as to how to move

00:10:44.350 --> 00:10:45.320
forward.

00:10:45.320 --> 00:10:48.129
I'll pause there to see if there's specific questions about

00:10:48.129 --> 00:10:49.639
any of these risks or anything

00:10:49.639 --> 00:10:54.960
I just mentioned.

00:10:54.960 --> 00:10:58.250
So again, this is the context for the assessment that we

00:10:58.250 --> 00:10:58.679
did.

00:10:58.679 --> 00:11:03.200
We looked at DME as we do many other similar organizations

00:11:03.200 --> 00:11:05.799
as to the capability to manage,

00:11:05.799 --> 00:11:09.009
monitor and mitigate these risks and really understand

00:11:09.009 --> 00:11:09.960
these risks.

00:11:09.960 --> 00:11:12.610
And again, in the context of where the organization is in

00:11:12.610 --> 00:11:14.879
terms of a transacting mandate or transacting

00:11:14.879 --> 00:11:15.879
profile.

00:11:15.879 --> 00:11:18.379
You're not trading, you're not market making, you're not

00:11:18.379 --> 00:11:19.159
speculating.

00:11:19.159 --> 00:11:23.759
So that was the context for our assessment.

00:11:23.759 --> 00:11:25.720
Okay.

00:11:25.720 --> 00:11:27.519
So what did we do?

00:11:27.519 --> 00:11:30.129
As I said, we were engaged to understand the existing

00:11:30.129 --> 00:11:32.000
energy and risk management program

00:11:32.000 --> 00:11:34.919
within DME.

00:11:34.919 --> 00:11:37.700
To do that, we were to collect and evaluate data, develop

00:11:37.700 --> 00:11:39.480
findings and make recommendations

00:11:39.480 --> 00:11:42.940
to this board and to the utility and those recommendations

00:11:42.940 --> 00:11:44.659
are available in this report

00:11:44.659 --> 00:11:48.240
and as well as a supporting detailed report.

00:11:48.240 --> 00:11:50.970
The scope included a review of governance, people, process

00:11:50.970 --> 00:11:52.159
and technology and we'll

00:11:52.159 --> 00:11:55.289
talk about that and how it ties into our capability

00:11:55.289 --> 00:11:56.559
maturity model.

00:11:56.559 --> 00:11:58.919
We specifically looked at the risk policy and the

00:11:58.919 --> 00:12:00.759
documentation supporting that.

00:12:00.759 --> 00:12:03.929
We looked again at the operations inside of DME for things

00:12:03.929 --> 00:12:05.720
like transacting processing

00:12:05.720 --> 00:12:09.240
and the entire transacting lifecycle.

00:12:09.240 --> 00:12:12.919
We talked a lot about where the utility is going in terms

00:12:12.919 --> 00:12:14.879
of the renewable dent in plan

00:12:14.879 --> 00:12:18.100
and the additions of those types of resources into the

00:12:18.100 --> 00:12:20.720
portfolio and the specific requirements

00:12:20.720 --> 00:12:22.379
that that brings.

00:12:22.379 --> 00:12:25.009
We talk a lot about the middle and the back office and just

00:12:25.009 --> 00:12:26.440
in terms of vernacular front

00:12:26.440 --> 00:12:30.250
office is the folks, that's the commercial end of the

00:12:30.250 --> 00:12:31.259
business.

00:12:31.259 --> 00:12:34.590
Middle office we refer to as the risk oversight function

00:12:34.590 --> 00:12:36.639
and then back office is typically

00:12:36.639 --> 00:12:40.200
settlements and accounting probably credit.

00:12:40.200 --> 00:12:44.029
We talked a lot with staff because as with other similar

00:12:44.029 --> 00:12:46.120
organizations, this isn't

00:12:46.120 --> 00:12:48.850
a very large organization so finding the appropriate way to

00:12:48.850 --> 00:12:50.940
create segregation between those functions

00:12:50.940 --> 00:12:53.909
is important and it sometimes poses challenges when there

00:12:53.909 --> 00:12:55.720
are fewer people to do that because

00:12:55.720 --> 00:12:58.559
sometimes you have people wearing multiple hats.

00:12:58.559 --> 00:13:01.799
And then we talked about risk reporting.

00:13:01.799 --> 00:13:05.269
The way we do the assessment is we talk to people, we

00:13:05.269 --> 00:13:07.559
assemble as much documentation

00:13:07.559 --> 00:13:12.200
as we can, we read the policies, the procedures, we ask

00:13:12.200 --> 00:13:15.519
about where the future state is, where

00:13:15.519 --> 00:13:16.519
is the utility going.

00:13:16.519 --> 00:13:18.860
Of course there's been a lot of discussion of that as of

00:13:18.860 --> 00:13:20.320
late and we were able to benefit

00:13:20.320 --> 00:13:24.019
from many of those discussions in terms of feeding our

00:13:24.019 --> 00:13:25.000
findings.

00:13:25.000 --> 00:13:27.990
And then there was a vetting process where we developed

00:13:27.990 --> 00:13:30.100
some initial recommendations,

00:13:30.100 --> 00:13:33.990
talked through those with staff and largely to make sure

00:13:33.990 --> 00:13:35.960
that we didn't get anything

00:13:35.960 --> 00:13:39.679
wrong or we didn't miss any details that are pertinent to

00:13:39.679 --> 00:13:42.279
the assessment, to our recommendations

00:13:42.279 --> 00:13:48.029
and we talked through a lot of comments and discussion

00:13:48.029 --> 00:13:50.679
around what we found.

00:13:50.679 --> 00:13:54.600
So Deloitte loves three letter acronyms so we use a CMM, a

00:13:54.600 --> 00:13:56.840
capability maturity model,

00:13:56.840 --> 00:13:59.860
to perform these assessments.

00:13:59.860 --> 00:14:02.120
And as I said we do it across four categories and that's

00:14:02.120 --> 00:14:03.840
down the left, governance, process,

00:14:03.840 --> 00:14:05.600
people and technology.

00:14:05.600 --> 00:14:09.240
And then we talk about three maturity scales.

00:14:09.240 --> 00:14:15.580
And I guess a couple things I'll point out on the scales.

00:14:15.580 --> 00:14:19.679
Just like the decision to be a price taker versus an optim

00:14:19.679 --> 00:14:22.080
izer versus a trader, neither

00:14:22.080 --> 00:14:23.399
of those decisions is wrong.

00:14:23.399 --> 00:14:26.059
It's just important to know where you are.

00:14:26.059 --> 00:14:29.059
As far as the maturity stages for an organization, there's

00:14:29.059 --> 00:14:30.960
nothing inherently wrong with being

00:14:30.960 --> 00:14:32.919
in the developing category.

00:14:32.919 --> 00:14:36.759
That's typically what we see for an organization and

00:14:36.759 --> 00:14:39.679
generally speaking we see that kind of

00:14:39.679 --> 00:14:43.120
evolution typically lasting a number of years.

00:14:43.120 --> 00:14:46.429
So you don't just start out in the middle of this maturity

00:14:46.429 --> 00:14:47.080
scale.

00:14:47.080 --> 00:14:50.389
A lot of the clients that have been up and running for some

00:14:50.389 --> 00:14:51.960
period of time, we find a

00:14:51.960 --> 00:14:54.909
lot of their activities fall generally in the prevalent

00:14:54.909 --> 00:14:56.480
scale and then leading would

00:14:56.480 --> 00:15:00.929
include kind of integrating technology and doing things

00:15:00.929 --> 00:15:03.120
more automated and more in a

00:15:03.120 --> 00:15:06.899
much more robust way that would be indicative of someone

00:15:06.899 --> 00:15:10.240
who's actively trading in the markets.

00:15:10.240 --> 00:15:12.460
When we do the assessment, we look across these four

00:15:12.460 --> 00:15:14.200
categories and in each of the categories

00:15:14.200 --> 00:15:16.659
there's a number of different elements and I think it's the

00:15:16.659 --> 00:15:17.679
last page in the report

00:15:17.679 --> 00:15:21.419
is the actual specific details of what we look at.

00:15:21.419 --> 00:15:24.250
We first look at where the organization is today and then

00:15:24.250 --> 00:15:26.320
through discussion and understanding

00:15:26.320 --> 00:15:28.940
of where the organization is going as well as our own

00:15:28.940 --> 00:15:30.919
opinion of where these capabilities

00:15:30.919 --> 00:15:35.539
need to be, we then make a recommendation as to what the

00:15:35.539 --> 00:15:37.840
future state should be.

00:15:37.840 --> 00:15:41.379
It's important again in the context of what the transacting

00:15:41.379 --> 00:15:42.879
mandate is, we don't always

00:15:42.879 --> 00:15:44.960
-- you might think that a consultant would say you always

00:15:44.960 --> 00:15:46.279
need to be in the leading practice

00:15:46.279 --> 00:15:47.279
category.

00:15:47.279 --> 00:15:49.299
In this case that's not necessarily true because there's

00:15:49.299 --> 00:15:51.259
not always return for the investment

00:15:51.259 --> 00:15:55.669
to put in processes, to put in systems, to hire a bunch of

00:15:55.669 --> 00:15:57.840
people to get to leading if

00:15:57.840 --> 00:16:00.980
the transacting profile and the risk profile doesn't

00:16:00.980 --> 00:16:02.000
warrant that.

00:16:02.000 --> 00:16:06.820
So that's important to keep in mind as we talk through the

00:16:06.820 --> 00:16:09.120
results in terms of where

00:16:09.120 --> 00:16:11.850
you think the organization is today and where it needs to

00:16:11.850 --> 00:16:13.399
be and all of that was informed

00:16:13.399 --> 00:16:16.940
by the types of risk that we just talked about, the trans

00:16:16.940 --> 00:16:19.279
acting profile that we talked about

00:16:19.279 --> 00:16:21.720
both today and where the organization is going.

00:16:21.720 --> 00:16:25.200
Anything I left out on that slide?

00:16:25.200 --> 00:16:26.200
I think so.

00:16:26.200 --> 00:16:27.200
Okay.

00:16:27.200 --> 00:16:28.200
Questions from the board?

00:16:28.200 --> 00:16:29.200
Let's get to the results.

00:16:29.200 --> 00:16:30.200
Okay.

00:16:30.200 --> 00:16:31.200
Now I'm going to hand it to Tim.

00:16:31.200 --> 00:16:36.200
So I'm going to try not to knock him over.

00:16:36.200 --> 00:16:37.200
Thanks Steve.

00:16:37.200 --> 00:16:40.240
So very similar slide to what we were looking at before.

00:16:40.240 --> 00:16:42.799
We've added a couple things here.

00:16:42.799 --> 00:16:46.279
The next column over from leading are the recommendations.

00:16:46.279 --> 00:16:49.120
So we've broken those recommendations out across each of

00:16:49.120 --> 00:16:50.120
the categories.

00:16:50.120 --> 00:16:53.759
And then we also prioritize them high, medium, and low

00:16:53.759 --> 00:16:56.080
based on our understanding of the

00:16:56.080 --> 00:16:59.460
direction that you're moving and our understanding of what

00:16:59.460 --> 00:17:01.159
's common in the industry.

00:17:01.159 --> 00:17:03.059
And then we also, to kind of link it back to the

00:17:03.059 --> 00:17:04.880
conversation where we started in terms

00:17:04.880 --> 00:17:09.089
of what are the risks inherent in the organization, also

00:17:09.089 --> 00:17:12.680
wanted to link those categories, governance,

00:17:12.680 --> 00:17:15.740
process, people, and technologies to the risks that those

00:17:15.740 --> 00:17:17.640
recommendations are addressing.

00:17:17.640 --> 00:17:20.980
I guess the last bit of context, you know, in the black

00:17:20.980 --> 00:17:23.000
circle with the C in it, that's

00:17:23.000 --> 00:17:24.880
where we plotted the current state.

00:17:24.880 --> 00:17:26.920
And then the green circle is the future state.

00:17:26.920 --> 00:17:29.740
And as Steve said, that future state was informed by our

00:17:29.740 --> 00:17:32.240
conversations with staff, our understanding

00:17:32.240 --> 00:17:35.880
of the future mandate for the energy and risk management

00:17:35.880 --> 00:17:36.720
program.

00:17:36.720 --> 00:17:39.849
So in terms of governance, you know, kind of right there in

00:17:39.849 --> 00:17:41.519
the middle of the developing,

00:17:41.519 --> 00:17:43.319
I think it's one more piece on that.

00:17:43.319 --> 00:17:45.700
Where these, kind of where the current and where the future

00:17:45.700 --> 00:17:47.079
state line up, it's certainly

00:17:47.079 --> 00:17:48.079
not a science.

00:17:48.079 --> 00:17:49.079
It's not quantitative.

00:17:49.079 --> 00:17:51.529
What we'll do is, as Steve talked about, there are a whole

00:17:51.529 --> 00:17:53.079
bunch of different subcategories

00:17:53.079 --> 00:17:54.079
under each one of these.

00:17:54.079 --> 00:17:56.660
What we'll do is we'll look at each of those subcategories.

00:17:56.660 --> 00:17:59.269
So for example, risk management committee might be one of

00:17:59.269 --> 00:17:59.680
them.

00:17:59.680 --> 00:18:02.200
And we'll, you know, based on what we've read and

00:18:02.200 --> 00:18:04.319
everything we've heard from everybody

00:18:04.319 --> 00:18:06.950
we've talked to, we'll plot where the risk management

00:18:06.950 --> 00:18:08.759
committee capabilities currently

00:18:08.759 --> 00:18:09.759
are.

00:18:09.759 --> 00:18:11.920
And we'll do that for each of the other subcategories.

00:18:11.920 --> 00:18:13.819
And then we'll go back and we'll look at governance as a

00:18:13.819 --> 00:18:15.079
whole and each of the individual

00:18:15.079 --> 00:18:19.000
items and use that information to plot it kind of at the

00:18:19.000 --> 00:18:21.319
overall governance level.

00:18:21.319 --> 00:18:24.859
So as Steve mentioned, developing is not necessarily a bad

00:18:24.859 --> 00:18:27.359
thing, especially for an organization

00:18:27.359 --> 00:18:30.750
that has really just started down this path a little over

00:18:30.750 --> 00:18:31.960
three years ago.

00:18:31.960 --> 00:18:34.210
So it's, you're kind of right where we would expect you to

00:18:34.210 --> 00:18:36.079
be in that evolution of developing

00:18:36.079 --> 00:18:37.079
to prevalent.

