Dec 12, 2017 City Council on 2017-12-12 1:00 PM
December 12, 2017 City Council
Full Transcript
Welcome, everyone, to this meeting of the Denton City
Council on Tuesday, December 12, 2017.
It is 1.03 p.m.
And we will move forward through our agenda.
We have on our first agenda citizen comments on consent
agenda items.
I don't see any blue cards for this specific agenda item.
A request for clarification of agenda items listed on the
agenda for December 12, 2017.
Ms. Member Briggs.
So I would like to request on the consent agenda to pull
item B for discussion.
And under individual consideration, item B, I'd like for
council to consider to remove
the item to a work session.
Okay.
And what's our first work session in Jan -- what's our
first meeting in January?
We've denied.
Is that okay?
That's okay with me if it's okay with council.
Yeah.
All right.
Okay.
The 9th of January.
So agenda item 2B for item for individual consideration
will be pulled until January
the 9th.
And you said consent agenda item B, as in Baker?
Mm-hmm.
Is that -- and I believe you're recusing from one of them.
Which one?
Yes.
I will be recusing from work session item B as well.
Okay.
Item B.
And I have one more question that's on the UNT, it's
consent agenda item G. So I'm curious
on the -- just to clarify the cost, the 112,000, that is
our share of the study.
And okay.
So and was the study our idea or UNT's idea?
A little background.
Both.
Okay.
Yeah.
The background on this is we've been meeting with the UNT
administrative staff for several
months now.
And one of the meetings this summer, there was a request to
close two or three streets
around the campus, Highland Bay 1, and I think in one of
the other avenues, I'm not sure
if that was A or not.
You know, and our position at that point in time was they
had recently done a traffic
study which appeared to us to be very different methodology
than we would use.
It was more of a counting type study, more of a pedestrian
study.
And the approach that we took is that we removed this
traffic analysis out of the small area
plan in order to work with one consultant that we could
both agree on with the methodology,
study not only the area around the campus but the area
around -- in the smaller plan
in general in order to have a similar set of facts, to even
have a conversation.
There was -- from UNT's perspective, they're envisioning a
more walkable campus from our
perspective.
We need the traffic data so we can have an intelligent
conversation.
If we close one street, what happens through modeling with
the other streets?
How are we redistributing traffic, that sort of thing?
So it was really agreed upon that we would need to do this
to work on a common set of
facts.
Can I follow up on that?
Oh, of course.
We just approved a small area plan and that study included
traffic.
So is that going to correlate?
Will they get access to this study?
Yes.
Is the timing good?
Not only will the traffic study sync up with the small area
plan, but UNT's got a presence
on both as well.
They're going to be working with us on the traffic study
and they also have a presence
with the small area plan.
So really it's in our attempt to not -- to avoid any
conflict down the road and have
a meaningful discussion based on facts and not perceptions
on their end.
Because our goals are slightly different.
We're looking at moving traffic and protecting
infrastructure.
They're looking at pedestrian -- closing off streets for
pedestrian safety, that sort
of thing.
So we're trying to figure out how to sync everything up
into one study.
Thank you.
Yes, Councilmember Ryan.
Excuse me.
I'd like to pull items G and H. It's mainly about H, but
since they're interconnected,
they have individual consideration on those items.
Okay.
Do you want a staff presentation?
That would be good if they can have a little something to
give to us.
I think I'll send an email off so they're aware of that.
Okay.
Great.
All right.
Anybody else want to recognize the more festive side of the
dais?
So thank you all for bringing us into the holiday spirit.
And I apologize for my shortcoming in that regard.
Yes.
Mayor Pro Tem.
On Consent Agenda, item E for the IOF Cemetery and the Oak
wood Cemetery, were those the bond
funds or is it a combination of the bond funds plus the
budget amendment that we did?
Because I remember we had like a $100,000 budget amendment.
These were mostly the funds that I think it was $300,000
that was approved by the council
to go to the project plus some other dollars that had been
allocated in the budget process
for that.
So those are the funds.
Okay.
That was my question.
Thank you.
Because I think we said just take them out of the fund
balance.
That's right.
We did a budget amendment.
We brought that back to the council.
This is less than the budget that we had for the project.
Okay.
And before we -- any other clarification of agenda items?
Before we move on to our work session, I just want to --
because most people may leave before
we get to the closed sessions if we could show off our new
glass there.
If Mr. McDonald could flip that switch right behind him,
you'll notice that instead of
having to draw the blinds, we can simply flip a switch and
when we're into executive sessions.
So thank you all very much for that.
I think that's very cool.
Very cool.
You're like, okay, Mayor, let's move on.
All right.
We're moving on to our work session reports.
Agenda item 3A is receive report and hold discussion to
give staff direction regarding
the energy management organization review being conducted
by Deloitte.
Good afternoon, Mayor, members of the council.
As you know, we've been working with Deloitte to look at
some aspects of the DME operations.
We hired Deloitte most recently to look at some of the
benchmarking for our energy management
organization and to also do an overall assessment of that
organization and the governance policies
for that.
So today we have with us Stephen Engler and Tim Metz and
they're going to provide a presentation
to you on their findings.
This is the same presentation that we provided to the
public utilities board yesterday.
So Stephen.
Thank you, Brian.
Good afternoon, Mayor and council.
Thanks for having us back.
Steve Engler and my colleague Tim, we're going to walk
through a summary of our findings,
plan about 30 to 40 minutes of prepared remarks, but happy
to take your questions throughout
that time or at the end.
So just to give you an overview of what we're going to
cover, we'll start out with the
objectives and then kind of reset the framework under which
we were asked to come and do the
assessment, talk about the assessment itself, the scope of
the review and how we conducted
it.
Then we'll talk about the delayed capability maturity model
, which is the benchmark that
we use in these types of assessments and how we frame that
given the entity that we're
looking at.
And then we'll go into some details of the summary results
and the recommendations of
that.
Then we'll talk a little bit about the benchmark analysis
for fiscal '17 and beyond.
If you recall the last time we were here, we did kind of a
look back on the previous
year's benchmarks and we'll have some recommendations
around next steps for that as well.
And again, if you have questions throughout, please feel
free to interrupt.
So just to kind of reset the context with which we were
asked to come and do this assessment,
one of the questions that we received, I believe from
council the last time we were here, was
to identify the risks that have been introduced to Denton
Electric or the EMO since bringing
the energy management function in-house.
That kind of set the stage for based on those risks that
the company manages, what are the
capabilities of the organization to identify, to monitor,
and to mitigate those risks.
And then finally, the last piece, as I mentioned, was to
analyze some different recommended
approaches for establishing fiscal '17 benchmark for the
performance of DME and make some recommendations
as to how to proceed.
So that's kind of the charge that we were given.
And I spent a couple minutes just kind of setting the stage
and talking about the concepts
that really feed into the work that we did and how we
perform these assessments because
the context of the organization and the type of transacting
profile is very important in
how we not only do the assessment itself, but in terms of
the recommendations that we
make.
And we try to draw a distinction between risk and
uncertainty.
Oftentimes we use those words kind of interchangeably.
In this context, we talk about risk specifically as the
possibility of suffering from adverse
outcomes.
And in this case, those adverse outcomes might be higher
rates for customers, higher costs
to the utility, or lower revenues.
In contrast, when we talk about uncertainty, we're
referring to unknown events where the
probability of the occurrence is difficult to quantify.
And the difference there may be subtle, but it's around the
risk of -- the risk would
be that the cost would increase or the revenues would
decrease.
The uncertainty is to the degree or the amount that they
could change.
They both talk about expectations into the future, the
difference being that risk can
be mitigated, whereas uncertainty will always exist.
And I think therein lies the charge to a large degree of DM
E and the EMO organization that's
been created is how do we mitigate the risks that the
utility faces by nature of the fact
that they're in the business of buying and selling
commodities.
But in doing that in such a way that you can avoid fore
going opportunities to pass benefits
along ultimately to the customers.
Another kind of setting the stage concept I want to talk
through is just when we look
at organizations, we think about the transacting mandate or
the transacting profile of those
organizations.
And if you'll excuse the strange colors, if you look along
the bottom axis, we look at
organizations along a continuum from price taker in the
lower left all the way through
proprietary trader on the far right of that X axis.
And in between are organizations that we would describe as
asset optimizers.
And just to explain those briefly, if I'm a price taker, it
means I have exposure into
the commodity markets, but I'm not going to do anything
really proactive.
I'm going to take the prices that the market offers me,
either to buy commodities that
I need or sell commodities that I have in excess.
All the way to the right end of that scale would be trading
companies.
So organizations that are willing to take speculative
positions, they may or may not
have assets to back up the trading that they're doing.
But these are organizations that are really on the bleeding
edge, if you will, of trading
activity, truly trading as opposed to transacting.
And in the middle are companies that we work with often
that have physical assets, have
presence in the commodity market.
Their objective is to optimize around those asset positions
.
So either maximize the revenues generated by owning an
asset or if conversely minimizing
the costs associated with running that asset.
And we're not going to take positions that extend beyond
the capacity of those assets.
And if you think about those different companies along that
continuum, when we look at capabilities
and we do an assessment of the capabilities required to
manage the risks associated with
those different profiles, the things to keep in mind is
that the same risks exist, whether
I'm a price taker or a proprietary trader.
The difference comes in probably the degree to which you're
exposed to those risks, maybe
the complexity and the interrelated kind of nature of those
risks.
And then in following that logic, the capabilities required
to manage those risks will increase
as you move to the right.
That's the context that we try to keep this in.
Our recommendations, we always try to keep, we call them
fit for purpose, that if you're
not proactively or speculatively trading the implications
on requirements for infrastructure
and policy and risk management capabilities are
correspondingly lower.
Okay?
So just to talk about the risks for a second, I apologize,
this is a bit of an eye chart
with the slide.
I should say that all of the recommendations that we're
going to talk about here are in
the written report that we have.
Coming back to the first question that I mentioned when we
spoke with counsel last time, the
question that posed to us was what risks have we introduced
to the organization by bringing
this function in house?
And I think the short answer to the question is that there
really are very few, if any,
net new risks.
It's really the difference is where are those risks being
managed and what's the level of
exposure or the complexity of those risks that the EMO is
now managing.
If you look down the left-hand column, it starts with
market risk on the top and then
down through credit operations, model risk, and some others
.
These are all very common risk areas that we would see for
an organization that's active
in the commodity markets, an energy company that owns
assets and is in a market like ERCOT.
These risks exist whether you're a very small player or a
very large complex trader.
And in most cases, these risks existed prior to the
establishment of the EMO three years
ago.
The difference really is the management or the mitigation
of those risks was outsourced
via the contract that you had with the third-party provider
.
And now in the current state, in our view, those risks are
recognized to still exist
but have been managed in-house as opposed to being outsour
ced.
I think that's a key distinction and maybe a clarification
or maybe a further discussion
from the conversation we had last time because in our
assessment, again, there really are
no net new risks to the organization with the one exception
probably being the renewable
variability risk.
With the increase of renewable sources into the energy
portfolio, you are probably more
exposed than you were before, and especially if you moved
to the 100 percent goal that
the variability of the availability of those assets will
introduce risk to the organization
that's probably slightly different than would have been
managed before with traditional
fossil-based generation assets.
I think that then will probably translate to more complex
price risk.
So how do you back up those assets?
How do you fill in those potential gaps in the day ahead,
the week ahead, or the forward
markets?
I'll pause there to see if there are specific questions on
this slide or the risks associated.
I guess -- I mean, I hear what you're saying about there's
a new risk given if we move
our renewable portfolio to either 70 or 100 percent.
But yet when we think about -- because the risk is they don
't show up.
And that's the uncertainty, I believe, is what I heard you
saying earlier on.
But the risk is mitigated in that you plan or you have a
plan for those moments where
they don't.
It's an additional risk, but do you see it as an unmanage
able one, I guess?
And I wouldn't say that --
No, I don't mean to imply that at all.
And I understand that the renewable plan and the work that
's going on relative to that
and the contracts and the type of contracts and the supply
plan that you have is really
designed to anticipate when those gaps might occur and
where you've got back up.
And then the DEC obviously is the ultimate backup, as that
report has shown as well.
Thank you.
Appreciate it.
Okay.
All right.
So let's get into what we did and how we did it.
I'll quickly go through this.
Our objectives were really to understand the DME, the trans
acting profile, and the current
capabilities of the organization.
Remember, getting back to where are you on that continuum
informs us as far as where
we think you need to be in terms of risk management
capabilities.
The scope included everything that we would describe as
front, middle, and back office.
So front being the commercial transacting, you know, ones
taking the positions, middle
office being the risk oversight function, and the back
office is typically accounting
settlements and those.
But it also extended to governance, people, process and
technology around all of those
components.
We understood the type of transacting activities that are
happening today and also in the context
of the renewable plan, how might that transacting profile
change in the future?
And we spend a fair amount of time with staff talking about
risk reporting and the capabilities
there and what are the things that you're looking at.
And then again, in the future, what are the things that you
might need to look at that
might be slightly different?
In order to do this, we spent time with staff and got -- we
were provided with a host of
information including policies, procedure documents,
existing risk reports.
We spent a lot of time talking to staff about what they do
and how they do it and, you know,
kind of incorporating that into our benchmarks so we could
answer some questions around where
you are today and where do we think you need to be.
As I said, we spent a lot of time also talking about the
future state and where things are
evolving to take that into consideration with our
recommendations.
We developed a draft set of recommendations, discussed
those with staff and had a little
bit of back and forth in terms of shaping those to the
final recommendations that you
have in the report and that we'll summarize here.
This slide is meant to be illustrative of the different
maturity stages.
I should say that the bullets on here aren't meant to be
specific to DME.
They're really just descriptive of that level of maturity.
We look at the categories down the left-hand side,
governance, process, people and technology,
and within each of these categories we have a number of
elements or components that we
assess specifically and I think those are included in the
appendix to this report.
And then we look at what we've defined into three different
stages of maturity.
And if you think back to my comments on the different types
of transacting profiles from
price taker up through proprietary trader, you can think
about these maturity stages
similarly.
There's nothing inherently good or bad about being in any
one maturity stage.
It's more a question of timing often that when we look at
younger organizations, if
you will, naturally they'll tend to be more in the
developing stage.
More mature organizations in terms of how long they've been
around, that's when you
start to extend in our experience into the prevalent and
the leading practice areas.
So the question is how long you stay in each one of these
areas in terms of the development
of the capabilities and does that level of maturity match
the risk profile that you have?
Sorry, I just lost my train of thought.
I'm going to make another comment.
It'll come back to me.
Okay.
So and when we do these assessments, sorry for the blip, as
I said we talked about where
the company is today and we think about where you're going,
what's evolving, what's changing.
So when we develop the results of these assessments, which
we'll walk through in a minute, we tend
to identify where we think the organization is currently
and then our recommendations
are geared to drive the organization to where we think you
should be or need to be based
on the risk profile that we anticipate.
Okay.
So with that I'm going to hand it to Tim and he's going to
go through the specific results.
Thanks, Steve.
I guess before I jump into the results, maybe kind of
wanted to give an overview, kind of
an executive summary of kind of what we saw and what we
heard.
