Meeting Summary: Public Utilities Board Date: April 24, 2017 Time: 9:00 AM Location: Council Work Session Room, City Hall, Denton, TX
Key Topics and Discussions - Eagle to Locust Transmission Line (PUB17-092): Staff presented two routing options for a new 138 kV transmission line connecting the Locust and Eagle substations. The existing alignment (blue route) was recommended due to fewer impacted landowners (3 vs. 11), fewer tree removals (7 vs. 25), lower construction costs, and alignment with existing infrastructure. Public comment was received regarding proximity to residential properties and potential electromagnetic effects. Staff confirmed both routes require new easements and that the Eagle substation will utilize gas-insulated technology. - Consent Agenda (Items A–E): Routine approvals for contracts and agreements, including alternative fuel transportation services with Atmos Pipeline, a water main cost participation agreement with Love’s Travel Stops, a TMPA decommissioning plan deadline waiver, reappointment of a UTRWD board representative, and procurement of refuse/recycling containers. - Closed Session: Deliberations regarding Energy Trading Risk Management (ETRM) software vendor selection, contract execution, and associated legal consultation under Texas Government Code §§ 551.071 and 551.086. - ETRM Contract Amendment (PUB17-082): Staff explained that the current ABB/Ventyx ETRM system lacks the flexibility required to manage hourly variability from wind and solar assets under the Renewable Denton Plan. The proposed amendment would cost $204,000 (including prorated annual fees), resulting in approximately $443,000 in savings compared to the original contract. The existing software will remain the system of record until a replacement is implemented. - ACM Update (PUB17-099): Presentation of comparative employment metrics for the Water, Wastewater, and DME departments. Staff noted that a comparable report for the Solid Waste & Recycling Department is in preparation.
Motions, Votes, and Outcomes - Motion to recommend the blue route for the Eagle to Locust transmission line. Passed unanimously. - Motion to approve the Consent Agenda (Items A–E). Passed unanimously. - Motion to approve the April 10, 2017 meeting minutes. Passed unanimously. - Motion to approve and recommend the ABB/Ventyx ETRM contract amendment to the City Council. Passed unanimously. - Motion to adjourn. Passed unanimously.
Decisions Made - The Board formally recommended the existing (blue) alignment for the Eagle to Locust transmission line project. - All Consent Agenda items were approved for implementation per staff recommendations. - The April 10, 2017 minutes were approved as submitted. - The Board approved and recommended the ETRM contract amendment with ABB/Ventyx to the City Council.
Action Items or Next Steps - Staff will schedule a public hearing with the City Council regarding the Eagle to Locust transmission line route in approximately one month. - The Assistant City Manager of Utilities or designee will implement all approved Consent Agenda items. - The City Manager or designee will execute the ETRM contract amendment upon City Council approval. - Staff will prepare and present a comparative employment metrics report for the Solid Waste & Recycling Department at the next scheduled meeting.