Apr 24, 2018 City Council on 2018-04-24 1:00 PM
April 24, 2018 City Council
Full Transcript
Good afternoon.
Welcome to this meeting of the Dutton City Council.
Today is Tuesday, April 24th.
The time is 1.03 p.m.
We'll start with our work session reports.
Item A is receive a report, hold a discussion, and give
staff direction regarding the construction
of the G. Rowland-Vela Athletic Complex Capital Project.
Good afternoon.
Gary Pack and Director of Parks and Recreation.
I wanted to give you an update on the G. Rowland-Vela Soc
cer Complex.
This is a follow-up to the April 3rd presentation that
staff provided that was primarily focused
on funding discussions and options, as well as design
construction options as well.
Some of the questions that came up during that presentation
were specifically focused
on finishes within the facility, the cost of the restroom,
and some alternatives that
could be considered, looking at some comparable facilities
within the industry and other municipalities,
as well as options that we could look at for the restroom,
concession stand, and then the
breezeway that's part of that structural design as well.
Again, the focus specifically for the presentation is this
area in the yellow box.
This is the main entry point to the entire facility.
It's designed symmetrically.
Obviously, you can cut the facility in half, but that's
where everyone's coming in and
out of the soccer complex, the four fields, as well as the
playground area.
Looking at some of the finishes, this is a burnished CMU
block.
That's what the exterior of the building will look like.
We haven't finalized color, although we'd look at the
design of the existing facilities
within North Lakes, and to match that, it's kind of like a
cream, khaki-type look with
green roofing structures.
This is a burnished CMU block, in addition to some accents
with a glazed tile on the
walls as well as the buildings themselves.
Then precast stone in select areas, specifically along the
roof edges and the wall edges.
Then the roof is a standing seam metal roof.
We talked a little bit about storm shelters and protection
for the community.
It's designed for up to approximately 115 miles per hour.
It's not tornado-proof in a sense of anything higher than
115.
It is a standing seam post-tension slab concrete base with
footers for the actual concrete
that the building sits on.
The facility itself, this area here is the restroom, and
then this side section is the
actual concession stand.
Here's your women's restroom, your men's here with your
plumbing chase in between both
the restrooms.
This area right here is currently designed for athletic
storage, and then this area over
here is our electrical room.
A comment came from Councilman Hudsmith, and he's not here
today, about the possibility
of adding a family changing room as an option.
That's something that's starting to show up more and more
in public facilities.
Not that it's a requirement, but more of a demand from the
public, especially when you
have, if I'm out there with a daughter or a special needs
individual, I can go in there
and take care of them as opposed to sending them into a
restroom, into the women's room
by themselves.
He had asked if this was an option to turn this into a
family changing area.
We reached out to Dunaway, and they did confirm that that
is an option.
We could look at that and basically run this chase right
down to this area here, and then
put in one urinal or a toilet for that specific need.
Then this side over here, this L-shaped area is the con
cession area.
This square back here is actually concession storage.
Here's your vending area for the concession stand itself.
Then this is in itself is a maintenance storage area for
staff.
Each one of these buildings, they're identical in square
footage of 978 square feet apiece.
Then the breezeway itself, which incorporates the actual
roof structure, that is that main
entry gate into the facility, but it includes everything
within the blue outside of the
building.
All the concrete work is included into that price as well
in that square footage.
Do you have a comment, Council Member Briggs?
If there was a storm, would you go into the restrooms or
into the breezeway?
You could take them into the restrooms, into the storage
area.
That could be opened up if staff was on property as well as
the concession area in the maintenance
room.
But the breezeway would not be as safe?
The breezeway is just a covered structure.
So if it was raining or hailing, that would be a safe place
to go.
It just provides cover.
Okay.
Thanks.
You're welcome.
Okay, so the total square footage of both facilities in the
breezeway component is 3,300
square feet.
That works out to be, based on the cost from our lowest bid
, $269 in change per square
foot.
To kind of give you an idea in regards to how that compares
to other bidders on the
project, our average square foot was $254 a square foot.
When I figured out those numbers, I did remove bidder
number two just because that price
was so low.
I figured there might be an issue with that bid because it
was so off of all the other
bidders.
So that's $75.75.
While it sounds like a good number, it just doesn't seem
right.
So I took that out of when I figured out the average.
So based off of that, bidders three, four, five, and six,
it's pretty comparable in
regards to those other bids that we received.
In comparison to other like facilities within DFW, they
range from $263 a square foot up
to $377 a square foot.
Now I know specifically this third one, Randall Mill Park
in Arlington, is a green design.
So I think that dictated a little bit of the higher price
point.
But as you can see, at $263 being the lowest in this sample
, we are towards the lower end
of those comparables.
I have a question.
In one of our, I think it was audit finance committee
meeting, we had a proposition for
a precast concrete building.
And I think the direction was to look at that cost in
comparison to these costs as well.
Can you speak to that a little bit?
Sure.
I have it on a later slide.
Great.
But I can jump to that if you prefer.
No, it's okay.
Okay.
Okay.
Some comments from Dunnaway and Associates, they're our
architect and engineering firm
on the project.
It is designed as a full service facility for sports
industry, as well as the anticipated
number of visitors that we have at the complex.
The building is designed appropriately for major public
facilities in obviously durability
and abuse just by the repetitive use.
It's similar in style to other park facilities, whether it
's in Denton or other parks with
DFW.
It is commercial grade with anticipated long-term
performance.
Mechanical and plumbing, it's more complicated.
It's not a typical toilet that you would have in your house
with the amenities that support
that.
These remain to be used and flushed repetitively on a
Saturday when there's a large amount
of people within the property.
And then the cost per square foot, Dunnaway feels is very
advantageous compared to the
current market.
Some additional comments, North Rock Construction was our
lowest bidder.
They had, in attaining some questions and comments, they
had made a comment that ready
mix concrete and the steel will be rising in May.
Their bid is good until May 18th.
And we had a third party cost estimator look at this and we
just got this on Friday.
And their evaluation of the exact drawings that we provided
was $913,000.
So it actually, the third party came in a little bit higher
than our current contract,
our current bid.
I'll try to frame this the best I can in regards to cost
comparisons from residential commercial.
Residential typically is a frame facility with wood and
commercial is more steel and
concrete.
Wood is not as stringent on residential compared to
commercial.
A mechanical as I mentioned earlier in plumbing in a
typical household obviously you don't
have as many restroom units or restroom facilities in a
house compared to a restroom where that's
its main purpose and it's getting heavier use.
Roofing where you may have shingles.
Granted, we have shingled facilities within our park system
, but metal or a rubber type
of roofing material is more commercial grade.
Finishes, they obviously vary based on the preference of
the homeowner or the commercial
builder.
And then vandalism, I put low to none on residential.
My kids abuse us about everything we have in the house.
So that was to qualify the kids in the house.
But vandalism in a commercial grade facility in our parks,
we get a lot of vandalism in
our public parks.
So that's made to withstand some of that level of vandalism
.
We're providing some options for City Council to consider.
Option one is to proceed as designed with the full
construction as proposed.
We'd move forward with North Rock construction.
Again the deadline for the bid is May 18th.
And again this would serve as the gateway point in the
entry point to the entire facility.
On April 3rd we provided you a breakdown of the cost and
this is the identical breakdown
that we provided at that point in time.
Again that works out to be $269 a square foot, total of 3,
300 square feet.
Option two would redesign the facility, remove the con
cession and the breezeway from the
project.
And we'd have to determine if we want to redesign the
position of the building.
We could easily take out the breezeway, which is this
component here, as well as the concession
stand and leave the restroom where it's at.
But as the focal point it might be a little awkward.
It's not centered, everything being symmetrical.
Obviously we could live with that the way it is and decide
if we wanted to build that
down the road and add to that at that point.
But that's a decision we'd have to make a decision on.
If we did remove the concession and breezeway there would
be some amendments that would be
needed to the construction drawings.
We had a quote, it's about $13,000 to do that redesign work
.
And then the cost from our lowest bidder is $517,000 to
build the restroom itself.
So it's not a 50% reduction from a square footage
standpoint.
Option two, again there's the breakdown of the $517,000 in
regards to its major components.
And that consists of the elimination of the concession and
breezeway.
The restroom would still be 978 square feet.
And then the cost per square foot actually rises with that
reduction to $529 a square
foot.
And then option three and four in regards to prefab
structures.
This option three is a restroom and storage only.
If we decided that we just didn't want to be in the con
cession construction business,
this is approximately 675 square feet, costs approximately
$200,000 at $295 a square foot.
And then option four, same prefab structure but this
includes a concession component and
it's slightly larger at 936 square feet and a little bit
more at 300,000 square feet at
a total of 320 approximate square feet cost per square foot
.
In summary, those options, option number one is proceed as
designed at the $889,000 or
$269 a square foot.
Redesign the facility, remove the concession stand and
breezeway.
We would do concessions outside of that facility.
So whether it's under a tent or bring in food trucks or a
trailer of that stance, we would
plan accordingly.
And then option three and four are modified designs with
alternative structure components
that would be prefabricated and providing that resource.
At this point in time, I'd like to entertain any questions.
>> I think you have them already queued up.
>> Nobody's requested questions yet.
>> Okay.
>> All right.
We'll just go around the horn.
We'll start with customer Gregory and then just go around.
In the back up, you provided also the presentation that we
received on April the 3rd regarding
funding.
Do you have that on your -- can you go ahead and get to
that slide or not?
>> Actually Tony was step up and talk about the funding
breakdown.
Tony pointed to Director Finance.
Councilmember, if you recall from the previous presentation
that we had made, I think even
at the last meeting, the initial funding was 1.33 million
that was included in the 2014
bond program.
There was some additional funding that was already included
in the program for that,
about 1.9 million.
What we had recommended was that we, you know, switch some
funding around.
I think the council was hesitant about that.
So the last meeting we came back to you that we would draw
down the general fund balance
additionally to get this project completed.
So the proposal that you'll receive on May 1st, part of a
budget amendment, is that we
would draw down fund balance in the general fund, about $2.
1 million to get this project
completed along with additional half a million dollars in
some CIP savings to get to the
full $6 million.
So those would be the sources of funds.
I don't have a slide for you, but that's the sources of
funding we would recommend.
Yes, sir.
Councilmember Ryan, did you have a comment?
Yes, thank you.
How do we determine how big a restroom facility needs to be
?
Do we not have standards?
Because when I look at the option one, the original design,
it's showing a total of
eight toilets and urinals combined, and then on options
three and four, you've only got
four total.
Right.
The option three and four are similar facilities that we
have in our park system to provide
an alternate that we could provide at our existing parks.
Now the change here is with Vela being four soccer fields,
obviously, and we're having
tournaments out there, you potentially have 16 teams going
at the same time, coming in
and out.
So there's a lot more use.
So that is going to dictate more facilities from that
standpoint.
You could design 20 urinals and toilets out there, but at
some point in time, you can't
build it for Easter Sunday type of a mentality.
So you're going to accommodate as best you can based off of
a proposed budget.
Okay.
Because I mean, we're not looking at this.
I mean, there's a difference in the design, but there's
also a difference in how much
capacity the facilities have.
And I would think that there would be something out there
in some criteria manual that would
say just like with restaurants, it's based on the number of
square feet or the number
of seats you have as to how big your restaurants need to be
, that there should be some sort
of something out there criteria wise that should tell us
what we would need for four
soccer fields.
We have Dunaway and Associates here.
I don't know.
Is there any component that's the standard for so many ur
inals per field ratio?
If you'll come to the mic.
Yeah, because we're broadcasting.
Thank you.
Good afternoon.
Philip Neely with Dunaway Associates.
There's no published criteria for sport fields number of
restroom stalls, state, local or
federal.
There's some rules of thumb and we've through the years and
a number of complexes we've
done in terms of number of fields and like you're talking
about when you're the transition
from with one group finishing and another.
So what you're seeing on option one is very normal with
that many fields, but there's
not like there would be in the uniform building code.
There's not a code requirement for number of men's and
women's on a sports facility.
Okay.
Thank you.
Councilmember Riggs, did you have a question?
Yes, go ahead.
So a few things.
I appreciate all the options because from the beginning I
had trouble with how much
it cost and so just looking at option four, we saved nearly
$600,000 by going back in
and separating from the original design.
So my question is, have we done that with other things
because this is just one aspect
of the $6 million.
Have we looked at how much it would cost if we did other
things in house?
So to answer your question, we have, but not to the full
extent of serving as a general
contractor.
If you remember back on the April 3rd presentation, we
provided some options of not building all
of the fields or phasing it in and staff at the time was
proposed to do some of the turf
installation, hydro mulching and tree planting as a
component to help reduce some of the
expenses, but we did not look at concrete irrigation, fence
insulation or serving as
a general contractor.
Okay.
Thanks.
Mayor Pro Tem and then we'll come back.
On the prefabricated buildings, as far as I understand that
it's concrete, correct?
So what is the storm protection level of a prefab building
like that?
I'd have to get back to you and I don't have the exact wind
load on those facilities.
So I couldn't give you an accurate response.
And so just so we're clear, it's prefab, but it's an actual
building that's been built
with concrete and then it's moved over to the site.
It's yeah, it's prefabbed walls that's put in place.
The concrete is, you know, could be thickness varies.
I think the ones that we have on property are 10 inches
thick approximately.
We already have some on property.
We do not not on North Lakes, but within the park system.
Where are they?
Mack Park and Roberts Field.
Okay.
Okay.
Thank you.
Councilmember Gregory.
Thanks.
Well, I appreciate the information that you provided and I
appreciate the fact that you
were comparing the construction cost for option one with
other cities and their construction
cost.
I think that's very helpful.
It seems to me that to to delay means an obvious increase
in cost when we do build.
I prefer the original option having had kids playing in
tournaments, especially when there
are a lot of teams having a facility that has a breezeway
gives folks a place to go.
If the weather is if it gets rainy or if it is hot and
people need to get in out of the
sun for a little while.
That's especially true when you have tournaments and people
are out at the fields for 12 hours,
eight to 12 hours.
And that happens a lot.
So to have a breezeway have the full facility means that we
could get to host more tournaments.
And we have a facility that does not provide those kinds of
amenities.
It means that the tournaments will go elsewhere rather than
to dent.
Meaning that our kids have to travel.
Our our teams have to travel somewhere else rather than
other teams traveling to us at
times.
So I would prefer to move ahead with option one.
Councilmember Ryan.
Another question I have on the original plan.
You showed the electrical room and assume that that was not
only just for the building
but also for all of the field lighting and etc.
That would all be controlled from there.
I believe so.
Is that true?
Where would where would we do it on options three or four?
There's not a electrical room.
We have to modify that building or add a separate to
provide that component.
Yes.
Okay.
So that would be an additional cost as well.
Councilmember Duff.
I guess the way I look at this is this is not something
that's just going to be there
for a short while.
It's something that's going to be there for a long time.
And I personally think that if we're going to do it we need
to do it right.
And that that would be option one.
Anybody else?
Councilmember Bray.
Do you have a question or comment?
I'm not in favor of option one.
I'm in favor of if anything option four.
And I still would be in favor of looking deeper into the
project to see what we can separate
to save costs just as a benefit for the taxpayers.
Thank you.
Yes.
Mayor Pro Tem.
I have a question about building shade structures.