I mean I think overall everything that we heard made a lot
of sense.
We didn't find any glaring gaps or holes given the size of
the organization, their transacting
mandate and how they operate.
I think it's very consistent with where we kind of see you
in the growth of the organization
from just a couple years ago, kind of three years ago
starting it up to where you are
now.
So as it relates to kind of looking at the results at a
high level, in addition to the
developing prevalent and leading evolutionary maturities
that Steve talked about on the
previous slide in the four main categories, we added the
recommendations to that.
So at each category a high, medium and low priority.
And then we also identified the risks that those
recommendations would map back to on
the slide that Steve talked about a little while ago.
So in each of these categories, governance, process, people
, technology, there's really
a whole bunch of individual elements that when taken
together affect the governance
or represent the governance.
And so when we look at identifying where the current state
is using governance as an example,
what we do is we go through each of those individual pieces
, things like risk management
committee, the risk policy, objectives, the risk management
program.
And we look at and identify where we think the current
state is based on what we're
hearing and what we've read.
And then also the recommended future state.
And so when we take all of those individual pieces, the
summary that you get is what you
see on this slide here in terms of the current state across
each of the categories and then
the future state.
So as you can see, all of the current state assessments are
right there in the developing.
Some are kind of right there in the middle of it.
Some are kind of on the edge of developing.
And there's really, there's not necessarily a science
behind it.
We're not quantitatively placing these, but really kind of
taking a look at the results
as a whole and identifying where you are.
And so as you can see in terms of the recommended future
state, we have recommended and what
we heard is kind of moving into the middle, right in the
middle of the prevalent, all
the way to kind of on governance and process to the edge of
leading.
And so in the case of a couple of these, it might look like
big movements, but as we get
into the recommendations, I think what you'll see is there
is a lot of low-hanging fruit
here.
Some relatively simple things, light lifting things that
could be done in order to really
enhance the governance and especially the technology as
well and really take big steps
moving forward as you look to implement those
recommendations.
Any questions?
Okay.
So now I wanted to take a couple of minutes to walk through
some of the recommendations.
So all the recommendations on this slide represent the high
-priority recommendations that were
identified on the previous slide.
And so as you can see, the governance really has the bulk
of the recommendations.
And if you were to group these together, I kind of talk
about three to four main groups.
So the first group is really kind of the first three or
four bullets on this slide, which
is around kind of thinking through the governance hierarchy
and the oversight.
So currently, that hierarchy is city council.
The board has a role in that.
And then there are two committees within DMA, the strategy
committee and the operating committee.
So kind of stepping back and thinking through that and
asking the question, is that the
right hierarchy to have?
And so one of our recommendations is that at the DME level
to consider consolidating
the strategy and the operating committee, making it a
single risk management committee.
Part of that is there's a significant overlap in the people
that sit on both of those committees.
And so having a more focused, concentrated group to provide
that oversight would likely
pay dividends.
And that includes taking a look at the governance document,
the risk policy, the procedures
manuals as well.
I think it's clear that when both of those documents were
set up early on, a lot of thought
was given to how the oversight would be, the different
processes that would comprise the
risk management program.
And I think just over time, as things have evolved, some of
those things have changed.
Some of the, they're doing some of those things.
There's some new things that, from a risk management
perspective, that are being done.
And so just going back through that and making sure that
that document's tight and accurately
represents what's being done would again pay dividends.
The next group of it, really right in the middle of the
slide, update appendix A and
appendix E of the risk policy.
Again, it's about making sure that those, the limits and
the approved products are specific
and representative of what the front office and what the
energy management organization
is focused on.
And then finally, the last three, I guess the last group of
three, actually step back.
So on the last bullet then, reconcile the DOA.
DOA is delegation of authority memorandum.
So there's a memo that goes out on a periodic basis.
Just making sure that that, as you look to make changes to
appendix A and E, making sure
that those changes kind of carry through into that memorand
um that gets sent out.
And so then the last main bucket is around the design and
document the financial hedge
strategy, quantify the risk profile annually, and define
risk limits linked to objectives.
So kind of to tie back to something we've already talked a
little bit about, it's, you
know, as you've introduced a little bit more uncertainty
into the portfolio related to
the renewable supply variability, kind of taking a step
back and making sure that the
variability is well understood, the potential impact, cost
impact or rate impact of that
variability can be quantified, and that there's a
mitigation plan there to manage that, to
the point made earlier.
And we'll come back to that piece of it as well when we
talk, when we get to the benchmark
piece.
Also on the process side, it's really about the
communications are focused on reporting
and communication, making sure that there's a clear set of
reports that can be provided
not only within DME, but, you know, to the city council and
to the board as well.
And then just making sure that everybody is, you know, has
a consistent set of those reports
so that everybody is, you know, talking from the same sheet
of music, if you will.
On the technology side, I think one of the things that we
heard and learned is that,
you know, the systems and the technology that staff uses on
a day-to-day basis, there are,
you know, there's some gaps in the functionality and the
capabilities of that system.
And so taking a look at what it is they need to support the
program and finding a solution
that can be implemented in order to support the day-to-day
activities would help take
a big step forward.
And then finally around the people, making sure that across
the front, middle, back office,
so the front office being the group that executes
transactions, the middle group, the group
that is responsible for the risk oversight and the back
office, the group that accounts
for it, making sure that there's, you know, there's
redundant resources across those groups
to help step into, you know, any gaps in resourcing that
might exist.
And so it's really about making sure there's redundancy
across those resources to support
the mission of the energy and risk management program.
Okay.
A couple of questions.
Councilmember Hutzpeth.
Thank you, Mayor.
Regarding the technology component, assuming it's
functioning currently, so what your analysis
is, there's ways to pare that down or remove some processes
, steps.
I'm assuming there's some kind of -- they have a
methodology currently, and this is
saying that there can -- that can be paired down.
Am I on the right track there?
I don't know about paired down.
I think what we heard -- what we saw and what we heard is
that the system that's currently
in place doesn't have all of the capabilities that DME
would need in order to oversee and
manage the risk management program, and risk is currently
designed.
It doesn't necessarily have the analytics that are needed.
There's limited reporting capabilities.
So -- and this kind of ties into the people recommendation
here.
I think there's a lot of effort right now, a lot of manual
effort that goes into being
able to prepare reports on a daily basis.
Yeah, there are -- there are certainly technology solutions
out there that can help facilitate
those things, such that, you know, the resources aren't
using all of their time preparing report
-- manually preparing reports in more time, analyzing, you
know, and having time to respond
to the risks that the utility faces.
So on the technology front, it's about, you know, as -- you
know, defining what's needed,
what capabilities are needed, what reports are needed, and
then finding a solution that's
really fit for purpose.
It might be something that's, you know, cheaper than the
current system that's been implemented
and being used, but it's kind of less about the cost and
more about how does it support
the mission and the day-to-day activities of the utility.
Okay.
So just to make sure I'm tracking with you, so the
technology component, the people component,
that would be -- so for example, if you find a technology
that completes the reporting
faster, more efficiently, more accurately, that would then
dovetail into people as they're
assigned positions, that sort of thing.
Am I right?
Well, it would certainly make the -- it certainly help
facilitate the day-to-day activities
of the individuals involved in the program, absolutely.
Okay.
All right.
Thank you.
I've got a question on the prepared daily portfolio level
risk report.
What is that exactly, and is that prepared for the day
ahead or for the current day?
I mean, and what's the purpose of that?
So it's more of a forward-looking report.
So, you know, when we think about -- when I think about
risk management, you know, I
might think about it in the context of a rate -- the rate
year, for example.
And so if I -- you know, if I'm managing -- my risk
management program is focused on managing
the rate charge to the customer, I might look at a rate at
risk.
So over the course of the next year, how much variability
might there be in rates given
supply is going to change over time and prices are going to
change over time?
And that might then inform decisions I make about, you know
, what to do in the day ahead
or what to do a week from now or what to do in the forward
markets.
So that daily portfolio level risk report would supply
would help everybody understand
what the risk in rates might be for a particular year and
then drive decision-making on how
to mitigate those risks.
Okay.
I might have read that.
I was thinking this is a daily report, but that's not what
you're saying.
You're saying this is a report that covers a certain span
of time based upon sort of
an overall risk report based upon assumptions of, you know,
renewables and either showing
up or not showing up.
So it's not a -- it's not a daily report is what -- or is
it?
Yeah, it can be.
It can be a daily or weekly report.
The daily focus here focuses on, yeah, how often do I send
it out?
The portfolio level report goes to the over what period of
time am I looking?
Gotcha.
Okay.
I'm looking at a rate year or calendar year, for example.
That's helpful.
I appreciate that.
Thank you.
You're welcome.
Any other questions for this slide?
Oh, are we through with this slide, people?
Any other questions so far?
Okay.
All right.
Go ahead.
Okay.
And not much more to say here.
I think we covered -- I covered this off on one of the
previous slides.
So when we looked at the program, I think that when you
look at how the organization
is structured, staffed, you know, there's a lot of the
capabilities are there to manage
the risks the utility currently faces.
And then we talked about the technology piece as well.
Okay.
Anything you'd add, Steve?
Okay.
So now we'll transition to the FY17 benchmark analysis.
So I guess before we get into the results of the analysis,
I wanted to walk through
the two options that we really looked at.
And then we'll also talk a little bit about an alternative
approach to perhaps consider.
So the really two main approaches, the first one being
looking at the day ahead -- using
the day ahead power prices and a three and a half heat rate
adder.
So if you recall the last time we talked about the
benchmark, this one is in a lot of ways
very similar to that benchmark with the third party.
And so the three and a half heat rate adder, if you recall,
represents the risk associated
with providing the power as well as some component of that
being profit or -- profit margin or
premium.
And so in this case, option one would look at what the day
ahead prices for electricity
were over the course of the year in question.
So FY17, take those as a function of the load that was
supplied.
So how much electricity did you need, adding in that three
and a half heat rate adder to
establish the benchmark.
And so it has some benefits.
It has some disadvantages.
One of the main advantages is that it's very easy to
measure.
It's very easy to go out to ERCOT, pull down day ahead
power prices.
The utility would know the load that was supplied, and you
could very easily quantify it.
One of the disadvantages is that it's constantly moving
with however power prices are moving
throughout the year.
So as you go through the year, if generally prices are
rising, the benchmark is going
to rise over time and vice versa.
And then the other aspect of this is it's always going to
include some premium in there
related to the three and a half heat rate adder.
And so one of the things that we did, you'll see on the
previous -- the next slide is we
looked at this benchmark, option one, both with the adder
and without the adder, to provide
an understanding of how much of a cushion that that
provided in the benchmark.
And then the second option is -- really uses a forward
curve approach.
So on any point -- on any day and time, I can go out to the
financial markets and I
can see what the markets expect the price of electricity to
be, you know, one year from
now, two years from now.
And so this benchmark uses the forward curve on a
particular day, so in this case the end
of September, right before you start the fiscal year.
So we went back in the case of the analysis and looked at
what the price for power was
in ERCOT on September 30th of 2016.
And then we used that forward curve to -- and the load,
again, a forecast of the load, to
establish a benchmark that then the EMO would manage
against in order to, you know, demonstrate
cost savings or value, depending on how you describe it.
And so the advantage of this is it's market-based and you
can set a very clear target at the
beginning of the year to manage to.
The disadvantage is that it can be -- it's disconnected
from objectives, risk, and the
impact of uncertainty, which we talked a little bit about
in some of the previous slides.
So I guess before I move on to the results, I just wanted
to pause real quick and see
if you had any questions about either of those.
Any questions?
Okay.
So in terms of the table that we have here, the top third
is what the benchmark calculation
was in the different options.
And again, option two kind of has -- sorry, option one kind
of has option 1A and 1B with
and without that heat rate adder.
The middle section here were the costs for FY17 as supplied
by DME.
And then the bottom third are the savings.
So I guess if we jump to the bottom real quick, the good
news is that under all three benchmark
scenarios there were cost savings for FY17.
The level of those obviously differs a little bit.
Is there a question?
Yeah.
No, go ahead.
Finish your thought because I just have -- yeah.
So as you can see, and we'll go back up to the top and we
look at the benchmark calculation
under option one, you've got about 37 million in the case
of where you're just -- you're
looking at the day ahead and the heat rate adder, and about
29 million in the case where
you're just looking at the day ahead heat rate.
So the difference between those two and then -- and thus
the corresponding difference down
below in the savings is purely a function of that premium,
the three and a half heat
rate premium, which was very similar to the premium that
was embedded in the previous
contract.
And then when you look at the forward curve, which as I
mentioned was established on 9/30/2016,
the savings for FY17 would be about $4 million.
Okay.
Yeah, the question is -- make sure because it's been a few
days since I read this.
So the EMO costs provided by EMO, that represents our cost
of energy and does that also -- or
does that just represent all the expenses associated with
the production or with DME?
In other words, it's not just the energy cost, but it's
personnel, the EMO, the MMO group
expenses and things such as that.
Okay.
So that's all in.
That's all in there.
That's all in.
All right.
So if you look at the -- I say worst case scenario, but the
one that shows the least
amount of savings is that middle option, which is the
option without the heat rate adder.
So -- but when you look at it, you go from a $2 million
savings to a $10 million savings
simply by what benchmark you're choosing, which that's a
big spread.
I mean, so it's just a little -- it's interesting.
And I eventually would like to hear from DME as far as what
they think is the more appropriate
benchmark because that's been our concern is how do we
measure this?
But when you can choose one that creates a $10 million
savings and the other one -- but
which one represents more accurately the market and is that
-- would that be option three?
So you're hitting on the exact question, I think.
And when we spoke last time, one of our observations was
whatever benchmark you choose, everyone
needs to be crystal clear on the elements, the components
of it, how it's calculated
and what drives it one way or the other.
The question, I think, to read in your question a little
bit as well is what's reality in
terms of -- Absolutely.
-- how could -- if we're effectively looking to replace
what the EMO is doing, would anybody
be willing to do that in the market similar to the previous
agreements you had at a zero
premium?
Probably not.
I mean, they would want to be compensated for assuming that
risk.
If you remember before -- Yes.
-- the risks before were all outsourced and effective.
The management of those risks were all outsourced.
So the question becomes what's a reasonable heat rate
number that someone would be willing
to absorb those risks and aware that risk on your behalf?
And so is that really what -- so these options -- because
that's a good point.
In other words, if we decided to do something different and
let's say outsource it, then
which one of these three options would more accurately
represent what the requirements
would be in the marketplace for that?
And so either -- I'd like to hear what y'all's thoughts are
on that.
Just from just a professional perspective and then at some
point hear DME's thoughts
on what would more -- and so I'll ask you first.
If hypothetically speaking -- obviously nobody's made this
decision, but this is what the whole
purpose of this presentation is.
If we were to say, okay, we had to -- something happened
and we lost the EMO for some crazy
reason.
We had to go out and contract it.
Which one of these three options do you see based upon your
professional opinion and just
expertise in the marketplace say would more accurately
reflect what we would expect?
I think it would be something very similar to option one.
I don't know that the premium, the three and a half heat
rate premium would be one and
a half or if it would be three and a half, but it would
certainly be some cost for the
energy, probably using the day ahead as some type of -- as
a benchmark plus some premium.