00:18:37.079 --> 00:18:40.619
I think in terms of moving forward, what we've heard in the

00:18:40.619 --> 00:18:42.920
recommendations that we made

00:18:42.920 --> 00:18:46.880
would really move you to the right-hand side of prevalent.

00:18:46.880 --> 00:18:47.880
Seems like a big jump.

00:18:47.880 --> 00:18:50.509
I think when we get into the recommendations on the next

00:18:50.509 --> 00:18:52.680
slide, there are a lot of recommendations

00:18:52.680 --> 00:18:56.930
that can be implemented or acted on fairly easily that will

00:18:56.930 --> 00:18:58.920
have a lot of value and will

00:18:58.920 --> 00:19:01.470
really significantly move you across that evolutionary

00:19:01.470 --> 00:19:02.079
spectrum.

00:19:02.079 --> 00:19:04.079
So we'll take a look at those in a second.

00:19:04.079 --> 00:19:07.619
On the process, kind of right on the border of developing

00:19:07.619 --> 00:19:09.599
to prevalent, again, I think

00:19:09.599 --> 00:19:12.750
there are just a handful of recommendations here, only a

00:19:12.750 --> 00:19:14.680
couple high priority ones, that

00:19:14.680 --> 00:19:18.390
will have a lot of value and really help you move to the

00:19:18.390 --> 00:19:19.119
right.

00:19:19.119 --> 00:19:22.930
People, again, kind of right in the middle of developing, a

00:19:22.930 --> 00:19:24.880
couple recommendations that

00:19:24.880 --> 00:19:27.119
will help you take some big steps forward.

00:19:27.119 --> 00:19:31.450
And then on the technology side, I think there's kind of

00:19:31.450 --> 00:19:34.480
one primary recommendation that we'll

00:19:34.480 --> 00:19:37.089
talk about in terms of the system infrastructure and the

00:19:37.089 --> 00:19:38.640
tools available to staff that can

00:19:38.640 --> 00:19:42.119
have a really profound impact on the program overall.

00:19:42.119 --> 00:19:43.119
Any questions?

00:19:43.119 --> 00:19:44.119
Sure.

00:19:44.119 --> 00:19:49.519
Go ahead, if we ask the same question again.

00:19:49.519 --> 00:19:50.519
Oh, boy.

00:19:50.519 --> 00:19:53.390
Now, maybe you plan to answer this later, so if you do,

00:19:53.390 --> 00:19:55.000
then you don't need to answer

00:19:55.000 --> 00:19:56.000
this now.

00:19:56.000 --> 00:20:02.539
So of these four categories, which would you say is the

00:20:02.539 --> 00:20:06.759
biggest problem area in the status

00:20:06.759 --> 00:20:11.680
quo and which is our greatest strength in the status quo?

00:20:11.680 --> 00:20:14.079
I mean, I can get a sense just by looking at this, but

00:20:14.079 --> 00:20:15.400
going into more detail.

00:20:15.400 --> 00:20:18.009
On the other hand, if that's something you plan on talking

00:20:18.009 --> 00:20:18.720
about later.

00:20:18.720 --> 00:20:20.960
We'll go into a little bit more detail on the next slide.

00:20:20.960 --> 00:20:23.490
But I think in terms of, I wouldn't describe it as a

00:20:23.490 --> 00:20:25.400
weakness, but where I think you can

00:20:25.400 --> 00:20:28.940
make a handful of small changes and really have a big

00:20:28.940 --> 00:20:31.460
impact is on the governance side.

00:20:31.460 --> 00:20:34.000
So in terms of kind of rethinking through the risk

00:20:34.000 --> 00:20:36.319
management committee and kind of the

00:20:36.319 --> 00:20:37.720
governance hierarchy.

00:20:37.720 --> 00:20:41.180
So starting at the city council level, going down into the

00:20:41.180 --> 00:20:43.240
organization and into the day-to-day

00:20:43.240 --> 00:20:47.029
activities and oversight, I think there's a lot of benefit

00:20:47.029 --> 00:20:49.000
that can be achieved there.

00:20:49.000 --> 00:20:51.609
I think on the strength side, I think very clearly the

00:20:51.609 --> 00:20:52.359
processes.

00:20:52.359 --> 00:20:57.140
It's very clear to us that when DME started to go down this

00:20:57.140 --> 00:20:59.400
path of wanting to go live

00:20:59.400 --> 00:21:02.470
with the EMO, that there was a lot of thought given to kind

00:21:02.470 --> 00:21:04.079
of the day-to-day processes

00:21:04.079 --> 00:21:07.200
that would be needed in order to achieve that mission.

00:21:07.200 --> 00:21:10.289
And that's very clear in all the risk policy and all of the

00:21:10.289 --> 00:21:12.079
procedures manuals that we've

00:21:12.079 --> 00:21:13.759
read in that area.

00:21:13.759 --> 00:21:16.759
So it's very clear a lot of effort was put in that.

00:21:16.759 --> 00:21:19.490
Yeah, I'll just add, I'm remiss that I meant to give you a

00:21:19.490 --> 00:21:21.759
preview of the overall answer

00:21:21.759 --> 00:21:23.640
to Tim.

00:21:23.640 --> 00:21:30.710
When we started the assessment, there are certain basic

00:21:30.710 --> 00:21:34.039
things that we look for.

00:21:34.039 --> 00:21:36.380
We look forward with these assessments for an organization

00:21:36.380 --> 00:21:37.460
that has some purview over

00:21:37.460 --> 00:21:43.160
commodity price and liquidity risk management.

00:21:43.160 --> 00:21:44.359
We look for segregation of duties.

00:21:44.359 --> 00:21:45.799
We look for kind of a framework.

00:21:45.799 --> 00:21:47.920
We look for, as Tim said, processes.

00:21:47.920 --> 00:21:50.200
We look for people in certain spots.

00:21:50.200 --> 00:21:53.920
And I think in general, all of that is there.

00:21:53.920 --> 00:21:56.599
There were no gaping holes.

00:21:56.599 --> 00:21:59.369
There was nothing that jumped out as an organization or in

00:21:59.369 --> 00:22:01.480
terms of capabilities that gave us really

00:22:01.480 --> 00:22:03.240
serious concern.

00:22:03.240 --> 00:22:07.819
There are things, as Tim said, that I think can be pushed

00:22:07.819 --> 00:22:12.160
along with relatively light lifting.

00:22:12.160 --> 00:22:14.630
It seems to us that because there's been kind of an

00:22:14.630 --> 00:22:16.599
evolution in where the organization

00:22:16.599 --> 00:22:19.730
is going and the focus on renewables and there's been some

00:22:19.730 --> 00:22:21.640
personnel changes, that some of

00:22:21.640 --> 00:22:24.670
the documentation is just out of sync with what's actually

00:22:24.670 --> 00:22:25.480
happening.

00:22:25.480 --> 00:22:28.200
But again, the framework is there.

00:22:28.200 --> 00:22:31.470
And I think a lot of the recommendations really are to

00:22:31.470 --> 00:22:33.960
update the governance documentation,

00:22:33.960 --> 00:22:36.789
the policies, some of the risk limits, some of the

00:22:36.789 --> 00:22:38.920
reporting that's being done to match

00:22:38.920 --> 00:22:40.039
what's already happening.

00:22:40.039 --> 00:22:43.440
So just kind of getting that in sync and some of the things

00:22:43.440 --> 00:22:45.079
that we'll talk about.

00:22:45.079 --> 00:22:48.539
I guess the other -- I agree with Tim on core strength

00:22:48.539 --> 00:22:49.960
being processed.

00:22:49.960 --> 00:22:53.180
That's kind of the framework that we look for and that we

00:22:53.180 --> 00:22:54.119
see in place.

00:22:54.119 --> 00:22:59.160
And the people, I think, it's an experienced group.

00:22:59.160 --> 00:23:00.160
They understand the market.

00:23:00.160 --> 00:23:02.880
They understand the risks that are being managed.

00:23:02.880 --> 00:23:06.339
And pretty much without exception, what we always talked

00:23:06.339 --> 00:23:08.039
about in terms of objectives

00:23:08.039 --> 00:23:10.299
for the organization, and maybe we get into this with the

00:23:10.299 --> 00:23:11.559
benchmark a little bit, it's

00:23:11.559 --> 00:23:15.700
all about managing the price risk that flows through to the

00:23:15.700 --> 00:23:17.319
end-use customer.

00:23:17.319 --> 00:23:20.369
That's a central focus of the organization, came out in

00:23:20.369 --> 00:23:22.000
almost every discussion.

00:23:22.000 --> 00:23:25.109
And I think the experience of the group that's doing that

00:23:25.109 --> 00:23:27.319
will help as an asset to the utility,

00:23:27.319 --> 00:23:30.319
to the city.

00:23:30.319 --> 00:23:33.319
Any other questions?

00:23:33.319 --> 00:23:34.319
Okay.

00:23:34.319 --> 00:23:35.319
Okay.

00:23:35.319 --> 00:23:39.160
So now I want to take a couple minutes to walk through all

00:23:39.160 --> 00:23:42.279
of the high-priority recommendations.

00:23:42.279 --> 00:23:45.839
So again, most of them are focused in the governance area.

00:23:45.839 --> 00:23:48.859
And I'll kind of talk about the governance recommendations,

00:23:48.859 --> 00:23:50.559
I think, in four main groups.

00:23:50.559 --> 00:23:53.390
The first is related to -- and Steve mentioned this --

00:23:53.390 --> 00:23:55.279
related to the risk policy and the

00:23:55.279 --> 00:23:59.220
governance hierarchy, the documentation that's in place,

00:23:59.220 --> 00:24:01.720
and the risk management committee.

00:24:01.720 --> 00:24:05.859
Going back and taking a fresh look at those, and really

00:24:05.859 --> 00:24:08.359
tailoring it to what's actually

00:24:08.359 --> 00:24:11.470
being done, what are the actual activities, kind of who's

00:24:11.470 --> 00:24:13.240
doing what, who's overseeing

00:24:13.240 --> 00:24:16.519
what and playing what oversight role.

00:24:16.519 --> 00:24:22.000
I think all those things were envisioned at Go Live.

00:24:22.000 --> 00:24:25.319
And over time, as the programs evolved and as you really

00:24:25.319 --> 00:24:27.359
got into the day-to-day, those

00:24:27.359 --> 00:24:28.640
things have changed a little bit.

00:24:28.640 --> 00:24:31.259
So it's simply about going back and taking a fresh look at

00:24:31.259 --> 00:24:32.720
them and understanding what

00:24:32.720 --> 00:24:34.220
needs to change.

00:24:34.220 --> 00:24:37.430
As it relates to the governance hierarchy, so currently

00:24:37.430 --> 00:24:39.240
there's the city council plays

00:24:39.240 --> 00:24:42.140
a role, you all play a role, and then within the

00:24:42.140 --> 00:24:44.759
organization, within DME, there's the

00:24:44.759 --> 00:24:48.200
strategy committee and there's the operations committee.

00:24:48.200 --> 00:24:51.839
So kind of taking a look at that and understanding and

00:24:51.839 --> 00:24:54.619
really making a decision as to what the

00:24:54.619 --> 00:24:57.359
role of the strategy committee and the operations committee

00:24:57.359 --> 00:24:59.000
are playing, and consider making

00:24:59.000 --> 00:25:00.480
that a single committee.

00:25:00.480 --> 00:25:03.000
There's a lot of overlap in who sits on both of those

00:25:03.000 --> 00:25:03.839
committees.

00:25:03.839 --> 00:25:07.240
It's our understanding that often those two committees will

00:25:07.240 --> 00:25:08.240
jointly meet.

00:25:08.240 --> 00:25:11.049
And if that's the case, recognizing the commitment of

00:25:11.049 --> 00:25:13.359
everybody's time in these matters, think

00:25:13.359 --> 00:25:16.220
about whether it just makes sense to kind of streamline

00:25:16.220 --> 00:25:17.799
that process, have a single

00:25:17.799 --> 00:25:21.089
committee with a single mission and oversight

00:25:21.089 --> 00:25:24.279
responsibility, and then simply make sure

00:25:24.279 --> 00:25:27.910
that that risk management committee regularly meets, has a

00:25:27.910 --> 00:25:29.720
standard agenda and reporting

00:25:29.720 --> 00:25:34.680
package that they follow, and just shore that piece up a

00:25:34.680 --> 00:25:36.039
little bit.

00:25:36.039 --> 00:25:39.500
The next group is update of Appendix A and Appendix E. So

00:25:39.500 --> 00:25:42.160
Appendix A is to the risk policy

00:25:42.160 --> 00:25:44.400
and it says, "Here are the limits.

00:25:44.400 --> 00:25:49.640
Here are the things that the front office or DME can't do."

00:25:49.640 --> 00:25:52.730
And Appendix E is here and talks about what the approved

00:25:52.730 --> 00:25:53.759
products are.

00:25:53.759 --> 00:25:59.799
So trading power or different fixed price instruments.

00:25:59.799 --> 00:26:00.799
Both of those exist.

00:26:00.799 --> 00:26:05.160
I think they can be built out a little bit more to be more

00:26:05.160 --> 00:26:06.319
specific.

00:26:06.319 --> 00:26:09.619
So everybody has a crystal clear understanding of what they

00:26:09.619 --> 00:26:11.279
're authorized to do up to how

00:26:11.279 --> 00:26:14.039
much they can do those types of things.

00:26:14.039 --> 00:26:17.500
And it ties to the last bullet on here in terms of reconcil

00:26:17.500 --> 00:26:19.160
ing the DOA memorandum.

00:26:19.160 --> 00:26:22.579
So delegation of authority is DOA.

00:26:22.579 --> 00:26:25.309
There's some inconsistencies in a memo that goes out on a

00:26:25.309 --> 00:26:26.720
regular basis versus what's

00:26:26.720 --> 00:26:31.880
actually in the ERMPs is the risk policy document.

00:26:31.880 --> 00:26:35.509
So making sure that those two things are synced up so

00:26:35.509 --> 00:26:37.819
everybody's on the same page.

00:26:37.819 --> 00:26:42.650
And then I guess really the third group of these is the

00:26:42.650 --> 00:26:45.720
three of the final four bullets.

00:26:45.720 --> 00:26:48.670
So starting with designing and documenting a financial

00:26:48.670 --> 00:26:50.480
hedge program, quantifying the

00:26:50.480 --> 00:26:54.240
risk profile, and then establishing risk limits linked to

00:26:54.240 --> 00:26:55.279
objectives.