So if we were to build a shade structure elsewhere that's
explicitly for a shade structure, how
much would that I know that's a kind of big question to ask
you but how much would that
cost like if we wanted to cover the seating for instance?
So obviously that's going to depend on size.
I haven't bid one of those out recently.
I don't know what we've most recently placed.
We can get you a cost estimate for that.
Shade structures vary from what we have over our existing
bleachers which rain can penetrate
for the most part.
It's just a penetrable surface of fabric to actual roofs
that could be put in place that
are more safe from hail as an example.
So that can vary as an option.
Okay.
Appreciate that.
And I really commend you on your presentation because it
has all of the information plus
some that we requested.
So very good presentation.
Thank you.
My recommendation would be to go well my direction would be
to go with either option three or
four.
I was really impressed with the prefabricated concrete when
we got the presentation and
our audit finance committee.
And I mean it's concrete so it's going to become more
strong with time.
The fact that it's already at Mack Park and Roberts Field
indicates to me that it does
have a good long-term lifespan.
I don't know how long they've been at Mack Park or Roberts
Field.
Just I think 2016.
Okay.
So relatively new.
So I'm satisfied with either three or four with
understanding that we can add amenities
like shade structures and things of that nature to make the
experience more comfortable for
people.
Also, we have the option of you know doing electrical for
food trucks if we wanted to
do something like that.
I think looking at the entire picture is a good way to
approach you know bringing these
these competitions to the region or to our area.
Just to add a comment to Councilman Gregory in regards to
tournaments and his experience.
Just this weekend I spent the weekend in Plano and on
Sunday we were there from we started
at nine o'clock in the morning so we got there at eight and
we're there till 11 o'clock
at night.
We weren't sitting there the whole time and we went and had
lunch and that type of thing
but you do spend a lot of time with for tournaments in
facilities.
So it's you know try to provide as much comfort as you can
and an enjoyable experience.
So it's something I personally experience myself.
Councilman Ryan.
It's difficult to say I think I'd like option three or four
a little better than one but
we are not getting the same amount of facility out of it
and I'm afraid that we'll end up
you know if you ever had the opportunity before they tore
down Cowboy Stadium those restrooms
were very there wasn't enough there enough facilities there
and I don't want people to
decide not to come back to Denton because they had to stand
in line too long.
I'd like to see the numbers to have the same amount of
facility in an option three or four
and also look at that electrical room.
We may be right back up to that same cost so that's that's
where I am on this is I really
can't make a decision without knowing what the cost is on
three or four to add on to
that.
Is it going to be the same same amount per square foot to
add more or generally it's
going to reduce them.
The the pricing on option three or four is is roughly what
we paid for 2016 for those
facilities just to kind of get a price point so those are a
couple years.
Okay well it doesn't sound like I mean it sounds like we've
got a couple who prefer
option one definitively and then a couple that prefer
option I guess for three or three
or four and then Councilmember Ryan is needing to see more
more costs.
I think the discussion we're having here is is commensurate
with the struggle that we
have with just some of these costs in general.
I mean I struggle with this I understand it's commercial
development I understand the different
codes and things that are required for commercial
construction.
In other words the cost that we're seeing I mean the the
contractor didn't come in and
modify any costs they just this is what that just refined
what the breakdown of the costs
were.
We don't know if we were to bid out the plumbing or
something like that if it would come in
less I mean they I don't know what is an average
contractors up charge is it 10% 15% what what
what is dude you know I may be done away may want to
provide more detail to that I was
assuming 15% on some other projects we've done in the past
in regards to the breakdown
that third party gave us I do have that and they gave a
breakdown of the actual let's
see not specifically these same same exact breakdown
categories per se it was eight hundred
eighteen thousand dollars for all those amenities and then
all the additional expenses general
liability builders risk permits and fees subs bond premiums
for subs and general contractor
and overhead and profit was roughly another hundred
thousand dollars to get it to nine
hundred thirteen thousand dollars and that was from pre-
construction services that did
a third party analysis of that bid so they actually came in
higher than what our current
bid is.
Who came in higher?
The third party estimator that did it for us.
Because I think that's a good point on option four we don't
have an electrical room which
one of the most expensive things in a project or your
mechanicals your HVAC your electrical
and your plumbing so that may add I don't know what that
would add to it but I mean
it's not going to add five hundred thousand dollars to it
they may add fifty thousand
or forty or something like that by the time it's all said
and done and when I look at
option four I mean this is a tough decision I mean it's
just very difficult to pay two
hundred fifty nine dollars a square foot for in essence
concrete brick and things such
as that we've got I mean we've got to figure out a way how
and if we're going to be doing
this a lot I mean I think it's worth the the investigation
to say if we were to hire some
if we were to have people on staff to do these if we're
going to have a lot of construction
projects what is the price differential I mean and I
understand the advantages and disadvantages
of contractors or in-house and but that that all can be
explored that can you can nail
some of that down pretty succinctly the thing I struggle
with is number one I don't want
to pay nine hundred thousand dollars but when I look at the
options that are presented this
is just the ones that are presented and I appreciate the
detail of your presentation
because it's helpful it's very helpful when I look at
option four all right and I see
what it is and I see that it's nine hundred thirty six
square feet and it's three hundred
and twenty dollars of per foot yeah we'd be paying almost
triple that but we're getting
almost three more than three times the square footage when
you include the breezeway I don't
I really the breezeway I I'm not sure about I mean if we're
going to be constructing these
kind of structures for utilitarian functions such as people
go to get food people go to
use restroom but if we're also constructing them for pseudo
shelters I mean if we're constructing
them for tornado shelters that's very different than
constructing them for a shelter to get
out of the rain some hail and some lightning and and and I
'm not saying either one's right
or wrong I'm just saying those are very different policy
decisions which carry a lot of different
costs differential right in that and that's certainly I
think something we need to start
considering because we've got a lot of construction
projects going on not just with parks so I
think I would like to see if we're going to go with option
four I would like to see what
additional costs it's going to be whether it's on site
electrical modification to that
structure or if you have to put it somewhere off site what
is that what is that going to
do to it okay because it seems like the the square footage
for the actual restrooms and
the concession stand are 978 each and in option four it's 9
36 for both is that correct I mean
so I'm looking at option four it says the total square
footage for the prefabricated
structure restroom storage and concession right the total
is 936 yeah so so here is
your restroom facilities here right you basically have to
see a 50 percent of the space in regards
to toilets and then you have storage here and then the con
cession area here so there's
like three sections to the building so does this hold up
our moving forward on the project
in general this particular component the the bid is expires
on May 18th if we're going
to do a change order in regards to that contract we'd have
to work through that process so
I would anticipate we could move forward with the contract
and then do a deduct to take
that out so it would be comparable to that's a good
question I I'm not sure what the cost
would be on the entire project if we took out the entire
restroom facility I doubt very
seriously that they will give us a dollar for dollar
reduction correct I mean that's
evident off compared to option one and option two it's not
you know 50 percent when you're
taking off half the building right Councilmember breaks so
on the on the number two for 250,000
that you said you didn't even like include in the scoring
did anybody look at that bid
to see and compare it or did y'all just kind of throw it
away because it was too cheap
I'm just curious because it's I did not I don't have
communication with the bit the
bidders and that was done prior to me getting here I took
it out just because I felt personally
that with it being almost you know a third of the cost a
little less a little more than
a third a little less than a third that compared to the
other prices that it seemed it seemed
off that's extremely low cost at $75 a square foot so it
just seemed like something was
wrong there and I would be concerned that there would be
expenses that would show up
at a later date yeah yeah plus the total bid is is you know
approximately $200,000 higher
than the overall bid as well I was just wondering about the
individual structure within that
bid I know that the total bid is is overall higher but this
is all individualized and
so I was wondering if the the structures compared to each
other within one and two they are
there they've been on the same documents so it's the same
structure but their number
you know I don't know how they came up with that number I
didn't see the breakdown of
their analysis because that wasn't part of it it just
raises some concern that that's
very low
so if you leave the slide up so what I'm seeing here are
the the bids that came in yes which
you said the bid expires May 18th yes sir and if a bid exp
ires what happens we have
to start over you re-bid it yes sir so when we look at
these we've got six bids we've
got two in the 5.6 5.8 range the rest are seven million or
above and those include the
same option one restroom configuration am I right on that's
correct okay they're bidding
off the same document right so from a purely take out my
just shock and dismay at construction
but if you look at this deal from a truly financial
perspective given the facts on the
ground so if we go with option four that saves us half a
million dollars roughly six hundred
thousand dollars we get half or less than half of what we
originally wanted if the bid
expires or let's say it didn't expire we are 1.1 million
dollars away from the nearest
bid other than bid two which we've sort of thrown out
because somehow something looks
a little that's probably just either residential component
construction or something because
you can't even build you can't even build residential for
that in addition with approximately
expenses and construction are going up about one percent a
month so the longer that delays
that will have an impact on the overall cost as well right
right okay has anybody asked
the the one who's got the bid if they're able to knock off
a couple hundred thousand
dollars or can you do that is that first of all can you do
that under the procurement
laws in the state of texas we have asked for their best and
final offer twice so technically
you're supposed to so basically that's about as far as we
can go legally okay and the question
about the seventy five dollar per square foot i just want
to clear that up as deputy manager
langley said we still got a bid that's 150,000 higher we
are not able to mix and match components
of so i think i think where you're going mayor is right it
's very possible that as these
contractors get busier we could rebid this out and come
back with an even higher price
so that is a risk sure of course yes mayor pro tem on page
excuse me page 23 questions
for consideration so when i do the math dividing eight
hundred eighty nine thousand by 270
dollars per square foot comes out to 3300 square feet so
that's the breezeway component
that's everything that's both the restroom the concess
stand and the breezeway components
which is the concrete around the restrooms in between the
restrooms and the roof structure
so the actual restroom and concession portion of it is how
many square feet those are nine
hundred and each change 978 square feet piece okay yeah and
i suspect that you know if we
let's say if we took off the breezeway and just sort of
backed all that up somehow end
to end you're you're not really i mean you've got concrete
and a metal roof supporting structure
and the actual material of course the way things are priced
these days i probably would
be shocked at what that would be but so so a cost for the
breezeway just the roof component
itself was roughly 90 plus thousand dollars if you wanted
to pull that component off that's
an option to be considered say that one more time it was 90
thousand dollars approximately
okay is that including the supporting structure down to the
concrete are you just talking
about the metal what does that include the the breezeway
itself is cantilevered off of
the buildings and the the actual walls of the structures
right so if we need to omit
some some support in those beams specifically that's
something we'd have to look into but
that's how it's designed is to utilize the building as its
main support the okay all
right councilmember griggs did you have a question comment
well even if i decide hey
you know from a financial perspective we you know if we
looked at option one we still don't
have a consensus on that because it's sort of it's it's
three who favor option i'm saying
hypothetically it's three who favor option one and three
who do not favor option one
at least at this time so that's i mean we're sort of back
to where we are at least i understand
at least if you're on an official vote a tie leads to
defeat of whatever the underlying
motion was if i'm correct is that correct mr city manager i
mean mr city attorney i'm
sorry say that again if if you're in a voting situation and
someone makes a motion which
we're not in a voting situation this is simply for
discussion and someone makes a motion
and it's seconded but it's a three three tie the motion
that's on the floor fails because
it's a tie correct all right well i think given that i
think there's just more information
that we need but the risk is that you know can we get that
done in a timely manner before
the bid expires you know the the addition of the electrical
facilities either added
on to option four the prefab building or we have to build
it somewhere else or we have
to have it contracted to put on to this structure and so i
don't know how these prefab structures
are designed or manufactured and then we don't know for
certain if we take the restroom out
of the current bid we don't have a definitive answer i know
you said option two is redesigning
it and removing it but but that's not that's something
different we don't know if we decide
to take it out if we reduce our bid by the 890 000 or
whatever that was that if it's
a dollar for a dollar we don't know that do we well there's
there's still going to be
some infrastructure going to have to be in place the condu
it's running to the the structure
itself you're still going to have to be there water tap
that type of thing but that that's
my point i mean if if we if we say that okay bidder one
winning bidder take this out but
we got to get we got to keep the plumbing coming to it we
got to keep the electrical
coming to it what does that reduce our bid by well if they
come back and say oh it reduces
it only by 500 000 so then we've got to add the 300 000 or
whatever that delta is to the
cost of whatever option we choose and now we're back to you
know maybe a couple hundred
thousand dollar difference so i think it's critical that we
know that number the the
one of if we take the the the if we did it some other way
except with this current bidder
what is it going to reduce our contract price to because my
hunch is if it only changed
it 100 to 150 000 i could be wrong but that may make it
that may make a difference in
i mean somebody's thought about it if we're if we're only
going to be building this something
that's half the size saving 150 or 200 000 in the end and
have a risk of losing the bid
expiring and rebidding it sometimes you just got to look at
these things so council member
gregory then council member would you show the design for
option four please i think
what would be helpful for the next discussion which we're
going to need to schedule very
soon is that we look at not only a comparison of option one
to option four let's look at
it in terms of square feet let's look at it in terms of how
much square footage is dedicated
to storage and option one as opposed to option four how
many toilets there are in option
one as compared to option four of course get get a revised
notion of the cost for option
four with with electrical facility also and if that means
that there's less storage we
need to we need to see that so that we're really looking at
what we're really getting
for this reduced price and and and if what we're getting
you know is going to accommodate
16 teams and their guest and i agree with that because i
think my biggest concern in
why i really couldn't decide at this point which way to go
is because options three and
four only have four stalls total and i feel like we really
need the eight that is designed
the other item that i heard mentioned is you had impact
fees are are they in the building
cost or when you did you had the breakdown to the 889
how much of the electrical is actually for the facility how
much of the plumbing is for
other parts 120 000 in plumbing you're going to have to run
the water line pay the tap
fee just to do the irrigation so if that's included in the
building cost the building
cost really isn't 889 it's much lower but if we're going to
have to pay those separately
to do this smaller building are those types of things
included in the 200 000 300 000
options three and four yeah there would have to be a little
bit more of an analysis on
the bin it looks great right now but i think i think
inevitably i'll end up on option one
once we look at all those but i really need to see what
those numbers are first we tried
comparing the best we can from apples to apples but in some
aspects we we have different flavors
of apples and from different locations i guess in regards
to what the finished product is
the functionality the amount of units that are in each
facility but we try to provide
options for council's consideration based off of similar
things that are in the industry
yeah because the the option four which is the prefab
building you took off of a similar
one we have over in mac park so was that price inclusive of
of the infrastructure getting
to the structure or is that just that's what we pay the
manufacturer to make this building
ship it here we pull it off and we set it down it is my
understanding that this was
replacing an existing structure that was within the park
correct so the infrastructure was
already there so okay i think it's really clear that really
to get a good analysis of
let's say option one and four obviously you want to compare
the actual amenity what's
what's in one what's on the other square footage and number
of stalls etc but you really need
to have an ability to dissect the cost because if the
infrastructure costs are not in this
300 000 to bring the plumbing that's to bring the
electrical then we don't know what that
is and if that's built into the other one then that means
it's going to have to stay
that amount so i think it's a matter of what amount of the
cost of option one is infrastructure
getting to the site and then actually erecting the building
because if we're looking at this
purely from a cost versus what asset what's the amenity we
're getting we have to be able
to know pretty clear if not we're going to be somebody's
going to come back to us in
parks with an amendment a contract amendment saying it's
going to cost an additional 100
000 150 000 and we just i'd rather know that up front mayor
pro tem well on option one's
breakdown it says that you know plumbing is 130 000 it has
a lot of the cost that you're
talking about broken down i don't think they're exactly
transferable but it looks like it's
about 230 to 250 000 for all of the electrical and plumbing
are you in the actual cost breakdown
or 18 on what slide 18 slide 18 of the present of this one
this well but yeah is the because
when we look at the the actual cost projections the bid
alternates or well that's the bid
alternates where's the so i looked at that that's for the
whole project okay so we don't
have a breakdown so i'm sorry mayor pro tem are you saying
that the the plumbing the 130
000 is to come from the sewer main or the water line to
this structure that's what it
appears to be that's the cost or is it including all the fi
xtures all the plumbing within the
this is a breakdown of the concession stand the restroom
does not include the irrigation
water to the facility i i can't answer that okay 100 but we
do have other uh you know
irrigation related issues and water related questions yes
to follow up on that so if we
don't have the cost of taking the lines to this facility
already in these bids that's
a fixed cost across all four projects is that am i
understanding it correctly i believe
yes that's the way i understand it i don't know if don away
has any additional comments
on that well i think i think your quote your statement is a
is a correct statement my question
is i don't know if part of that cost is in this cause he's
saying no i i can't 100 answer
that question okay so um does somebody need to come up and
address that and i see head
shaking i hear i hear voices trembling um does anybody have
an answer to that question on
this so the the gentleman from north rock constructions
here if you'd like have him
come up and yes give a little more detail and he stayed his
name that'd be great yeah
come on up here and okay yes the the sewer line is in a
different line item running to
the building within you know five ten feet of the building
okay so this cost is basically
just to connect to that and do the buildings okay same with
the water line water electrical
like you said that that there would be something different
there because of all the electrical