And some factors I think will drive whether that premium is
one and a half versus three
and a half, including kind of the number of counter parties
that are willing to provide
the service.
So the more counter parties you could get to bid on that, I
think the more better pricing
or better premiums you could expect.
But it would probably be something very similar to one.
So what I heard you just say then was the second -- the $29
million savings would not
even be the floor because somebody is going to ask for at
least some adder.
Whereas the $36 or $37 million, that may be the top end.
So if you had a one and a half or two -- is that a percent
or is that just a dollar amount
or is that the heat rate -- add two to the heat rate, I
guess.
You're probably looking at somewhere around $32 to $33
million or somewhere in the middle
between those two.
Okay.
All right.
Okay.
So you don't want to get to where you can choose which one
just to sort of fit the savings
that you may try to achieve.
All right.
I appreciate that.
Thank you for that.
Just to tee up the -- sorry.
My only point is I think you framed that well because the
middle option that we're seeing
here, the middle one basically is probably the most
conservative option without actually
going out and obtaining bids.
I don't know that anybody could really answer your question
without having formal bids submitted.
No, I understand.
Sure.
I think you're right.
It would probably be somewhere in the middle there.
Okay.
So just to maybe tee up the transition because we looked at
these options as kind of a cost-based
benchmark.
What Tim is going to describe now is more of a performance-
based benchmark, which Tim
mentioned kind of looking at a rate at risk.
What we're going to walk through next is something for the
council and for the board to consider.
What we often suggest to organizations is what is it that
you're striving for as an
organizational goal?
What we heard a lot when we spoke with staff almost in
every meeting that we talked about
was the ultimate responsibility of that organization is to
manage the prices that are passed through
to the ratepayers, to the residents of Denton.
And I'm sorry, one last question before we move on from
that last slide just so I make
sure I understand.
So on the option, let's say let's use option one that you
were talking about.
That's where you go out and you contract with someone and
they may give you a premium added
onto the heat rate.
But that cost, just to be clear, but that cost, which is a
third party's energy costs,
also includes again, once again, the expenses for DME as
far as it's an all-in cost, even
including the third party contract.
Or is this just an energy cost that you're, I'm trying to
make sure I'm understanding
what the savings are because the EMO costs us some money
just to have it.
And if they're included in this, that's great.
But if not, then I've got to subtract that.
I just want to make sure I'm not having to subtract
anything out of these savings to
get to a net number.
So I think if you took the costs for the EMO that were non-
energy related, I think if you
were outsourcing it, a chunk of them might go away.
I don't know that they would all go away.
You still need to have oversight of that contract,
oversight of the counterparty.
There's still some back office functions that would exist.
So it's not as if all of those EMO costs would go away, but
some portion of them would.
Is my question making sense as far as I just, because the
whole point of this discussion,
I believe was to look at in the past, we've said, well, by
having this organization, we're
able to save X amount of dollars, but we didn't really have
a good benchmark to measure that
by.
This is what we're trying to establish here.
And I just want to be sure that I'm understanding that,
okay, if we use this benchmark and the
EMO costs us, say we use benchmark one, it's $37 million.
And EMO costs us, I don't know, what is it, $3 million, I
'll just pick a number.
That I'm not having to subtract off of these savings the
cost of the EMO that it's already
included in that benchmarking cost.
Is that, so, and the answer to that question is yes, they
are.
Yes.
Okay.
All right.
Thank you.
Yes, Mayor Pro Tem.
Then what is the EMO cost line?
The $26.5 million here.
That is the energy that was procured in FY17 plus the cost
to support the EMO, so personnel,
systems, other expenses.
I thought, but I thought you were saying that the EMO costs
were already in the benchmark
costs.
I guess I'm confused by the question.
Wasn't your question if the EMO costs are included in the
benchmark?
Yes.
Yes, because if you're saying that the EMO costs, that
middle line, is what the actual
cost of the energy that was paid by the rate payers, which
includes the part of the EMO
for the salary, the staff, technology, whatever, to produce
that energy, that's an all-in number
for our discussions, $26 million.
In our benchmark costs of $36.7 million, you've got how
much the energy would cost plus you've
also estimated that this is what the EMO costs associated
with it, which would be similar
to the middle line, whatever that subset is.
Yes, in order to be apples to apples and have a savings
calculation that, or savings result
that made sense, you'd have to have those costs in both the
benchmark and in the actuals,
and those are in here.
Okay.
Yes, Mayor Pro Tem.
So what else is included in the benchmark costs?
So the benchmark cost is the energy plus the 3.5 heat rate
encapsulates a lot of those other
costs, it encapsulates risk, it encapsulates profit margin.
So in that risk number would be the systems and the people
that the third party supplier
would need to have in place to effectively manage those,
which they're doing in that
outsourced model.
Okay.
So as Steve was saying, I think as you kind of continue to
think about this as an evolution,
so you start something out, you may start in developing and
you move more into the prevalent.
I would, I think it makes a lot of sense to think about the
benchmark in the same way.
So going into this, the frame of mind might have been, let
's be able to quantify how
much we're saving in order to support the decision to
establish the EMO and moving forward.
I think it makes sense now as the EMO is more established
and more completely managing the
risks of the utility to also think about evolving how you
think about the benchmark.
And I think one way that makes a lot of sense is to move
from cost savings to more of a
performance or value add based approach.
And so one way in which you might do that is to rather than
think about how much did
I save, well what outcomes was I able to achieve because I
had this risk management function
in place.
And as Steve mentioned, it kind of goes back to what are
you trying to manage to?
What are the outcomes you're looking to promote?
And when we talked with staff, we kind of heard, we heard
two pieces to that.
One is stable electricity rates when prices rise, but then
also competitive and lower
rates when prices fall.
So one potential approach to that would be, well, as prices
rise, I'm just going to have
as much fixed price power as I possibly can so that when
prices go from $50 to $100, my
customers don't have to participate in $100.
I think when you look at it kind of solely from that
dimension, what happens is when
prices fall, now you're no longer competitive and you get
questions about, well, how come
one town over, their prices are significantly lower than
mine?
And so the way in which you kind of navigate both of those,
you know, both of those dimensions
is you have a set of paired and market compatible
objectives, and in the coming slides I'll
talk a little bit more exactly what I mean by that.
You have a hedge strategy with risk limits that have been
demonstrated to help you achieve
those objectives.
And then you have to have the right infrastructure, going
back to the technology question that
we had earlier.
You have to have the right infrastructure, the deal capture
, be able to capture transactions,
view them, quantify the risk and monitor in place to help
you decide when to act.
And so if we kind of bring it back to the benchmark, it's
really the first two of these
that then form -- will help form the basis for the
benchmark and give you a platform
to assess how well did we perform last year and how much
value did we add to our customers.
And I'm sure you probably got it in the upcoming slide, but
-- and I appreciate that and I
understand that concept and that strategy.
I guess, though, as I think through it, you're -- there's
still going to be at the end of
the day potentially a question that says how do we measure
this strategy that we've implemented
with the EMO, and if you're able to benchmark items number
one and two, okay, but you're
still going to come back to if we didn't have it, even
using one and two, what would our
-- what would it have cost us and how do we measure that
and how do we -- and I'm assuming
that's going to be explained in the next couple slides.
Absolutely, yes.
So we'll walk through that in a little bit more detail in
the next couple slides.
So it starts with the objectives.
So if we think about -- I talked about market compatible
and balanced objectives.
So this is -- it's kind of meant to represent what that
means.
And so there's kind of two pieces to the objectives.
There's what we call portfolio risk or managing the
customer's rate at risk.
And so in this case, I would be executing transactions in
order to prevent against the
possibility of higher prices.
We also look at the hedges -- the transactions that I have
executed, how well are they doing
and what do I need to do in order to make sure that as
market prices fall, I'm able
to pass along the value of those lower prices to my
customers.
Well, when you have these two objectives, they tend to be
in tension with one another.
In other words, every time you hedge to protect against
higher prices, you create the probability
that you might be wrong and you might actually forego
passing along lower prices to your
customers.
So the way that we manage that is by having an option
strategy that allows you to balance
both of those things.
So what I mean by that is if I've hedged a whole lot to
protect against higher prices,
options allow me to capture some of that value if prices
were to fall because they benefit
me in falling price environments.
And so the combination of those two things allows me to not
only protect against rising
prices but also benefit from lower prices.
And so these three objectives then form not only the basis
for how I'm going to manage
and make decisions as I go throughout the year, but they
also then form the benchmark
against which I'm going to assess my performance, not only
relative to what I said I was going
to do, but we can also use the same framework to look at,
well, if I had done nothing, if
I was purely a price taker, what would the cost have been?
What would the impact have been to my rate payers?
And what value was I able to deliver to them because I wasn
't a price taker, I was more
of an asset optimizer.
And the way that we do that is we explicitly state three
objectives.
First one, going back to that rate at risk.
So I'm going to manage my energy cost adjustment so I don't
pass along more than a X percent
year over year rate increase to the customer.
And as you go through this and you do that risk profile and
the hedge strategy that we
talked about in the recommendations section, you can fill
in a number there.
And so maybe that number is 5 percent, just to pick a
number.
I pair that with my second objective, which is I'm going to
manage those hedges or those
fixed price transactions I've placed so that customers'
customer rates are never more than
X percent above what the market rate for electricity might
be.
So in other words, if electricity prices, if power prices
fell by 5 percent, I want
to be able to pass along as much of that 5 percent decrease
in power prices to my customers
as I possibly can.
And then the third piece of it is I need to have that
options budget so I might say I'm
going to set aside $500,000 in order to manage the tension
between objective one and two.
So you go throughout the year and the EMO is managing to
both of those first two, really
I guess all three objectives.
And then you get to the end of the year and then what you
do is you look back and you
say, well, what actually happened?
Well, from when I set my budget back on, just to pick a
date, September 30th going into the
year, power prices or my energy cost adjustment would have
risen 7.5 percent if I hadn't
done anything.
But I only have to raise it 1 percent because I've actively
managed my portfolio.
I've hedged to protect against those higher prices.
I have the benefit of this renewable portfolio.
And you can measure that you did better than you said you
were going to do because I was
going to protect against 5 percent.
It was actually 7.5 percent so I can assign a 6.5 percent
value to the EMO related to
managing to this objective.
And you can convert that into total dollars based on what
the overall energy cost adjustment
would have been without having the EMO in place.
And then similarly, if you look at a year, consider a year
in which prices might have
fallen, you can go back and you can measure how much the
energy cost adjustment would
have fallen or you would have been able to decrease it if
you hadn't hedged.
And so maybe if that was the market fell by 8 percent, well
, because of the hedge program
and this second objective here, you can also measure, well,
I'm capable of passing back
6 percent of that 7 percent decrease.
And so again, you can quantify regardless of whether prices
go up or prices go down,
you have the framework and the ability to quantify the
value in both of those types
of environments.
So I want to make sure I understood what you just said.
This is very all high level technical so I'm just trying to
understand it.
What I heard you say was that you can look at your end of
the year and look at what you
were able to do with the EMO either by minimizing your
energy cost adjustment and/or maximizing
your option, your hedging activities.
So this is where I might need to help me understand.
I thought what I heard you say is and what you compare that
to is if you don't have
an EMO, which my implication in that statement was, well,
then you're just saying you're
comparing it to just the performance of the market without
any intervening kind of decision
making either through our EMO or through some other
contractor if we didn't have an EMO
who would be managing our energy portfolio.
Am I understanding that?
Is that?
Yes.
Okay.
Where I get my concern or my question or my observation is
if you're comparing it simply
to the market function, I don't know if that's realistic
from the standpoint of what we would
be doing as a decision maker.
If we didn't have an EMO, I don't think we're going to go,
well, because you have to have
somebody manage it.
I mean, I think per ERCOT, you have to have somebody who is
it a QSE or what do they call
that or something or so that means they're just saying we
're just going to pay whatever
the market is.
If it's high, it's high.
If it's low, it's low.
Is that really a strategy that is an option?
I mean, I guess it could be, but I don't think you would be
recommending that we, I mean,
obviously by your three objectives here, you're not saying,
hey, just, but you're comparing
it to if it just, if you just simply went by market pricing
.
So I'm not understanding how that really is a realistic
comparison of a sales number.
Does that make sense?
It does.
If we go back to that option one, that's the same approach
that that benchmark is using
to establish that benchmark.
You're purely a price taker.
Now it's kind of separate the QSE, the scheduling side of
it, separate the scheduling function
piece of that, because that would need to be, that cost
would need to be included in
there because you're right.
You couldn't just not schedule your load and supply.
But we can, you can incorporate that in both the objective
and what you're managing to
and also the market, the pure price taker version of that.
Okay.
I need to understand when you say pure price taker option
one, are you talking about that
one slide that had the savings and those kinds of things?
Which option are you talking about?
Option one here, the very first row, the 30th.
Where you had the $10 million savings?
Yeah, 37.
So in that scenario, you're assuming that you're just going
to take whatever the market
price for power is on each day that you need power.
You're not, it doesn't consider any type of active
management and the third party wouldn't
actively manage that on your behalf either.
Well, that's a very good point because that's an assumption
I did not read into that option.
So, these three options are simply you take what the market
price is with no management
of energy.
Is that, is that, is that correct?
It is true for option one.
Option two, it's different because in option two, you're
fixing the price as of September
30th of the prior year, establishing a benchmark that you
then are managing to.
So that's a good point that they are option one and option
two are very different in that
regard.
Okay.
All right.
And that's, it's one of the maybe disadvantages of option
two is, you know, because you are,
you're fixing the price of power, if prices simply rose
throughout the year, you would
have fewer cost savings.
If they fell, you would have larger cost savings.
So it's, and you're not, and this goes back to the, it
doesn't consider objectives or
risk.
You're not changing it there, you're just establishing that
benchmark and forgetting
about it till the end of the year when you go back and look
at what the savings might
have been.
Okay.
All right.
Oh, Council Member Briggs had a question.
So that was really interesting conversation.
I'm glad you brought that up because I wasn't making that
connection either.
And so my follow-up question to that is that the savings of
10 million you confirmed was
compared to the market pricing only.
Is that how we, DME was getting their numbers before our
savings under the prior contract?
Yes.
Comparing it to market pricing only?
Yes.
Okay.
With, I guess maybe a little bit of a qualification to that
.
So under the prior contract, the price for power was
determined based on a fixed heat
rate, which was under the last proposal, 15.75 times
whatever the natural gas price was on
that day.
Now that natural gas price went up and down just in, you're
basically a price taker on
the natural gas side.
The heat rate was fixed.
So it's a little different than option one here because now
all of the power price is
moving up and down.
It wasn't moving quite as far up and down under the
previous contract.
Okay.
And so I just wanted to circle back and maybe we didn't
call this out on this slide, but
when you look at this first column here and what was
actively managed prior to go live,
when we look at the commodity price risk, which is what we
're talking about here, that
was not something that was actively managed.
Okay, good.
So yeah, it's sort of buried in there.
Okay, good.
I'm glad we sort of ferreted that out.
That's good.
Council Member Hutzbeth?
Yeah.
So I have a question regarding the kind of some of the
conversation about the cost, right?