00:26:55.279 --> 00:26:58.009
So that's going back to the risks that Steve talked about a

00:26:58.009 --> 00:26:59.339
little bit earlier in terms

00:26:59.339 --> 00:27:02.589
of kind of the complexity of the price risk, the

00:27:02.589 --> 00:27:05.900
uncertainty of the renewable supply, really

00:27:05.900 --> 00:27:09.589
clearly understanding what risk that introduced into the

00:27:09.589 --> 00:27:11.839
portfolio, tying it to something

00:27:11.839 --> 00:27:15.539
specific like a rate at risk, and understanding what are

00:27:15.539 --> 00:27:18.319
the types of activities or what financial

00:27:18.319 --> 00:27:21.869
risk mitigation activities might we do to help manage that

00:27:21.869 --> 00:27:23.759
supply and that price risk.

00:27:23.759 --> 00:27:26.230
And that's something that we'll come back to here in a few

00:27:26.230 --> 00:27:27.559
slides when we start to talk

00:27:27.559 --> 00:27:30.839
about the benchmark as well.

00:27:30.839 --> 00:27:33.450
On the process side, it's really about reporting and

00:27:33.450 --> 00:27:34.480
communication.

00:27:34.480 --> 00:27:40.029
So making sure that there's a singular risk metric or a set

00:27:40.029 --> 00:27:42.779
of paired risk metrics that

00:27:42.779 --> 00:27:47.289
help describe what the risk is and where you are relative

00:27:47.289 --> 00:27:48.599
to that risk.

00:27:48.599 --> 00:27:52.680
And then being able to communicate what that is and provide

00:27:52.680 --> 00:27:55.200
daily reports to all stakeholders

00:27:55.200 --> 00:27:58.059
and everybody responsible for oversight.

00:27:58.059 --> 00:28:02.680
So each day everybody's on the same sheet of music.

00:28:02.680 --> 00:28:06.220
From a technology perspective, there is currently a system

00:28:06.220 --> 00:28:08.799
in place that doesn't have the capabilities

00:28:08.799 --> 00:28:13.460
that DME needs in order to execute what they need to on a

00:28:13.460 --> 00:28:17.079
day, their daily responsibilities.

00:28:17.079 --> 00:28:20.190
And so taking a look at that, identifying what else is out

00:28:20.190 --> 00:28:21.859
there that might meet needs

00:28:21.859 --> 00:28:25.319
and finding the right fit for purpose system to support the

00:28:25.319 --> 00:28:26.960
day-to-day activities.

00:28:26.960 --> 00:28:29.880
And then finally on the people side, as was mentioned

00:28:29.880 --> 00:28:32.079
earlier, there's been some turnover

00:28:32.079 --> 00:28:34.339
roles or positions have changed.

00:28:34.339 --> 00:28:37.529
Making sure there's the right redundancy across the front

00:28:37.529 --> 00:28:39.319
and the middle and the back office

00:28:39.319 --> 00:28:43.640
such that nothing falls through the cracks and there's a

00:28:43.640 --> 00:28:46.119
consistent level of execution

00:28:46.119 --> 00:28:47.119
of the program.

00:28:47.119 --> 00:28:53.259
Can you explain a little bit more what you mean by the

00:28:53.259 --> 00:28:55.920
right redundancy?

00:28:55.920 --> 00:28:56.920
Sure.

00:28:56.920 --> 00:29:00.039
Because redundancy tends to have negative connotations.

00:29:00.039 --> 00:29:03.789
Here I see it's a positive, especially when you're talking

00:29:03.789 --> 00:29:05.079
about staffing.

00:29:05.079 --> 00:29:06.079
So if you could explain.

00:29:06.079 --> 00:29:07.079
Yeah.

00:29:07.079 --> 00:29:09.000
In this case, I think redundancy is meant to be positive.

00:29:09.000 --> 00:29:12.009
So from a middle office perspective, for example, if I've

00:29:12.009 --> 00:29:13.819
got one person that's responsible

00:29:13.819 --> 00:29:18.009
for always preparing the reports that go out on a daily

00:29:18.009 --> 00:29:20.440
basis or on a weekly basis, to

00:29:20.440 --> 00:29:23.660
the extent that that person isn't available for some period

00:29:23.660 --> 00:29:25.319
of time, I guess the question

00:29:25.319 --> 00:29:27.559
is who is going to provide those reports?

00:29:27.559 --> 00:29:31.019
So making sure that you've got staff cross-trained to step

00:29:31.019 --> 00:29:32.980
into a role that maybe is not their

00:29:32.980 --> 00:29:37.150
primary or day-to-day role, but that they can fill in the

00:29:37.150 --> 00:29:39.119
event that it's needed.

00:29:39.119 --> 00:29:42.440
And on the governance, it looks like a long list, but it's

00:29:42.440 --> 00:29:44.079
a lot of low-hanging fruit

00:29:44.079 --> 00:29:48.720
that we can implement rather quickly to get from developing

00:29:48.720 --> 00:29:51.839
to a higher level of an organization.

00:29:51.839 --> 00:29:57.130
So in reading the report, the whole report, I'm impressed

00:29:57.130 --> 00:30:00.359
with where they are for a three-year

00:30:00.359 --> 00:30:04.160
organization actually.

00:30:04.160 --> 00:30:06.799
And just a kind of overarching comment on that and to

00:30:06.799 --> 00:30:08.599
follow up on a couple of Tim's points,

00:30:08.599 --> 00:30:11.819
what we try to do is identify things here that stitch

00:30:11.819 --> 00:30:14.319
together, hopefully, logically.

00:30:14.319 --> 00:30:18.109
In my view of how this can work, you've got a policy that

00:30:18.109 --> 00:30:20.099
outlines what are the risks

00:30:20.099 --> 00:30:24.180
that we're exposed to and what's our appetite relative to

00:30:24.180 --> 00:30:25.319
those risks.

00:30:25.319 --> 00:30:28.950
What are the tools that are available to the organization

00:30:28.950 --> 00:30:30.119
to manage that?

00:30:30.119 --> 00:30:33.460
So the policy is kind of the, it's the enabler for the

00:30:33.460 --> 00:30:35.680
organization to go out and manage

00:30:35.680 --> 00:30:38.869
the risk within whatever boundaries the organization and

00:30:38.869 --> 00:30:41.240
the board and the city council ultimately

00:30:41.240 --> 00:30:42.920
set.

00:30:42.920 --> 00:30:47.089
The RMC can act as the body just to be the oversight of

00:30:47.089 --> 00:30:47.880
that.

00:30:47.880 --> 00:30:50.720
Is that happening according to how we've laid it out?

00:30:50.720 --> 00:30:54.000
Are we within our risk tolerances?

00:30:54.000 --> 00:30:57.089
If the organization says, well, there's a new type of

00:30:57.089 --> 00:30:59.039
instrument or a new transaction

00:30:59.039 --> 00:31:01.640
we want to do that's not previously authorized, that would

00:31:01.640 --> 00:31:02.960
be the body to review that and

00:31:02.960 --> 00:31:03.960
make recommendations.

00:31:03.960 --> 00:31:06.769
And I would also see that as kind of the conduit of

00:31:06.769 --> 00:31:09.319
information to both the board and the city

00:31:09.319 --> 00:31:14.069
council and establish kind of a more regular update and

00:31:14.069 --> 00:31:16.839
information flow as to where we

00:31:16.839 --> 00:31:19.569
are, where are we going, what have we done, did anything

00:31:19.569 --> 00:31:21.240
unusual happen, all those kinds

00:31:21.240 --> 00:31:22.240
of conversations.

00:31:22.240 --> 00:31:24.720
The RMC can really be the engine to do that.

00:31:24.720 --> 00:31:27.609
And then a lot of the other pieces like to mention the

00:31:27.609 --> 00:31:29.559
system, that's another part of

00:31:29.559 --> 00:31:33.190
the toolkit, if you will, just to enable the organization

00:31:33.190 --> 00:31:35.039
to, you come in in the morning

00:31:35.039 --> 00:31:38.839
and are we long, are we short, where are our prices, can we

00:31:38.839 --> 00:31:40.799
execute instruments and have

00:31:40.799 --> 00:31:43.710
them go into the system so it's all a complete system of

00:31:43.710 --> 00:31:44.359
record.

00:31:44.359 --> 00:31:46.789
Those are all the things that kind of enable that, but the

00:31:46.789 --> 00:31:48.240
governance and the policy piece

00:31:48.240 --> 00:31:52.140
of this and then executed through the RMC is really what

00:31:52.140 --> 00:31:54.079
will drive it, I think.

00:31:54.079 --> 00:31:57.240
Yeah, it's huge.

00:31:57.240 --> 00:32:03.480
And then I think we made these points a couple times.

00:32:03.480 --> 00:32:08.339
Basically, it's our observation that even though they're on

00:32:08.339 --> 00:32:10.400
the system side, there's

00:32:10.400 --> 00:32:13.000
some work that can be done there and some additional

00:32:13.000 --> 00:32:15.920
infrastructure that should be provided.

00:32:15.920 --> 00:32:18.789
The organization is generally well positioned, well

00:32:18.789 --> 00:32:20.920
structured in staff and highly capable

00:32:20.920 --> 00:32:25.079
of managing the risks that the utility faces.

00:32:25.079 --> 00:32:27.450
And then again, just kind of coming back to that technology

00:32:27.450 --> 00:32:28.839
infrastructure, putting that

00:32:28.839 --> 00:32:35.240
in place would go a long way to really supporting the day-

00:32:35.240 --> 00:32:36.559
to-day.

00:32:36.559 --> 00:32:40.019
And now we get to move on to the FY17 benchmark analysis

00:32:40.019 --> 00:32:41.960
and we'll walk through this kind

00:32:41.960 --> 00:32:42.960
of in two parts.

00:32:42.960 --> 00:32:47.200
One is looking at a couple of alternatives for FY17 that

00:32:47.200 --> 00:32:49.319
have been, I think have been

00:32:49.319 --> 00:32:52.279
proposed and then also providing an alternative view on

00:32:52.279 --> 00:32:54.279
what that benchmark might look like

00:32:54.279 --> 00:32:56.720
going forward.

00:32:56.720 --> 00:33:01.259
So first, the two alternatives that we looked at, one,

00:33:01.259 --> 00:33:04.480
option one, looks at what the day-ahead

00:33:04.480 --> 00:33:07.359
price for power was during the year in question.

00:33:07.359 --> 00:33:13.160
So in this case, we looked back starting October 1, 2016

00:33:13.160 --> 00:33:17.480
through September 30, 2017, would

00:33:17.480 --> 00:33:20.779
constitute the FY17 benchmark.

00:33:20.779 --> 00:33:22.759
And just what was the day-ahead price of power?

00:33:22.759 --> 00:33:27.549
So every day, ERCOT posts power prices for what they expect

00:33:27.549 --> 00:33:29.640
for the next day or the day

00:33:29.640 --> 00:33:30.640
ahead.

00:33:30.640 --> 00:33:33.079
So that meant if we just went back and we looked at what

00:33:33.079 --> 00:33:34.599
all of those power prices were

00:33:34.599 --> 00:33:38.990
versus how much energy or load there was, that constitutes

00:33:38.990 --> 00:33:41.400
the first part of the benchmark

00:33:41.400 --> 00:33:42.400
one.

00:33:42.400 --> 00:33:45.859
And then similarly to the contract that was previously in

00:33:45.859 --> 00:33:47.599
place, there's a heat rate

00:33:47.599 --> 00:33:52.130
adder or a premium that gets added into that to account for

00:33:52.130 --> 00:33:53.700
risk and profit.

00:33:53.700 --> 00:33:57.390
So option one, in a sense, is very similar to what the old

00:33:57.390 --> 00:33:59.640
benchmark looked like, except

00:33:59.640 --> 00:34:04.609
it's now based on the market price of power on a day-ahead

00:34:04.609 --> 00:34:05.559
basis.

00:34:05.559 --> 00:34:08.400
And so there's some advantages to this particular option.

00:34:08.400 --> 00:34:11.800
One, it's very simple to quantify and to measure.

00:34:11.800 --> 00:34:13.599
ERCOT posts those prices every day.

00:34:13.599 --> 00:34:16.639
We can go back and we can very easily capture them.

00:34:16.639 --> 00:34:18.860
We can add in the three and a half heat rate adder and we

00:34:18.860 --> 00:34:20.159
can get to what the benchmark

00:34:20.159 --> 00:34:21.159
is.

00:34:21.159 --> 00:34:23.559
There are also a couple disadvantages to that.

00:34:23.559 --> 00:34:28.380
One is that it does move with the day-ahead markets.

00:34:28.380 --> 00:34:30.989
We can only calculate it after the fact, after we know what

00:34:30.989 --> 00:34:32.400
all of those day-ahead prices

00:34:32.400 --> 00:34:34.719
were in any particular year.

00:34:34.719 --> 00:34:40.440
And it doesn't really require an active management.

00:34:40.440 --> 00:34:44.710
Because the benchmark is moving with whatever the price of

00:34:44.710 --> 00:34:47.119
power is for that year, if power

00:34:47.119 --> 00:34:50.199
prices go up, overall the benchmark would go up.

00:34:50.199 --> 00:34:54.320
If power prices go down, the benchmark would go down.

00:34:54.320 --> 00:34:59.000
That and I think given the direction that you're moving,

00:34:59.000 --> 00:35:01.639
moving further away from the previous

00:35:01.639 --> 00:35:04.730
benchmark and getting away from the idea of a three and a

00:35:04.730 --> 00:35:06.480
half heat rate adder probably

00:35:06.480 --> 00:35:07.480
makes a lot of sense.

00:35:07.480 --> 00:35:10.360
I mean, you're no longer in the situation where you have a

00:35:10.360 --> 00:35:11.840
full requirements contract

00:35:11.840 --> 00:35:14.449
with one counterparty and they're taking on a lot of those

00:35:14.449 --> 00:35:14.960
risks.

00:35:14.960 --> 00:35:17.360
You're managing those risks yourself now.

00:35:17.360 --> 00:35:20.090
And so that three and a half heat rate probably doesn't

00:35:20.090 --> 00:35:21.840
make as much sense as it used to.

00:35:21.840 --> 00:35:26.079
The second option is more of a forward-looking benchmark.

00:35:26.079 --> 00:35:30.769
So if we went out on the last day of September in 2016, we

00:35:30.769 --> 00:35:33.199
can look to the forward markets

00:35:33.199 --> 00:35:36.570
to understand what the expectation of power costs are going

00:35:36.570 --> 00:35:38.000
to be all the way through

00:35:38.000 --> 00:35:43.719
the fiscal year, all the way through September 2017 of the

00:35:43.719 --> 00:35:44.900
next year.