that's coming into that building supplying other areas and
things like that okay so um
so why i've got you so what you're telling me is the
infrastructure is coming to this
particular uh design option one and for the plumbing for
eight toilet and this is including
all the fixtures this is including the sinks the faucets
the toilets whatever's in the
concession stand that doing the rough-in plumbing the stack
out and the finish for this structure
is 130 000 for the plumbing yes and we had three estimates
come in on that and two of
them were right next to each other right around 114 000 114
and 116 and then the third one
was 150 okay um and do you know off the top here how many
fixtures there are i mean i
don't want to count them but you got eight toilets i mean i
was just trying to get a
price per fixture on that because i know that's how they
bid a lot of these things is a price
per fixture um i'd have to ask for a breakdown okay okay
that's so you're answering the question
of this 129 is simply to take care of the plumbing
infrastructure or anything in this
list for that structure only except for electrical we may
have to figure out something different
okay fair enough thank you appreciate that that's very
helpful and just to answer another
question yes we did we did come back and the price had been
reduced in when we were asked
to for our final best offer okay so for the total the total
price not just this but for
the whole for the whole contract this this did come down as
well okay uh any idea and
if you don't answer that if you don't know this i'm okay
with that because you've heard
us talk about if we were to say let's just pull this
component out what how much that
may be off of the total that you know would you get a
dollar for dollar reduction or it
wouldn't be a total dollar for dollar because that area
will have to do something with that
area um say when we pull out the the breeze away in the red
and the concession stand then
what we did is we added a 13 000 dollar price start to to
go ahead and do concrete to fill
that area right um unless it's going to be grass it just
depends on those those kind
of okay just whichever way we'll still need to get that
number then as far as yep okay
hey thank you very helpful the other side of that too is on
a prefab we've set quite
a few prefabs i and i'm not sure if then we can speak to
that but i know that there are
size restrictions and how big you can actually buy those in
okay and the cost dramatically
goes up with the crane size the set of things all right
thank you very much i appreciate
it okay that's helpful we do know then that the fixed cost
is there uh so really for me
the only out remaining question is what would be if we
pulled this out to do a different
option what would be the new price what would be the
reduction from the current contract
on that and then an exam examination of the electrical
because that's i mean that's especially
if it's handling the entire if it's handling the entire
field it's not just handling a
concession stand it's handling all the lighting and
everything that's pretty substantial
well just to move things along my guess is that there will
probably be about 10 percent
i have five to 15 percent added on to these final costs
just for different types of contingencies
just based on my experience these past two years there's
always additional costs so i
think really what you're looking at is option one is about
a million dollars option two
is 600 option three would probably be 300 with electrical
and everything option four
would probably be about 400 somewhere in there so given
those numbers and the fact that it
seems like you guys really don't want the prefab option i'm
willing to go with option
two just to move this thing along um but i i will not vote
for a one million dollar concession
stand and toilet facility okay all right any other comments
let me look at let me go back
to the presentation so you're saying option two which is
saying i can live with option
two because i'm taking the temperature and it seems like
people really don't want the
prefab buildings so as a compromise so would that that's
removing the brief that's removing
the concession and breezeway yes i think i explained at our
last meeting why i wouldn't
be voting for a concession stand yes you did i understand
okay all right any more comments
um well i'm not sure that really moves the needle much uh
but yeah so if if we could
maybe just have that that number of if you if you took it
out what is that contingency
and also if if i mean mayor pro tem makes a good point and
that is um we've seen where
we've had to come back and increase bids but so this 889
for option one so that is a contract
that we have accepted the bid on right so the only way that
's going to go up is if we
make a change is that how i see this well during
construction something could happen
um you know there could be like a rock boulders underneath
there that we have to deal with
and outside of that outside of sun some unforeseen because
you build that into all contracts
you know given you know if we got to do this this this or
this i understand that but if
all the things per the bid sort of play out from a
construction perspective um then they
they build it for that price unless we change it or they
encounter some unforeseen unreasonable
contractually omitted or or contracted around situation
that would require additional cost
that's correct okay you know if we decided we wanted to um
to go in and change the storage
area here this athletic storage area and put in that family
changing area that would be
our decision right to request that cost and make the
modification okay all right councilmember
briggs just for clarification when you're gonna bring
something back it's going to be um option
four plus the what it would cost if we did the um plumbing
and electrical on the the
prefab is that so we can get a better idea of total cost
well or no it's currently in
the design based on what north rock just communicated so it
's stubbed up within 10 feet of the building
so then the concept would be if whoever does the prefab
structure they would tap into that
area wherever it's it dead ends okay so done away did the
bid done away did the design
they're the architects engineers and north rock
construction is the is the lowest bid
that did the baffo for us and then they contract out
plumbing and and what have you for other
jobs is that i don't i'm not 100 clear on what they do
themselves and what they contract
out you know where their specialty is okay all right thanks
yeah question on the um so
on these prefab buildings so they are they have probably
the plumbing within the building
but as far as the rough end plumbing which when they go to
set that slab down and they
go to set that prefab building down there's a place for the
toilet to be hooked up there's
a place for the water line to be hooked up there's but so
somebody's got to get those
connections is that part of that bid so the the prefab
structures that we put at mac park
already had infrastructure in place right so when they pull
it off the stuff out's already
there yeah so you had to cut that off you know 10 feet from
the building and start over
and that building goes into place you're tying that into
that meter or wherever that area
is where it's stubbed off for the electric water okay sewer
well and i hate to get in
the weeds and we can we'll move on from this but because it
's important i think to know
what we're what numbers we're going to be receiving okay
because it's one thing to hook
up a water line and a sewer line to a line that's brought
from the the main and all the
other connections the drain connections in the building
have been funneled into your
drain pipe but it's another to have to do the rough end
plumbing so when you put the
building down the drains are already in place whereas like
with the the prefab building
if it didn't fit in the exact same location that the other
drain lines where they they're
gonna have to do a new rough end plumbing for that i would
assume there's some modifications
that are going on yes yeah so i think you have some
direction we just maybe not we've
not covered every base but the the basic point is let's get
as close to comparing cost to
cost as we can and see exactly try to really filter it down
to what are we getting what's
it actually costing us based upon all these variables and
then i think we'll be able to
move forward from that and you want that comparison from
option one and option four i believe
so as much net you know what that net is yeah okay okay
fantastic thank you all right we'll
move on to the next agenda item which is receive report and
hold discussion give staff direction
regarding policy and application process to reviews have to
review excuse me housing tax
credit requests good afternoon mayor and council members i
'm sarah keichler i'm the director
of public affairs i'm here today to present a revised
housing tax credit application and
policy so by quick way of background i know we've had a few
work sessions on this topic
but the texas department of housing and community affairs
administers the federal housing tax
credit program so the developers can apply with tdhca for
four percent and nine percent
housing tax credits they fill out an application and tdhca
ranks their application on a number
of factors and one of those factors is if they have a
resolution of support from the
community where their project will be located so council
asked staff to come up with a policy
and application process that could be implemented to review
these requests for support really
to establish expectations for the applicants and to also
streamline the review process
instead of going back and forth with the developers coming
forth with that request so here is
a kind of a breakdown of the meetings we've had so far the
first work session was in june
of 2017 and we presented research of how other cities
handle these requests it ranges from
just having a basic application to really function as an
information for informational gathering
tool to having some policy preferences stated to going even
as far as having policy minimum
thresholds on october 10th we came back with the revised
draft policy and application it
was really kind of a basic application that listed some
factors that may be considered
by council when they review the application applications
and then we just condensed and
streamlined the application somewhat and made it so that
four percent applications could
be considered year round and the nine percent would be
considered on a schedule in line
with the tdhca requirements after that work session city
council requested a joint work
session with the denton housing authority board that work
session was held on december
fourth following that work session the denton housing
authority board of commissioners did
send us did send the city a letter with their feedback on
the draft application and policy
just a couple things to note from their letter it was
included as an exhibit in your backup
they had requested that the timeline for four percent be
year round which already exists
and that the nine percent be matched annually with the qap
from the state which we'll do
as well for criteria they had commented that the criteria
the general criteria that we
had listed in the policy was too vague and unclear they
really didn't know which projects
might receive council support and then third they just
wanted some clarification and some
of the narrative sections that we had in there about what
items would be requested and should
be filled out as part of that application they also noted
that although they can provide
preliminary financial information for their projects it
would be just that preliminary
it may change as they go on with the developers so as we
were doing that in december of last
year tdhca released their timeline for nine percent
requests with a deadline of march
first due to the quick timeline and we did have interest
from a couple developers staff
decided to test out the draft application and policy with
interested developers we did
have two that completed the application staff met with them
did review one withdrew their
application and the other one which was palladium t's lee
came before city council and city
council approved a resolution of support for that nine
percent housing tax credit project
we did ask both those developers for their feedback on the
process that we used in the
application they expressed support for having this type of
process in place it really sets
clear expectations to them what we're requesting by when
and what they need to attend the only
feedback they had for improvement is that they offered if
the policy would state some
preferences or criteria that would be helpful for them in
determining could their project
be successful in denton so based upon the feedback from the
developers from the dha
board and additional staff review we've made some revisions
i think council member breaks
had a question on the one that withdrew the application was
that just something on their
end or was it something involved with the city it was on
their end so tdhca will actually
release a preliminary scoring matrix and they kind of
reviewed it and didn't think their
application was going to score high enough to receive that
very competitive nine percent
housing tax credit so they decided to put their efforts in
some of their other projects
which were scoring a little bit higher in the state's
criteria thank you
so here were some of the changes that we made for the
application we added the self scoring
matrix that tdhca has so we can actually see how they
ranked themselves on those criteria
and we adjusted the requirements in part three which is the
narrative section we did get
some feedback that when requesting letters of support or
opposition from the school district
or county sometimes those letters will be sent to ask for
their feedback but they'll
receive no response back so we at least want to have it
documented they reached out to
get input from the school district or county but if no
response is received that that's
okay sometimes for the nine percent housing tax credits
especially that are going through
the process extremely fast and in two months time sometimes
the school district doesn't
prefer to comment on in support or opposition but they
receive the notification letter and
then third for the four percent requests although they can
be accepted year round and reviewed
by city council we put at least 60 days minimum time frame
in there so that we're not rushing
through the review process and we can by the time we bring
the request forward to council
we have all the information that you're looking for and
that we can go through a couple reviews
if needed and that's just to set the expectations not that
you feel like you're pressured to
either support or oppose a project and then the last
recommendation that staff had based
upon the develop feedback from the developers and from the
DHA board was to state policy
preferences in the in the policy itself so there's really
two paths council can head
down you can keep the basic draft application and policy
and it's really just going to be
an informational gathering tool to help facilitate and
streamline the process of review or go
down the second path which is setting policy preferences
for which projects may be supported
here in Denton and I'll go over what staff recommends and
how we got to that place and
this is still provides you all the flexibility although
these are listed as policy preferences
you still have council still has the ultimate decision to
support a project or not so staff
spent some time reviewing the city's strategic plan Denton
plan 2030 the consolidated plan
for HUD policy documents that are ready existed as well as
previous council discussions to
come up with maybe what are some policy preferences that
council could consider if you if you
wish so the first is the acquisition and rehabilitation or
renovation of existing existing affordable
housing Denton plan 2030 contains a goal to maintain and
preserve affordable housing and
neighborhoods including reinvesting and reinvestment in
existing housing stock the second is senior
housing developments Denton plan 2030 includes a goal to
expand the availability of housing
choices for existing and potential community members most
in need of housing including
seniors third is the mix of affordable and market rate unit
developments Denton plan
2030 supports this policy preference and encourages mixed
income housing and neighborhoods to
address neighborhood stability and conservation the fourth
is the distance between other HTC
projects in the city of Denton and this is this preference
would actually align with the
TDH CA policy which scores applications higher if the
proposed development is not within a
two mile radius of existing housing tax credit developments
the fifth would be proposed development
would be subject to property tax it's based on previous
discussions with council property
taxes ensure that there are funded community resources
available to serve a growing population
and then six is designated designating set aside units for
supportive housing programs
and this is stated in Denton plan 2030 as well as in the
city's strategic plan to help
those most in need and those most vulnerable those are the
policy preferences we're suggesting
so we're seeking direction for any revisions if you would
like to head in that direction
of stating those policy preferences this is something that
we would recommend annually
that we review with the city council and we can make any
revisions as needed if you'd
like us to proceed we recommend bringing our resolution
back at the next council meeting
to officially adopt the draft the application and policy
councilmember breaks so I'm good
with all the options here I do have a question though I
think last legislature we saw some
efforts to restrict local control on what councils can do
regarding the housing tax
benefits do we see any legislation coming forward to prohib
it us from doing this we
will be closely monitoring that going into the next
legislative session and bringing
that as part of the city's legislative program there was
legislation introduced during the
last session but it was not approved or passed which would
remove a local government's authority
to give a resolution of support any other questions I think
if we'll go back okay here
we have no this is fine on slide five on recommendation
five I can't speak for any other council members
I mean that I have more flexibility with that one depending
on the partnerships and what
those funds would go so these are not you know set in stone
in the sense of you can't
modify from that I just want to make sure that that of all
those I'm probably the most
flexible on that given what the actual deal points are or
the terms are for a particular
project because what I don't want to do is send a message
that if there's partners out
there that you know developers want to work with it may
take it off the tax rolls that
the city is sending a message that you can't talk to him
because it's not going to be it's
not going to be worth it but that's just me so I don't know
if that's something that could
be tweaked a little bit to provide some maybe if the
council so desires but those are my
thoughts on it but I'll let others speak for themselves if
they if they would like any
other questions or comments about the go ahead I'm sorry I
can offer one suggestion to it
proposed development would be subject to property tax or
demonstrate significant community investment
sure we've had that prior wording I know the Denton Housing
Authority said well what does
significant community investment mean but at least I think
it would set the tone that
it's not just subject to property taxes right you know if
you can demonstrate how those
funds would be used and reinvested in the community which
is also part of the application
sure okay yeah that sounds good yeah yeah okay anything
else all right thank you thank
you I've had a request council members to move and we're
not there yet but just I'm
gonna take care of it while I'm remembering it the closed
meetings to the end of the agenda
so that once we get through with the work session any staff
that's not needed for the
items for individual consideration that they can be
released is that is that okay all right
I see shaking of the heads okay fantastic all right that's
what we'll do we'll move
it and I'll probably call it just right after in this order
on the agenda so just remind
me we'll go on then to agenda agenda items excuse me work
session reports 1c which is
receive report hold discussion and give staff direction
regarding existing pavement failures
on selected concrete streets
afternoon mayor council taught us to city engineer wanted
to discuss pavement failures
with you on concrete streets throughout the city of Denton
one of the issues has been
cropping up for us over time but really more as an issue
that has really come to the fore
for us over the last several years has been concrete
pavement that is failing in residential
neighborhoods primarily there are a lot of reasons for that
you see a wide variety of
things we have some pictures here just to give you an idea
of what we're talking about
there's a little bit of lamination going on here at this
curb these look fairly minor
but they're indicators of things that may come to be much
bigger issues I have to hand
it to our field crews I went out to try to get pictures of
where these failures are occurring
and I'm usually too late to catch it and they haven't taken
pictures beforehand they've
gone out and already fixed them so what you've got here
where I've seen some early looks
at pavement failures that are coming up one of the things
you do see here that's a concern
for us is you've got a longitudinal crack and you've got
some cracking at the joints
and corners that can really hint at some other things we're
seeing this across the board
and a lot of different areas throughout the city again
primarily with concrete streets
and residential neighborhoods that are newer than five to
eight years old so concrete pavement
just so that we got some base framework to work through
that top layer is your concrete
it can be anywhere from six inches to 12 inches thick
depending on the type of roadway that
you have and then you have what we call a base course says
non-erosive what that basically
just means is we're rolling something into the soil
underneath that could be a concrete
cement mixture it could be lime which is typical in our
area it could even be something totally
different where we over excavate and put some we call flex
base in which is just building
the foundation for the roadway that will typically be
anywhere from six inches and a very lightly
used area to 12 inches or even 18 inches even if we built
this road of asphalt you'd still
have the same basic layers and then the sub base is if you
were in an area where you had
a lot of destabilized soils you might do something extra
beneath that that's not typical in this
area that's something you would use in other areas.