Because that kind of, if a citizen comes to me potentially,
their question is going to
be exactly what you pointed out.
One city over, here's how much we're paying.
That's easy to find out.
What's lost on me is how the energy rate or cost for that
particular day, for that quarter
to that, that seems like it's more difficult for the lay
person to trace, find and correct
me if I'm wrong.
Is that something easy to look up and I'm just not up to
speed on it?
Because given the two scenarios, it's easy for me to call
my friend in Louisville and
say how much are you paying per kilowatt hour, right, or
whatever that is.
That's easy.
So I'm trying to see, I just, I hadn't heard you speak to
that because I can tell you that
the natural, my natural thought is if we own it as a
citizens group, then there should
be savings, there should be an advantage versus someone
that's strictly just buying something
retail or having it managed in a retail fashion, if you
will.
So that's what I, that's kind of, if you could just speak
to that component of first, educate
me, where do I go find the daily rate on the market?
So that's step one.
But step two is if a citizen came and said, where's the
savings because this is a municipality
owned power source, where's the savings compared to someone
that's just dealing with co-serve?
Does that make, and if I'm wrong, correct me.
No, I think I understand the question.
And you're right.
I think the, you know, a citizen's cost, actual cost is,
you don't have real time information,
necessarily real time information on that as an end user.
I can look at my bill at the end of a month and see what my
bill was.
And depending on how rates change, I can see that, you know
, last year my bill was $100,
this year it's $125, you know, why?
I might not understand why other than the fact that energy
prices are higher.
So I think that's part of it.
I think the other thing, you know, is I think you were
asking about retail rates.
Yeah.
So for example, if I'll just, my assumption is if I own it,
there should be just, by the
mere fact that I'm buying it wholesale and selling it
retail, I mean, whatever that is,
I mean, fix the terminology, but ownership should have
privileges versus someone that
does not own their own power company.
Now, they don't have the cost with the trucks, this, that,
and the other, and maybe there's
more downtime than here.
I just don't, I just need to understand that better.
What is, what are the benefits?
If not, because I'll tell you, immediately your mind goes
to the rates.
That's just, that's, and like you said, it may be reactive,
look at the pricing.
I think you're spot on, but it's a fact.
It's easy to look at, and it's the initial point of a
question for a citizen 99% of the
time.
Hey, they're paying this rate over here.
You know, so I just need to understand the value and how
that, if there's a savings or
if there's not a savings because we have to buy trucks and
poles and store equipment,
if that removes the savings.
I just need to understand that and understand where to go
find that live energy cost for
the day, the quarter, whatever that, however it's reported.
Let me, let me address it.
Because I think the scope of this presentation is primarily
towards looking at the EMO, either
with or without the EMO as far as how it affects our
overall energy strategy.
What you're asking, and we can get you the answer to that
as far as is there a data,
is there a website where somebody can go look at what the
costs are for all the different
utility companies for residential rates.
And then understanding that that is the primary concern.
But I think what we, and that's a very good question you
asked because what you're asking
is what's the value of having a municipally owned utility?
Right.
I mean, not just what, whether it's 10 cents a kilowatt
hour or it's 8 cents a kilowatt
hour, but what are some of the other either value added
aspects or deterrents or detriments
to that?
And I think that's probably a little bit past their scope,
but I think that that's a great
question that we need to have some discussion on coming up
in the future.
But as far as that immediate answer of is there a website
where we can, people who call
you can say, here's a website, go check it out.
If you know that, then that'd be great.
No, I just, what I wanted to do is add to the comment you
made about the value add.
I don't think it's about savings because if, I mean, you
could go out and you could compare
what my, what's the rate in my bill to what a retailer
might provide.
And that's, I mean, it's a data point today, but what
owning it gets you is the ability
to manage the risk and manage price risk going forward.
So it kind of comes back in a way to this.
So that same retailer, as prices are rising, they're going
to, that price is going to change
every day and it's going to continue to go up.
The fact that I own something, I own the assets and I can
manage the risk associated with
those assets allows me to make decisions that don't result
in my customers bills going up
day after day when prices are steadily rising.
So that's the value add I think that you get from ownership
.
So for me, it's less about cost savings and more about what
value am I adding based on
the activities and the decisions I'm making to manage my
risk.
Council Member Duff had a question, but did you have a
follow up or?
You know, I just like him to move to District 1 and take
that.
Okay, yeah, yeah.
No, but those are good questions that we can get some of
the answers to.
Council Member Duff.
Yeah, I'm just trying to, you know, wrap my head around
this whole thing.
If I go back and look at what EMO does, it looks like with,
I mean, there's a lot of
moving parts there.
I mean, they literally sit there and look at what the wind
's doing in West Texas and
I'm sure they're going to be looking at the price of
natural gas once we get the deck
up.
So it looks like to me, I mean, they're literally buying
power on a 15 minute basis, I think.
So you've got so many moving parts and you go into the
summer when, you know, the prices
are going to go up.
And you know, another advantage I can see with the deck is
the fact that all the coal
plants are shutting down.
There's some big ones shutting down into first of the year.
And so where's that power going to come from?
So I guess what I see is that EMO, I mean, is literally
saving us money.
And you know, how that's all going to work in with deck and
what is deck going to cost
us in all of that, you know.
It's pretty complicated.
Did you have a question?
Oh, okay.
You just looked at me like you had a question.
Okay.
Sorry, go ahead.
Yeah, just I mean, an overarching comment.
I think, you know, maybe to get back to your question
before about don't we still have
to compare the cost to if we were to outsource this.
And I think that's a very valid point that if even if you
have, you know, you follow
kind of a plan like we're outlining here, which is more
objective based in terms of deciding
did we do well or did we not do well, there's still
probably the option to have somebody
else try to do well on your behalf, right?
So I agree that there may be for some period of time it
makes sense to still have that
cost benchmark.
I think overall what we're recommending and some of the
comments I think tie back to that
is as an organization, what are we trying to do?
And if the example we're giving is we want to manage the
cost per kilowatt hour that
the citizens of Denton are ultimately paying.
And it's our job at DME to not have the gut through the
roof.
And if things go in our favor, we want to participate in
that favorable market.
If we can agree that that's the right benchmark, then I
think or if that's the right objective
as an organization, what that helps you do is then decide
what are the transacting activities
that we're going to authorize in order for us to try to
participate and achieve those
objectives?
What are the limits we need to define and put in our policy
such that we can make sure
that no one's going outside of, you know, what we what we
deem to be authorized?
It helps add a level of clarity to both what we're doing
and how we know, you know, when
we're doing that well and when things are going outside of
the scope of what's expected
from either the council or the board or the ratepayers.
Having that objective serves those purposes in terms of
defining the activities of DME,
but it also can, I think, help the conversation and maybe
the transparency that the councilman
is getting to in terms of how do we tell our customers, our
citizens, how well we're doing.
I think the answer to your question lies in, you know, yes,
they can go to ERCOT and see
where prices settled yesterday and where would they, you
know, are anticipated to go tomorrow.
There's a difficult conversion from that into what's on my
bill, and that's kind of the
translation of wholesale to retail, and that's where you
get into who owns the wires and
all the systems that back that.
But I think you can bake all of that in to an objective
that says we don't want to pass
more than a five percent increase to our customers on any
given on any given year.
Thank you.
And then I think just to wrap up, I think Steve hit on a
number of these things.
You know, to the extent that, you know, you thought it made
sense to go down the path
of kind of moving to more of a performance or value-add-
based approach for a benchmark,
these would kind of be the next steps that you might take
as part of that.
So as Steve, you know, talked about, it's about, you know,
what's the exposure, what's
the range of outcomes, how am I going to -- what activities
am I going to undertake to manage
that exposure, all the way through the ability to set risk
limits to know when you're inbounds
and when you're out of bounds.
So not necessarily something that needs to be done, you
know, today, tomorrow, but, you
know, over the course of, you know, some period of time, if
that's the direction you were
to move, this would be how you would approach that.
Any questions, comments?
Is that there's some -- never mind.
Questions or comments?
And as far as -- you had mentioned on the next steps, it
was based upon your three options
or the benchmarking.
You're talking about the three options?
Yes.
Okay.
Those.
Okay.
Got you.
All right.
Okay.
I appreciate that.
I guess what I -- go ahead, Brian.
You're getting crowded up here.
Yeah.
Well, I just wanted to take -- yeah, I just wanted to take
a moment to thank Tim and Stephen.
I think they've done a great job working through this.
I know this is very technical data, but what we want to do
is come back to you in the next
couple of months.
We're going to bring forward the resource plan that we've
been talking about with enterprise
risk consulting.
We've been working on that.
We want the council to formally approve that.
There's going to be a pro forma, new financial pro forma
for DME that we'll want to talk about.
And then look at these specific issues of performance of
how do we want to benchmark
this going forward from a value add perspective to have a
policy discussion with the council
about options of how we could do that, how that might look,
so that on the front end
you know what that's going to look like going forward.
So we've got additional steps to do that going forward, but
we will be doing that in the
next few weeks with you.
So I think this has been very helpful for us to look at
that.
There will also be things that we'll need to do from our
organizational standpoint of
bringing forward a new risk management policy, bringing
that to you to have a discussion
about those options and a variety of different issues.
So more to come.
Sure.
I do have a quick question for Mr. Morrow if you, if,
welcome.
Thank you.
Happy to be here.
Yes.
And I know that you are fairly new to our organization, so
this is going to be a softball
per se, but I'm assuming some of this, it made sense to me,
but obviously you're tasked
with really deciphering this report and coming up with what
you believe is to be the best
recommendation to move forward.
And just wanted to give you an opportunity to comment.
If you had any, and if not, that's okay too.
Well I, thank you George Morrow, General Manager of DME.
Yes, I'm happy to be here in Denton.
It's been my third week, so I, yeah, I don't know
everything yet.
But I've been in the electric utility business for 39 years
and worked a lot in this area.
So power supply, power resources are my expertise.
And I'm very comfortable with what I heard today.
I'm very comfortable with the report that we received from
Deloitte.
For us, it's kind of like getting that annual physical.
You know, it was three years after we implemented the EMO
and it was time to do a quick assessment
and give us some other places to go.
So we're going to be following through on lots of the
smaller recommendations that were
made and doing some of the bigger things, which is updating
the risk management policy
that was put in place in 2014.
There's some low-hanging fruit there that we're going to
move forward on.
And thank you for your comments in that regard.
We're looking at a new model to do the kinds of mach
inations and calculations that are required
to do some of the benchmarking that we want to do going
forward.
So I think it's great that Denton has a community-owned
utility, you know, 105 years old.
There's lots of benefits of having a public power utility.
That was one of the thoughts I had as you were discussing
that, including managing and
controlling your own destiny in the power markets and power
resources.
You can decide to go 100 percent renewable or 70 percent.
In California, there's still people at 25 and 30.
You'll be moving ahead of that pack pretty quickly, and you
'll be gaining some of the
benefits of doing that from an environmental and rate
standpoint.
So local control, you can decide, you know, we want blue
lights.
You can say, hey, on this street, I want to go underground,
or I don't want to go underground.
You know, you've got a lot of things that you can't control
if you weren't managing
the utility that I think, as we think through all of the --
all sides of this, it's a much
bigger question than just this power supply piece.
So I thought the questions were great and look forward to
more discussions as we move
down the road.
And again, I did want to thank Brian, our deputy city
manager, for carrying the ball
on a lot of this stuff while you were transitioning to a
new general manager.
And look -- and he's -- we're working very well together.
Fantastic.
Thank you.
Appreciate it.
Thank you.
Okay.
Thank you, gentlemen, for that.
And any other questions or comments?
Okay.
Thank you very much.
Thank you very much.
Appreciate it.
Let's take a quick five-minute break before we move on.
, thank you.
Thank you.
All right.
Welcome back to our meeting of Denton City Council, Tuesday
, December the 12th at 2.30.
We're on work session agenda item 3B, and Councilmember Br
iggs has completed the proper
paperwork, I believe, and to recuse herself from this item.
And so we're going to now take up agenda item 3B, receive
report, hold discussion,
provide staff direction on -- provide direction, excuse me,
on design options and schedule
for the proposed reconstruction of Fire Station 3.
Good afternoon, Mayor, members of council.
Mark Nelson, director of transportation here with the City
of Denton.
Appreciate the opportunity to visit with you this afternoon
on what we hope to be the last
design discussion on Fire Station 3.
I would like to point out we certainly have our Fire Chief,
Paulsgrove, Assistant Chief
Hedges, our design architect, David Robinson, with us, as
well as Dean Hartley, our facilities
manager, who have been participating as we move through
this process.
So really this afternoon, wanted to visit with you kind of
where we are with the particular
-- with this particular project.
And really at the end of the day, end of this presentation,
we have a couple more design
components as it relates to the roof and the HVAC system in
terms of opportunities where
council may want to weigh in on those design elements and
costs associated with this particular
project.
With that, I'll move on with maybe a little less technical
presentation than what we heard
in the last hour.
So just to reorient you, this is the location essentially
at McCormick and Avenue A. There
on the -- in the red outline is the existing Station 3.
You can see I-35E there on the bottom left side of the
slide.
That we have roughly right at three acres of property.
The area here that you see the ground disturbed, that's an
old hotel site that we purchased.
A portion of it had to be acquired for the 35 Express
project, clipping the corner of
that property.
And so we were able to acquire that piece of property as it
fit in with the fire department's
strategic plan in terms of districts and where they put
their people and apparatus.
This is another shot of this.
This gives you the orientation.
From what you've seen last time, this has moved a little
bit counterclockwise.
But you can see where the fire station here in this light
red or pink color here is, the
shading here of the access into the back of the station.
And then the departure route across the existing McCormick
Street onto Avenue A.
Just a reminder, as part of this project, we would be
looking to close a segment of
McCormick Street, which is from Underwood down here to
Avenue A.
So a short segment.
And so we'll be working with our Traffic Safety Commission.
We'll have to follow through that process to make that
happen.
One other note, we're also working very closely with TechSt
ot on the actual right-of-way lines
for ultimate location for the 35 Express project through
there to ensure that where we place
our facility, we don't run into any hiccups down the road.
So this is the more traditional design.
This is one of the concepts that was brought before you
back in September.
This particular elevation is similar to what you see at the
new station two out on McCormick
and what is being constructed with the new station, station
four up on Sherman Drive.
Has more masonry, brick masonry elements to it versus what
we looked at before was a more
contemporary that had a little bit more glass and steel
structure to it.
So this is the layout.
If you may recall, in September we brought forward three
different design options.
We were given the direction to move forward with the larger
design option with about 16,100
square feet.
And essentially what the design team has done is gone back
and embraced the request from
council to see where we could reduce or might we be able to
reduce that total footprint.
So you see in the top right corner a reduction of about 420
square feet.
Some were shaved off, kind of made the vehicle bay a little
skinnier, if you will.
And then some changes in the living quarter and the support
area.
You know, primarily this vestibule area was a little bit
larger.
And then the entry lobby was a little bit larger as well.
But there was other changes in some of the support areas on
the north side of the facility
as well.
So when we brought this forward to you in September, we had
roughly an estimate of about
$5.8 million.