00:35:44.900 --> 00:35:48.900
And what we can do is we can take that forward curve and we

00:35:48.900 --> 00:35:51.159
can multiply it by the load,

00:35:51.159 --> 00:35:54.760
how much electricity you expect to need in that year.

00:35:54.760 --> 00:35:57.369
And that serves as the benchmark for on that day what it

00:35:57.369 --> 00:35:58.920
might cost to procure all of the

00:35:58.920 --> 00:36:02.760
power or all the electricity that you need in that year.

00:36:02.760 --> 00:36:05.769
And then as you go throughout the year and you buy in the

00:36:05.769 --> 00:36:08.400
day ahead markets or you know,

00:36:08.400 --> 00:36:12.340
the renewables, you have renewables at whatever the

00:36:12.340 --> 00:36:15.440
contract price is, you can then compare

00:36:15.440 --> 00:36:18.260
your actual costs back to that benchmark of what it would

00:36:18.260 --> 00:36:19.840
cost, what it would have cost

00:36:19.840 --> 00:36:23.469
to lock in all of your electricity on the day before the

00:36:23.469 --> 00:36:25.559
beginning of that fiscal year

00:36:25.559 --> 00:36:28.289
and you can get an understanding of how well you did

00:36:28.289 --> 00:36:30.000
relative to that benchmark.

00:36:30.000 --> 00:36:33.159
So again, this also has some advantages and disadvantages.

00:36:33.159 --> 00:36:36.789
The advantages is that it's market-based and it also sets a

00:36:36.789 --> 00:36:38.480
very clear target to be.

00:36:38.480 --> 00:36:41.110
Going into the year, you for the most part know exactly

00:36:41.110 --> 00:36:43.119
what it is you're managing to

00:36:43.119 --> 00:36:45.719
and you can actively manage it.

00:36:45.719 --> 00:36:50.619
The disadvantages, it doesn't consider what the objectives

00:36:50.619 --> 00:36:52.599
of the utility are, the risk

00:36:52.599 --> 00:36:53.599
or the uncertainty.

00:36:53.599 --> 00:36:56.690
So for example, if we simply have that benchmark and you

00:36:56.690 --> 00:36:58.639
know, set at the beginning of the

00:36:58.639 --> 00:37:04.059
year, even if the DME and EMO is actively managing that

00:37:04.059 --> 00:37:07.119
risk, if an event happens and

00:37:07.119 --> 00:37:10.960
prices go up, then it's going to be more costly to procure

00:37:10.960 --> 00:37:13.960
power and you may not be as accurately

00:37:13.960 --> 00:37:18.130
measuring the value that they're adding or how well they're

00:37:18.130 --> 00:37:19.960
managing those risks.

00:37:19.960 --> 00:37:23.210
So I think both of these have some advantages and they both

00:37:23.210 --> 00:37:24.840
have some flaws as well.

00:37:24.840 --> 00:37:27.059
So what we wanted to do next was then kind of look at the

00:37:27.059 --> 00:37:27.960
actual numbers.

00:37:27.960 --> 00:37:31.590
So we went back and recalculated the benchmarks and took

00:37:31.590 --> 00:37:34.079
the actual costs for the last fiscal

00:37:34.079 --> 00:37:36.519
year in order to calculate what the savings are.

00:37:36.519 --> 00:37:39.000
And similarly to what the news was the last time around,

00:37:39.000 --> 00:37:40.599
the good news is that under either

00:37:40.599 --> 00:37:43.360
benchmark there are savings.

00:37:43.360 --> 00:37:46.090
And so just to orient everybody to the slide, the top half

00:37:46.090 --> 00:37:47.519
is the calculation or the top

00:37:47.519 --> 00:37:50.239
third is the calculation of the benchmarks.

00:37:50.239 --> 00:37:53.380
And I'll come back to the one right there in the middle in

00:37:53.380 --> 00:37:54.119
a second.

00:37:54.119 --> 00:37:57.130
The middle of the slide is what the actual costs were as

00:37:57.130 --> 00:37:58.760
provided by DME and then the

00:37:58.760 --> 00:38:02.420
bottom third are the savings under each of the different

00:38:02.420 --> 00:38:03.300
options.

00:38:03.300 --> 00:38:07.280
So to kind of go back up to the top, that middle row here,

00:38:07.280 --> 00:38:09.320
what we did is we took option

00:38:09.320 --> 00:38:12.320
one, and as I mentioned before, about the three and a half

00:38:12.320 --> 00:38:13.840
heat rate adder, we simply

00:38:13.840 --> 00:38:17.300
took that out and said what would the day ahead benchmark

00:38:17.300 --> 00:38:18.760
have been if you didn't include

00:38:18.760 --> 00:38:22.719
that premium for risk and profit.

00:38:22.719 --> 00:38:26.500
And used that as just kind of another comparison or another

00:38:26.500 --> 00:38:28.280
alternative to look at.

00:38:28.280 --> 00:38:32.239
And as you can imagine, when you take that adder out, the

00:38:32.239 --> 00:38:34.400
savings on option one dropped

00:38:34.400 --> 00:38:37.539
from about 10.3 million to about 2.4.

00:38:37.539 --> 00:38:40.880
So the difference is purely related to that three and a

00:38:40.880 --> 00:38:42.420
half heat rate adder.

00:38:42.420 --> 00:38:46.179
And then when you compare that to the option two, which was

00:38:46.179 --> 00:38:48.239
the forward curve benchmark,

00:38:48.239 --> 00:38:54.539
the 10.3 savings under option one would have been $4

00:38:54.539 --> 00:38:55.800
million.

00:38:55.800 --> 00:38:57.679
So just a little bit over $4 million.

00:38:57.679 --> 00:39:01.920
So either way you look at it, there are savings relative to

00:39:01.920 --> 00:39:04.280
either of those benchmarks.

00:39:04.280 --> 00:39:05.280
So pause for a second.

00:39:05.280 --> 00:39:06.280
See if there are any questions.

00:39:06.280 --> 00:39:13.400
Okay.

00:39:13.400 --> 00:39:17.030
So I wanted to think about it a little bit differently for

00:39:17.030 --> 00:39:17.880
a second.

00:39:17.880 --> 00:39:22.420
And if we go back to what's the purpose of the cost savings

00:39:22.420 --> 00:39:24.719
calculation, is it simply

00:39:24.719 --> 00:39:25.719
to save costs?

00:39:25.719 --> 00:39:27.599
Is it to add value?

00:39:27.599 --> 00:39:30.409
So if you assume, and we talked to, Steve mentioned earlier

00:39:30.409 --> 00:39:31.780
, when we had conversations

00:39:31.780 --> 00:39:36.619
with staff, it was very clear that the objective was to

00:39:36.619 --> 00:39:40.800
manage the cost to end users, to customers.

00:39:40.800 --> 00:39:44.599
And so if you assume that in order to assess the

00:39:44.599 --> 00:39:48.000
performance and the value of DME, kind

00:39:48.000 --> 00:39:50.809
of what we think the benchmark calculation, this cost

00:39:50.809 --> 00:39:52.840
savings calculation is doing, well,

00:39:52.840 --> 00:39:55.139
then it probably makes a lot of sense to think about it in

00:39:55.139 --> 00:39:56.679
terms of what the desired outcomes

00:39:56.679 --> 00:40:02.050
are and how well DME and the EMO does achieving those

00:40:02.050 --> 00:40:03.480
outcomes.

00:40:03.480 --> 00:40:07.019
And so if we hypothesize a couple, what would be considered

00:40:07.019 --> 00:40:08.800
good outcomes, one might be

00:40:08.800 --> 00:40:12.320
stable electricity rates when prices rise.

00:40:12.320 --> 00:40:15.780
Another might be competitive and lower rates when prices

00:40:15.780 --> 00:40:16.320
fall.

00:40:16.320 --> 00:40:19.869
So in other words, if you're protecting your customers

00:40:19.869 --> 00:40:21.920
against rising prices, you don't

00:40:21.920 --> 00:40:25.750
want to be blind to the fact that prices might fall and now

00:40:25.750 --> 00:40:27.880
you're passing along a higher

00:40:27.880 --> 00:40:31.519
than market rate of electricity to your customers.

00:40:31.519 --> 00:40:36.320
So it's really managing the pair of those objectives.

00:40:36.320 --> 00:40:38.320
And so how do you go about accomplishing this?

00:40:38.320 --> 00:40:41.860
Well, one, you hypothesize a set of paired objectives and

00:40:41.860 --> 00:40:43.440
you make sure that they're

00:40:43.440 --> 00:40:44.440
market compatible.

00:40:44.440 --> 00:40:49.059
In other words, if I'm managing too aggressively to prevent

00:40:49.059 --> 00:40:51.519
higher prices, am I losing out

00:40:51.519 --> 00:40:55.530
on opportunities to pass along lower prices to my customers

00:40:55.530 --> 00:40:55.820
?

00:40:55.820 --> 00:40:58.550
And so the way that you make them market compatible is the

00:40:58.550 --> 00:41:00.599
second piece of this, which is by having

00:41:00.599 --> 00:41:03.809
a hedge strategy and risk limits that have been

00:41:03.809 --> 00:41:07.099
demonstrated to achieve those objectives.

00:41:07.099 --> 00:41:10.730
So you might do that by going back and looking over time

00:41:10.730 --> 00:41:12.960
and quantifying how a particular

00:41:12.960 --> 00:41:16.849
hedge strategy achieve those two objectives across a range

00:41:16.849 --> 00:41:18.199
of market prices.

00:41:18.199 --> 00:41:20.929
And the good news is that if we look back over the last 10

00:41:20.929 --> 00:41:22.320
to 15 years, we've got a

00:41:22.320 --> 00:41:25.519
number of times when prices were really high and they moved

00:41:25.519 --> 00:41:27.119
really low or they went from

00:41:27.119 --> 00:41:29.440
low to high and vice versa.

00:41:29.440 --> 00:41:32.530
So it gives you a lot of data with which to understand that

00:41:32.530 --> 00:41:32.800
.

00:41:32.800 --> 00:41:35.690
And then the last piece, the way that you accomplish this

00:41:35.690 --> 00:41:37.800
is by having the risk infrastructure.

00:41:37.800 --> 00:41:41.780
So the ability to capture transactions, understand,

00:41:41.780 --> 00:41:45.039
quantify your risk, monitor where you are,

00:41:45.039 --> 00:41:48.929
so that when the time comes, you know when to act and you

00:41:48.929 --> 00:41:50.239
know how to act.

00:41:50.239 --> 00:41:52.769
And so kind of taking it back to the benchmark, it's really

00:41:52.769 --> 00:41:54.199
the first two of these, one and

00:41:54.199 --> 00:42:00.989
two here, that would form the basis for the benchmark and

00:42:00.989 --> 00:42:04.599
how you assess performance.

00:42:04.599 --> 00:42:08.139
So the way that you do that is kind of taking it back to

00:42:08.139 --> 00:42:09.599
the objectives.

00:42:09.599 --> 00:42:12.599
And really, it's -- we talked about two, I guess it's

00:42:12.599 --> 00:42:14.320
really three of them, and I'll

00:42:14.320 --> 00:42:18.400
explain why in a second, but they kind of all work together

00:42:18.400 --> 00:42:20.559
in order to provide a balanced

00:42:20.559 --> 00:42:21.559
approach.

00:42:21.559 --> 00:42:24.780
So the first is setting an objective around what we call

00:42:24.780 --> 00:42:26.639
portfolio risk or managing the

00:42:26.639 --> 00:42:27.920
customer's rate of risk.

00:42:27.920 --> 00:42:31.699
So if we don't want to pass along more than a certain

00:42:31.699 --> 00:42:34.840
percentage rate increase to customers,

00:42:34.840 --> 00:42:37.239
how do we manage that?

00:42:37.239 --> 00:42:42.179
Recognizing that you're going to have a lot of fixed price

00:42:42.179 --> 00:42:44.480
supply and recognizing that

00:42:44.480 --> 00:42:47.360
you might hedge at really high prices and then prices fall.

00:42:47.360 --> 00:42:50.090
The second piece of it is managing the hedges that have

00:42:50.090 --> 00:42:51.019
been executed.

00:42:51.019 --> 00:42:55.579
So if I bought power at $80 and the price of power today is

00:42:55.579 --> 00:42:58.159
$50, what should I do about

00:42:58.159 --> 00:42:59.159
that?

00:42:59.159 --> 00:43:01.659
How do I manage that or how do I prevent that outcome from

00:43:01.659 --> 00:43:02.360
occurring?

00:43:02.360 --> 00:43:05.670
And then the way that you do that is by having an options

00:43:05.670 --> 00:43:07.679
budget available to manage the

00:43:07.679 --> 00:43:08.679
tension between the two.

00:43:08.679 --> 00:43:11.289
And so what we mean is that, you know, every hedge that I

00:43:11.289 --> 00:43:12.760
place to protect against higher

00:43:12.760 --> 00:43:16.599
prices creates a likelihood or a probability that I might

00:43:16.599 --> 00:43:17.920
have been wrong.

00:43:17.920 --> 00:43:24.110
So options are the way in which you can balance those

00:43:24.110 --> 00:43:25.920
things out.

00:43:25.920 --> 00:43:28.539
And so when, you know, when you kind of take it through

00:43:28.539 --> 00:43:30.440
that process in the end, you know,

00:43:30.440 --> 00:43:34.000
this is, if you will, the benchmarks that you establish.

00:43:34.000 --> 00:43:37.070
So I might have my--the first piece of my benchmark might

00:43:37.070 --> 00:43:38.440
be I'm going to manage my

00:43:38.440 --> 00:43:41.980
energy cost adjustment so that the cost of serve customers

00:43:41.980 --> 00:43:43.639
don't increase by more than

00:43:43.639 --> 00:43:47.550
X percent with some confidence, with some level of

00:43:47.550 --> 00:43:48.800
confidence.

00:43:48.800 --> 00:43:51.429
The second piece of it is I'm going to manage my fixed

00:43:51.429 --> 00:43:53.460
price transactions that so customer

00:43:53.460 --> 00:43:56.690
rates aren't more than X percent above whatever the market-

00:43:56.690 --> 00:43:57.679
based rate is.

00:43:57.679 --> 00:44:00.360
So that's the competitive objective.

00:44:00.360 --> 00:44:03.519
And then finally, I'm going to set aside, you know, $500,

00:44:03.519 --> 00:44:05.199
000 in options premiums to

00:44:05.199 --> 00:44:07.559
manage the tension between the two.

00:44:07.559 --> 00:44:10.840
And so you set these at the beginning of the year.