One of the major contributors that we've seen over time to
concrete failures is that we
have a lot of utilities under the road so just to give you
a quick synopsis of what
kinds of things you're you're trying to contend with when
we're building these roadways is
you've got sewer lines you've got stormwater pipes you've
got water pipe you've got service
is that run back and forth you've got utility cables for
fiber for electricity all kinds
of things running out on the street anywhere we put that
pipe there's two things that are
potential to happen you typically dig a trench to put it in
so now I've dug a hole in the
existing soil and I've put in something different.
Usually we handle that through a detail that says here's
how much you have to compact that
dirt and you have to pound it real good tamp it down so
that it won't settle underneath
the rail underneath the road even a trench just as wide as
a small pipe can do damage
to a roadway if not compacted correctly.
There are a lot of different types of pavement failures out
there.
This little illustration right here gives you some idea of
the different types of pavement
failures that we deal with routinely the primary type that
we're concerned about with the failures
we're seeing today are these longitudinal cracks.
They're more of a concern for us because they typically do
propagate through the entire
depth of the concrete when we see those that's usually
because there is something that is
not underneath the roadway supporting the roadway so the
roadway tends to break.
The problem with rigid pavements versus asphalt which we
call a flexible pavement.
Rigid pavements were designed much like the foundation of a
house to either bridge over
something weak underneath or it was designed as kind of a
raft so it would float in the
soils that we have here where you've got a lot of clays.
The clays here when it gets hit by water they tend to
expand and when we go through the
drought season then it tends to shrink and when that
happens you just have a lot of different
stresses on the concrete that you don't have in other
places.
It makes it very hard.
That's why houses settle there's a lot of reasons for that
but that's one of the many
reasons houses do so.
Roads are no different they're just longer and straighter
typically.
And you're trying to protect the roadway and all the
utilities underneath it with what
you're building so you may be bridging it you may be doing
other things with that structure
to try to hold that pavement up.
By its very nature concrete is rigid so it acts as a
structure over the soil underneath
so whereas asphalt will tend to when it when the soil fails
underneath asphalt you'll
see the asphalt immediately start to show signs of it.
It might start to warp a little bit you might see a crack
there's something going on you
see it quickly so you can address the issue fast.
Concrete is by its nature designed to withstand a lot more
torture.
It's a rigid concrete rigid pavement so because of that it
's built more like a structure and
you don't see those failures until they really become an
issue.
So you're looking for subtle clues as quickly as you can
find them to make sure you see
them but by the time by and large you see a true failure
that causes a structural collapse
of the roadway where it starts to bend or fracture or
pieces of it starts to pop off
full depth then what you end up finding out is is there's a
much broader problem underneath.
That could be due to improper installation of utilities it
could be not compacted well
soils all underneath it could be other things there could
be materials or chemicals in the
soil that are interacting with that lime and it does
something instead of salt making that
more solid under the roadway it actually gets gummier and
mushier and it makes it harder
for that concrete to withstand all the all the loads that
you're putting on it all the
stretching and compression that you're going to put on it
over its life.
Typical life cycle for concrete pavement is 30 years they
can get 50 to 75 years depending
on how we build them and one of the things you typically
see with concrete pavement this
is a good illustration of what that life cycle would look
like if we can get 75 percent of
its lifespan out of 30 years for this before we start doing
any kind of minimal renovation
or reconstruction you're talking closer to 20 22 years
before we do anything.
I think Councilmember Briggs had a question.
Yes ma'am.
To this slide because I know that some of the calls and
issues are coming from preserve
the concrete and other some newer residential areas that
have the concrete street and they
immediately call us no matter how long it's been to fix it
do we require the the builders
who build the street to to do the to go by this time period
I mean what at what point
is it our responsibility right after it's built or is there
or are they responsible
for it up to a certain point given this chart.
There's a variety of ways to answer that so let me take a
stab at it.
So when they go build one of these streets they come in
they talk to city staff the design
criteria manual that we have in place sets forth a certain
amount of concrete that has
to go in at a minimal depth right now at seven inches it
used to be six inches we also require
a certain amount of steel to hold that concrete together
and then we require a certain depth
of that lime stabilization right now our manual shows seven
inches of concrete on top of eight
inches.
Historically the rule of thumb was six inches on six inches
and we found over time that
especially in our area that's not thick enough you end up
having to go do something to it
or you find out that the materials underneath that soil
were never analyzed through a technical
exploration so I go out there and I core with a machine
drill into the soil and I find out
what's underneath it I can find those things that will make
that lime not work well should
I use something different.
If I don't want to spend that money to go do that then what
we've put into the manual
is use this as your minimum because it's a very
conservative pavement design to handle
the worst case scenario in the city.
If you'd like to do something different then you need to go
do that analysis so that's
in place.
Let's say you come in you do all those things you do the ge
otechnical analysis or you opt
to just use our standard here's the minimum specification
we'll accept if you go forward
that we permit it the contractor will go build it our
inspectors are supposed to be out on
site they get there as frequently as they absolutely can
with all the work we have going
the contractors also required to do pavement samples so as
they're pouring concrete they
pull concrete we call them cylinders because they're in
little six inch or three inch
cylinder depending on how much of that test we want they
pull that out of the concrete
that comes on site and then they go and set it in an incub
ator for 27 days or close to
that and then we break it to see if it meets the minimum
specification is it strong enough
so all those things happen they even do that with the soil
underneath the roadway as they
sample that to see if it has been compacted enough we get
those tests back from the contractor
to make sure that we're seeing what we thought we saw in
the field just while they were placing
it and then once the contract is complete they put
everything in and we've said yes
this looks good they are required to give us a two-year
maintenance bond so we have
a warranty for two years the problem that we're seeing with
these pavement failures
our streets crews and our inspectors are catching what they
can within that first two years
but we're seeing these just outside the warranty period so
they're happening at three years
at four years at five years and we've really seen a run on
these over the last five years
that's where we're noticed so it means they happened eight
years ago basically okay thank
you does that answer your question yeah okay all right so
the pavement life cycle one of
the things I would like to bring your attention on this
particular chart is if you look at
the excellent good fair poor very poor and failed that also
coincides with our OCI our
pavement scores so a hundred would be excellent you get
down to good we're at 80 percent
fair at 60 percent 40 20 and zero so if you see those
pavement scores when we're talking
about maintaining a 40 as a target because a lot of things
are lower than a 40 and we
want to get up to a 60 we're talking about these things
right here and it relates to
the pavement life cycle once you get down below fair and
get into the below 60 percent
you're incurring a lot more cost over the life of that
concrete to maintain it and reconstruct
it so that's where we're coming up with these OCI's and how
that impacts us long term just
to give you an overview of where we're noticing a lot of
these pavement failures we see a
lot of them on the south side of town if you see in yellow
that's where our crews have
been exact have been extremely productive and they've gone
out and replaced what they found
we've still also started to see some on the north side of
town we're overlaying this on
soils maps so that we know are there some soil conditions
that are causing this is it
just perchance a lot of things happening all at one time
you know one of the things that
we're struggling with is we have limited amount of
resources when it comes to inspections
we have six public works inspectors and they are averaging
on on average they're trying
to manage somewhere between 70 and 90 projects between
those six so if you just run the numbers
and I wanted to get them on site an hour a day to make sure
that everything's getting
done correctly I can't get there without them working 12 to
15 hours a day five days a week
that means they're going to be out there trying to inspect
something when the contractors
not there so the reality is is they're either on site for
an hour or two one day and then
they got to move to something else and they don't come back
for another two or three days
or they're on site for 15 20 minutes looks good and then I
move on these guys do a really
good job of getting out and making sure that they see
everything they can see but the realities
were just not there that often one of the things that we
have seen over the last five
years on this slide it says payment failures date back 2005
that goes back to a subdivision
wind river the states off of unicorn and wind river that
whole area on the south side of
town just east of Teasley there was a lawsuit that lasted
eight years I'm sure several
y'all remember that one after that lawsuit streets really
took a lot of time to make
sure they were keeping up with it and within the last two
years is when we've seen the
primary expense and the total number of lane miles here is
about 60 to 75 percent when
we've seen it over the last two years we've spent nearly
three and a half million just
trying to keep up with them before that over the two or
three years before that they've
been noticing them they just they're worn as many and that
just tells you it's propagating
over time we're just not we're still not getting the 10
years the 20 years out of life for
that concrete that we should be getting before we have to
do anything so I want to ask you
about that because I mean I understand what you're saying
and I'm I hope in this budget
process I would much rather spend a little money on a
couple few extra inspectors than
this if that's what the issue is but I mean I obviously you
know in this area the soils
are horrible yes so when you say we should be getting 10 to
20 years of life I can't
think of anything that has been poured in concrete where
within the first five or eight
years first of all within the first year you may see a ha
irline shrinkage crank all right
you may see something a little bit larger that's not
necessarily indication of some
structural failure absolutely so I'm just trying to
understand when you say that what
the expectations are I'm trying to understand what the
expectations are of somebody builds
a street it should last 10 or 20 years until we do X well
you're going to have cracks that
develop that people can go seal to keep water penetration
from from eroding the sub base
you might depending on how it was poured what weather
conditions you might see a little
bit of scape so are you saying and I'm just trying to
understand what you're saying about
what your expectations are so when we pour concrete street
there should be no kind of
I guess I'm gonna say maintenance for better lack of a word
but you're distinguishing
between maintenance whatever that means on a concrete
street I know what it is for asphalt
compared to for a concrete street what are you what are we
having to do now that you
don't think we should have to do until 10 or 20 years once
somebody's poured a street
or a different number based on so that's a good question
yeah what I don't expect to
do is to rip up a whole panel four or five of them in a row
and put them back down okay
you're saying remove it all together that's something
underneath it we're talking about
yeah you're you're absolutely right there are a slew of
pavement failures that can happen
out there and they don't structurally cause the road to
fail okay what we're seeing is
is say a road typically crowns in the middle like this we
're seeing in the middle of the
road the road collapsing like this okay now you still drive
on it but at some point you're
gonna get more of it to pull apart and that's what we're
actually seeing is you're saying
the crown of the road drop a foot okay all right typically
it lines up with a utility
line sewer line is where we're really seeing them but doesn
't necessarily mean that's where
we're seeing all of them some of them we're seeing and it
looks like we're having some
other issues out there we don't know exactly what's causing
them okay but we're talking
about a full depth concrete structural pavement failure not
some spalling on top some scaling
maybe they didn't get the moisture just right and the top
quarter inches flakes not I mean
we're not talking about those things those are easy you
basically paste that over with
another substance and it's good to go okay we're not
talking about those issues we should
not have to reconstruct a panel of pavement for 30 years
that's what I'm talking about
that's the expectation when we design these roadways okay
all right okay all right sorry
trying to get my train of thought back no no you're getting
there's a good question
there yeah so some of the areas that we've noticed this are
on the south side of town
but we're also starting to see them on the north side in
town all of them primarily in
newer subdivisions that are ten years or less in their age
that's exactly the type of areas
where we're not expecting to have complete structural
failure of a one panel two panel
if you go on google earth you can actually see on one
stretch of roadway where our crews
were taking out an entire block to replace those panels
because once you pull one where
you're seeing the primary failure you get into the dirt you
end up finding out there
it's much bigger an issue than you thought okay so that
those are what we're talking
about so some of the possible causes we've hit on them
throughout the discussion just
in different ways but just to summarize those there's a
lack of upfront geotechnical exploration
a lack of desire to want to go check and see what's out
there so that this doesn't happen
because it costs money it absolutely costs money to get a
geotechnical engineer involved
and have them go and test it and the standards that we had
one of the vast majority of these
subdivisions were put in were using pavement thicknesses
that were much thinner you didn't
know if they would or would not work on that particular
soil type because nobody really
checked it so we used that standard or we grandfathered
something in as opposed to either
having a stronger section like we do now a little bit more
concrete stronger foundation
to that concrete or have the developer go and do the ge
otechnical exploration tell us
what they think it should be substandard pavement design we
just talked about that six on six
was a rule of thumb let me just let me ask you a real quick
question
I want to make sure I didn't I heard what I heard you said
that you something about
geotechnical and the developers tell us what they think
should be or say that one more
time so one of the common complaints we hear from
development from the development community
is they don't want to go pay for geotechnical exploration
so they don't want to go pay to
have a bunch of holes drilled that's that is a common
comment that we hear so they just
want to use the rule of thumb or they would use the minimum
pavement section of course
so yeah okay all right I've just had some comments I'll
just save them for the end
some other possible causes or construction defects it could
be that when the inspectors
not on site or maybe one of them some of the materials that
were used in the concrete mix
had something in it that caused the concrete to fail sooner
that's a possibility it could
happen lack of quality control we talked about that and
just not being able to have enough
bodies on site enough of the time to make sure that we know
what's going on and we're
getting the right quality of work TV I'm sorry customer
breaks and so back to that do we
have any recourse if we go back in and something has failed
say in the third year and we noticed
that they did something not right or skipped a step is
there or since it's two years past
it bad on us because we didn't catch it kind of thing
typically I've seen that be a very
hard road hoe because it's very hard to point back to well
you didn't do this you didn't
do that after so much time has gone by if there's a very
clear indication of that you
can absolutely try to make that case I believe that was
part of what we tried to make the
case with that wind river Wind River subdivision was
exactly that scenario was something was
not right whether it was design or it was construct ability
or methods or even materials
that was the path we were trying to go down it's very hard
to make that case so it's
something we need to make sure upfront and yes and ahead
absolutely thank you you're
certainly talking about concrete roads yes sir the street I
live on is asphalt yes sir
and Emerson between Old North Road and Nottingham between
Nottingham and Rockwood it's been
rebuilt the good thing about my section of the street is
that we don't even have to
have road humps in order to have speed control because