There was a direction to move forward with -- there was a
direction to move forward with
a higher -- a higher or more robust foundation, which was
about 190,000.
So that increased that number up to about $6 million.
Now as we progress through the design elements or design
process, we get a little more clarity
focus on what the costs are.
And so now we're looking at roughly the $6.2 -- $6.28
million for the current design with
recommended -- with recommended design elements.
What we see here at this point in time is a couple of the
design options in front of
you today for discussion.
What you see is the HILO, which is the city standard.
We have that -- we're using that type of roofing system
throughout the city.
In fact, this particular facility we're in here had the
roof replaced in 1992.
We're looking to replace it in the next six to eight months
, so roughly a 26-year lifespan
on that.
It's a 20-year standard.
The TPO is more of a 12- to 15-year life.
And so, you know, for the cost, life -- life cycle cost, we
're recommending -- staff is
recommending the HILO 20-year roof.
In terms of the HVAC system, what we're looking at this
variable refrigerant flow, what that
particular system allows is rather than having a multitude
or several different units as
a single unit, and it allows to -- allows the opportunity
to control the temperature
throughout the -- throughout different zones versus, you
know, shutting down or utilizing
separate units in different locations.
Here those are on the VFR, the very -- VRF.
It is a -- is roughly a 20-, 25-year system as well,
whereas the rooftop units are going
to be in about the 12- to 15-year range.
And we look at about a 3.5- to 4-year payback on -- on --
in terms of operating efficiencies.
>> Is the variable refrigerant flow -- is that a chiller
system or is that -- no?
>> Yes.
>> No, it's not?
Okay.
That's fine.
I just -- I don't even know the -- I just -- I just wasn't
familiar with that.
I just didn't know if it was a chiller.
Okay.
All right.
>> Any additional questions on this?
>> I can't speak because Todd's gut is taser out fixing to
tase me on it.
I'm just kidding.
No, that's good.
So you're saying the difference is only about 100 grand
from staff's recommendation to whatever
the other option is, it's $90,000.
>> Correct.
>> So --
>> On the high load versus the TPO, I believe I read in the
backup that there's a significant
hail difference.
>> That is correct.
>> Right.
So that's -- that's the reason that this roof has been
around since '92 for anything that
were the TPO in this area has been replaced at least three
times by hail during that time
period?
>> We've not replaced it in that time frame.
We've done -- certainly we've done the maintenance process.
We've gone through different maintenance.
>> But any buildings we had TPO on probably got replaced
due to hail.
>> That would be correct, Dean.
>> Actually, we don't have TPO on it.
>> Actually we've been in the high load system since '93.
So basically we don't have anything that has TPO on it
anymore.
>> Okay.
Great.
Great.
Thank you.
Any questions for staff on this?
I'm assuming you're asking for direction of do we go with
the staff recommendation on
the high load --
>> Correct.
I've got a few more slides if you --
>> Sorry?
>> I have a few more slides if you --
>> Oh, okay.
All right.
Go ahead.
Yeah.
>> So I did want to bring to your attention we did have a
deficit.
We presented roughly about a 1.275 deficit.
That's this number here to the right.
Back in September due to the increase in the costs, we're
looking at about a 1.6, 1.7 million
dollar deficit at this point in time.
Once we get closer to going out to bid, we'll get better --
a better -- or a tighter number
on that and move that forward and look at working with our
finance office in terms of
probably a reimbursement resolution in terms of finding out
exactly what that total dollar
amount is.
So this would be the schedule.
If we receive direction, we start moving forward, final
izing the construction document and then
move forward with submittal for the building permit phase.
Again, we'll have to -- we have to plat the property.
Still need to see about doing the street closure.
And then as you can see, move through this process with
essentially in the December timeframe
potentially initiating an 18-month construction schedule.
So with that, I would take any questions that you may have.
I can go back to those slides if you'd like to visit with
those particular options.
>> Any questions?
Is it staff's direction -- staff -- is it council's
direction to -- Council Member Hussbett
and Mayor Potem?
>> So one question.
So lessons learned from the fire department on McCormick.
>> I think that's right.
Markingbird.
So have we put in place the new construction plan that then
makes it punitive if the -- would
that be applied to this project?
I guess is a better question.
That makes it punitive for them to fall behind or for -- as
we incur bumps along the road,
we get a -- >> We haven't gone to that point yet in terms
of advertising that.
But I think what you're asking about is A plus B or the --
and we can certainly add
that in and take that direction forward.
>> We're studying capital projects right now, a couple road
projects in this building project
in particular that we might implement that in and make that
recommendation to you.
Not only to try to incent them and do it a little bit
quicker, but obviously building
those penalties if they're late.
>> Okay.
>> But yeah, I'm all -- I think to the -- for the value, I
'm okay with moving forward with
the recommendation.
>> Mayor Pro Tem.
>> I just wanted to point out that the high load roof
system actually has a warranty on
hail of four inches, up to four inches of hail, is that
right?
Whereas the TPO system has no warranty on hail.
>> That's correct.
>> Right.
>> I know way too much about commercial roofs, so I cannot
get in favor of the TPO roof system
for our purposes.
It's going to -- there's no way we're going to have a 20-
year roof, and I think what we're
really looking at is more of like when there's a hail storm
, we'll have to replace it.
>> Okay.
All right.
Any other questions?
All right.
So direction is to go ahead and go with staff's
recommendations.
>> Very well.
>> Yep.
>> Thank you.
>> All right, if somebody could maybe grab Councilmember Br
iggs.
>> All right, moving on to agenda item -- what session
report 3C?
>> Agenda item 3C, receive report, hold discussion, give
staff direction regarding the potential
funding for small-scale traffic improvements and Vela
Athletic Complex project.
>> Thank you.
Mario Kenizar, City Manager, Mayor, members of the Council.
Wanted to bring a couple of topics to you for your
consideration and direction.
One of those is, as mentioned, it's to give staff direction
on the potential funding for
some small-scale traffic improvements, and I'll cover those
here shortly, and then also
to provide some funding solutions for the Vela Athletic
Complex project.
Also here we have members from the finance department, also
from engineering, public
works, and from the parks department and finance department
here to answer any specific questions
that you might have.
Back in August 26th of 2017 at your council retreat, one of
the things that you all mentioned
that you'd like for staff to consider doing is to look at
some small-scale traffic improvement
projects that, A, would increase the mobility of our
community, that could be done quickly,
designed quickly, and that could get things going.
And so one of the things that we were able to do with PRET
AM and our traffic engineering
department is they identified six projects that they
believe could get done, could get
started pretty quickly, if we could identify the funding,
could make an immediate impact
to the community, and lastly, could be completed, certainly
started, if not completed within
the current fiscal year.
And these are some of the areas and projects and
intersections that were identified as
part of that project.
I have a question.
Well, it's a specific question about one of the specific
projects.
Is this a good time to do it?
You can.
And then Todd is here to be able to answer some of the more
technical questions about
that, but certainly please.
Okay.
A couple questions.
One is on Carroll Boulevard and Sherman Drive.
That caught my eye because of the size.
And I'm going to look at your 77 Dallas Drive.
Northbound left turn, I'm assuming that should be Lane.
Yes.
And improve the turning radius on the southeast corner.
So I'm at the corner of Carroll and Sherman.
It's right there where the fairgrounds are.
You got two, if you're coming, if you're heading north on
Carroll, you got two lanes that turn
right onto Sherman.
And then I think you can go straight.
Help me understand what this is.
Northbound left turn lane from where?
Sherman?
You're coming from Carroll?
Yeah.
Is there?
Yeah, you have to go to the microphone.
Good afternoon.
I'm Preetam.
Yes.
Add a northbound left turn lane.
That's the first component.
So we're adding a northbound left turn lane that gets into
back of Kroger.
There's no left turn lane that gets you into back of Kroger
.
So that's before the light?
That's at the light.
Okay.
All right.
So that's the first component is adding more radius for the
right turn.
Okay.
So when you say turn left, because there's the behind the
stores there, behind the retail
center, there's obviously parking, I mean, access, ingress,
ingress, as far as the concrete
behind the building.
And then there's the fairground has a sort of an entrance.
They may be common.
You're saying that's where you want it?
The left hand turn lane?
Yes.
Well, what that does is helps take the left turning people
out of the equation.
There's two lanes that go, there's one lane that goes
straight and it's a shared lane.
So it will help remove the left turners away from the,
through traffic.
Okay.
Is that, and the only reason I ask is it seems like that's
really only an issue during events
at the fairgrounds or the fair itself.
I mean, because other than that, it's just accessing the
rear part of Kroger, which people
can get to, I think, from the side of the store and the
left turn.
So it helps improve the signal timing.
That way we can eliminate the signal time that's allocated
to the left because what's
happening is more timing is getting allocated for that
through movement.
Whereas higher volume is going, doing from Carroll to
Sherman.
We need that left turners from Sherman to Carroll going
south or even northbound making
the right turn.
So green is not, the green time is not getting properly
allocated and adding that turn lane
will help us design it that it's distributed properly and
it gives more time for the turners.
For the right turn, for the left turners from Sherman onto.
Onto the, onto Carroll.
Correct.
I know it.
Okay.
We're going to add a left hand turn lane, not because it's
needed, but because somehow
it will help.
Enhance capacity.
Exactly.
Well, it's not needed to get people from Carroll turning
left into the fairgrounds.
It's more to help the timing of a light coming from Sherman
turning left onto Carroll.
So you can't adjust the timing.
Because it's a shared movement, the way the green time is
split, it's given more to accommodate
all the through and the left turners at the same time going
northbound.
And that's a very low movement going northbound on Carroll
where Carroll kind of dead ends
all the way up there.
So that timing can be allocated more to Sherman.
So why couldn't you, why couldn't you split off the right
turn?
Because what I'm hearing you say is when the light turns
green, there's no designation
of your turning left or your turning right.
It just turns green.
Is that my understanding?
Correct.
And what I'm hearing you say is the green, there's not very
many people going straight.
Most of them are turning right anyway.
Correct.
So you can turn right on red.
Am I, is that correct?
I mean, from Carroll onto Sherman, you can turn right.
I guess I'm not understanding.
For $425,000, I'm struggling with if we were to just make
the light shorter, the northbound
going straight to full green, is the concern is you're
turning right?
You won't have the people turning right as quickly?
I think the concern here is not enough capacity to move
people out of the way that the movement,
the primary movement or the primary traffic movement is
weird.
It's more of Sherman to Carroll and back and forth.
And there are some intermittent traffic vehicles that are
waiting to go other movements.
And if you get them out of the way, it will help address
the issue.
And I get that.
But when you say help get them out of the way, when you've
got people heading north
on Carroll, which as you said is very intermittent because
there's not a, that's very sporadic.
It's not near as much traffic.
So obviously I'm not a traffic engineer, but this, what I'm
hearing on its face, I'm having
a hard time making sense of it at this level of financing.
So let's just say you said we're going to reduce the signal
light green timing from
Sherman and Carroll heading north.
Because the people who are turning right, they don't have
to have a green.
So it's just the people going straight or quote unquote
turning left into the, which
that could be an issue maybe at certain times of the year
with events.
But on average, what I'm hearing you say is that's not the
issue.
We're trying to figure out how do we get more people from
Sherman turning left on the Carroll.
Is that, am I, is that correct?
So how does, how does reducing the light time for the north
bound people for on Carroll and
increasing the time for the left turn on from Sherman to
Carroll, if you just change that
timing somewhat, whatever is appropriate, how does that not
help that?
Why do we need to spend $425,000 to do it?
And there's probably a good reason, but, and this may be
too technical, but that's, I mean,
I'm having, I need some help here.
Yeah.
The way that intersection is set up, it is really close to
the driveway, the other driveway
on Carroll.
Going into Kroger.
Yes.
So this is the driveway I'm talking about.
So there's one driveway here.
A lot of people make this left.
This through movement, I can't zoom in.
So this through movement is shared.
It's currently shared.
So through left is shared and this backs up up to this
driveway.
So if we get the left turners that are once in a while
showing up and have a short left
turn in here, the through movement will be cleared off.
The people trying to get up to the Kroger driveway can go
in.
So you're saying it's stacking up back because one person
may be turning left and they can't
get through.
They can't get to university and that creates an issue for
people making a left from university
going north to turn into Carroll because that thing is
stacked up up to university.
Show me what they're turning left into.
It's a driveway.
That's the driveway.
And this signal sometimes becomes confusing because of
safety concerns.
It turns green and if this person is making a left, he's
not moving, he gets honked at.
And he can't move because it's a yield green which they
have to yield to this through movement.
So it is connected.
It will function better.
We've run the models and we've looked at the actual
functionality of the intersection and
just creating this little left turn pocket will really help
take out one or two cars
that are really lined up here.
So you're telling me that you go in, you cut the median out
, you put in the left turn lane.
I guess you change the signal light, I guess.
Yes, you'll have a protected left.
That is $425,000?
No, I think the chunk of the cost is this corner.
Widening this corner and moving this pole is the big cost
because this corner is not
-- currently, if you see there are a lot of cars that can't
really turn this radius, the
two lanes that are receiving and in order to make this ADA
compliant, this corner is
the chunk of the cost.
Didn't we just change -- didn't we just do that ADA
compliant?
I mean, it looks like those are brand new kind of --
These are at least one or two generations old because these
are completely detectable
warnings.
These are older designs.
The newer one has two feet.
So when you say there's not enough radius, I mean, I drive
that all the time.
Okay, yeah.
Well, I'm okay with -- I understand the left-hand turn lane
now.
I do.
But if it's $200,000 or $300,000 to take that little chunk
of land, anyway, that's --
Moving this pole is a big chunk of money.
That's what it is.
Well, that's my point.
Yes, anyway.
Okay.
Yes.
So I'm going to kind of be the opposite on you.
I think that that --
That doesn't surprise me.
Removing that section there is really important because
when I first got on council, I had
a lot of people email me about that and I actually have had
an accident there because
when you turn, both lanes turn at the same time and there's
not enough space for both
cars to get there.
So you're saying the lanes merge?
You side swap.
No, they don't merge, but you have two vehicles turning at
the same time into those -- into
the separate lanes and you're really close.
You can kind of accidentally merge into somebody's lane
there.
Okay.
All right.
I mean, it's -- I would completely be okay with just doing
that part and not doing the
other part.
This is the most expensive one.
But I'm sure it all -- well, yeah, but I think it's the
most necessary.
And that's fine.
I mean, if that's the case, my thought is, well, then good
heavens when we designed this
to begin with, why in the world did we -- I mean, if it was
a problem then, why did we
even -- that's done and gone.
Councilmember Ryan.
Yeah.
I think a lot of my comments have already been handled, but
I don't understand why on
the stoplight, this stoplight right here, we can't add an
arrow and do as we do here
on Bell Avenue that you have one direction at a time moving
to get that left-hand turn
lane rather than the expense of adding another lane in
there.
Yeah.
We looked at that alternative, but as I mentioned, the
primary move is this left turn from Sherman.
So that gets blocked when this green arrow gets going.
If everything is green here, that means only this direction
is going, which is what happens
on Bell.
Well, in my experience in that area has been that more of
the backup hits on Elm and Locust
than what hits on that corner.