00:44:10.840 --> 00:44:13.449
Everybody--you know, there's general agreement as to what

00:44:13.449 --> 00:44:14.880
those limits are and what you're

00:44:14.880 --> 00:44:15.880
managing to.

00:44:15.880 --> 00:44:18.360
And at the end of the year, as you go back and you take a

00:44:18.360 --> 00:44:20.079
look at it, you can very clearly

00:44:20.079 --> 00:44:22.690
measure, "Well, this year, you know, I said I was going to

00:44:22.690 --> 00:44:23.960
manage to a 3 percent rate

00:44:23.960 --> 00:44:24.960
increase.

00:44:24.960 --> 00:44:28.050
I actually only had to pass along a 1 percent year over

00:44:28.050 --> 00:44:29.440
year rate increase.

00:44:29.440 --> 00:44:32.980
And here's why, because these are the activities that I did

00:44:32.980 --> 00:44:33.239
.

00:44:33.239 --> 00:44:36.449
Here's the outcomes that we realized as a function of them

00:44:36.449 --> 00:44:36.800
."

00:44:36.800 --> 00:44:39.079
In some years, it might be that prices fell.

00:44:39.079 --> 00:44:41.639
And so, you know, what you'll be able to say in that case

00:44:41.639 --> 00:44:43.239
is, "Well, the market fell by

00:44:43.239 --> 00:44:44.519
5 percent.

00:44:44.519 --> 00:44:47.590
And because I was actively managing my portfolio and my

00:44:47.590 --> 00:44:49.599
exposure, I was able to pass along

00:44:49.599 --> 00:44:55.000
4.5 percent of that 5 percent drop in market prices."

00:44:55.000 --> 00:44:58.820
And then you can also very clearly say, "I spent $200,000

00:44:58.820 --> 00:45:00.559
in options to do so, you know,

00:45:00.559 --> 00:45:03.039
less than the $500,000 that I budgeted at the beginning of

00:45:03.039 --> 00:45:03.599
the year."

00:45:03.599 --> 00:45:06.610
And so then each year, you'd come back and you'd reconsider

00:45:06.610 --> 00:45:08.280
these objectives, you'd reset

00:45:08.280 --> 00:45:10.420
the limits of what you're managing to, and at the end of

00:45:10.420 --> 00:45:11.760
the year, you can very clearly

00:45:11.760 --> 00:45:14.860
measure where you are relative to those objectives and

00:45:14.860 --> 00:45:15.880
those limits.

00:45:15.880 --> 00:45:19.690
And so this is the direction that we would recommend moving

00:45:19.690 --> 00:45:20.000
.

00:45:20.000 --> 00:45:24.539
You know, it's more -- it provides a very clear benchmark

00:45:24.539 --> 00:45:27.159
across multiple dimensions.

00:45:27.159 --> 00:45:30.239
It's -- you know, you can come to agreement on what those

00:45:30.239 --> 00:45:32.159
inputs are prior to the beginning

00:45:32.159 --> 00:45:35.260
of the year, and then you can very clearly measure them

00:45:35.260 --> 00:45:36.840
after the fact as well.

00:45:36.840 --> 00:45:43.320
Steve, anything you'd add?

00:45:43.320 --> 00:45:47.239
All right.

00:45:47.239 --> 00:45:51.489
So in terms of next steps, this is one that we had talked

00:45:51.489 --> 00:45:53.760
about at the last meeting we

00:45:53.760 --> 00:45:54.760
presented.

00:45:54.760 --> 00:45:57.570
I think if you -- you know, if you think about what the FY

00:45:57.570 --> 00:45:59.619
17 benchmark, you know, is now

00:45:59.619 --> 00:46:02.750
and what you -- the direction you might take it, maybe for

00:46:02.750 --> 00:46:04.599
FY18, this would be what we

00:46:04.599 --> 00:46:08.559
would recommend -- the process we would recommend going

00:46:08.559 --> 00:46:11.000
through in order to be able to come

00:46:11.000 --> 00:46:13.869
to agreement on what those objectives are and then set

00:46:13.869 --> 00:46:15.800
realistic and market-compatible

00:46:15.800 --> 00:46:16.960
risk limits.

00:46:16.960 --> 00:46:20.050
So it would be about understanding what the exposure of the

00:46:20.050 --> 00:46:21.639
current portfolio of supply

00:46:21.639 --> 00:46:25.809
and load is, understanding how different hedge strategies

00:46:25.809 --> 00:46:28.000
help you manage the exposure in

00:46:28.000 --> 00:46:32.000
supply and load, and then using that hedge strategy to set

00:46:32.000 --> 00:46:33.960
risk limits, update those

00:46:33.960 --> 00:46:38.260
objectives so that everybody, you know, has a known set of

00:46:38.260 --> 00:46:40.320
objectives and limits that

00:46:40.320 --> 00:46:45.079
they're managing to as you go into the next fiscal year.

00:46:45.079 --> 00:46:47.199
Okay.

00:46:47.199 --> 00:46:49.800
Discussion?

00:46:49.800 --> 00:46:54.139
Well, I just want to say I appreciate the board's indul

00:46:54.139 --> 00:46:57.639
gence for fairly detailed information.

00:46:57.639 --> 00:47:00.269
I also want to thank Stephen and Tim for all their work on

00:47:00.269 --> 00:47:01.440
this and our staff.

00:47:01.440 --> 00:47:04.050
They've been great to work with, very professional and

00:47:04.050 --> 00:47:05.800
comprehensive in their approach.

00:47:05.800 --> 00:47:08.090
We've got a number of things to bring back to the board and

00:47:08.090 --> 00:47:09.199
the City Council and talk

00:47:09.199 --> 00:47:10.199
about that.

00:47:10.199 --> 00:47:12.090
We're going to be doing that in pretty quick order, in

00:47:12.090 --> 00:47:13.599
particular on the governance issues.

00:47:13.599 --> 00:47:18.519
This is something on the management policy that we have.

00:47:18.519 --> 00:47:20.980
We created that back in 2014, but really hadn't had a

00:47:20.980 --> 00:47:22.559
discussion with the board or council

00:47:22.559 --> 00:47:23.559
since that time.

00:47:23.559 --> 00:47:26.429
So we want to have a good discussion of what's appropriate,

00:47:26.429 --> 00:47:28.019
what are the recommendations

00:47:28.019 --> 00:47:30.309
that we want to put in there, and then on at least an

00:47:30.309 --> 00:47:31.800
annual basis come back and talk

00:47:31.800 --> 00:47:34.840
about that every year of what do we need to tweak, what are

00:47:34.840 --> 00:47:36.280
areas that we can improve

00:47:36.280 --> 00:47:38.570
on and how can we manage that differently, and to keep that

00:47:38.570 --> 00:47:39.719
really front and center for

00:47:39.719 --> 00:47:41.480
both the board and the City Council.

00:47:41.480 --> 00:47:42.960
But we've got a lot of work to do.

00:47:42.960 --> 00:47:45.239
We'll be bringing this back in future meetings with you.

00:47:45.239 --> 00:47:48.260
Again, just want to say thank you for your time, and Tim

00:47:48.260 --> 00:47:50.039
and Stephen, thank you for all

00:47:50.039 --> 00:47:51.039
your work.

00:47:51.039 --> 00:47:54.039
Thank you.

00:47:54.039 --> 00:48:00.179
Just in terms of I'm thinking what's a good nutshell bumper

00:48:00.179 --> 00:48:02.880
sticker takeaway for me to

00:48:02.880 --> 00:48:09.440
explain to a layperson who doesn't have time to read all of

00:48:09.440 --> 00:48:10.480
this.

00:48:10.480 --> 00:48:15.380
And I haven't yet been asked, so what do you, by the public

00:48:15.380 --> 00:48:19.199
, what do you think of this report?

00:48:19.199 --> 00:48:21.739
And I just wanted to run by you what I was thinking of

00:48:21.739 --> 00:48:23.440
saying, and so you could let me

00:48:23.440 --> 00:48:28.760
know if this was a correct assessment or not.

00:48:28.760 --> 00:48:31.500
My sense, and I think this is a little different than what

00:48:31.500 --> 00:48:33.280
Susan's sense of it, but maybe this

00:48:33.280 --> 00:48:37.519
is just two sides of the same coin, I'm not sure.

00:48:37.519 --> 00:48:41.929
From reading the report and from hearing your presentation

00:48:41.929 --> 00:48:44.760
that this is not a diagnosis of

00:48:44.760 --> 00:48:46.400
a terminal illness, right?

00:48:46.400 --> 00:48:51.619
It's not, so this is not your, this is a sick organization

00:48:51.619 --> 00:48:54.480
and it's in serious trouble,

00:48:54.480 --> 00:48:59.340
but rather, and this is what I was planning on telling

00:48:59.340 --> 00:49:02.639
people if this is correct, rather,

00:49:02.639 --> 00:49:06.530
you're in pretty good health, but you don't have a doctor

00:49:06.530 --> 00:49:08.360
and you need a doctor and a

00:49:08.360 --> 00:49:13.000
health plan in place and you're very lucky that you've been

00:49:13.000 --> 00:49:15.199
doing well so far and we're

00:49:15.199 --> 00:49:19.500
going to be fine as long as we have these things in place

00:49:19.500 --> 00:49:20.840
that we need.

00:49:20.840 --> 00:49:24.469
And so anyway, is that, or if you would want to tweak that,

00:49:24.469 --> 00:49:26.280
I mean, I'm not interested

00:49:26.280 --> 00:49:27.800
in hearing that that's a good example.

00:49:27.800 --> 00:49:30.409
I'm just thinking is this right and if it's not, well, what

00:49:30.409 --> 00:49:31.760
would be good, you know, in

00:49:31.760 --> 00:49:34.940
one sentence, kind of analogy for somebody who really doesn

00:49:34.940 --> 00:49:36.320
't have the time to go into

00:49:36.320 --> 00:49:39.280
this at the level of detail that we do.

00:49:39.280 --> 00:49:41.889
I think it's a fair comment and, you know, in the doctor

00:49:41.889 --> 00:49:43.360
analogy, that's the kind of

00:49:43.360 --> 00:49:46.989
the governance and the policy infrastructure that needs a

00:49:46.989 --> 00:49:47.719
refresh.

00:49:47.719 --> 00:49:49.519
I think that's accurate.

00:49:49.519 --> 00:49:53.150
I think in general what I suggested, the assessment of the

00:49:53.150 --> 00:49:55.480
capabilities and then the benchmark

00:49:55.480 --> 00:50:00.070
discussion, they come together in terms of as an

00:50:00.070 --> 00:50:03.760
organization and as, you know, what

00:50:03.760 --> 00:50:07.840
are the objectives of DME as an organization through the

00:50:07.840 --> 00:50:10.280
city and what's the ultimate kind

00:50:10.280 --> 00:50:12.960
of metric or measurement of success.

00:50:12.960 --> 00:50:15.429
And if as an organization you can define that and that

00:50:15.429 --> 00:50:17.079
might be, you know, what are the

00:50:17.079 --> 00:50:20.619
rates that our citizens ultimately pay for electricity and

00:50:20.619 --> 00:50:22.159
there are other factors as

00:50:22.159 --> 00:50:24.489
well as where does that electricity come from and all those

00:50:24.489 --> 00:50:25.800
discussions around renewable

00:50:25.800 --> 00:50:27.360
are built into it as well.

00:50:27.360 --> 00:50:31.780
But I think gaining consensus on that ultimate objective

00:50:31.780 --> 00:50:34.800
can help then drive, you know, what's

00:50:34.800 --> 00:50:38.260
the framework within which we're going to expect the DME

00:50:38.260 --> 00:50:39.800
and the EMO to operate and

00:50:39.800 --> 00:50:43.019
as an aside, we started just talking about DME and then

00:50:43.019 --> 00:50:44.760
kind of this EMO is a separate

00:50:44.760 --> 00:50:47.000
entity I think should go away as a concept.

00:50:47.000 --> 00:50:51.480
I think it's all within, you know, the utility.

00:50:51.480 --> 00:50:55.380
If we can define the objective that will enable as a risk

00:50:55.380 --> 00:50:57.880
oversight function you to define

00:50:57.880 --> 00:51:00.739
what are the parameters within which they are going to

00:51:00.739 --> 00:51:02.360
operate and it also will help

00:51:02.360 --> 00:51:05.269
define how do we do and all those discussions kind of after

00:51:05.269 --> 00:51:06.760
the fact in the first part of

00:51:06.760 --> 00:51:10.309
the work that we did which is, you know, kind of digging

00:51:10.309 --> 00:51:12.280
into a calculation and you can

00:51:12.280 --> 00:51:15.449
always debate like the different variables that are used to

00:51:15.449 --> 00:51:16.679
do that calculation.

00:51:16.679 --> 00:51:20.219
Our recommendation to think about a performance-based

00:51:20.219 --> 00:51:23.480
benchmark is, you know, in some ways a departure

00:51:23.480 --> 00:51:26.500
from the cost-based benchmark that I think has been in

00:51:26.500 --> 00:51:28.320
place to date but maybe gets the

00:51:28.320 --> 00:51:31.389
organization back into the singular focus of we're trying

00:51:31.389 --> 00:51:32.840
to protect our rate payers

00:51:32.840 --> 00:51:35.849
and the citizens and they're not paying, you know, above a

00:51:35.849 --> 00:51:37.119
certain amount or that they

00:51:37.119 --> 00:51:41.369
can benefit from, you know, from market moves that are in

00:51:41.369 --> 00:51:42.400
our favor.

00:51:42.400 --> 00:51:47.309
I think that kind of as a goal post is the key takeaway for

00:51:47.309 --> 00:51:49.559
me and I think in order to

00:51:49.559 --> 00:51:52.670
get there, back to your question, the framework is there,

00:51:52.670 --> 00:51:54.599
the people are there, that, you

00:51:54.599 --> 00:51:57.960
know, it's kind of -- it's there.

00:51:57.960 --> 00:52:00.849
I think the goal is to identify what ultimately are we

00:52:00.849 --> 00:52:02.920
measuring and that will fill in some

00:52:02.920 --> 00:52:03.920
of the blanks.

00:52:03.920 --> 00:52:06.119
Very long-winded answer to your question.

00:52:06.119 --> 00:52:08.079
And, Deb, we're more in agreement than not.

00:52:08.079 --> 00:52:09.079
Yes.

00:52:09.079 --> 00:52:12.269
And I think I would just add one, you know, one piece to

00:52:12.269 --> 00:52:13.840
that and it's -- I don't think

00:52:13.840 --> 00:52:18.079
it's everything's your way or because you've been lucky.