several years ago we had all of the
lines to every house replaced going out yes so the ones
that are further away because
the line the line was on the south side of the street so
every 80 feet we have a dip
significant because so it was that lack of quality control
that that when they were putting
in those new I don't know if they were water or sewer lines
that they did not compact the
soil properly and so so you've had that failure of it could
be I don't know the particulars
of that I don't know if that was done by in-house crews or
if that was done by a contractor
I don't know I would need to know those particular details
and we could look into it and find
out more about it we have a debate as to whether we want
them fixed or not because cars go
very slowly sure but but we have some extra bills for our
alignment yeah issues so potential
solutions one solution that we've already put in place is u
pping the minimum requirement
for roadways so we've we've taken what is a pavement design
for some of the worst areas
of town where we know by experience we've had to go with a
thicker pavement section
that's the minimum requirement now if you would like to it
even says this in the manual
whenever you're doing a project if you would like to come
in and do the geotechnical exploration
and tell us you want to use a different pavement design
based on a sign sealed report from
a geotechnical engineer or licensed professional engineer
state Texas will be glad to look
at that that's absolutely an option but we just want that
assurance that you've done
that otherwise we're going to go with our preferred minimum
that minimum is is conservative
and it does have varying depths and strengths and we've
also given them the ability to
with the current manual to say you don't have to do purely
lime stabilization if you'd
like to use flex base which is another option there are
other alternatives that we'll even
consider there as well when you said that our minimum is
very conservative I don't
know what that means means we're building it stronger for
some of the more worst case
soil types in the city thank you that way we don't have to
worry about even if you're
in an area where you could go less we want to make sure if
you're not going to do the
upfront homework then we need to do that and I would say
that with our CIP projects we
do test every project we core and drill every 500 feet if
not closer to make sure that we've
done that exploration up front so on the minimum pavement
standards those have increased how
does that compare still say because we want to encourage ge
otechnical exploration how
does that price compare with our minimums increased is it
still more financial prudent
for them to do the minimum rather than the geotechnical
exploration it depends on the
particular project and what they're putting out there I
mean if it's a very large subdivision
absolutely and I don't mean to imply that every developer
in the community doesn't want
to that's absolutely not the case with the vast majority of
developers we work with understand
that it's it benefits them in the long run to do their
homework up front and not come
back with well I just don't want to do it but we do have a
few that like to make that
claim so we've given them the option both ways what is it
possible to I'm sorry is
it possible to expand the guarantee from two years to say
like three if they do one and
not the other it's definitely a possibility I don't think
there's a limit on how much
we can ask for it now it does offset in price if the
contractor is going to be held to something
they've put in place there's a limit to how long they want
to be responsible for a road
because there are a lot of other things that could be the
cause of a road that fails so
there is a limit to how far they'll go before the price
just gets exorbitant anything can
hold together for two years almost I mean it seems okay
thanks so some of the other
possible outcomes of this assessment so what we're
recommending is that we engage a consultant
to go identify what's really causing these problems they're
wide enough spread we've
invested enough money instead of us taking a knee-jerk
approach to the solution we'd
like to have a holistic approach to the solution which may
generate us coming into a program
approach to resolving these payment failures that are
outside the warranty period it may
mean that we need to have more inspection staff available
or we even look at contract
inspection staff to make sure that we can handle the ups
wing in development projects
and CIP projects and then making sure that we don't let
projects go by under a grandfathered
set of standards you know just because you came in 30 years
ago doesn't mean you get
to use the 30-year set you still got to go by what we're
doing today so our recommendation
is we approve a contract with Tegnault and Perkins we have
negotiated contract with them
we'd like to seek council's recommendation and approval to
go forward with engaging them
to test the vast majority of these areas and new areas that
are under construction now
that may have gotten through either a grandfather or just
making sure that we're double checking
what we're doing so that we don't have any issues with
those subdivisions as they're
laying out concrete streets.
Tegnault and Perkins was part of our recent RFQ they were
on the roadways and transportation
segment of design and then based on that we'll be getting
better recommendations we'll bring
back to you on what the pathway forward is to resolving
these issues correcting these
issues and where we stand in that program in itself and
then of course we may find out
that there are some other recommendations that they see
once we dig into this and really
get an idea of what the causes were there may be some other
things that come out of
that we'd like to be able to come back to you and present
what those might impact for
us in the future.
Any questions?
Explain to me when you say grandfather clause grandfather
what does that mean?
So let me give you an example.
Yes I can give you an example that I've heard.
One is a developer comes in and has platted a piece of
property say six years ago seven
years ago and this was with some previous staff that is not
here anymore.
They come in they get the plat or they at least start the
preliminary platting process
they haven't gotten CEPs or civil engineering plans
together so they're ready to go build
the project they wait a few years and they come back in
four or five years later when
they're really ready to go and they bring us the plans.
Well I want to use what I was approved under originally.
Well there were staff again no longer here that allowed
stuff to go through with the
previous set of design requirements.
So this is really easy to figure this one out.
Are we still doing that are we still going by that practice
?
No.
Okay so that's off the table.
There's not any more grandfathered stuff in.
Okay.
All right.
Okay.
Any questions?
I mean it sounds like from what you're telling what you're
sharing is that when we're when
people are putting in new water and sewer lines that were
somehow the compaction isn't
correct or the moisture isn't correct so that those lines
cave in.
That could absolutely be.
And erode the base underneath.
All right any questions comments recommendations you're
going to get insulted to give us a
more definitive answer and then we'll come back with a yes
for the pathway.
As we said on the slide this contract would be coming to
you next council meeting for
approval.
All right great.
Thank you very much appreciate it.
Thank you Todd.
Okay so we are skipping the closed session items till
moving them to the end of the agenda.
So now let's take a little break.
Yeah let's take about a five minute break.
And 18 at 2 55 our first item on the agenda are items for
individual consideration.
Item 1A is considered option of an ordinance of the city of
Denton Texas amending the code
of ordinances related to Chapter 2 administration titled
ethics.
We do have a blue card wishing to speak so I'm going to now
recognize the public speaker
Mr. David Zoltner if you'd like to come and state your name
and address your time will
begin.
And this is an item for individual consideration so it's
not a public hearing to so to speak
you would need to have a blue card so just want to let that
make that announcement to
the rest of you.
Thank you Mayor and Council my name is David Zoltner.
I live at 2501 Timber Trail in Denton.
A bit of a disclaimer I've kind of lost track on where you
were moving and the status of
this ordinance over the past couple of months.
March and April for me were family funerals and flu and
other exciting things so I'm kind
of catching up on where you are.
First I want to categorically support this final draft of
this ethics didn't ethics code
and offer my appreciation to every member of this council
and especially Alan Boracuis
for all his hard work and thoughtful meetings.
Especially since two years ago majority of this council
publicly scolded a sitting council
member for even suggesting that Denton needed an ethics
ordinance.
After that memorable work session a group of private
citizens went to work drafting
an ethics ordinance believing an initiative petition might
even be eventually necessary
to get this job done.
One of the basic principles of that ethics code drafted by
citizens was the belief that
an ethics board should be as apolitical and independent as
humanly possible to earn the
public's trust.
That independence would be far less about credentials than
how members were actually
chosen to serve on an ethics board.
We felt that a best practice would be a formal inclusive
nominating process allowing as many
as possible across the community to participate.
The least acceptable option in our opinion and according to
current thought from ethics
scholars at the time would have had individual council
members appointing their personal
chummies to oversight ethics board as if an ethics board
was just another routine appointment.
Last week I sent some background information to council
members on the philosophy behind
this nomination process and I hope you've had some time to
look it over briefly.
Let's consider hypothetically just for the moment what it
would mean in terms of public
trust if each of the following were standing members of a
nominating committee as to submit
names to a pool to be considered and chosen by council
majority to your five or seven
member board.
The Denton Bar Association possibly, the Serv Denton Board,
school trustees, the school
superintendent, the city manager, Denton Interfaith, the
commissioners, the dean's office of TW
and UNT, the list would be endless in a town of this size.
If the effective date of this code is still four months
away, on September 1st there is
still plenty of time and opportunity for this council to
fully explore how this board is
to be seated to maximize public trust.
I hope you'll consider this as a constructive suggestion
realizing that Denton has a unique
opportunity to raise the ethics bar and present a model
code for other Texas cities to emulate
and follow Denton's lead for a change.
Thank you.
>> Thank you.
>> Any questions for the speaker?
>> Yes, councilmember Riggs.
>> So are you suggesting that council put in certain groups
and then those groups nominate
someone from the community and then council approves like
say seven from that nominated
group from the community members?
>> Yes, there are a number of different ways to actually go
about this.
This nominating committee or I talked to Alan about this
after one of your meetings and
although this is not commonly done, as far as he knew
anywhere close to us here, he understands
the philosophy behind this independent board.
Actually some other cities actually have a regional ethics
board where, for example,
three or four cities that are sister cities close to each
other that are somewhat familiar
with each other's ordinance would share a complaint.
In other words, you would not have any vested interest
whatsoever.
Names would be irrelevant.
And so there's a number of different ways to do this, but
this nominating committee
or nominating board would hopefully -- I know you can't
always do it, but it would hopefully
strip the politics away from this as much as possible where
names and things such as
that are irrelevant.
So it's just an option.
He's aware of it and he didn't feel like it was his place
to recommend it to you, but
it's just something to consider.
Because you've got four months to do this.
This is not just another committee, in my opinion.
So I hope you'll take this very seriously moving ahead.
>> Thank you.
>> Thank you.
>> Thank you.
>> Okay.
I see no more cards, so does the staff have a presentation?
>> I do.
Brian Langley, deputy city manager.
I have a very short presentation.
I know you've had many hours of discussion on this, so I'll
get through this very quickly.
Just in terms of background, the city council formed a
charter review committee in October
2016 to look at various charter issues that you were
concerned about.
The charter review committee did look at a number of issues
, and on the ethics matter
in particular, they presented their recommendations to you
in June of 2017.
And those were ultimately approved by the voters in
November of 2017.
Then the council, after that, hired the attorney of Alan
Borquez to begin working with you
to draft this ordinance.
Number of different meetings that we've held since June of
2017 on this issue have various
drafts that we've looked at over the last few meetings,
including three public hearings
that were held to get a variety of public comments on the
ethics ordinance.
The key elements of the code of ethics are the following.
It would apply to the mayor, council, planning and zoning,
zoning board of adjustment, public
utilities board, and all the department heads that are
appointed by the city council.
And to a limited extent, some of the former city officials
and vendors.
It also would prohibit gifts over $50 and no more than $200
from a single source per
fiscal year.
And it would create a seven member board of ethics to hear
complaints of alleged violations
in the code.
And it would include sanctions for violations of the code
of ethics.
Yes.
So on that 200 from a single source, that doesn't mean from
one individual.
That means total, right?
$200 total from all sources, like individual people.
Let me look at the exact language for you.
Six different people can't contribute $200 in a single year
.
It would be from one single source providing one gift to
you, a gift of four different
gifts of $50 in that one particular year.
Is there a maximum though in gifts that one can receive or
is the only limit $200 from
one source so that say six different people can give you $
200 per year?
The maximum would be $200 per fiscal year.
And the language in that section reads that she'll be a
violation of this article for
a vendor to offer or give a gift to a city official exceed
ing $50 per gift or multiple
gifts commutatively valued at more than $200 per single
fiscal year.
Does that make sense?
Hopefully I answered that question for you.
So it's one vendor, if they try to give more than four
gifts of individual gifts of $50,
that would be prohibited.
Let's say, so the way that it's worded, five different
vendors could give you up to $200.
So there's not a limit on the amount of gifts you can
receive per year.
And that's why I thought that that was per year, not per
vendor.
So I understand your question.
Yeah.
I'm a little confused by that.
I thought our maximum total allowed gifts was $200 per year
, not per vendor.
That would make more sense to me, I think.
And that's why we included all those exceptions, I thought,
for community functions, tickets
given out, that kind of thing.
So the wording is different from what you thought.
We can certainly go back and address that.
I understand your question.
I think the way I'm interpreting the language here is it
would allow it from multiples.
Yeah.
Okay.
Well, we need to get some clarification on that to make
sure that we all have an understanding
of what that was supposed to be.
We can certainly do that.
Okay.
I'm sorry.
Go ahead.
Last slide.
If the council does want to move forward with adopting the
ordinance tonight, we would then
need to consider nominations for the Board of Ethics on
that process.
We'd develop some training for the city officials and the
board.
We'd also need to bring back the rules of procedure for the
ethics -- Board of Ethics
itself and then develop an internal procedure for the
receipt of complaints and maintaining
the conflict of interest logs.
All the things we've been talking about.
Mayor, those are my brief comments on the ordinance.
Be happy to answer any other questions that you may have.
And I think we had a -- somebody's going to fill out a blue
card and I know we're not
supposed to take those until after agenda item is called.
We've done that out in the regular meeting.
Because we didn't know exactly what time this meeting was
going to start.
If council is okay with that, then we'll move forward with
that once I get it.
So I have a question.
We had something that was added.
It was section 2.277 about subpoena authority.
And it helped me understand just what the origin of that
was because I know we've been
meeting a long time and we haven't really discussed that.
Was that just Alan's recommendation?
What's the origin of that?
There was a -- as you may remember going back to when we
worked with the charter review
committee, they had some recommendations they brought forth
, the specific things that they
wanted to include in the ordinance.
They did not include the subpoena powers in that
recommendation.
But through several discussions that we had with the city
council, the city council added
some language that would be submitted to the voters to
include that provision, that requirement.
That language was ultimately approved by the voters to
include those subpoena powers.
So you're right.
It wasn't discussed with the council over the last few
weeks.
And I think it probably should have been.
But we didn't discuss it with the council.
And so we wanted to add that into the ordinance to be
consistent with the charter.
So because I know that there was a charter provision about
adding subpoena power.
But was that just a separate charter provision or was that
embedded within the ethics portion
of the charter?
It was embedded within the ethics portion of the charter.
Okay.
Of the language that was submitted to them.
I'm going to go with Councilmember McGregor and then
Councilmember Briggs.