The Elm and Locust lights just up the road there tend to
regulate how many cars can get
down to that corner.
Okay.
And that's fair enough.
I mean, if that's it and your experience has been that it's
hard to do that, it just -- it
looks like we put in some new ADA there.
I mean, I don't know how old that is, but we've spent some
money and we're going to
go rip it up.
So, okay.
I do have another question on one of the other projects.
Okay.
I'm sorry, y'all, but if we're going to spend this money, I
'd like to know what we're spending
it on.
Okay.
US 77 Dallas Drive and Teasley Lane.
Add turn lanes and channel -- help me understand what that
means.
That means -- I think picture speaks better than words.
Give me a quick second.
Sure.
Okay.
And this is one of the most congested locations in the city
.
That they're fixing to shut down, right?
That's correct.
Okay.
I just want to make sure I understood that.
So especially this southbound -- I'm sorry, this northbound
left turn lane that wants to
travel from Dallas Drive to Teasley.
This left turn lane we're talking about.
Okay.
And this typically backs out no matter what time of the day
.
It typically backs out under the through lanes.
And if you look at it closely, go back a little bit, there
's a drainage inlet here.
So this is a major drainage channel in the middle of the
street.
And in order to extend these curbs back all the way and get
the median -- get two left
turn lanes within this area, we can actually shift the
median here, redesign the poles
and move the poles out.
And then have two left turn lanes here.
And channelize this all the way back.
All right.
That's majority of the project.
There are some other changes.
These two left turn lanes could be moved back.
It can be widened on this side.
We have some right of way.
So these two substandard left turns will be back to normal
standard.
These are really tight left turn lanes.
I'm okay with that.
So to tag onto this, if you'll pull the map up at the
location of Woodrow Lane and Shady
Oaks Drive.
So we're going to need to do a trade out here somewhere.
Because that is horrible.
When you're talking about Carroll Boulevard and left turn
lanes and through traffic, you've
got to get a right turn lane.
And I was there the other day looking at it and I thought
this would be a bear.
You've got to probably get right of way.
You've got to move a pole.
This one?
Yes.
And to turn, yeah.
When you go to turn right onto Shady, onto Woodrow Lane,
that backs up all the way back
to the railroad track.
I think the right turn lane is under construction.
We designed it.
And if I'm not mistaken, they've already started working on
it.
No, there's nothing.
No.
No.
Maybe some utilities removed.
But it should be under construction.
I think so.
You're saying that right?
The streets department is, we have a design and they're.
Okay.
It's in the works.
It's in the works.
Could somebody verify?
I mean, just send me something after this.
Yes, absolutely.
We'll send you a report.
Because if we're going to put more traffic on that road, I
mean, it's going to be a bear
to, I mean, the other day, literally, I was past the
railroad tracks up by, close to where
the circle, the traffic circle is.
And it was simply people wanting to either go straight, but
everybody's wanting to turn
right, except for one person, like you said, over on
Carroll is wanting to go straight
and they have to wait for the lights.
Okay.
So there is a plan.
There is a plan.
We have a design that the left, the right turn lane starts
about here and then it's
flares out.
And that is estimated to be.
Completed we can give you a schedule.
I'd appreciate that.
All right.
Okay.
All right.
Council member.
No, that was just my same point that if you're going to put
more traffic there.
And then that adds to the problem.
There's a red light camera there, which then has everyone
terrified that you don't, you
know.
Yeah.
You don't turn.
Right.
Right.
So, and if you don't know the rules.
And I think that's kind of to, I think that's the trick,
right?
Even when you're talking about that, that corner and the
other intersection, it's drivers
today aren't drivers.
The younger kids, I don't, I just don't think it's the same
experience.
That's why you see a lot of less people turning into their
own lane, less experience.
And that's why I think that that other intersection on
Carol is a problem.
People are terrified to turn into the near lane.
Yeah.
And so just habits are you, you swing out, you know, and so
I think that that's a part
of the issue as well.
But yeah, this intersection was going to be mine.
Okay.
All right.
So then what I'm hearing you say is that since this one is
already in design.
In the works.
And the other one is more you're getting direction today.
This one should be finished before the other one is correct
.
Okay.
Yes.
Council member speaking about this one particularly, do we
have any plans to update or restructure
teesley repave?
I mean, I'm sorry, Dallas drive.
Repainting Dallas drive.
That's a very good question.
I'm not.
Yeah.
Well, I mean, if we're doing like $725,000 worth of work, I
just curious if that if we're
going to have to go back in and I don't have a good answer
on that one.
I know we don't have anything with it being a textile
facility.
Okay.
And then being in the area working on that ramp.
I'm not sure how far they're coming up off I 35 years they
're redoing this section.
We can find that out for you and bring that back.
Okay.
Yeah, what will make the request?
It's a good good point.
So we'll make the request.
Hey, I'm good.
We're getting a right hand turn lane at Shady Oaks and Wood
row.
That's that's just that's I mean, that's one of the major
thoroughfares going east
west and it just is it's a huge bottleneck.
It is and it's something that we as a staff we've honestly
been looking at that entire
connection.
Yes, as we're emptying more traffic that direction.
I know I live on the south side.
So I travel that way frequently.
It's one of those things where we're looking at what is the
ultimate shape and configuration
of Shady Oaks look like.
Right, because we've we've done from Woodrow to Luke 288.
Right brand spanking new for years old and then we in the
bond package Morris from Luke
288 to Mayhill was going to get reconfigured to four lanes
I believe.
But all the traffic usually traveling there is coming down
Shady Oaks which is a single
lane no left turn.
No there is a left turn lane in the middle and okay.
You got some tight turns and you got a railroad crossing.
It's not a real safe configuration.
Councilmember and a roundabout.
Yeah, yeah.
We love the roundabouts.
Okay and if you could put the project list back up one more
time I just want to see if
the council has any more questions or if I had any more
questions.
Keith you got a question.
Okay.
Yeah.
Go ahead.
So at University on Old North Road the green light had been
extended and that's been you
can definitely tell there's not a lot of people trying to
jump out in front of traffic but
also University and Nottingham.
Can you tell me why this one was up there and that one wasn
't?
There's a couple of reasons I can go back to the map.
And also expand on the price a little bit.
So there are two things.
I think Old North is right here and Nottingham is here.
Nottingham serves this particular area of the suburb.
This area is served by Old North.
One of the things that is it is a higher volume
intersection just because Mingo kind of turns
in and becomes comes on the south side.
The other thing is there's a lot of new development on this
corner that will be using Old North
and that's anticipated and it's under construction.
So all those factors playing to making this one step ahead.
Even cost wise there's more right of way take and more
requirements and at Old Nottingham
because it's already developed all the corners are
developed.
There were houses too close especially at Nottingham you
have driveways right in front
of the intersection if you look at the you have houses
right next to the intersection.
That becomes a tough it the turnaround time for that
project and the cost is higher.
Less traffic is another criteria that we looked at not
enough traffic but if you compare that
with Old North it is higher traffic only if I can find it
but it's higher traffic as well
as open land that's available on either corner that we have
better right of way require I
mean we can get right of way it's a bigger intersection
that we can work on.
And so is it the 500,000 is that a new light I mean because
I'm wondering what the price
it includes everything it includes upgrading all the lights
it also includes taking right
of way for the turn lanes constructing the turn lanes
everything and design.
So on either side you'll have turn lanes at least 150 foot
turn lanes on both directions
north south.
Oh okay so it's a larger it's not just putting an arrow in
a light to turn okay all right
thank you.
I would expand on this that Nottingham was the next one up
we've got we had actually
had about a dozen traffic improvements that we identified
the main criteria that were
what we're ready right now what can we go in and do this
fiscal year and so we've got
another six that we'll probably be bringing back to you
during next budget year same type
of thing immediate impacts you know helping helping move
traffic a little bit more but
that was just one that took a little bit more design work
so we've got it's in the queue
for the next time we come back to you.
Okay any other questions on specific projects.
All right thank you thank you great answers thank you
appreciate the information wonderful.
So these are the lists that we we together with pre tam and
Todd's work or Todd's help
so equal two point one two million dollars and so just
wanted to provide that information
to you and so and then the next one is here recently the
staff presented some information
about the Vela project and and not to go through all the
all the bullet points there but as
you can see they look the Vela project will serve a number
of different sports activities
there on that side the engineers estimate is projected to
be a little over five point
five million dollars based on the information that staff
has at this point the there's a
shortfall for Vela at two million three hundred and thirty
thousand dollars and so one of
the things that we wanted to do is show you some how we how
we would recommend you can
shore up the funding for that project to let you know too
that we're going to be bidding
this project later this month with the bid opening later in
the at the end of January
2018 so obviously we're still at the engineers estimate so
we won't know what those prices
are until the bids come in they're evaluated.
So what I did is I went ahead and combined the fiscal
information for the traffic improvement
projects based on the information provided by the finance
department they've identified
about three million dollars of additional funds that
revenues exceeded expenditures
for fiscal year 2016-17 and so one of the things that's
being recommended is to allocate
majority of those those those additional funds towards
those small traffic improvements that
were just presented and then for the Vela sports complex
projects one of the things
we're looking at doing is reallocating a placeholder that
was set for property acquisition
based on discussions from staff that property again the
property has not yet necessarily
been identified has not been purchased so we believe that
this might be a good use of
funds to reallocate those funds from that to to the sports
complex also reallocating
some monies for a master plan and design of an amount of
seven hundred fifty thousand
dollars to Vela and then a difference of five hundred and
seventy five thousand towards
Vela coming from the fiscal year 2016-17 budget revenues
and funds that were identified so
in total for for the Vela that comes up with a shortfall of
two million three hundred and
thirty thousand all said if you were to allocate the two
million one hundred and twenty thousand
for small traffic improvements from the fiscal year 2016-17
budget and in the five seven
five hundred seventy five thousand towards Vela it would
still leave approximately three
hundred and five thousand dollars that we could increase
the fund balance in the general
fund.
So what what does the what is the shortfall for Vela after
all these applications of funds
should be well based on what we know today should be zero
but we won't know until the
bids come in and ladies anywhere and they're evaluated.
All right so then you take the the budget of five seventy
five which is a and and part
of this three million yes sir then you've added the
Southwest Park the property acquisition
so if we do all that it all works out the way it's supposed
to and if the budget if
the bids come in like we anticipate then the Vela project
is funded fully that's my understanding
based upon and we're still having a 305 going into the
general fund so that if the bids
come in and they're a little high or then we have at least
still some opportunity to
make that up correct.
I believe also too is part of the bid the construction
documents for Vela there's a
number of alternates that the that the contractor can bid
so it gives the staff options of what
to incorporate for the final bid.
Well I really want to encourage that I'm assuming you mean
alternates is if they come in high
that we sort of scale it back initially and do something
that's a little unless it just
blows this whole thing up.
We just need to we just need to build it.
I mean obviously we won't know if the bids come in two
million dollars more which if
that happens we're all going to be looking at each other
like what just happened but
I just again I'll just reiterate I really encourage us to
to move forward on that.
Yes Councilmember Riggs.
I thought you had a question.
I did but I answered it myself.
Oh okay.
And I would just add just we know this is weighing on the
council right now we're going
out to market to get bids make sure we've got a very
certain funding gap that we can
identify for you.
One of the other things that we're doing just to put try to
put you these a little
bit because I know we're dealing still with the fire
station three project is we have
been working with our finance director to identify
opportunities for that we have we
currently are holding CO's that could be moved if necessary
to help make sure that
we've got these projects fully funded but our main point
today was to talk to you about
some additional cash that we can we can bring forward to
make some immediate impacts but
we're I think we're constantly refining and refining and
handling the finance plan
so our goal is to make sure that they like it's built the
way it was intended fire station
three is taken care of and that we get these traffic
improvements out of the way still
working within our current fund balance policy so I think
it's a good message and I hope
the council sees as such.
When you say working within the current fund balance policy
what are you talking about?
Well we're actually we adopted a budget that had a fund
balance assumption I believe about
twenty three point seven or roughly twenty four somewhere
in that neighborhood and we're
actually adding to it at this point but we're making sure
we're trying to manage this a
little bit more proactively so you don't feel like you're
you're having to make cuts on
projects that were promised to this community and we're
able to work within our existing
tax levy.
And on any of the funds that are being maybe this is my
word so if it's incorrect let me
know reallocated from maybe some old projects to the Vela
complex if they were if it was
bond funded money are we we're going back to the is it bond
advisory committee?
Bond oversight committee.
Bond oversight to double check with them and get their
approval or just feedback and those
kind of things.
That would be the process we'd go back to the bond
oversight committee let them know
this is our recommendation make sure they incur with that
but again both of these were
ones that we felt like made sense the property acquisition
was an undetermined piece of property
at some point in the future so we really didn't have
something identified for that it was
really a placeholder and then the parks master plan money
is just reducing the scope of that
master plan to have more of a conceptual master plan rather
than a very detailed engineering
type drawing so still moving forward the master plan in the
southwest park it just wouldn't
be as detailed.
Right okay.
Yes Council Member Hudspeth.
Just thank you just as an aside we talked about it last
week as well I just again want
to stress that those two pieces of property that we're
hanging on to I look forward to
those reports because I think at some point we need to
before we I get it these projects
I'm not saying these projects specific but in general
before we start taking from projects
and we're just sitting on something that potentially has
value for again just like the land acquisition
for some undetermined purpose I think at some point you
need to look inward and reconcile
what we're going to do there before we start you know going
too far down taking from projects
that have been determined at least understand what we have
and understand the value to the
whatever potential buyer.
Okay great.
So last slide is if you are in agreement with this we'd
like to move forward with the recommendation
of allocating those funds for those two projects if you
concur then we'll work with our finance
team to bring forward a budget amendment for the current
budget year at your next meeting
which would be January 9th.
Sure.
What are what's the estimated completion of the traffic
projects as far as just overall
are we doing those serially are we doing them one at a time
or they going to are we talking
about a year or two.
Well the intent is that we would certainly get started with
construction this fiscal
year and our intent is to get them done in this fiscal year
and nearly completed this
fiscal year.
That's the intent the criteria of getting those those
recommended on that list.
Okay great.
All right any other questions comments.
Yes briefly as we want to make my comment is I would be in
support of that but of moving
forward with both but I just would stress the messaging
especially that Dallas Drive
component some of those things you know it's just going to
be super important that we we
go above and beyond messaging just because of the how those
I mean obviously they're
important we're working on them but just to get that
information out best we can.
Yeah it's a good comment.
Thank you.
All right thank you.
Appreciate it.
All right we'll move on to agenda item 3D receive report
hold discussion give staff
direction regarding city staff and organizational changes.
Okay.
Okay.
Oh is it.
Okay.
All right.
Okay.
Just have a couple of comments and presentations.
I don't know if I like being up here.
Wow.
Is this what I look at this what it looks like from up here
.
No we've got a couple people have announced the decision
they made to to move on from
the city and so I wanted to say a few remarks about them
and give them a plaque because
I think they've been so instrumental to our organization
and have really just enjoyed
working with them so the first one will be Galen if you'll
come up Galen Gillum he's
like oh no.
Can you speak into the mic please.
Thank you Mayor.