00:52:18.079 --> 00:52:20.690
I think it's -- to date it's been a lot of individual, you

00:52:20.690 --> 00:52:22.039
know, a lot of individual

00:52:22.039 --> 00:52:24.849
effort and I think the governance recommendations I think

00:52:24.849 --> 00:52:26.760
will help make it less of an individual

00:52:26.760 --> 00:52:29.780
effort and more an organizational effort which I think will

00:52:29.780 --> 00:52:31.559
streamline and make that process

00:52:31.559 --> 00:52:37.280
easier and more transparent.

00:52:37.280 --> 00:52:42.190
We're lucky that we have the people who have been able to

00:52:42.190 --> 00:52:46.000
make these decisions on staff.

00:52:46.000 --> 00:52:48.960
That's all we have for you.

00:52:48.960 --> 00:52:49.960
All right.

00:52:49.960 --> 00:52:50.960
Thank you very much.

00:52:50.960 --> 00:52:51.960
Thank you.

00:52:51.960 --> 00:52:56.670
And I've been told that we are going to pull the closed

00:52:56.670 --> 00:52:59.199
meeting item and so that brings

00:52:59.199 --> 00:53:02.440
us down to the consent agenda and I've been asked to pull

00:53:02.440 --> 00:53:04.000
item B. That should -- oh, I'm

00:53:04.000 --> 00:53:05.000
sorry.

00:53:05.000 --> 00:53:06.000
Just curious how come we're pulling that.

00:53:06.000 --> 00:53:07.000
Larry, how come we're pulling the closed meeting?

00:53:07.000 --> 00:53:07.570
We can't put in a note, sir, so we decided years ago we'd

00:53:07.570 --> 00:53:08.000
take off those agendas.

00:53:08.000 --> 00:53:09.000
Okay.

00:53:09.000 --> 00:53:10.000
So it's a -- will be discussed by Council tomorrow?

00:53:10.000 --> 00:53:11.000
No.

00:53:11.000 --> 00:53:12.000
It's not.

00:53:12.000 --> 00:53:13.000
It's not.

00:53:13.000 --> 00:53:21.469
They're getting their -- they're going back to the old

00:53:21.469 --> 00:53:24.000
first.

00:53:24.000 --> 00:53:25.000
Thank you.

00:53:25.000 --> 00:53:26.000
Thank you.

00:53:26.000 --> 00:53:27.000
Okay.

00:53:27.000 --> 00:53:28.000
Consent agenda.

00:53:28.000 --> 00:53:30.039
Then we've been asked to pull item B off the consent agenda

00:53:30.039 --> 00:53:31.119
because that should have been

00:53:31.119 --> 00:53:34.039
an item for individual consideration.

00:53:34.039 --> 00:53:36.840
So that leaves one item A on the consent agenda.

00:53:36.840 --> 00:53:42.679
Does anybody wish to pull it?

00:53:42.679 --> 00:53:45.679
Or a motion to approve the consent agenda item A?

00:53:45.679 --> 00:53:47.679
I move.

00:53:47.679 --> 00:53:48.679
Okay.

00:53:48.679 --> 00:53:50.679
Do I have --

00:53:50.679 --> 00:53:51.679
Second.

00:53:51.679 --> 00:53:52.679
Okay.

00:53:52.679 --> 00:53:53.679
All in favor?

00:53:53.679 --> 00:53:54.679
Aye.

00:53:54.679 --> 00:53:55.679
Aye.

00:53:55.679 --> 00:53:56.679
Okay.

00:53:56.679 --> 00:53:57.679
Items for individual consideration.

00:53:57.679 --> 00:53:59.679
Should we take B first?

00:53:59.679 --> 00:54:00.880
Okay.

00:54:00.880 --> 00:54:08.420
So we'll be taking, well, the consent agenda item B. I don

00:54:08.420 --> 00:54:09.400
't know how to say it, so --

00:54:09.400 --> 00:54:10.400
All right.

00:54:10.400 --> 00:54:32.840
Tidistus, City Engineer.

00:54:32.840 --> 00:54:36.719
I've also got the project manager, Lee Perry, here.

00:54:36.719 --> 00:54:40.860
I'm bringing to you today a project that is currently on

00:54:40.860 --> 00:54:41.719
our CIP.

00:54:41.719 --> 00:54:45.320
It was a bond funded project, I believe.

00:54:45.320 --> 00:54:48.440
Pack four, phases one and two, you've actually seen before.

00:54:48.440 --> 00:54:51.309
We came last month and actually got council to -- and you

00:54:51.309 --> 00:54:52.840
all to award the contract to

00:54:52.840 --> 00:54:57.349
move forward with construction on that piece of the project

00:54:57.349 --> 00:54:57.679
.

00:54:57.679 --> 00:55:01.159
Ultimately, this was all supposed to be one project.

00:55:01.159 --> 00:55:04.789
But for a lot of different reasons, funding being one piece

00:55:04.789 --> 00:55:06.480
of it, we were -- we weren't

00:55:06.480 --> 00:55:09.360
able to do all of that project at one time.

00:55:09.360 --> 00:55:12.130
Time has just not been our friend on some of these projects

00:55:12.130 --> 00:55:12.400
.

00:55:12.400 --> 00:55:16.119
So what we have today is the second phase of that project

00:55:16.119 --> 00:55:18.320
asking for the design contract

00:55:18.320 --> 00:55:20.559
to go forward.

00:55:20.559 --> 00:55:26.360
So this project in general -- let me go back a little bit

00:55:26.360 --> 00:55:27.320
here.

00:55:27.320 --> 00:55:29.719
It's a project that, like I said before, connects to the

00:55:29.719 --> 00:55:31.960
project that's currently going to construction.

00:55:31.960 --> 00:55:34.500
It'll start construction shortly after the first of the

00:55:34.500 --> 00:55:36.000
year, which runs primarily through

00:55:36.000 --> 00:55:37.000
downtown.

00:55:37.000 --> 00:55:39.219
And let's skip past a couple of slides here and get to the

00:55:39.219 --> 00:55:39.559
map.

00:55:39.559 --> 00:55:41.920
It's a little easier to follow.

00:55:41.920 --> 00:55:45.949
So phases one and two, the creek itself, peck four, Pecan

00:55:45.949 --> 00:55:48.159
Creek, tributary four is what

00:55:48.159 --> 00:55:50.519
that really stands for.

00:55:50.519 --> 00:55:54.150
Ties into Pecan Creek, a little bit off the screen here,

00:55:54.150 --> 00:55:56.079
comes up, crosses Locust and

00:55:56.079 --> 00:55:58.159
Elm and then follows to the north.

00:55:58.159 --> 00:56:01.699
And the creek itself actually runs through a couple of

00:56:01.699 --> 00:56:03.519
channels up north of Oak.

00:56:03.519 --> 00:56:09.599
No, we didn't make it that far, sorry.

00:56:09.599 --> 00:56:12.210
Up to Mulberry and then it goes just north of Mulberry,

00:56:12.210 --> 00:56:13.679
comes back across Carroll and

00:56:13.679 --> 00:56:16.920
all the way back over through this neighborhood.

00:56:16.920 --> 00:56:19.320
Is that Prairie Street?

00:56:19.320 --> 00:56:20.320
Bernard, sorry.

00:56:20.320 --> 00:56:24.400
It gets all the way back over to Bernard.

00:56:24.400 --> 00:56:27.130
Part of what happens here, and you don't see it on this map

00:56:27.130 --> 00:56:28.760
, is there is a floodplain that

00:56:28.760 --> 00:56:32.760
takes in a very large amount of this entire area, trying to

00:56:32.760 --> 00:56:34.480
outline it here as best I

00:56:34.480 --> 00:56:37.000
can so you can get a sense of the area.

00:56:37.000 --> 00:56:39.730
It takes into account a very large area of downtown and it

00:56:39.730 --> 00:56:41.079
inundates quite a few homes

00:56:41.079 --> 00:56:44.389
in the neighborhood back to the west of Carroll, this area

00:56:44.389 --> 00:56:45.400
back in here.

00:56:45.400 --> 00:56:48.800
So a lot of homes drain into this creek.

00:56:48.800 --> 00:56:51.320
What this project will do is it will remove a good number

00:56:51.320 --> 00:56:52.599
of those homes, I think all

00:56:52.599 --> 00:56:55.059
of the homes out of the floodplain, and then it removes the

00:56:55.059 --> 00:56:56.539
vast majority of the businesses

00:56:56.539 --> 00:56:59.630
out of the floodplain by taking everything into a box

00:56:59.630 --> 00:57:01.800
instead of it being an open channel.

00:57:01.800 --> 00:57:04.690
It brings it into a box so all those buildings, all the

00:57:04.690 --> 00:57:07.039
vacant land that's there for development

00:57:07.039 --> 00:57:10.679
in the downtown area on that south side is now available to

00:57:10.679 --> 00:57:11.800
be developed.

00:57:11.800 --> 00:57:13.739
We can do a lot more with it since it will be out of the

00:57:13.739 --> 00:57:15.079
floodplain and the floodway.

00:57:15.079 --> 00:57:17.599
The floodway is the key factor there.

00:57:17.599 --> 00:57:20.329
On the map there is a floodway, the FEMA map today, there's

00:57:20.329 --> 00:57:21.440
a floodway that runs through

00:57:21.440 --> 00:57:23.880
downtown, prevents a lot of development.

00:57:23.880 --> 00:57:26.880
Not put a structure in the floodway.

00:57:26.880 --> 00:57:30.769
So what this project does, phase one and phase two, is this

00:57:30.769 --> 00:57:32.320
green and blue line.

00:57:32.320 --> 00:57:35.260
That is ongoing right now, we'll be going to construction

00:57:35.260 --> 00:57:35.719
soon.

00:57:35.719 --> 00:57:38.159
Phase three and four, there's a couple of lines here.

00:57:38.159 --> 00:57:41.469
This yellow line is the original projection of phase three

00:57:41.469 --> 00:57:43.360
and phase four goes from Carroll

00:57:43.360 --> 00:57:46.300
back to the west to tie into the open channel just through

00:57:46.300 --> 00:57:47.599
this neighborhood.

00:57:47.599 --> 00:57:49.820
Now this, it's kind of a misnomer through here, I believe

00:57:49.820 --> 00:57:51.039
this is just a little drainage

00:57:51.039 --> 00:57:54.400
ditch, is that correct?

00:57:54.400 --> 00:58:03.679
That picks that up.

00:58:03.679 --> 00:58:06.329
It's a bit of a channel, but it is out of the floodplain by

00:58:06.329 --> 00:58:07.760
the time we get in there.

00:58:07.760 --> 00:58:11.139
So what we're looking to do with this project, and you'll

00:58:11.139 --> 00:58:13.159
see a dashed purple line here.

00:58:13.159 --> 00:58:16.050
As we originally looked at this project, it was remove the

00:58:16.050 --> 00:58:17.719
floodplain, putting the boxes

00:58:17.719 --> 00:58:20.969
in underneath the road, which is a lot easier for us to

00:58:20.969 --> 00:58:23.079
access because you know you're not

00:58:23.079 --> 00:58:25.110
going to get buildings, you're not going to get a lot of

00:58:25.110 --> 00:58:26.519
structures or homes or businesses

00:58:26.519 --> 00:58:28.360
that we got to interrupt to get in there.

00:58:28.360 --> 00:58:31.130
It's bad enough to interrupt traffic, we definitely don't

00:58:31.130 --> 00:58:32.960
want to do that on private property.

00:58:32.960 --> 00:58:35.730
The problem we're running into is you still have what's

00:58:35.730 --> 00:58:37.440
left of this channel that we can't

00:58:37.440 --> 00:58:40.440
completely take away because you still have to allow those

00:58:40.440 --> 00:58:42.300
homes and those businesses that

00:58:42.300 --> 00:58:45.139
have traditionally not had anywhere to drain other than

00:58:45.139 --> 00:58:46.920
that creek, we can't completely

00:58:46.920 --> 00:58:47.920
take it away.

00:58:47.920 --> 00:58:50.750
So we're still going to catch that water in this channel

00:58:50.750 --> 00:58:52.360
left on the north side here.

00:58:52.360 --> 00:58:55.420
So an alternative proposal, and that's part of the reason

00:58:55.420 --> 00:58:57.400
why the contract for basic services

00:58:57.400 --> 00:59:01.860
is just over $900,000, is to look at both the yellow ph

00:59:01.860 --> 00:59:04.000
asing and the purple to say that

00:59:04.000 --> 00:59:07.650
may be a better alignment from the standpoint that it still

00:59:07.650 --> 00:59:10.119
provides a lot better and potentially

00:59:10.119 --> 00:59:13.800
a lot less construction cost to us by leaving this drainage

00:59:13.800 --> 00:59:15.519
channel in place as much as

00:59:15.519 --> 00:59:17.000
possible.

00:59:17.000 --> 00:59:19.989
By the time we take the vast majority of the floodplain out

00:59:19.989 --> 00:59:21.559
, this really just becomes a

00:59:21.559 --> 00:59:22.800
little collector ditch.

00:59:22.800 --> 00:59:25.760
It's not a floodplain prone area.

00:59:25.760 --> 00:59:28.280
So that's why you see these two alternatives here.

00:59:28.280 --> 00:59:30.829
It's also partially why you see a little bit higher

00:59:30.829 --> 00:59:32.840
contract cost than we potentially would

00:59:32.840 --> 00:59:34.119
have seen.

00:59:34.119 --> 00:59:37.469
We also have, I need to go backwards, we got our slides a

00:59:37.469 --> 00:59:39.320
little bit out of order, I'm

00:59:39.320 --> 00:59:41.619
sorry about that.

00:59:41.619 --> 00:59:44.840
Some project costs as we estimate right now are looking at

00:59:44.840 --> 00:59:47.079
1.2 million for design, which

00:59:47.079 --> 00:59:49.639
is what you have before you right now.

00:59:49.639 --> 00:59:51.360
That takes into account quite a few items.

00:59:51.360 --> 00:59:55.059
Now if you look at what that really runs on a project that

00:59:55.059 --> 00:59:57.019
's not that unusual to see it

00:59:57.019 --> 01:00:01.010
running in the 10 to 12% range, when you also consider that

01:00:01.010 --> 01:00:03.320
there's a lot of potential properties,

01:00:03.320 --> 01:00:05.519
there's a couple of different scenarios we need to look at.

01:00:05.519 --> 01:00:07.980
And we've got some construction costs or construction

01:00:07.980 --> 01:00:09.480
administration services built

01:00:09.480 --> 01:00:10.480
into that contract.

