Apr 10, 2017 Public Utilities Board on 2017-04-10 9:00 AM
April 10, 2017 Public Utilities Board 14364
Meeting Details
| Meeting Date: | April 10, 2017 |
|---|---|
| Board: | Public Utilities Board |
| Video ID: | 14364 |
| Has Transcript: | Yes |
|---|---|
| Has Agenda: | Yes |
AI Summary by Dentron 3000
Meeting Summary: Public Utilities Board Date: April 10, 2017 Location: City of Denton Council Work Session Room
Key Topics and Discussions - Hartlee Field Substation Site Selection: Staff presented five potential locations for a new electric power transmission substation to accommodate growth within Denton Municipal Electric’s service territory. A public hearing was conducted. Multiple residents voiced concerns regarding visual impact, property values, traffic congestion, and proximity to homes and schools, with strong opposition to sites along Hartlee Field Road. Staff noted the yellow site is city-owned, which may streamline acquisition, while alternative sites face landowner opposition. Gas-insulated substations were not considered due to significantly higher costs. Board members discussed the need for photo simulations, construction traffic management, and reviewed staff-provided information regarding health and noise impacts. - Pecan Creek Interceptor IV Project: Staff presented details on the final phase of the concrete interceptor project, consisting of approximately 2,000 feet of 30-inch sanitary sewer line required for Clean Water Act compliance. The route runs adjacent to Denton High School, with construction scheduled for summer months to minimize disruption. Five bids were received, with Dickerson Construction Company submitting the low bid. - ACM Update: Staff provided an update on the New Business Matrix, noting completion of two items and ongoing work on a comparative report of water and wastewater department employee counts relative to similarly sized municipalities. - Closed Session: The board adjourned to a closed meeting to discuss real property acquisition and legal consultation regarding the DME Hickory substation, in accordance with the Texas Open Meetings Act.
Motions, Votes, and Outcomes - Motion to recommend the yellow site for the Hartlee Field Substation to the City Council, with conditions to locate it on the northernmost edge of the property and investigate a construction traffic easement. Proposed by Charlie, seconded by Susan. Passed. - Motion to approve the Public Utilities Board meeting minutes from March 27, 2017. Passed without objection. - Motion to recommend approval of IFB 6375 to Dickerson Construction Company for $1,038,187.00 for the Pecan Creek Interceptor IV project. Proposed by Barbara, seconded by Lillio. Passed.
Decisions Made - The board formally recommended the yellow site for the Hartlee Field Substation to the City Council, subject to northern placement and construction easement investigation. - The March 27, 2017 meeting minutes were approved as submitted. - The board recommended awarding the Pecan Creek Interceptor IV construction contract to Dickerson Construction Company.
Action Items or Next Steps - Staff to prepare photo simulations/renderings of the proposed substation site for the upcoming City Council public hearing. - Staff to investigate the feasibility of a construction traffic easement to divert heavy equipment away from Hartlee Field Road. - Staff to complete and present the comparative report on water and wastewater department staffing levels relative to peer municipalities. - City Council to hold a subsequent public hearing and make a final decision on the Hartlee Field Substation site. - Construction of the Pecan Creek Interceptor IV project to commence during the summer months, pending final approvals.
Agenda Chapters
Transcript
8732 wordsAgenda
3 pages... (truncated, showing first 2000 characters)