Appreciate that Mayor Pro Tem thank you.
Just to sort of share with you some of the accomplishments
that Galen has had over the
years here with with us of course he began his tenure with
us with DME 2011 gosh time
flies doesn't it and he's worked on a number of projects as
DME expanded its service delivery
to Denton residents and businesses and I will tell you I
think probably for me personally
and I and of course you know DME is doing their thing over
there and they come over
here present projects but I think one of the most important
things that that he's done
is is recently as he's helped us with our transition as
starting in the role of director
of capital projects in May of 2017 because as we've seen we
've been a little behind
and trying to get caught up and add some organization and
some structure to these these projects
that we've been doing and he's certainly done that he's
provided leadership and stability
during a transitional time in the department and I think
that goes without saying I think
you've been a stabilizing force I think your leadership and
just your demeanor and how
you deal with people and and how you approach problems and
projects has been exactly what
we needed in that regard so thank you so much for that.
There's increased okay here's increased responsiveness to
citizen requests now we just stopped right
there that's enough because of you know some of our efforts
have probably been less than
stellar in the past but we certainly strive to do the best
we can and I think you've
helped us do that so thank you so much for that.
Establish a positive rapport with cog and text dot staff
that's not easy I mean those
are large bureaucracies and they have people coming at them
from all over the place and
and I think if you just look at some of the projects that
we've got going and some of
the projects that we've had assistance with here recently
that have really helped us the
Mayhill Road expansion being one of them to be able to get
some new alignment to get some
funding potentially on that Mockingbird Lane and several
other street reconstruction projects
Galen's been instrumental in moving the CIP department
forward by recruiting and mentoring
a very talented staff so they've got some big shoes to fill
and so I look forward to
seeing the work of your mentorship and your leadership and
training them to be the same
and responsiveness and problem solving.
Your positive approach to building your staff is confidence
and competence and increasing
service delivery to make Denton a better place will be
missed and I wish you the best of
luck wherever you land and we have a little plaque for you
I want to make sure I don't
get them mixed up here and we hate to see you go but I
understand that life moves forward
and people make decisions to do some different things and
we sure appreciate your contribution.
Staff says the City of Denton expresses its gratitude to
you Galen Gillum for dedication
and valuable service to the City of Denton Texas serving
from March 2011 to December
2017.
Your contributions have been greatly appreciated.
Todd Hyman thank you so much I appreciate it.
You were fixing to run out of here.
Thank you so much.
Okay one more Mr. Chuck Springer if you'll please come
forward and I was trying to think
I won't go into the impression Chuck because there's a
radio show I listen to all the
time that talks about Chuck and they're imitating the old
basketball coach from Baylor.
The basketball coach from Baylor that had just a few
problems what was his name?
Bliss.
Bliss yes yes so anyway let me Chuck but that's okay we're
not talking about you being
never mind Chuck come on I'm sorry well I don't know yeah I
don't know if I like this
up here.
Chuck has served as director of finance from February 2013
to January 2018.
Having some very very difficult times also coming out of
the recession as Brian was moved
from director of finance you came in and it has been so
great working with you.
Todd calls you what is the budget sage the wise old sage
and I totally agree.
Chuck has over 30 years of experience in local government
finance 30 years of experience
and has been instrumental in successfully leading several
projects for the city of Denton including
the following redesigning the budget process and I'm sure
that wasn't easy but this last
year the last couple years have been wonderful so thank you
so much for that.
I think it's been exactly what this council has wanted and
what the community has wanted
as well.
Led an effort to create a lean government initiative in the
organization which we've
seen the byproducts of that and the different organizations
that have followed that procedure
and streamlined and brought some projects forward and some
changes to the processes
that have really helped the city the bureaucracy the
administration but also more importantly
our community.
Refunded all of the city's outstanding utility system
revenue bonds which yielded a savings
of approximately six million dollars.
Well that's not pocket change that's we don't have that I
mean that's that's a lot of money
that has gone to helping conserve money save money for our
ratepayers and we can either
give that back to them or do other projects that would have
cost that much money to begin
with.
Implemented a Kronos timekeeping solution now I have no
idea what that is so can you
tell me what that means?
Clocking in and out.
Okay all right well wow all right that's that's great I
should have known that I guess sorry
about that.
Clocking in and out with your new salary ship?
No no no if that nevermind.
Completed the preparation of the comprehensive annual
financial report the CAFR for four
consecutive consecutive years with no audit findings.
That's impressive I mean that we have that kind of
reporting that can be looked at from
an internal audit company and have no findings that that
really speaks to the integrity of
the process and to your work and to the integrity of the
numbers so thank you so much.
Completed bond funds to simplify project oversight.
Chuck has also built a very strong team in the finance
department and provided consistent
leadership on a number of key issues during his tenure.
As Chuck you will greatly be missed we wish you well in
your new role as the director
of administration of the town of Prosper.
So there our loss is their gain but you're just going to be
right down the road so when
Tony gets you know the question or I have a question I'm
just going to call you up and
you'll hear that I need to talk to you Chuck but all
kidding aside thank you so much for
your service to our community and to this city and really
bringing your honesty and
your integrity and your commitment to the numbers and to
the accuracy of those numbers
to our community and with that we also have a plaque for
you.
The city of Denton expresses its gratitude to you Chuck Spr
inger for dedication and invaluable
service to the city of Denton Texas serving from February
2013 to January 2018.
Your contributions have been greatly appreciated and they
will greatly be missed so thank you
so much for your service.
Thank you Chuck.
You bet.
You bet.
My pleasure.
Thank y'all that's all I have.
Okay it's always good to really honor and show our
appreciation for our staff members
as they move forward in their life and what they brought to
our community so thank you
guys very much you will greatly be missed and surely
appreciate the contribution that
you've provided to us in your years of service.
Okay I will now convene the closed session at 327.
We will consider the following items and let's all watch
for the turning of the light switch.
Consultation with attorneys under Texas Government Code
section 551.071.
Deliberations regarding real property under Texas
Government Code section 551.072.
Deliberations regarding personnel matters under Texas
Government Code section 551.074.
[BLANK_AUDIO]
[BLANK_AUDIO]
All right, welcome everyone.
We are now, we have concluded our work session and our
closed session items.
And we will now convene in a special call meeting of the
Dent City Council on
December the 12th, 2017, this Tuesday at about 5.58.
We will move into our agenda now, which is the consent
agenda.
Just anybody wanna raise their hand?
Yes, Council Member Ryan.
I move approval of the consent agenda with the exceptions
of items B, G, and H.
>> Okay, we have a motion.
We have a second for approval of consent agenda items
except for B, G, and H.
We'll be taking an individual consideration.
And on that note, I wanted to remind everyone that under
agenda items two,
which are items for individual consideration, agenda item B
has been
pulled and will be considered in January.
Is that right?
Yep.
Okay, we have a motion and a second for the consent agenda
item.
Save those items pulled.
Everybody, we will now move on to the agenda items that
were pulled.
Agenda item B is an item for individual consideration.
Consider adoption of an ordinance accepting competitive b
ids and awarding
contract for the supply of parkland maintenance products.
Believe we have a presentation on that or no?
Or?
We pulled it all together.
>> Pull that for a work session?
>> Oh.
>> Or was the?
>> No, no, no.
The spraying policy, I asked for that, a presentation on
that for-
>> For today?
>> Yes.
>> Yes, yes.
Yeah, agenda item B on items for individual consideration
were a work session.
For-
>> Well, we may have misunderstood.
I thought that you wanted a future discussion of item two,
excuse me,
one B on the consent agenda.
So we'll need to bring that back.
>> Well, I would like that as well.
I mean, a bigger discussion as well.
>> So we won't be voting on that today.
Is that correct?
>> Sorry for the confusion.
>> Yeah, we thought it was-
>> Is that the rest of the council's understanding as well?
>> I thought it was moved to January.
>> That's what we understood.
>> Okay, okay.
Yeah, I think it got confused with the individual item two
B and one B.
That's fine.
That's good.
>> Sorry about that.
>> No, we're good.
One less item for individual consideration.
Agenda item G is considered option of ordinance authorizing
city manager
execute an analogical agreement with the University of
North Texas.
And Councilman Ryan, you pulled this, I believe.
And did you want a presentation on this?
>> Yes, kind of a combination of G and H.
They're interconnected.
One is the agreement with UNT and
the second one is actually authorizing the funds to be exp
ended.
>> I'll tell you what I'd like to do.
We'll go ahead and have the sort of staff presentation to
cover them both.
We'll vote on them individually, so I'm gonna go ahead and
call H so we can.
Agenda item H is considered option of ordinance authorizing
city manager
execute professional services agreement for traffic
engineering planning services
related to traffic study to be performed in an area within
and
adjacent to the University of North Texas.
>> Good evening, my name is Preetam Deshmukh.
Thank you, Mr. Mayor, council members.
I'm here to talk about both agenda items G as well as H as
they're both interrelated.
The first one is the interlocal agreement with the UNT
between the city and the UNT.
And the second is the professional services agreement award
for
a consultant to perform a traffic study.
A little bit of background where this all began.
I believe there was some initial confusion as to what kind
of elements or
what exactly is covered under the small area plan which the
city is currently
under contract.
It was a city initiated project.
We looked at an area around UNT and
we're looking at the big planning level picture there.
And we hired a consultant, we authorized professional
services through a city
council meeting on August 1st and the total contract amount
for
that particular project is 239, 252.
That scope, a little bit of clarification here,
that scope did not include detailed traffic impact analysis
.
It did include transportation level assessment and I'll get
,
next slide I'll get in details.
So this is a cost breakdown of what was brought forward in
front of the council
for this particular consultant and the two items, item D
and C here.
The total cost is about $20,000, a little over 20.
And it only includes a planning level assessment of these
particular items.
They're looking at streets, sidewalks, transit, bicycles,
and parking.
This is not a detailed traffic impact analysis that will
tell you what kind of
impacts are associated with this big picture planning
exercise which is
the small area plan.
And so in the meantime,
what we were doing is we were having several meetings with
UNT.
It was kind of a parallel process that was happening.
And UNT adopted their master plan in 2015.
As part of their master plan, they came with an impact
analysis,
traffic analysis.
And what they came up with were pretty sort of some kind of
numbers that were associated with a subjective analysis.
It was not consistent with what we typically perform for
traffic impact.
And based on that particular analysis,
UNT was proposing closure of three streets, which is High
land Street,
which is between Avenue C and all the way to Welch.
There's Maple, which is another one-way street just south
of Highland Street,
same segment between Avenue C and Welch, and then Avenue C
throughout the campus.
It starts all the way south of, south at Eagle and goes to
Hickory Street.
If you look at Avenue C, it is quite a big thoroughfare
that connects all the way
north, it converts into Jago Avenue, it kind of jogs a
little bit.
And a closure, I'm sorry, closure of this street would
create significant traffic
on North Texas as well as Welch Street.
And these are some things that we had not looked at and
we were not seeing any impact analysis in UNT
Transportation Master Plan.
So those are the things that we really wanted to look at.
So what we needed, irrespective of the small area plan,
was a traffic study that looked at these particular clos
ures and
its near term as well as long term impact.
And we were ready, UNT was ready to partner with us.
They actually agreed to share cost to do a traffic impact
analysis.
After we went through the process of small area plan, we
selected a consultant.
One of the sub-consultants for that particular bigger
picture plan
was a traffic consultant was Walter P Moore.
And we thought it would be a good idea to tie the two
things and
have the same consultant work on both the small area plan
as well as this traffic
impact study, that way we get consistent numbers.
And this exercise is more of a partnership between UNT and
the city trying to come to the same ground as far as
understanding the impact.
And agreeing on what the mitigations would be, near term
and long term.
So that's why we felt that this was necessary.
It's not so much so that UNT was having us do it or we're
trying to have UNT do it.
And we agreed on a cost share which came up to a little
over $112,000.
It is a separate contract with Walter P Moore,
who's a sub-consultant on the small area plan.
So if you look at the big picture, these are some numbers
that will show you
what the cost sharing and costs are.
If we would not partner with UNT,
we would end up with almost $464,000.
Because a study was necessary for those street closures to
happen.
And UNT believed that they already had a traffic study and
we did not believe that.
So ultimately we ended up with this little over $350,000.
And I think that is pretty much it, if you have any
questions.
>> Go back to that last slide.
So we've got the traffic study that we're splitting with UN
T of $224,700.
So we are having to do another traffic study for the small
area plan?
>> No, that's not part of the small area plan.
What small area plan does is a planning level assessment.
They will tell you that if- >> No, no, that's fine.
I'm just looking here at this 463,952 total cost between
the small area plan and
the unit, but so this 239, what is that?
That's the small area plan itself.
>> Correct.
>> Okay, nevermind, gotcha.
I just saw that 351, but that's for both the small area
plan and
the traffic study.
>> Correct. >> Got you, all right.
Okay, yes?
>> Well, one of the email responses I got talked about the
fact that some traffic
counts have already been done prior to Thanksgiving.
Is that our counts?
>> It was a joint effort.
UNT did want to, and we agreed that we did want to look at
traffic conditions
when they were typical non-holiday seasonal traffic.
And given the timeline that UNT is running, they wanted to
push at least
getting the count portion completed so that those counts
could be used towards
the study.
>> Okay, and what was the condition of Hickory,
which has been open close, open close, open close?
>> Majority, we did check that, and majority of the segment
was open for
the week that these counts were collected.
What we are trying to do is we will go back, we have a
little bit of reserve,
we will go back after Hickory Street project is completed,
which I believe doesn't happen until end of next year or
even into 2019,
which is really late for UNT or even us to wrap this study
up in conjunction with
the small area plan.
So we will come back and adjust some of the counts and redo
the counts on Hickory,
because that's the only segment that might have some disc
repancies with the current
count.
But other than that, there are two locations that were
closed and
were not counted as part of the counts.
>> But if Hickory is closed, then you're gonna have a
higher count on the other
streets right now, because people are gonna find other
routes.
>> Yes and no, it wasn't completely closed.
The Hickory Street when we counted was open that particular
part that's completely
shut down at Bonnie Bray was open.
It was instead of two lanes, it was open one lane.
The week of.
>> So your concern Councilmember Ryan is that given sort of
our city projects in
that area that the, I don't wanna say accuracy, because it
's gonna be accurate,
but it representing normal traffic patterns may not
necessarily be reflected.
>> Right. >> In the traffic study with what's going
on around the campus at least in this particular area, is
that the concern?
>> That is true, cuz right now in that area, I mean,
I don't know if it's still that way today, but last week
Oak Street was a two way
street where it hasn't been before because they were det
ouring Hickory around.
And this is the first that we've actually seen what roads
UNT is looking at
closing down and that creates an issue.
I'd like for this to actually come back as a work session
to us before we
move forward on it simply because Avenue C is the only road
that runs from
University 235 between Bonnie Bray and Carroll Boulevard.
>> Well now when you say, okay, so my understanding right
now it's just
approving the traffic study, this isn't approving any road
closures, is that correct?
>> No. >> Okay, so you wanna come back with
the traffic study for a work session or, yeah, we're not
approving-
>> Well, and I understand we're not approving what UNT's
wanting.
I'm just saying we weren't given enough information on this
upfront.