01:00:10.480 --> 01:00:12.920
So the consultant will be working with us hand in hand

01:00:12.920 --> 01:00:14.519
through the construction phase

01:00:14.519 --> 01:00:18.000
to make sure this project gets done timely and effectively.

01:00:18.000 --> 01:00:21.539
A little bit spent on that will usually, by and large, save

01:00:21.539 --> 01:00:23.000
you quite a bit during the

01:00:23.000 --> 01:00:25.280
construction phase.

01:00:25.280 --> 01:00:28.469
We are looking at potentially $300,000 in property acquis

01:00:28.469 --> 01:00:29.000
itions.

01:00:29.000 --> 01:00:30.440
That's that purple line that you saw.

01:00:30.440 --> 01:00:32.199
We're meant to continue to get some easements.

01:00:32.199 --> 01:00:36.099
We are working with the county to try to get some

01:00:36.099 --> 01:00:38.920
additional aid and help there.

01:00:38.920 --> 01:00:41.530
And then the construction costs right now are currently

01:00:41.530 --> 01:00:43.280
projected at $9.3 million.

01:00:43.280 --> 01:00:44.940
So it's an expensive box.

01:00:44.940 --> 01:00:48.340
Anytime you start putting boxes of this size in, they're

01:00:48.340 --> 01:00:49.699
always expensive.

01:00:49.699 --> 01:00:51.400
We are going through the process.

01:00:51.400 --> 01:00:53.920
What's in that number is a contingency factor.

01:00:53.920 --> 01:00:56.320
So we're trying to give you the worst case scenario of what

01:00:56.320 --> 01:00:57.360
we think this is going to

01:00:57.360 --> 01:00:58.360
be.

01:00:58.360 --> 01:01:01.480
Of course, we will analyze all options to try to keep that

01:01:01.480 --> 01:01:03.320
cost down as much as possible.

01:01:03.320 --> 01:01:07.559
We are proposing to have Fris and Nichols, who did the

01:01:07.559 --> 01:01:10.019
design for phases one and two,

01:01:10.019 --> 01:01:13.309
they picked up where T. Nolan Perkins did the study for the

01:01:13.309 --> 01:01:14.760
entire street stretch of

01:01:14.760 --> 01:01:16.559
this creek.

01:01:16.559 --> 01:01:19.699
They picked up and did the design for the PEK4 phase one

01:01:19.699 --> 01:01:21.260
and two construction.

01:01:21.260 --> 01:01:23.659
So that is part of the reason why we selected them for

01:01:23.659 --> 01:01:25.559
three and four, is it's just a natural

01:01:25.559 --> 01:01:26.719
extension of this project.

01:01:26.719 --> 01:01:29.139
So instead of getting somebody else on board which would

01:01:29.139 --> 01:01:30.880
have taken longer, we'd potentially

01:01:30.880 --> 01:01:33.659
have some conflicts between the two, just trying to get

01:01:33.659 --> 01:01:35.360
them to marry up their designs.

01:01:35.360 --> 01:01:38.119
It kept this in one shop and kept it moving forward.

01:01:38.119 --> 01:01:39.119
They were very qualified.

01:01:39.119 --> 01:01:42.329
We used them on multiple occasions and they are known

01:01:42.329 --> 01:01:44.559
throughout the state for this type

01:01:44.559 --> 01:01:47.559
of work and more.

01:01:47.559 --> 01:01:50.719
We ran through quite a bit of that.

01:01:50.719 --> 01:01:53.840
So our recommendation is that we would ask you to approve

01:01:53.840 --> 01:01:55.440
this contract or recommend

01:01:55.440 --> 01:01:58.349
approval to counsel this contract for $1.2 million with Fr

01:01:58.349 --> 01:01:59.239
is and Nichols.

01:01:59.239 --> 01:02:01.460
If you have any questions, I'm here to answer any questions

01:02:01.460 --> 01:02:02.159
you might have.

01:02:02.159 --> 01:02:05.159
I'm going to leave Perry's here as well.

01:02:05.159 --> 01:02:06.159
Yes sir.

01:02:06.159 --> 01:02:11.650
So the way I see this is by doing this, you talk about

01:02:11.650 --> 01:02:14.480
removing the floodplain.

01:02:14.480 --> 01:02:18.400
Which allows land to be developed.

01:02:18.400 --> 01:02:20.670
So you have the cost side, but now you're going to have a

01:02:20.670 --> 01:02:21.400
revenue side.

01:02:21.400 --> 01:02:25.190
Because then with the developed land, you'll have increased

01:02:25.190 --> 01:02:26.440
property taxes.

01:02:26.440 --> 01:02:30.710
You'll be able to basically pay for over time the cost of

01:02:30.710 --> 01:02:31.920
doing this.

01:02:31.920 --> 01:02:35.760
And to the homeowners, it would seem like if they can even

01:02:35.760 --> 01:02:38.039
get insurance, their insurance

01:02:38.039 --> 01:02:40.389
cost, at least in that area, is going to go down because

01:02:40.389 --> 01:02:41.719
they're not being paid enough

01:02:41.719 --> 01:02:42.719
floodplain.

01:02:42.719 --> 01:02:43.719
Yes sir.

01:02:43.719 --> 01:02:44.719
So a lot of benefits for all of this.

01:02:44.719 --> 01:02:47.449
It also improves our rating standing with the Federal

01:02:47.449 --> 01:02:49.159
Emergency Management Agency.

01:02:49.159 --> 01:02:50.159
Okay.

01:02:50.159 --> 01:02:51.159
Thank you.

01:02:51.159 --> 01:02:52.159
Go ahead, Dan.

01:02:52.159 --> 01:02:55.159
I just want to clarify the construction costs.

01:02:55.159 --> 01:02:56.159
Yes sir.

01:02:56.159 --> 01:02:59.079
So is this, they've been approved or not approved?

01:02:59.079 --> 01:03:00.519
For this project, no.

01:03:00.519 --> 01:03:01.519
This is three and four.

01:03:01.519 --> 01:03:03.239
For phase one and two, yes.

01:03:03.239 --> 01:03:04.239
That contract asks.

01:03:04.239 --> 01:03:09.280
So you're going to present these in the 2020 bond package?

01:03:09.280 --> 01:03:12.159
Unless we can find other sources of funding, yes sir.

01:03:12.159 --> 01:03:15.320
We're constantly looking for other ways to fund this work.

01:03:15.320 --> 01:03:18.050
Grants, wherever we can find out their partnerships, we're

01:03:18.050 --> 01:03:19.159
constantly looking.

01:03:19.159 --> 01:03:22.190
But yes, right now the only source of funding we know of

01:03:22.190 --> 01:03:24.519
would be a 2020 debt program.

01:03:24.519 --> 01:03:28.409
So Derek, the one and two, the phase one and two was

01:03:28.409 --> 01:03:31.039
supposed to do the same things that

01:03:31.039 --> 01:03:32.880
you're saying the three and four is doing.

01:03:32.880 --> 01:03:33.880
Yes.

01:03:33.880 --> 01:03:36.380
So when did we realize that one and two wasn't going to do

01:03:36.380 --> 01:03:37.840
exactly what we thought it was

01:03:37.840 --> 01:03:38.840
going to be?

01:03:38.840 --> 01:03:40.880
I'm not sure how far back that history goes.

01:03:40.880 --> 01:03:43.159
I know when I got here in July, we went through and started

01:03:43.159 --> 01:03:44.760
going through every single project

01:03:44.760 --> 01:03:48.719
to look on how far they can go.

01:03:48.719 --> 01:03:50.719
And this was one of the first ones we looked at and said, "

01:03:50.719 --> 01:03:51.800
We're not going to get that

01:03:51.800 --> 01:03:52.800
far."

01:03:52.800 --> 01:03:55.170
I knew that, but to answer your question on how far back

01:03:55.170 --> 01:03:56.440
that went, I don't know.

01:03:56.440 --> 01:03:57.440
Okay.

01:03:57.440 --> 01:03:58.440
Okay.

01:03:58.440 --> 01:03:59.440
Thank you.

01:03:59.440 --> 01:04:00.440
Deb, did you have a question?

01:04:00.440 --> 01:04:01.440
Oh yes, I did.

01:04:01.440 --> 01:04:04.579
Well first I wanted to say thank you for this and thanks

01:04:04.579 --> 01:04:06.639
for pulling this from the consent

01:04:06.639 --> 01:04:07.639
agenda.

01:04:07.639 --> 01:04:10.250
I was going to ask to have it pulled and I was already

01:04:10.250 --> 01:04:11.800
planning on voting yes for it,

01:04:11.800 --> 01:04:14.530
but because of the cost, but also because it's such an

01:04:14.530 --> 01:04:16.159
important and timely issue.

01:04:16.159 --> 01:04:20.329
And I think it's important that the public see what the

01:04:20.329 --> 01:04:23.559
city is doing for flood preparedness.

01:04:23.559 --> 01:04:24.559
Yes.

01:04:24.559 --> 01:04:27.789
As most of you probably saw, there was a recent article in

01:04:27.789 --> 01:04:29.880
the Denton Record Chronicle about

01:04:29.880 --> 01:04:34.150
flood preparedness in Denton and a lot of people in the

01:04:34.150 --> 01:04:37.199
community were expressing concerns

01:04:37.199 --> 01:04:38.199
about that.

01:04:38.199 --> 01:04:41.170
So it's really reassuring to see that we have such plans in

01:04:41.170 --> 01:04:42.599
place moving forward.

01:04:42.599 --> 01:04:46.829
And it is a big expense, but it is extremely important as

01:04:46.829 --> 01:04:48.960
Alan was saying in all kinds

01:04:48.960 --> 01:04:54.989
of ways and in addition to the ways that Alan said it, save

01:04:54.989 --> 01:04:57.599
lives and save homes.

01:04:57.599 --> 01:05:04.659
And my question was, how is this plan connected to, or is

01:05:04.659 --> 01:05:08.639
this plan connected to a larger

01:05:08.639 --> 01:05:13.460
city-wide flood preparedness plan moving forward as

01:05:13.460 --> 01:05:17.559
considering all the growth that we're having

01:05:17.559 --> 01:05:22.030
in other parts of town, for instance around Bucky, the B

01:05:22.030 --> 01:05:24.320
ucky's area there was a lot of

01:05:24.320 --> 01:05:28.440
concern about the drainage of the homes around there.

01:05:28.440 --> 01:05:34.599
Is this tied into a larger plan for flood preparedness city

01:05:34.599 --> 01:05:37.480
-wide or is that something

01:05:37.480 --> 01:05:42.400
that would be created at a later date?

01:05:42.400 --> 01:05:44.800
It is something that we're working on and developing.

01:05:44.800 --> 01:05:48.429
It is one of those key components that after the 2007

01:05:48.429 --> 01:05:50.440
floods that this was one of those

01:05:50.440 --> 01:05:54.739
areas that was identified real quickly that it was an issue

01:05:54.739 --> 01:05:55.079
.

01:05:55.079 --> 01:05:57.710
So yes, you have some revenue benefits on this, but the

01:05:57.710 --> 01:05:59.039
primary cause of this was a

01:05:59.039 --> 01:06:02.079
safety project and that's where this comes from.

01:06:02.079 --> 01:06:04.719
We are looking at all of our floodplains.

01:06:04.719 --> 01:06:06.400
We are required to do so annually.

01:06:06.400 --> 01:06:10.570
We are in a, because we are members of the community rating

01:06:10.570 --> 01:06:12.519
system with FEMA, we have

01:06:12.519 --> 01:06:15.320
to go through an annual audit process.

01:06:15.320 --> 01:06:18.489
And usually the five-year audit, because a five-year is a

01:06:18.489 --> 01:06:20.480
very detailed audit of everything

01:06:20.480 --> 01:06:23.349
we've done from a permitting standpoint with developers,

01:06:23.349 --> 01:06:24.920
with homeowners that have come

01:06:24.920 --> 01:06:27.800
in, they're wanting to build a brand new home.

01:06:27.800 --> 01:06:30.409
And on an annual basis, we just do a double check, make

01:06:30.409 --> 01:06:32.079
sure are we still doing everything

01:06:32.079 --> 01:06:33.199
that we thought we would do?

01:06:33.199 --> 01:06:35.829
And it requires us to look forward on what are we going to

01:06:35.829 --> 01:06:37.400
do over the next five years.

01:06:37.400 --> 01:06:40.619
So yes, this is a part of that plan, but it's an ongoing

01:06:40.619 --> 01:06:42.440
process for us of what needs to

01:06:42.440 --> 01:06:43.440
be done next.

01:06:43.440 --> 01:06:44.440
Yes, ma'am.

01:06:44.440 --> 01:06:46.960
Okay, any further questions?

01:06:46.960 --> 01:06:55.800
Do we have a motion to approve?

01:06:55.800 --> 01:06:56.800
And a second?

01:06:56.800 --> 01:06:57.800
Second.

01:06:57.800 --> 01:06:59.800
All in favor?

01:06:59.800 --> 01:07:00.800
Aye.

01:07:00.800 --> 01:07:02.800
Any further discussion?

01:07:02.800 --> 01:07:07.039
Let's see, then.

01:07:07.039 --> 01:07:10.349
Item A, consider the approval of the public utility board's

01:07:10.349 --> 01:07:11.079
minutes.

01:07:11.079 --> 01:07:16.639
Were there any changes that anybody saw?

01:07:16.639 --> 01:07:22.559
Okay, then it's approved as presented.

01:07:22.559 --> 01:07:27.730
And item for individual consideration B, receive a report

01:07:27.730 --> 01:07:30.920
and discussion, hold a discussion

01:07:30.920 --> 01:07:33.530
and provide staff direction concerning the approval of a

01:07:33.530 --> 01:07:34.960
contract for the radio network

01:07:34.960 --> 01:07:41.800
design and installation services.

01:07:41.800 --> 01:07:42.800
Good morning.

01:07:42.800 --> 01:07:43.800
My name is Tim Fisher.

01:07:43.800 --> 01:07:45.280
I'm director of water utilities.

01:07:45.280 --> 01:07:51.360
I've got a brief presentation on this project.

01:07:51.360 --> 01:07:55.590
The water production division uses licensed and unlicensed

01:07:55.590 --> 01:07:58.320
microwave radios for communications

01:07:58.320 --> 01:08:00.800
between their various facilities.

01:08:00.800 --> 01:08:05.280
Some of those are permanent or are staff 24/7, others are

01:08:05.280 --> 01:08:06.360
unstaffed.