And then Councilmember Ryan.
Thanks.
So that was one of the reasons why I wanted us to go back
and look and see what we were
charged with doing to make sure that we covered all of our
bases.
Yes, sir.
But I was surprised that we hadn't covered that base and I
was surprised when I saw it
there because I'd forgotten about it.
I have a couple of questions about that because I think it
's fair if we're trying to get information
to make a determination that we have access to information
or that the ethics board would
have access to information.
I am also concerned, however, that this might be used in a
way that becomes a phishing expedition
asking for information that's maybe not relevant.
So I guess one of the questions, and this may be a question
for an attorney, is would
it be appropriate in the ordinance to give any direction to
the ethics board as to how
when a subpoena for documents might be issued or when a sub
poena for someone to appear might
be issued.
So that's a question, there's another question that goes
along with that is in legal proceedings
I know that when there's a trial or something when somebody
is, there are people that can
issue subpoenas.
My guess is that there has to be some logic, some reason
behind it, some legal rationale
for it so that it's not, I think there's something in the
Constitution about search and seizure
that there has to be probable cause or something.
So can somebody talk to me about that and the legality
involved there?
Typically when a subpoena is used in a trial setting it
will be to subpoena individuals
or documents to a trial and I think that is what is
contemplated here when there's a hearing
before the board of ethics is what they would want to use
that for to be able to compel
attendance or production of documents.
So would there be any protection if they were asking for
documents that were not applicable?
So they say we want any and all financial documents, you
know your checkbook, register
and your bank statements for the last five years.
Typically what happens in a civil or criminal proceeding is
a motion to quash is filed by
the individual that the information is being sought from
and we would need to develop procedural
methods to address that before the board because typically
that would go in a civil case or
criminal case and we go before the judge in which that
trial is pending.
My concern is I want an ethics board to have access to the
information it needs.
On the other hand I don't want them to have free rein to
ask for any and all documents
that might or might not be relevant and I would certainly
want to have some procedures
in place to protect folks privacy rights.
Also I would want some procedures in place to ensure a
level of fairness and a level
of certainty that the documents that are asked for,
documents that are needed in order to
render a fair judgment.
How do we go about doing that?
We might be able to scope out the range of information of
what could be subpoenaed by
the board and limited to that but I think that you have no
idea what would come before
the board in terms of types of violations that they may be
considering and so it would
be difficult to craft that.
Do we have any rules, I think we have some rules that for
some actions on the part of
the ethics board that there has to be a super majority vote
?
Right now that was it.
That was the only time they had that.
That was the only time they had it was on the frivolous
complaint but other than that
everything was done by a majority of the members of the
board.
I believe that's correct.
Before we get into too much discussion because I think
there's a little bit further discussion,
I wanted to give the speaker an opportunity to speak.
Is that okay with the council members?
Sure.
Okay.
If you'll come up and state your name and address your time
will begin.
And since I allowed that if there's anybody else that wants
to fill out a blue card and
speak feel free to do that.
Simply because we didn't know what time this was going to
start so it's hard to gauge when
you need to show up.
Thank you.
Name and address.
Members of the council.
I'm John Johnson, 319 West Oak here in Denton, 76201.
Thanks for giving me the opportunity to speak.
I was watching you on my computer at the office and you
guys took a really short break and
jumped right in.
So thank you.
So I'm here today kind of I would say representing the
business community.
The first of all I'll just say I'm in favor of an ethics
ordinance.
I think an ethics ordinance should be there to enforce
penalties on someone who does something
unethical.
I've emailed all of you as these revisions have gone
through with some concerns.
My major concern is this ordinance seems to me like it is
trying to prevent someone from
having the opportunity to be unethical.
And I don't think your intention would be to exclude any
certain members of the community
or people with a certain type of job to be able to serve.
For example, ZBA, it states you want people that are
architects, civil engineers, understand
construction, et cetera.
Yet those people have to represent their clients before the
city to make their living.
And the way this thing is written for a period of one year
after, they wouldn't be able to
do so.
It was two years, now one year.
I would prefer not to get into a bunch of details because
there's a variety of things
in here that I think a lot of folks have some concerns with
.
What I'm here to ask you to do today is, here it is on a
Tuesday at 3 o'clock.
I think you got quite a bit of feedback from the Chamber of
Commerce representative and
some other business folks about some concerns at the last
public hearing.
Those folks are all at work right now.
And so to take action on this on a Tuesday afternoon
without folks who are at work having
the opportunity to come back after having read this current
revision, I think would
be not very transparent.
So I would appreciate you guys considering taking action on
this at your next evening
meeting which would be, I believe, May the 1st or 2nd so
that folks have a chance to
review this revision, come to a public hearing in the
evening and give their feedback.
My personal feedback is unethical people will be unethical
no matter what your rules are.
And ethical rule following people will follow whatever
rules you have.
And so, you know, this seems to be crafted in such a way to
try to make sure that no
one has the opportunity to be unethical.
But the penalty is a letter.
And what the voters voted on was a stronger ethics
ordinance.
While this one's a lot longer and has a lot more detail in
it, at the end of the day an
unethical person gets a letter saying they're unethical.
I would prefer if someone does something unethical, under
handed, illegal, money under the table,
whatever it is, put them in jail.
Fine them 20 grand.
But let's don't preclude people that have the expertise
that we need on planning and
zoning on ZBA, on historical landmark commission and on
council from being willing or able
to serve.
Because I think attorneys, civil engineers, architects,
real estate brokers are going
to say they can't serve.
Thanks for giving me the opportunity to speak.
Thank you, Mayor, members of the council.
I wasn't going to speak today, but you got off on a topic
and you're still working on
it.
I just want to say something about subpoenas.
In my opinion, in my limited experience, I work on Fenner
arbitration boards.
Generally speaking, one side or the other is going to ask
for a subpoena and it's not
usually the board itself looking for more documents.
It could be, but you're going to have the opposing
attorneys or representatives give
you the reasons for or against the subpoenas and then the
board itself will be acting as
the judge to determine whether they need a subpoena or not.
So I don't think you need to limit the ability to subpoena.
You just need to train your board members in the
appropriate use of subpoenas.
I don't think you need to require a supermajority.
I think it's just a question of training.
Otherwise, I like the ordinance.
It's not perfect.
I support it 100%.
Thank you.
Okay.
Any questions over here?
We'll look over here to the right side.
Sorry.
Yeah, we'll go with Mayor Pro Tems.
I'll come over here.
Yeah.
I just wanted to clarify the vendor gifts issue.
It seems what I recall is that there was a $200 cumulative
limit for vendor gifts.
And so I wanted to go around and make sure that that's
accurate because I remember us
explicitly putting a limit on vendor gifts.
It was not an unlimited amount of money.
So that was my first clarification from the council.
And the second item I wanted to clarify was if that's
everybody's recollection and that
$200 is the annual limit, then there's a really easy fix to
that on section 2.273, which
is require, you know, putting a period and then saying this
shall be cumulative for all
vendors.
So.
Okay.
All right.
Well, let's go ahead and answer your question to the
council.
What is the remaining council's recollection of that
particular?
We'll go with Keely and we'll just start around.
Council Member Briggs, we'll start around and come back to
you.
Thanks.
Well, we're going to start here and then come around the
horn.
Yeah.
So my recollection is the same, that the $200 was max.
I recall I was at zero and then it kind of went up from 50
and then $200 decided we decided
to be the max.
And then there were some questions and concerns about that
being so low.
But then that's when all the exceptions and exemptions from
charity functions, backyard
picnics, that is the reason why those were added to that
section.
That's what I recall.
And I am in favor of it being 200 maximum.
I mean, we actually have held our staff to $0 in gifts.
And so allowing us and voting for us to have an unlimited
amount, but only 200 per vendor,
I think is not a good thing to do.
Okay.
So your understanding was that it's capped at 200 per
vendor per year.
No, no, total.
A vendor can that we could only receive up to $200 per year
in gifts from anybody, from
anybody, not per vendor.
Okay.
Gotcha.
All right.
Councilmember Ryan.
Well, I recall the discussion and I know we kind of talked
about both ways, which way we
wanted it.
And as I recall, this language has been in there since
about draft B or so.
It's been that way for quite some time.
Okay so then you're saying if we put it in terms of the
different direction of is it
$200 total a year amongst all people who are giving gifts
or 200 per vendor.
And I'm okay with either way.
All I'm saying is that this, this particular draft, that
portion is not changing the draft
since early on.
Okay.
Councilmember Gregory, any comments?
Councilmember Duff, any comments?
What I recall, it was $200 for a vendor.
And I don't have a big deal to yield to that.
You know, if it's a, it can be 200 max or it could be per
vendor.
But I think the way it's written right now, it says per
vendor.
Right.
Yeah.
Per year.
Yeah.
Yes.
Councilmember Gregory.
I think that's a change, we probably need to make it to sub
paragraph two and sub paragraph
three.
Because one of them refers to the city official and the
other refers to the vendor.
So let's take the first policy question.
Are we all okay with making it to where it's $200 per year
maximum amongst any gifts?
You know, you can't receive more than $50 from a single
vendor or source, but you're
limited to $200 maximum from any sources for that year.
Is that what we're saying is what we're wanting?
Is that okay?
Is everybody okay with that, that change?
Okay.
All right.
And then we'll work on how we make the changes to
accomplish that goal.
Any other questions on that or Councilmember Ryan, did you
have some additional questions
or?
I had additional questions.
Okay.
Any other questions on at least that policy that Mayor Pro
Temin brought up?
It sounds like we've got that resolved.
So then I'm going to go on to Councilmember Ryan and his
additional questions.
County is on the new ad of the subpoena power and I guess
this would be for legal.
Because we have a subcommittee as well that's listed in
here as to who has the subpoena
power.
Would this require a vote of the full board of ethics?
Would this be the chair?
Would this be the subcommittee?
Who actually would have that power?
It would need to be delineated in there and I would expect
that it would be limited to
the board itself and not to any subcommittee.
So I think that language needs to be added into this.
Yes, and I've got a couple questions on that.
And I think, I mean, what I don't want to be doing is
crafting this ordinance today
and then passing it today.
I think this is an important policy that we need to make
sure we get it clear and we have
an opportunity for people as we're making these changes to
come and speak to us if they
want.
So I have a question about the one that was added about a
vendor.
It's section, I think it's under definitions.
Yes, section 2269.
Says a person who provides or seeks to provide good
services and or real property to the
city in exchange for compensation.
This definition does not include those property owners from
whom the city acquires public
right of way or other real property interests for capital
improvement projects and I know
that our attorney had sent us some backup information on
that.
But I have a question about it.
We buy property for a lot of different reasons.
And capital improvement projects is broad to some degree.
But I don't think that necessarily unless the staff will
say that would cover probably
any purchase that we would have for real property for a
capital improvement project.
What I don't want to do is have a purchase that is not a
capital improvement project
that somehow falls outside of this because it seems like
the reason for this addition
was to exclude sellers from the particular rules of this
ethics ordinance that we're
purchasing property from.
Is that correct?
Yes, sir.
I think that was correct.
And Councilmember Gregory.
I think what we were trying to get at as I recall during
the discussion and I think why
we talked about capital improvement projects is the notion
of when the city approaches
a property owner about the purchase of property because we
want to expand the park or we want
to expand a roadway or something of that nature.
So when we're initiating the need to acquire property to
accommodate a public need, the
person that we're trying to acquire it from is not a vendor
.
They're just a property owner that has been approached by
us.
That's what I had in mind and if there is a better way to
word that than to say for
capital improvement projects.
But my thought is an individual in town who's owned a piece
of property for five years or
50 years and the city comes to them wanting to buy it isn't
really a vendor.
Okay and I understand that distinction but are you saying
that if someone has a piece
of property and they simply contact the city proactively to
say hey I've got this piece
of property it's next to X that you might have an interest
in?
Are you saying that they would somehow fall under the
definition of a vendor because the
city didn't seek them out first?
Is that the delineation in the who's making the initial
contact or no?
Well now you've confused me.
I don't know.
Okay well I just want to make sure that if we're going to
be thinking about this we're
not going to want to be changing this within the next three
or four months.
I mean it's going to be enough scar tissue in it as it is
to say hey we forgot this or
we've got a situation now we didn't think of.
So I guess if what the gist of it is that if the city is
purchasing property whether
it was approached by the seller or the city if it's being
purchased for a public use which
that entails a lot of different types of elements then they
're outside of the vendor definition.
Well I'm thinking it through.
So let's say a person has got a piece of property that is
on a street that it has been announced
is going to be widened.
We know we're going to be widening it.
We have the preliminary plans for how wide it's going to be
.
It's going to take a significant portion of that person's
property.
That person was going to put the property up for sale
anyhow now rather than just putting
it on the market they approach the real estate office of
the city and say I was going to
buy this you just want to buy the whole thing anyway.
I was going to sell this you want to buy the whole thing
anyhow.
I don't think that makes them a vendor I think they're just
trying to deal with it.
They're just getting they're dealing with the inevitable
but they're initiating the
contact.
I don't I don't think that makes them a vendor when they're
just initiating the contact.
Well any property that we're going to purchase would be for
public use or we couldn't be
acquiring it so we could just simply end the sentence at
property interest period and not
have the public or capital improvement project language.
Well and we'll run this I mean that's what I'm saying I don
't want to start crafting
this.
Yes Mayor Pro Tem.
So if I'm understanding what you said earlier correctly and
I'll touch on the vendor issue.
You're saying because there are some clarifications that we
've made in today's meeting that we
should postpone a vote until the next meeting which would
be I'm assuming it won't be during
our Denton ISD joint lunch so it would be May 1st.
So on May 1st that means that nobody can make any
adjustments to the ethics ordinance at
all because if we were to make any changes whatsoever then
by your logic we would also
have to postpone another week to give people time.
No no that's not right.
Okay.
Because I remember talking in the meeting last time that
the rationale at least I wasn't
in the meeting but the rationale I heard at the day is when
I was in the meeting that
we wanted a clean copy with no changes or modifications so
that we so that the public
number one would be able to see a clean copy and that we're
not crafting things on the
day.
So it's not a matter of making a period or ministry we're
talking about making some definitions
to the subpoena power.
So I'm not trying to push this off but I don't think we
have to also figure out how we move
this forward if we're still trying to find substance.
Some of these things change that we hadn't even talked
about and I'll be perfectly honest
with you I mean hearing one of the speakers talk about hey
what are some other options
for appointing the board we can consider that after it's
passed but I don't think that's
necessarily a bad idea to talk about that.
We don't have to do that before we pass it so that's just
my opinion there's five other
six other five other people up here so I'm trying to figure
out what what where is the
dividing line between well we can talk about board
composition after the ethics vote is
passed but subpoenas we need to talk about before the vote
is passed.
Well then we can talk about board composition before it
passes.
Well I'm just trying to understand the reasoning behind you
know if the ideas we need to.
I can tell you the reasoning.
The board composition has been in this ordinance draft for
since the beginning so we've had
you know plenty opportunity to look at it to to massage it
to entertain certain things
so that's been here.
The subpoena aspect of it showed up this week.
We've discussed the subpoena before.
Well we did but it didn't show up in a draft till right now
and and I got to tell you that's
a that's important.
I mean when you can compel people to produce documents I
mean unlike one of the speakers
you really don't have two parties here.