I just have a very difficult time adding another $110,000,
$112,000 to that small area plan even though it's being
called not part of
that small area plan, it really is, so.
>> So you want a work session to discuss?
>> To, I guess to kinda, I guess we don't necessarily need
the work session.
Now that we've kinda seen what UNT's got proposed, but that
.
I just feel like we're being asked to spend money on
something that we weren't
informed we were going to do in that small area prior to
this.
And if it was any private developer, when it came to a TIA
that we requested,
they would have to pay for it in full.
The city would not have to pick up one half of it.
So it sounds like your objection then is,
it's not so much you oppose to the traffic, the TIA, it's
us paying a part of it.
>> Correct.
>> Okay, all right.
Council Member Briggs.
>> So is the plan for the traffic study to come back to us
separate to
discuss the road closures or will that all come back with a
small area plan?
>> The traffic study is gonna work with the small area plan
.
So since we have the same sub-consultant,
it is going to look at the preferred alternatives in the
small area plan.
And look out at the future build out conditions and see
what kind of impacts
we have because of these street closures and the small area
plan.
What kind of impacts will be there throughout the
circulation network and
plan for those in the future.
So this study was really important for us, not only just
for
the street closures as well as to understand what's
happening in the region.
>> Okay, Mayor Pro Tem and then, yes.
Is UNT authorized to unilaterally close streets?
>> No. >> That's a very good question.
>> No.
>> So walk me through what, I just wanna save you a bunch
of money.
You can't close Avenue C.
That's not a good idea.
So what happens if UNT decides, well, we wanna close Avenue
C?
>> They will require city's authorization to close any
public streets.
But then that becomes an issue and it will.
>> So just walk me through the whole process.
Does it go somewhere?
Is there a hearing?
How does it work?
>> There would be a formal request made of the city to
close the street.
Basically the way this was structured is typically a TIA in
an area like this
would have been included, it was pulled out because UNT did
not agree with the
initial traffic consultant that staff had suggested partner
with the planning firm.
The way this contract is structured is they are in essence
paying for
the traffic study around the university.
We're covering everything else because in my argument to
them was it's
a symbiotic relationship.
If you start closing roads, to Councilmember Ryan's point,
you have an impact on other roads.
They had also done what I think, what I would gently call
more of a windshield type
survey where they were counting pedestrians and not doing
really an impact
analysis to the level that we would require along with the
if you close this street,
this might happen.
So this is really a way to, they are paying for their share
around the university,
within the university, just to get us data that we can talk
to each other.
Otherwise, our concern was we were relying on very
subjective,
emotional gut call type arguments rather than the facts to
present to the council.
We have definitely not given them any encouragement that we
would recommend
closing any street over there.
Some of those streets that you saw have relatively new
infrastructure in them,
which is a major concern of ours.
And in fact, I think Highland was recently repaved.
So there's a lot of meaty issues here, but this is really
an attempt,
we needed to do the traffic information study anyway.
It was really a attempt to find some common ground with
them to discuss
planning in the future as they're looking to try to get to
more of a walkable campus.
And we wanted to make sure that we were equal partners and
had the facts when those conversations come before you.
So it's really a cart before the horse.
In order to have a conversation with them, you need the
data.
And I think to Council Member Ryan's point,
could the traffic study be pushed off a little while?
I suppose it could.
I think that study, until you get the traffic patterns a
little bit more.
But that's a little bit of the history behind how this
happened and
why it happened is we just simply said we couldn't come to
the council unless we
had empirical data to even talk to you about.
>> Yes.
>> So let's say that we do the traffic study and
we're at odds over the impact of closing a street and
UNT still wants to close the street and we don't wanna
close the street.
So what happens? >> It's your call.
It's your street.
>> So it would be a council decision?
>> Yes.
>> You wouldn't go to PNZ or any of those types of places?
>> Traffic safety.
>> Yeah.
>> We would like to at least do traffic safety but-
>> Traffic safety, they handle all your recommended clos
ures and
then it'll come to you with a recommendation.
>> Okay.
Thank you.
>> Yes, Council Member Hussbett.
>> Can someone correct me if I'm wrong?
But first, I'm in favor of moving forward because, as I
understand it,
let me get my streets, Hickory Street, we removed the
meters and we're waiting on the bike lanes for this data.
So, I mean, there's a lot tied into this and it ties into
the decision on
the SUP for the restaurant there on the corner.
I mean, a lot of this data plays into my
calculation on how we proceed in this area.
But most importantly, Hickory is on hold, I think,
waiting on this data to decide the biking path and how they
're going to proceed.
So it has, and I don't think that there's,
I think it gives us a good launching point as far as the
numbers.
I mean, will it be different?
Yes, with Oak being two way versus one way.
I mean, I think there'll be some differences, but
I don't know that it's enough that the data can't be
extrapolated and
reconciled to that, that hey, the traffic's gonna be a
little heavier, but
at least we have a static launching point and I think it'll
move forward that bike path.
And so I would be in favor of moving forward just because
there's other things
tied to it that I don't, and I don't think it does any irre
parable harm to going forward.
I think those numbers can be extrapolated.
>> Okay, all right.
Yes, next member.
>> I am also in favor of this.
I assumed that it was part of the small area plan since we
were looking at parking and
I just assumed that they would take this type of data in
that plan as well to apply
it to their recommendations, so yeah, I'm in favor.
>> Okay.
Yeah, I think I'm good with moving forward, I think, for
some of the similar sentiments that Council Member Hutzpeth
shared.
It's, in some ways, we're getting, I think, probably a
traffic study that is needed
for less cost because we have a sharing of that cost with
UNT based upon their
desire to have these roads closed sometime in the future.
Question for the engineer.
Given Council Member Ryan's concerns about, okay, we're
really not testing and
sort of Council Member Hutzpeth's observation, is there a
way to sort of
look at the data on the ground from the traffic study and
go, okay, yes, this was closed?
Is there a way to, with some kind of accuracy,
modify that to where it might more accurately reflect a,
quote unquote,
normal traffic pattern if these other things weren't in
place?
Is that possible or do you, will you have enough data to
take a stab at that?
>> Yes, we discussed that with the consultant.
We have historical data up and down Hickory, Oak Street,
Bonnie Bray, North Texas.
So we have old counts that we've collected over the years
and
we can track them, compare how these new counts compare and
see if there are any changes, major changes.
And when we get closer to Hickory, there might be a little
bit of changes, but
the rest of the world should function the same.
>> Okay, all right.
Okay, any other comments, questions for staff presentation?
All right, we will consider these items separately.
G and H, what is that, 1G?
So staff, I mean, Chair would entertain, Council Member Br
iggs?
>> I'll move to approve.
>> All right, Council Member Hutzpeth?
>> Second.
>> All right, we have a motion and a second.
All in favor, agenda item, I think is 1G.
Signify by raising your right hand.
All opposed by like sign.
So motion carries four to two.
Agenda item 1H.
Chair would entertain a motion.
>> I'll move approval.
>> We have a motion for approval.
We have a- >> Second.
>> Motion for second.
All in favor signify by raising your right hand for agenda
item 1H.
All opposed by like sign.
Motion carries four to two.
Now we will move on to our items of individual
consideration for
agenda items two, which should be agenda item two A.
Consider adoption of an ordinance authorizing city manager
to execute
professional services agreement for engineering design
services relating to
design, bid phase, and construction services for the PEC
four phases three and four.
I thought I was in a gym class or something.
>> Good evening, Todd Estes, city engineer.
We're bringing to you tonight the continuation of a
contract or
a project that you all had seen and approved a contract
last, I think it was last month.
Where we are looking to extend PEC four, which is a bond
funded project.
It started phases one, phases two, primarily were
downstream or east of.
They were these blue and green lines you see on here.
They were east and west of element locust.
They take into account a large drainage area that has
associated with a flood
plane that runs through downtown and to complete the
process of removing the
downtown area from the floodplain, we need to complete
phases three and four.
So I'll bring up next slide is the actual drainage area map
for downtown.
So you can see over here at Bell Avenue and where the
railroad tracks are,
we have a very large drainage area that runs through
downtown.
I believe Chad, Chad's not paying attention.
>> Todd, you're doing a great job.
>> I believe we had 60, it's around 60 acres that's inund
ated by the floodplain
in this area that continues all the way over to Bernard
Street.
This area is part of this project.
The four phases would actually bring all of this floodplain
out,
bring all these properties out of the floodplain.
So the floodplain would basically go back to looking like
the previous slide where
you do not have a floodplain.
>> Okay.
>> So what we have before you tonight is the actual design
contract for the
construction of what you see in yellow and in red.
That's to pipe everything from an open channel into a box
culvert.
What you also have here is a line in dash purple.
That line right there is an alternative route that takes
into account that you,
if you see this blue line, my mouse keeps going away.
This blue line here is the center line of the existing open
channel.
So it's that concrete line and channel that runs through
downtown.
At some point, these properties still need to be able to
drain.
And the most cost effective means that we're trying to
analyze is,
is this purple line or is this yellow line the best way to
get there?
So we're evaluating both options with this design.
>> So when we go to a box culvert drainage system,
first of all, what does that look like?
Is it underground?
Is there something green?
>> It's underground.
You won't see it.
>> And then what happens to the open drainage system?
>> The open drainage system, we would need to be,
what's left of it would stay in place.
Because most of what you have out there,
we would not anticipate actually changing anything other
than just leaving it alone.
>> Would it just be an overflow or something?
>> No, it still carries stormwater.
The issue that you're always going to have is these homes
over here on the East side of Carroll,
and the businesses on the West, I'm sorry, on the East side
of Carroll,
on this side of the homes on the West side of Carroll,
they still have to be able to drain their property.
And the easiest way to get that water in is not to change
what they currently have.
But what does happen is, is when water is in that channel
today,
there's not enough capacity in that channel.
So what happens is as it rains and we get a worse event,
it just gets much higher than it can actually handle.
These boxes will allow the vast majority of that stormwater
to get out,
but you'd still use the existing channel itself to just
catch the regular runoff from those homes.
>> And in some places, the box culvert would replace the
channel?
>> Yes, in some places it would, specifically as you're
going through this downtown area.
>> And it would be covered with soil?
>> Soil, concrete, whatever is usable.
If it's a parking lot, it would be asphalt.
If it's bare ground, it would be soil with grass over the
top.
>> Okay. And would that, I'm sorry, who would own that
property then if it's covered?
It still belongs to the city, right?
>> It belongs to the city unless it was conveyed to a
private property owner.
It's going to be an easement to this point.
>> Oh, okay. All right.
>> Could you put the floodplain map?
I'm trying to, I'll leave this picture.
I'm trying to orient myself here.
Now, the courthouse is not on this frame, is that right?
>> No, it's just to the north.
>> It's up there, right?
>> Yeah, Elm and Locust are these two streets right here.
>> And the one where the, okay, there's Prairie.
Now, where does the TIF, where's the TIF boundary on here
heading south?
Does it go down to Prairie Street or does it?
>> Sycamore, if you believe.
>> Okay. Sycamore.
Is that north of Prairie or south of Prairie?
That's north of Prairie.
>> That's north of Prairie.
>> Okay. So some of this is, some of it, probably just a
little of it, is out of the
outside of the TIF, but some of that yellow is inside.
>> Yes.
>> And then the red, phase four, that's going west of
Carroll, is that right?
>> Yes.
>> Okay, so that's not, okay, so that's not in.
All right, okay.
And so this design contract is for the yellow and the red
with maybe the purple hatch?
>> Yes.
It gives us the ability to analyze both routes and then
design which route becomes the best option for us.
>> And is this still within the bond funded amounts?
This, because we're short, my understanding is.
>> We have funding for the design and the acquisition of
right away associated with it.
What we do not have funding for is construction.
>> So we'll have an opportunity to come back and talk about
funding sources for the construction.
Right now we're not, we're still within our bond guidelines
.
>> Yes.
>> But after the design and the purchase of the right away,
then we're out of money?
>> Yes, sir.
>> Okay.
Okay. Yes, Council Member Briggs.
>> Do you have a picture of the box culverts that were?
>> No, but I could get you one.
I mean, really most anywhere where we're putting the box
culverts in themselves, you will not see.
>> Okay.
>> Because they will be under a street or they'll be under
a parking lot or.
>> So I have, it's no secret issue with 50 foot concrete
channels.
And so that's not what we're talking about here.
What we're talking about is maybe getting rid of some of
those channels, right?
>> Yes, some of those would go away to be usable land
afterwards.
>> Okay. Okay. Just got to be clear.
>> Absolutely.
>> Thank you.
>> Okay. Any other questions on this agenda item?
Yes, Council Member Hussbett.
>> If Council would want to see, there's an example on
Maple Street,
Google Maps says like 100 block of maple.
If, I mean, if you wanted to see, I mean.
>> An example of.
>> Of the.
>> A box culvert or.
>> Yes, sir.
>> Yep. Well, actually, remember that park that was, we put
in some drainage, I thought,
by the old Davis bakery.
>> Exactly. That's what it is.
>> Is that, this is a vacant piece of land now.
>> Exactly.
>> Yeah. Okay. Yeah.
>> Do we own it?
>> Yes, we do own it, I believe. I believe we do. Yes.
>> So.
>> I could be wrong. We don't own it? Or do we? Oh, okay.
>> I have a follow-up question.
Do any of these areas that you're talking about include the
old channel that's made of rock
and stone from, that's just.
>> Yeah, I think that.
>> Done a while ago.
>> I do not believe that's part of this chat.
>> That's Eagle and Prairie.
>> Yeah, I think that's a different project altogether.
>> Is it? Okay.
>> I think that's this segment. I know which one you're
talking about.
And I believe that's over here. When you get down near
Eagle, there's a segment of it that's.
>> That's kind of historic.
>> Yeah, it's.
>> [INAUDIBLE]
>> Yeah, that segment, it's back in this area, right around
Briscoe Tire,
just in the north in that area.
And we're going to be north of there on Prairie.
And the channel that you're talking about, that's not part
of this.
>> Okay.
>> Okay. No more questions? If there are no more questions,
Chair would entertain Council's pleasure. Council Member
Ryan.
>> I will move approval.
>> Mayor Pro Tem seconds. All in favor, agenda item 2A,
signify by raising your right hand.
Passes unanimously. We're now on to concluding items.
And I have one that I'd like to address just real quickly
and then I'll record it.
Just wanted to have everyone keep Jenna Duncan from Denton
Record Chronicle and her family,
her fiance Michael Whitaker and Michael's father, I believe
his name is Charles.
And your thoughts and prayers, they were involved in a car
accident.
And we just really wish them the most speedy recovery and
our thoughts are with them.
So they're part of the Record Chronicle, which sometimes I
consider often part of
this council family, just like all families. We sometimes
have disagreements, but we all get over
them. So I just really wanted to mention that because I
really just want the community to keep
them and their thoughts and prayers. So thank you all for
indulging me in that.
Any other? You have no concluding items?
Please, everybody, let's make a note and the paper is not
here, they can't record that.
But Council Member Briggs has no concluding items. Does
anybody have concluding items?
Okay, great. We will stand adjourned then at 633 on
December 12, 2017.
[ Silence ]