01:08:06.360 --> 01:08:09.579
We use that communication system for the supervisory

01:08:09.579 --> 01:08:12.480
control and data acquisition or SCADA system,

01:08:12.480 --> 01:08:16.439
but we also use them for the security cameras and then for

01:08:16.439 --> 01:08:17.880
access control.

01:08:17.880 --> 01:08:22.779
The existing system tended to center around the northwest

01:08:22.779 --> 01:08:25.319
elevated storage tank up near

01:08:25.319 --> 01:08:32.399
loop 288 and interstate 35 on the northwest side of TAN.

01:08:32.399 --> 01:08:35.300
That tower was our highest tower and gave us the best line

01:08:35.300 --> 01:08:36.760
of sight to all the various

01:08:36.760 --> 01:08:41.770
locations until recently when we added the elevated storage

01:08:41.770 --> 01:08:44.479
at the southwest upper pressure

01:08:44.479 --> 01:08:50.079
plain, so that's a similar height location.

01:08:50.079 --> 01:08:55.720
Basically this is a shot of the northwest tower.

01:08:55.720 --> 01:08:58.960
Radio equipment is very small, compact.

01:08:58.960 --> 01:09:03.380
It's not real visible unless you look hard for it.

01:09:03.380 --> 01:09:08.279
Very directional from point to point.

01:09:08.279 --> 01:09:11.819
Arcadis Engineering, which is actually at the time was

01:09:11.819 --> 01:09:14.000
Malcolm Kearney, Arcadis later

01:09:14.000 --> 01:09:18.159
bought them out, did a SCADA master plan for us in 2012.

01:09:18.159 --> 01:09:22.000
One of the purposes of that study was to give us some

01:09:22.000 --> 01:09:25.399
assistance in how we sustain, maintain,

01:09:25.399 --> 01:09:29.670
and improve that system and then also how to budget for

01:09:29.670 --> 01:09:31.439
capital projects.

01:09:31.439 --> 01:09:36.090
A critical component of this was trying to develop improved

01:09:36.090 --> 01:09:39.159
reliability through redundancy.

01:09:39.159 --> 01:09:45.390
This is basically a redundant radio based system and a plan

01:09:45.390 --> 01:09:45.819
.

01:09:45.819 --> 01:09:48.119
This is the existing system.

01:09:48.119 --> 01:09:54.060
It all tends to direct its signal to northwest and then to

01:09:54.060 --> 01:09:58.039
each one of the various locations.

01:09:58.039 --> 01:10:02.239
The revised system will basically add a duplication in

01:10:02.239 --> 01:10:05.520
pathways and provide the redundancy that

01:10:05.520 --> 01:10:09.159
we're looking for reliability.

01:10:09.159 --> 01:10:14.220
So that helps us eliminate a single point of failure and

01:10:14.220 --> 01:10:17.560
gives us additional redundancy.

01:10:17.560 --> 01:10:21.600
We're proposing to use Johnson Technical Services.

01:10:21.600 --> 01:10:26.579
They're a Dallas-Fort Worth based area, a radio network

01:10:26.579 --> 01:10:27.800
provider.

01:10:27.800 --> 01:10:32.399
They are used by Denton County, DISD, City of Denton.

01:10:32.399 --> 01:10:35.159
They're also I think used by the Upper Trinity recently.

01:10:35.159 --> 01:10:37.479
They had a fiber based system.

01:10:37.479 --> 01:10:41.840
They were getting fiber cuts so they went to a radio based

01:10:41.840 --> 01:10:43.319
backup system.

01:10:43.319 --> 01:10:46.399
Project budget was 220.

01:10:46.399 --> 01:10:50.119
This is being procured through a Texas Department of

01:10:50.119 --> 01:10:53.560
Information Resources contracting mechanism

01:10:53.560 --> 01:10:57.100
very similar to a buy board so it meets the legal

01:10:57.100 --> 01:10:59.359
requirements for bidding.

01:10:59.359 --> 01:11:03.640
And with that I'll answer any questions that you might have

01:11:03.640 --> 01:11:03.960
.

01:11:03.960 --> 01:11:07.500
Is the water service or is that the only communication that

01:11:07.500 --> 01:11:08.720
happens on this?

01:11:08.720 --> 01:11:13.319
It is specific to the water department's needs, yes sir.

01:11:13.319 --> 01:11:17.960
And it's very focused on the security camera systems that

01:11:17.960 --> 01:11:18.880
we have.

01:11:18.880 --> 01:11:21.920
That was one of the bigger bandwidth issues that we needed.

01:11:21.920 --> 01:11:25.159
But then also for the control system.

01:11:25.159 --> 01:11:31.210
Some of our pump stations have supervisor decisions turn

01:11:31.210 --> 01:11:34.079
pumps on and off as opposed

01:11:34.079 --> 01:11:35.079
to having things automated.

01:11:35.079 --> 01:11:38.710
So those are run at the two treatment plants where we have

01:11:38.710 --> 01:11:40.680
staff and operations staff.

01:11:40.680 --> 01:11:42.479
Thank you.

01:11:42.479 --> 01:11:45.720
Any further questions?

01:11:45.720 --> 01:11:47.960
Move approval.

01:11:47.960 --> 01:11:48.960
Okay.

01:11:48.960 --> 01:11:51.960
Motion to approve.

01:11:51.960 --> 01:11:52.960
Move.

01:11:52.960 --> 01:11:54.680
Oh, he moved.

01:11:54.680 --> 01:11:55.680
We need a second.

01:11:55.680 --> 01:11:56.680
I'm sorry.

01:11:56.680 --> 01:11:57.680
All in favor?

01:11:57.680 --> 01:11:58.680
Aye.

01:11:58.680 --> 01:11:59.680
Okay.

01:11:59.680 --> 01:12:00.680
Thank you.

01:12:00.680 --> 01:12:01.680
Thank you.

01:12:01.680 --> 01:12:02.680
ACM, you're on, Maureen.

01:12:02.680 --> 01:12:03.680
All right.

01:12:03.680 --> 01:12:04.680
Thank you.

01:12:04.680 --> 01:12:12.090
Members of the board, in your packet there is a memorandum

01:12:12.090 --> 01:12:14.960
from George Morrow.

01:12:14.960 --> 01:12:18.350
He's our new general manager of DME and here to provide you

01:12:18.350 --> 01:12:20.079
with information about the

01:12:20.079 --> 01:12:21.359
Tesla roof tiles.

01:12:21.359 --> 01:12:24.430
If you have any specific questions related to what's in the

01:12:24.430 --> 01:12:26.039
memorandum, George is here

01:12:26.039 --> 01:12:28.039
to answer those questions if you have them.

01:12:28.039 --> 01:12:30.430
I'm just so surprised with all the roofs that had to be

01:12:30.430 --> 01:12:32.000
replaced that nobody replaced it

01:12:32.000 --> 01:12:37.800
with a solar roof.

01:12:37.800 --> 01:12:41.520
As far as, oh, I'm sorry.

01:12:41.520 --> 01:12:45.449
I would just like to just to say welcome to George and we

01:12:45.449 --> 01:12:47.640
're so happy to have you here.

01:12:47.640 --> 01:12:52.539
Yeah, if you wouldn't mind saying a little something to us

01:12:52.539 --> 01:12:54.880
and to the public about this

01:12:54.880 --> 01:12:57.880
memo.

01:12:57.880 --> 01:13:01.159
Thank you for that opportunity, George Morrow, general

01:13:01.159 --> 01:13:02.239
manager of DME.

01:13:02.239 --> 01:13:05.640
Yeah, I'm very happy to be here in Denton.

01:13:05.640 --> 01:13:07.119
This is the start of my third week.

01:13:07.119 --> 01:13:10.239
I'm fighting down the urge to think I know everything

01:13:10.239 --> 01:13:12.399
already because every day I learn,

01:13:12.399 --> 01:13:14.199
wow, I'm so far down the learning curve.

01:13:14.199 --> 01:13:16.000
There's a huge process here.

01:13:16.000 --> 01:13:18.829
It looks like you were in competent hands in the interim

01:13:18.829 --> 01:13:19.439
period.

01:13:19.439 --> 01:13:23.239
I want to compliment the work that Brian has done.

01:13:23.239 --> 01:13:26.439
Everyday amazed that he is carrying all these different

01:13:26.439 --> 01:13:28.520
buckets of projects and things and

01:13:28.520 --> 01:13:31.800
he's done an extremely great and competent job.

01:13:31.800 --> 01:13:34.300
I think our staff very much appreciated his leadership

01:13:34.300 --> 01:13:35.720
during the interim period.

01:13:35.720 --> 01:13:40.039
They're also looking forward to the new general manager.

01:13:40.039 --> 01:13:42.460
There's a lot of prescriptive things that we want to get

01:13:42.460 --> 01:13:43.720
moving forward that I've learned

01:13:43.720 --> 01:13:48.939
from looking at some of the public utility board background

01:13:48.939 --> 01:13:51.119
and hope to be in front of

01:13:51.119 --> 01:13:55.979
you many times as we move forward the organization during

01:13:55.979 --> 01:13:58.319
this transition period.

01:13:58.319 --> 01:14:02.970
Thank you all for your support during that pretty complex

01:14:02.970 --> 01:14:04.880
interview process.

01:14:04.880 --> 01:14:06.920
One of these days my goods will get here.

01:14:06.920 --> 01:14:08.920
Thank you again.

01:14:08.920 --> 01:14:12.619
I'd like to thank Brian too for the -- I know how hard that

01:14:12.619 --> 01:14:14.520
is to wear that many hats.

01:14:14.520 --> 01:14:15.520
So thank you.

01:14:15.520 --> 01:14:16.520
Thank you.

01:14:16.520 --> 01:14:17.520
Appreciate it.

01:14:17.520 --> 01:14:20.520
I'm glad George is here.

01:14:20.520 --> 01:14:25.470
And then the only other thing I'd just bring your attention

01:14:25.470 --> 01:14:27.560
to is this is the last meeting

01:14:27.560 --> 01:14:30.359
of the calendar year for the PUB.

01:14:30.359 --> 01:14:33.760
Our next meeting will be January the 8th at 9 a.m.

01:14:33.760 --> 01:14:36.489
And then again, just a reminder that we'll be moving to an

01:14:36.489 --> 01:14:38.039
evening meeting on the second

01:14:38.039 --> 01:14:39.039
meeting of the month.

01:14:39.039 --> 01:14:42.039
So the January 22nd meeting will be at 6 p.m.

01:14:42.039 --> 01:14:43.399
We're actually going to be in this room.

01:14:43.399 --> 01:14:46.529
We're able to make arrangements with another conflict,

01:14:46.529 --> 01:14:48.399
another committee that meets in

01:14:48.399 --> 01:14:49.399
this room.

01:14:49.399 --> 01:14:54.460
So we'll be in this meeting room from here on out as far as

01:14:54.460 --> 01:14:57.640
evening and morning meetings.

01:14:57.640 --> 01:14:59.640
Okay.

01:14:59.640 --> 01:15:01.640
Demetrius.

01:15:01.640 --> 01:15:07.859
I believe with the exception of the DME substation costs,

01:15:07.859 --> 01:15:11.800
which I know George is working on and

01:15:11.800 --> 01:15:15.159
will be bringing forward some information to the board here

01:15:15.159 --> 01:15:16.920
in the near future, I believe

01:15:16.920 --> 01:15:20.380
everything is covered on the matrix from the things that

01:15:20.380 --> 01:15:22.600
have been requested in the past.

01:15:22.600 --> 01:15:26.399
I think, Brandon, I still owe you some information

01:15:26.399 --> 01:15:30.159
regarding metrics on viewership and downloads.

01:15:30.159 --> 01:15:31.760
And we've been working on that.

01:15:31.760 --> 01:15:34.529
And so we'll get that to you, get that to the board under

01:15:34.529 --> 01:15:35.520
separate cover.

01:15:35.520 --> 01:15:39.600
And then we'll add that to the as part of an update at the

01:15:39.600 --> 01:15:41.520
next board meeting on the

01:15:41.520 --> 01:15:45.329
matrix just so you have that information so the public can

01:15:45.329 --> 01:15:46.560
have it as well.

01:15:46.560 --> 01:15:48.520
Okay.

01:15:48.520 --> 01:15:49.960
Then we're on to concluding items.

01:15:49.960 --> 01:15:51.960
Is there any items that?

01:15:51.960 --> 01:15:52.960
Deb?

01:15:52.960 --> 01:15:53.960
Yes.

01:15:53.960 --> 01:16:00.319
I had a suggestion.

01:16:00.319 --> 01:16:04.819
I know that we have a policy where we don't turn off the

01:16:04.819 --> 01:16:07.600
power for people in conditions

01:16:07.600 --> 01:16:09.800
of extreme weather.

01:16:09.800 --> 01:16:12.560
And that's a very good thing.

01:16:12.560 --> 01:16:19.060
And I was wondering if we could consider in the future

01:16:19.060 --> 01:16:23.159
having some kind of grace period

01:16:23.159 --> 01:16:30.159
at universal times of extreme financial difficulty as well,

01:16:30.159 --> 01:16:34.119
meaning specifically this time of

01:16:34.119 --> 01:16:38.399
year, the December, the holiday season, you see a lot of

01:16:38.399 --> 01:16:41.640
people, spending goes up, consumption

01:16:41.640 --> 01:16:45.649
goes up, and everybody is enjoying the holidays, but it's

01:16:45.649 --> 01:16:48.539
also a really stressful time financially

01:16:48.539 --> 01:16:50.960
for a lot of people.

01:16:50.960 --> 01:16:58.239
And even poor people are buying gifts for their families.

01:16:58.239 --> 01:17:04.210
And I think it would make a big difference with not much of

01:17:04.210 --> 01:17:07.119
a loss, as I understand it,

01:17:07.119 --> 01:17:12.829
to consider a grace period of December for people who pay

01:17:12.829 --> 01:17:14.159
deposits.

01:17:14.159 --> 01:17:22.960
We can certainly bring back a discussion of that item.

01:17:22.960 --> 01:17:25.960
Any other items?

01:17:25.960 --> 01:17:30.159
All right.

01:17:30.159 --> 01:17:31.159
Approval to adjourn?

01:17:31.159 --> 01:17:32.159
So moved.

01:17:32.159 --> 01:17:33.159
Second?

01:17:33.159 --> 01:17:34.159
Second.

01:17:34.159 --> 01:17:35.159
Okay.

01:17:35.159 --> 01:17:36.159
We're adjourned.

01:17:36.159 --> 01:17:44.159
[end of transcript]