You've got the board you have the complainant but I doubt
very seriously a complainant is
going to bring an attorney.
I guess they could but so as you know subpoena power is
powerful and as we heard whether
or not it's it's appropriate people ask for them to be qu
ashed and so that's a pretty
substantial judicial function.
Well so I thought when we discussed this that the idea was
the board itself will be creating
its rules of procedure.
And so yes we're entrusting to them the ability to operate
on a wide variety of issues compelling
people to show up the arguments that people make the
presentations that they make.
I would assume that that includes the subpoena power that
they have which councilmember Ryan
clarified that it belongs to the I think you clarified that
it belongs to the commission.
The board itself.
The board right.
So I mean if that I guess I'm trying to figure out where we
're going on the subpoena power.
We either want the commission to have it or we don't and if
we want them to have it we
can narrow the scope of what they have or we can allow them
to use their judgment within
the confines of the law and make their own rules which is
what we've done for every other
the confines of what law.
Well I mean they have some ability to get documents.
No I understand that but we don't but I don't know if the
board needs to be setting its
rules for what are the procedures if someone wants to
protest that subpoena.
I mean so I guess if we want to say that can the board that
's a pretty substantial judicial
function and so I mean when you're talking about I can ask
for all the documents from
you that I want and your only recourse is to do what with
the board of ethics or suffer
some type of sanction.
That's I'm not opposed to the subpoena power at all.
I'm saying let's make sure whether it's set at the board
rules which unless you're going
to have some people who are consulting with them providing
them some fairly strong due
process direction I'm just simply saying it's and there's
you're obviously you want to
go ahead and see if we can't push through this and vote on
it today I get that and I
don't have any problem with that and I'm not saying that
well unless I hear something on
the subpoena issue because I think showing up that that's a
substantial change to me.
I agree with you if okay here's where I agree with you if
we're going to talk about the
subpoena power let's hash it out right now and figure out
exactly what goes into that
subpoena portion of it as opposed to you know going around
the horn and talking about different
things you want to address the subpoena let's figure that
out right now you know address
vendors we'll figure it out and then just move on but I
mean then that's it like everything's
not going to be perfect and I just want to point out on
slide three or two I think I
mean we're at like meeting 17 I think several public
hearings I don't really know how much
more transparent than that you can get to be quite honest
and I do want to address the
Chamber of Commerce issue I don't know about you guys I've
gotten emails from the chamber
responded to all of them for some reason there is this
perception that people will not be
able to serve because of a conflict of interest the
conflict of interest laws are already
in the Texas code what we've done is lower the barrier to
what is a conflict of interest
financially and by relationships that means you can't vote
on one item out of perhaps
ten it doesn't mean you can't serve on a board or serve on
a commission it's just you're
accusing yourself from one item I explained this to people
on phone and email I just want
to put it out there again for the record people will still
be able to serve I recuse myself
from things having to do with clients doesn't stop me from
serving so just to clarify that
so that we don't have any more confusion maybe anyway so if
we want to move forward I would
just ask that let's please sure no details about what I don
't disagree with that I don't
disagree with that I think the vendor issue I think we've
come to as far as excluding
people who are selling the city property I think we've
resolved that I think we resolved
the $200 that it's a max from anybody in a year per year it
's per year it is am I confused
isn't it per year the $200 per year that was my recoll
ection of our conversation and we
could go back and watch video but that is what I thought we
all agreed on and that may
be true I think it's not written that way and if you wanted
to make that we could certainly
make that change that from any source the maximum gift for
any council member official
would be $200 we can make that change if that's what you
want to do it's the way it's written
is it's per source right now and I didn't catch that my bad
until the slide because
this is the first time since we talked about it that it was
specifically brought out on
the presentation so I just assumed that it was the way it
was when we talked about it
and so that's why I didn't catch it in that process but I
have a question about the subpoena
powers if I can because it is something new and I assume
that it's put in there and we
have to use it because it was in the charter or something
the charter committee and so
Mayor Pritchett McGarry mentioned we had 16 meetings and so
I'm just wondering is there
a reason why we're just now seeing it I feel a little bit
strange about that and I also
wonder if council member Gregory didn't bring it up last
meeting if we would have approved
an ordinance that didn't have it in there I don't know how
to necessarily answer that
hypothetical but your first question was why is it showing
up this late in the process
anybody have an answer for that I think the I think the
answer is is that one of the comments
that we received at last minute meeting was to cross-re
ference this versus the charter
review process we went back through that the city attorney
's office had indicated to us
that this was something that was approved by the voters and
recommended a change in
the ordinance to be there so that's the that's the reason
that we brought it forward so let's
go I mean of course mayor pro tem and I have discussion
about where do we go from here
you know it's so did slated for a vote today we can handle
it one of two or three ways
so I haven't heard from anybody else as far as that
particular issue so what are some
thoughts on that from the rest of my colleagues you know
don't everybody speak at once council
member Ryan well I do think that the subpoena power is big
enough that we've
been just trying to get that definition on paper that we
can actually see it I also go
to the fact that we're only a six member council today and
this is something you know it's
not that we're kicking the can down the road we're just
wanting to make sure that we we
have it proper and I believe the councilman member Husbeth
would probably like to be he
he actually was the one who brought forward having all of
our votes on each ordinance
so you know I I'll the the 330 in the afternoon I've seen
some stuff past in the past that
you question it this is a good ordinance it needs a little
final tweaking but on that
transparency I think that I would have last week and I
thought about the fact that this
was not a full regular 630 meeting would have said let's
move it to the first just so that
we would have that that type of openness on it so I would
prefer that we put it off and
have it next week at the 630 meeting okay council member Br
iggs well I I'm in favor
of going ahead if we could get everything together I came
today with the attention to
vote for it personally I didn't vote for it last week
because you had asked that we
had pushed it to this day and so that is that is why yeah
because I was absent during the
work session yes but I'm really glad that we didn't because
this new issue of subpoena
power came up and then we would be it would be a whole
different issue that we were talking
about so I I am okay I guess moving it until the next
meeting if it is wrapped up in a
bow and ready to go I don't want to push it off any more
sure so council member Duff
well I think until we get a clean copy out there for
everybody to see you know I'm all
for pushing it one more time but but we need to have it
finalized and next council meeting
vote on it the I think it would be better to wait till next
week simply because I think
we really need to parse out and be certain about what we're
voting on when we're voting
on this subpoena power I think that we just need to be
clear about that so then can we
say can we agree as direction for staff as a council that
we've made we've made a couple
changes today we've made the change of the $200 applies
annually for all gifts we've
made a slight change to the definition of a vendor as far
as people the city who's
seeking to purchase real property and then the only
outstanding thing is and we're going
to talk about it now I mean we're going to talk about it
now is the subpoena issue and
so this council is deciding that outside of those three
issues nothing else is going to
be changed in this ordinance and if we want to consider
appointment paradigms we can do
that afterwards for the for the board but is that go ahead
I know it's pretty strong
no no no all I'm concerned about is when I'm hearing us
talk about gifts and two thousand
two hundred dollars I'm hearing two different things I hear
you continue to use the word
annually okay then I may be wrong and I'm hearing other
folks saying we're striking
the annually and it's two hundred dollars total is that
lifetime I think I think what
I what I heard from the council's the direction is that you
did not want to receive more than
two hundred dollars in one fiscal year from any vendor from
multiple vendors so you can't
have ten vendors give you a hundred and fifty dollars and
that's fifteen hundred dollars
the maximum gift you could have in any one fiscal year from
one or multiple vendors be
two hundred that's that's what I think I heard if that's
your understanding okay does that
make sense okay Spina let's have the discussion so we've
had one recommendation or one observation
that it would be only issued by the full board we had one
observation request that would
it require a super majority or not we haven't really
discussed that anybody think that that's
where they're going in that direction or a simple majority
did you want to further comment
well I'm just I just want to explore what what this
authority might include so so let
me give an example there's somebody that is claiming that I
have violated the Texas open
meetings law because I'm deliberating with another council
member by text messaging and
so they they they ask and I say well I don't have any so
could but they think that I've
done it so would with this give this give the at the Board
of Ethics the authority to
subpoena all of my phone records to to make that
determination I think there's some questions
that we have reached out Alan Bork was about this and I
know he would like to look into
it a little bit farther to see how far we can go in a board
of ethics scenario and that
we I don't think we have all the answers to build to give
you what you want today on that
because I know there have been other questions coming up
with respect to subpoena violation
and how far you can go on that I mean if this were to be
analogous to the Texas Hill practice
remedies code then the answer to your question would be yes
I mean you could go I mean that's
subpoena we would be it would just be like going down the
hall going down the street
to the courthouse and having a subpoena issue at a civil
court and you know the say and
that's an option that you have here is to the extent it's
enforceable we could follow
the the rules for the Texas rule civil procedure and the
Texas civil practice and remedies
code in terms of issuing statements I don't even know what
all of those are but but my
guess is that they probably were crafted in a way that gave
some assurances for due process
yes would it be appropriate for us to add some kind of
language like that to to this
subpoena power I don't know we I'm not trying to be
difficult I'm just trying to not I think
we can craft where you want to go but the unknown that we
have right now is how far
can we go under existing law to do what you're wanting to
do as an ethics board right and
particularly with the board that's going to be made up of
primarily non lawyers and non
judges there are some issues that can create itself well
would we want to put in here some
kind of if we didn't use the language of referring to some
other set of rules for subpoenas would
we want to put in here some provision that a person could
object and appeal handing over
all of the pieces of information if they felt like that
some of them were not relevant or
that overstepped the boundaries I am way out of my league
because I don't know the link
legal language to say for all of this typically what would
happen is so proceeding is if you
wanted to turn over documents to the board and have them
make a determination as to whether
or not they would be used they'd be relevant they're just
called submitting in camera and
that's where they're sealed the board would look at and
then it'd be decide they decide
whether to use it in that proceeding but that's kind of the
cart before the horse in some
ways because that's the group that's going to be deciding
the fate of the person that
is probably being asked to submit those records so they're
going to be there in front of them
I think we really need to think through how this would be
used and I can see the need
for lawyers to definitely be involved in this in terms of
what the board may want I mean
it's it's a very broad question.
Yes, may I pretend?
For our purposes can we put in language that states that
the subpoena tower is sufficiently
narrow in scope for the purposes of the actual
investigation?
Let me start over again.
For the purposes of our ordinance understanding what city
attorney has mentioned about the
complications of issues I'm really not worried about that
because the fact is if something's
outside of the law we're not going to be able to do it so I
don't think you have to outline
every single thing in the law to make it legal you just say
if something's contrary to the
law it's going to be struck from this provision just like
in a contract so with respect to
the subpoena power our code requires that the board has a
subpoena power I'm sorry not
our code our charter requires that they have a subpoena
power and it's related to the investigations.
We're tracking so far?
Okay so for us what we could potentially do is just say
that they're going to be sufficiently
narrow for the purpose of the investigation and the details
of how that operates again
I would say belong to the board itself because they're not
going to be able to do anything
that's outside of the law they may think that the civil
practice and remedies code is too
onerous for instance or they may want something I don't
know more abbreviated than all the
timelines that are provided in that code so I would just
say that we can have a philosophical
discussion about it in the code but let them get into the
details of how they operate that
narrow subpoena power that's my suggestion.
Do we does the does a city council approve the rules and
regs of the ethics board?
Yes I suppose there's a section related to that that
addresses that.
So if you look in it's section 2-277 board of ethics sub
section K rules of procedures
the board of ethics shall adopt rules of procedure
governing how to conduct meetings and hearings
such procedural rules are subject to confirmation or
modification by the city council.
So Mayor I think that Mayor Pro Tem has probably offered a
modification to the wording that
would be sufficient for me I think unless I hear some more
discussion I'm comfortable
with saying limited to the scope of the investigation.
Question for legal let's say somebody is subpoenaed and
they're within the range of investigation
and they produce documents are those documents public
records pursuant to the open records
act or?
I do not know the answer to that question.
In other words do they stay confidential or if you if they
ask for something is it going
to be released or could it be released that's?
If it was some I'm just trying to think through since we
haven't had an actual hearing happen
we have developed rules of procedure how this would work is
when you're in trial and you
subpoena an individual to show up with documents and those
documents are broad what would be
I believe open to the public would be what is admitted into
evidence at that point.
Not just but then again you have discovery subpoenas which
are you know bring this stuff
we want to look at it and it would depend and that's why
there are different there are
a couple different types of subpoenas you have to look at
and so that I think a lot
of this could be fleshed out in the procedural rules I
think I agree with counsel one of
Gary's comment about we could draft language and hear and I
was just writing something
down that the subpoena power is the documents if it's
documents are going to be subpoenaed
have to be reasonably relevant or related to the scope of
the investigation at least
we have a standard there that's limited to what that
investigation is about and it's
just not you can't go ask you can't go ask for one thing
when it's not you know one thing
over here it's not related to anything over here which I
think is the concern I'm hearing
from one of the speakers and also what I'm hearing is
concern of the council so what
you would want to build a subpoena would be documents that
are related to that ongoing
investigation and nothing beyond that but then what's
reasonably related would be left
to the board to make that call.
So the board then that the board rules and regulations
would govern that the sort of
technical and procedural aspect of the production of the
documents the confidentiality of the
documents Texas law obviously would govern that as well.
Correct and I think a good starting place would be to look
at the Texas Rules or Procedure
and the Civil Procedure of Remedies Code as a tried and
true way of doing that I mean
laws been vetted out in court and you know we're not
reinventing out a whole cloth how
to do that but we would just limit the scope on the front
end.
Okay so then it sounds like that we are able to craft some
language that would limit the
scope sort of in general for the subpoena power and then
leave it up to the board as
it's formed to set their own rules and procedures that
govern that particular process.
Is that yes.
Which are subject to approval from Council reviewing
approval from Council.
Yes.
I'm good then.
All right so it sounds like though then what we've done is
we resolved the three issues
that were present as far as that have been asked about for
this particular ordinance
moving forward to get a clean copy no red line copy with
these changes that are made
and for a vote on is it May 1st.
May 1st.
May 1st.
And that that will be we can either put that on a public
hearing where people can speak
without a blue card or items for individual consideration
they can speak with a blue card.
I mean we've had public hearings before might as well just
put it on as a public hearing
I mean I don't think it's by law we have to but it's just a
courtesy public hearing
that could do public hearing and consider adoption of an
ordinance.
Okay.
You do that yes.
You got a council member right let me go with the council
member right.
Are we moving on to anything else yet or I have a separate
issue that I wanted.
Oh with the ethics.
No.
Oh something different.
Something different than ethics are we done with ethics or
are we.
You talk about something that we're something within I
guess I'll just ask the question
if you want to skip over it come back here again.
Where we have the effective date of September 1st.
Right.
My question is does that mean that if an offense takes
place prior to September 1st that it
disappears or would it be at the passage of this that it
now becomes an offense in any
any proceedings of the board would not happen until after
September 1st.
Okay.
Go ahead.
My understanding is that it's anything that occurs after
the effective date after September
1st.
Is that what y'all discussed last time.
I think that's what's in the I'm trying to find the section
here there's a section
of the document here.
I'm going to go ahead and recognize councilmember Briggs.
It would be my preference we did discuss it towards the end
of the meeting the effective
date was September because we were trying to get a timeline
on the board but it would
be I would like to ask council to consider as soon as it
passes that it would go into
effect that part and then the any complaints that are
received would be held off until
September but as soon as we pass it I would like for it to
go into effect as far as affecting
council.
Typically there's a 14 day period just for effective dates
in general.
Is that is that okay just or you're saying the minute we
pass it the next day it's in
it.
Whatever is typical.
Okay.
Yeah.
Okay.
All right.
Did you have.
Yeah.
I'm good with that you know I think you know something
occurs then you know we still have
time to put together by September the 1st.
So you're saying if something happens between the time that
we pass it and September 1st
the ordinance is in effect if there's a complaint file then
it's told sort of put on the shelf
until the board gets comprised and the rules and then it's
taken down.
I think it has to.
Okay.
All right.
Okay.
Is that everybody okay with that.
All right.
Just to be clear that's section 2-267 so that's the
prospect of this there about September
1st so that would be a revision of that section based on
that and there may be some other
pieces that we'd have to address related to that we'd bring
back to you.
Okay.
Yes I want to make sure that we're covered about what we're
changing there will be the
issue about make sure we've clarified the cumulative annual
amount for vendors in the
order in the ethics ordinance the definition of vendors as
relates to real property and
then did to clarify for Ms. Gary is that we're going to
limit the scope of the subpoena to
it to be reasonably related to the investigation.
Is that right?
Okay and then and then the board the board will they'll set
up their own rules subject
to then coming back to the council for approval.
Is that everything?
Yes.
What about the it's the board that has the subpoena power
not correct the entire board
not the other that's the entire board and then that the
effective that when the when
it's passed it's got an effective date of I guess it'd be
an effective date of the
14 days afterwards but then no hearings would occur until
the board is created and rules
and regs passed.
Is that yeah and and given that I think we you could say
September 1st for that but I'm
wondering what happens if if we get the board and they don
't get the rules and regulations
in place by September 1st.
Do we say or when it's when they're put in place I like a
date because it it maybe pushes
them to and pushes the staff to get that thing done.
September 1st is what you're advocating for but but if
something happens in between the
passage and September 1st then it's told.
So because of how this is posted on the agenda today do we
have to have a motion to postpone?
Yes.
Are there are there any other questions or issues with the
ordinance not issues but observations
comments.
So I want to make sure we all understand we've resolved now
it's four issues we've resolved
the vendor issue of $200 we've resolved the subpoena issue
of reasonableness we've resolved
the real property exception for vendors and now we've
resolved the effective date but
if a if a offense occurs or complaints filed after voting
to whenever I guess it's just
told till the board is ready to hear it.
I mean we can say September 1st is because it's really not
an effective date anymore.
It's just we want to have the board in place and the rules
and everything established by
September 1 because it's effective within the 14 days after
we pass it because if somebody
makes a complaint they're subject to this I mean people are
now subject to this ordinance
and so the September 1st date is more of a we would like
you guys to have all this in
place by then.
Yes.
Could we just say that no complaints will be can be filed
until September 1st because
we do have to have the auditor I believe it is it has to
put together the form that's
part of that time period but that the it's effective
immediately that if it's an offense
it's an offense but that no complaints can be filed until
September 1st.
Or at such time the board is duly constituted to be able to
accept because you're saying
the forms won't even be in place if if something happens
and somebody commits a violation somebody
wants to file a complaint two weeks after we voted on this
after May 1st then how do you
receive it who makes the determine I mean you've got a
whole procedural process that
it's not saying it can't be filed you're saying it can't be
filed until the the board
is in place and the procedures in place but that doesn't
mean that it's not a valid complaint.
Correct.
Yeah I'm saying that the effective date is here the it's a
violation at that 14 day point
but you can't file anything on that violation until either
the board is in place with the
rules and procedures or September 1st date.
Is everybody okay with that?
Okay all right so that's that clarification.
We'll need to to think about this a little bit more with
legal and perhaps Alan but there's
a limitations period section of the complaints and it
indicates that you can't bring a complaint
more than six months after the offense has occurred and so
six months from now certainly
wouldn't be a problem but if it had been a few months ago
depending on when that's being
brought forward that someone who wants to report something
there could be an issue so
just we may have to adjust some of the language there to
reflect that I just want to be clear
that that may be something we'd have to adjust with this
change on the effective date.
What I want to make sure that I understand is that the
ordinance will go into effect
14 days after it's passed any violation after the effective
date will be considered to be
an actionable violation it just will not be able to be
heard until the board has got its
rules and regs in place and it can act.
Is that what I understand?
Yes.
Okay anything else?
No sir.
Any other questions comments?
Yes you may put them in.
I mean I just wanted to point out we have one council
member short so to the extent that
that council member has any issues I would just say.
Staff needs to reach out.
Yeah staff needs to reach out immediately and that shouldn
't be a reason for not taking
a vote next week.
And I'll reach out to him as well.
Okay.
Thank you.
That's it.
Appreciate your time.
Any other?
Okay I see consultation going on.
Trey just pointed out that there's a 90 day provision that
the board will be orientation
will occur 90 days after the effective date of the
ordinance.
They may or may not have the rules and regulations in place
by then which kind of renders that
moot.
So do you want us to build a draft that after they get
their rules and regulations in place
and they get the board's gonna have to be appointed then
they're going to have to put
together rules and regs.
Yeah.
I think I know where you want to go on that.
Yeah I don't think that's a hard fast rule it's just saying
because this is the beginning
stage I mean so I think we need to have some flexibility in
that so sometimes these hard
dates is what gets us into trouble but see what you can.
Do on that you're just saying hey it says 90 days after the
effective date we make the
effective date on the 15th of May they got through three
months from there to have their
orientation will by that time they might even have been
constituted or just constant well
three months May June July I mean we're getting September 1
st so but look nobody's wanting
to drag out the appointment of the board.
I think we're going to get however we decide to appoint
them I think we're gonna get that
resolved and they're going to work diligently to get it up
and going and I think it'll happen
long before September 1st so but we've given at least some
ability to have some flexibility.
All right any other comments questions if if staff could
get those changes to us maybe
even before the Friday sort of packet so that we can if
there's any questions we can address
that yes Councilmember Briggs.
I was also going to ask if a copy could be put online for
the public to view as soon
as it's done because these are just a few changes so before
Friday that way they have
a little time to review.
Okay that's a good idea okay we haven't called it yet.
Yes Councilmember Gregory.
I move that we postpone item 1A until May 1st.
I have a motion second second all in favor please signify
by raising your right hand
against by raising your right hand so it's four to two I
thought you said you were okay
with it that's all right four to two so we'll move on to
May 1st.
Okay we'll go on to our next agenda item which is item 1B
consider approval of a resolution
of the City Council of the City didn't appoint a primary
member and alternate member as the
official voting representative North Texas Central
Government Regional Transportation
Council.
Good afternoon Mayor members of council I'm really excited
to be here.
Got a very short presentation here related to Regional
Transportation Council as you
may know the Regional Transportation Council is the policy
body for the Metropolitan Planning
Organization the City of Denton has representation on that
on that body there's roughly 44 members
from around the North Texas area of which 38 of those are
appointed elected officials
and six of them are appointed from various organizations
such as text dot Dallas text
dot Fort Worth the dart DCTA but along with the short is is
we the City of Denton has
a seat on the RTC we maintain primacy for that particular
seat due to population standards
when the City of Denton was reached 50,000 population back
in 1990 we were recognized
as having our own MPO rather than having our own office our
own MPO set up we chose to
work with the North Central Texas Council of Government so
with that said we maintain
primacy over that particular seat we represent a cluster of
cities including Lake Dallas
Corinth and Sanger and at present Mayor Pro Tembigere is
the primary member representing
the City of Denton and Councilmember Ryan is the current
alternate so this particular
item is a resolution for appointing a new a new member
Mayor Pro Tembigere has indicated
that with her schedule and moving off of council due to the
election cycle she had requested
that this item come forward to the Mobility Committee the
Mobility Committee considered
this last week and recommended a resolution to move forward
for your consideration to
appoint Councilmember Ryan as the primary member and there
was a discussion or a nomination
for Councilmember Briggs who serves on the Mobility
Committee as an alternate at this
point in time that was the only nomination for the
alternate position and so again we
do have a resolution in your backup for action today for
Councilmember Ryan as the primary
and the open alternate would be for your consideration at
this point in time.
So you're saying you want to serve as the alternate Council
member Briggs?
I would be happy to.
Anybody opposed to that?
Do we have to make an official nomination or we just put it
in the resolution?
You can point it at this point in time.
We can make that available for your signature.
Okay.
Yes.
Councilmember Briggs.
I move approval of the resolution with Councilmember Ryan
as our representative and Councilmember
Briggs as our alternate.
We have a motion.
Councilmember Duff second.
All in favor please signify by raising your right hand.
Motion carries unanimously.
Six zero.
Moving on to agenda item what is it 1C.
Consider approval of the resolution of the City Council of
the City of Denton Texas requesting
the Denton County Transportation Authority establish a
minimum $250,000 annual investment
in passenger amenities for the City of Denton service area.
Mayor members, Council, Mark Nelson, Director of
Transportation back with you again and
what we have in front of you this afternoon is a discussion
on DCTA passenger amenities.
Quick discussion here as you may recall earlier this month
DCTA presented to Council some
goals and objectives and responded to inquiries from the
Council.
One of the items that came out of that was taking a look at
closer look at passenger
amenities.
How do you establish passenger amenities?
How much is spent on passenger amenities?
What are passenger amenities?
So those in this case would be bus shelters, bus benches,
improved bus stop locations.
What came out of that discussion then was a request to move
forward and request that
DCTA actually establish an annual amount for passenger
amenities in our community for the
DCTA service area and the City of Denton and, you know,
what was basically outlined in that
presentation was roughly about 15% of the 300 bus stops had
passenger amenities, either
a bus shelter or a bus bench.
And so I believe the desire here is to create a more robust
passenger amenity program for
DCTA, provide a little bit of direction in terms of what
our anticipation of that particular
agency is in terms of providing service in our community.
So with that, that request was placed in front of the Mob
ility Committee last week and they
essentially recommended option one here, which is
establishing or considering this resolution
for a $250,000 annual amount for DCTA to plug into their
budget.
So with that, I'll stand for any questions that you may
have.
Any questions, comments?
I'll make a motion to approve so that we can see stop
seeing people sitting on the ground.
Second.
All right, we have motion and a second for agenda item 1C.
All in favor, please signify by raising your right hand.
Motion carries unanimously.
Moving on to item 1D, consider approval of a resolution of
the City of Denton, evidencing
support for the Denton community market and its grant
application for funding from FY
2018 Farm to Market Promotion Program.
Oh yeah, you're good.
Perfect timing.
We just called the item.
>> Yeah, we're fast with Mark.
Well, I just have a few slides as well.
So we're here today with a request from the Denton
community market for a resolution of
support regarding their application to the USDA Farmers
Market Promotion Program and
some staff assistance with their grant application and with
implementation over the three-year
period of the grant.
We've identified about six areas where we would assist the
market initially with some
grant writing review, assisting with avenues for community
outreach for the programs covered
under the grant, helping facilitate the use of some of the
city facilities for their meetings
and outreach efforts, partnering with the Denton community
market to facilitate two healthy
and sustainable living fairs annually, which would help
promote the market and our city
programs.
Cooking demonstrations, which is something that Sustainable
Denton puts on right now
through our sustainability series.
We do classes for preserving the harvest.
And then they've also asked that the city assist with
printing services through our
reprographics department.
Over the period of three years, we're looking at about $9,
000, so about $3,000 annually
in assistance and support.
In the resolution, we did do not to exceed $10,000 just in
case we had any increases
in cost for facility rental or printing costs, staff time.
I told you it was very brief.
And then Vicki's here from the market, Vicki Oppenheim, if
anyone has any questions of
myself or Vicki.
Any questions, comments?
Chair would entertain motion or action.
I'll move approval.
Okay.
We have a motion.
I'll second.
We have a motion and a second for agenda item 1D.
Everybody in favor, please signify by raising your right
hand.
Passes unanimously.
Thank you.
Okay.
Concluding items.
Who's got -- yes.
Council Member Briggs.
Okay.
So I would like a work session on increasing the homestead
exemption.
I know that we passed the effective rate, but tax bills
came in and the homeowners are
just not seeing the relief.
So I just would like to request that.
Also informal staff report on the noise ordinance.
I've been getting some complaints from homeowners that are
living close to bars.
I'm just curious if we have a maximum number of complaints
allowed.
And also if the police say there isn't anything they can do
, what can be done?
And then also in conjunction with that, what is the current
zoning requirement and with
our new zoning maps, will these type of establishments be
allowed near neighborhoods?
And also just as a side note, our smoking ordinance, the
negative effect of that was
that in the past these bars and the people were inside
smoking and now we've pushed them
outside into the neighborhoods.
And so it's creating a louder environment, which in the
past didn't.
And so I just thought that was interesting as something we
may not have thought about.
Last is ADA compliant sidewalk study update.
I know that we were supposed to have one and there is a
certain day that we are supposed
to have everything compliant and I'm not sure, just an
informal staff report.
And I brought this up because somebody reached out to me
that there is a large section on
Sherman Drive where a wheelchair actually has to get into
the busy road because it won't
fit and there's the only one sidewalk on Stewart Road.
There's not another option on the other side.
So I'd like to see if that sidewalk is compliant.
All right.
Yes Councilmember Ryan.
Thank you Mayor.
Just a little follow up.
I went ahead and did the search of our code of ordinances
and the only two places that
the smoking ordinance needs to be realigned with is 22.31
subsection 13 and 22.31.1.
I also, while I've spoken with staff on this on several
occasions, we were promised
a stoplight would be in about 24.99 in Robinson in December
, then January, then February,
now April.
We have only a couple days left in the month of April and
the light is still not there.
So I just wanted to bring this forward as a public item.
I saw that the contractor has been out there and at least
has the conduits and the pads
set so it's just a matter of getting the poles up and I
bring this up now because 21.81
is going to be shut down to one lane for several days
between Ryan Road and I believe it's
Bent Oaks but at this time we need 24.99 opened up fully in
order to help relieve that issue
of congestion over there.
I would like to get at least an informal staff report
possibly it would lead to a work session
on we have some water towers in town that have found out
that we are having to dump
water because of the age of it and that that's actually
costing us in the system and it's
in areas that will be developed in the future but is there
something that we could do as
a city to put infrastructure in that would create a quicker
use of that water so we're
not just having to dump it out because of its age.
And let's see agendas the timing on agendas I'd like to see
if we can work out something
so at least the chair if not the full committee gets it
gets agendas sent to them prior to
them being posted so if there's any changes that need to be
made that that can happen
and lastly I want to remind everybody to go out and vote.
Okay if I could weigh in on Councilmember Ryan's concern
about Robinson in 24.99 we
did get a briefing yesterday from Mr. Polster and I have
asked staff to reach out to the
contractor if there's anything we can do to reprioritize
projects on our end you know
to go ahead and make that trade-off we agree with you the T
iesley information is getting
out so we are investigating that and I understand the
frustration.
Okay anybody else?
Seeing none all right that concludes our agenda for the
open meeting I will now call the closed
session I will now we will now move into closed session at
421 on Tuesday April 24th 2018
pursuant to deliberation regarding personal matters under
government code section 551.074
and consultation with attorneys under government code
section 551.071.