Dec 08, 2015 City Council on 2015-12-08 2:00 PM
December 08, 2015 City Council
Full Transcript
Have a quorum? Actually everyone's present. Fantastic. We
'll go to our first work session
report, which is we only have one work session report and
then we have including items in our
open session. Receive a report, hold discussion, give staff
direction regarding the status of dent
municipal electric capital improvement program projects.
Before we get started just to uh
there wasn't any dinner orders so we do have the pressure
to get out as expeditiously as we can.
So I'm committed to that uh but we also want to make sure
we have a thorough discussion of the
the work session at hand. Yes. And I'd like to thank
Councilwoman Briggs for our Christmas
cheer that's around the table and just want to do a shout
out and say thank you. It made me smile
and warm my heart when I walked in so thanks. Thank you.
You bet. Thank you very much. Yes I'm sorry.
I would echo Ms. Wasney's comments today about the
Christmas cheer and I'd like to go along with with
the theme from yesterday of setting the bar higher than
leaving by six for dinner.
We could leave earlier than that Mayor. We can but I'll
make sure that we won't.
Just teasing. Okay Mr. City Manager without further ado.
Thank you Mr. Mayor. I appreciate it. I'd like
to call call on Mr. Brent Heath to open this discussion and
I think we have visitors who will
also participate in the presentation. Thank you Brent.
Thank you George. Mayor, Council.
We're here today to provide an update on DME's Capital
Improvement Program.
We have an executive summary that we would like to go over.
The bottom line is that the city of
Denton has a problem. We have a growth problem. That's a
good problem but we have to have the
infrastructure to serve it and we have an agent
infrastructure problem. The chart at the bottom
right hand corner of this map shows our megawatt demand.
The August the 19th of this year we hit
our second all-time peak electrical demand that we've ever
had in the city of Denton and that was
347 megawatts. We have a responsibility to respond to the
growth and agent infrastructure problem and
to be able to supply electricity to the citizens of Denton
both as the electric provider here at
the city of Denton and also a regulatory responsibility. We
have and we follow a sensible
public involvement process to listen to and consider all
practical suggestions that are made to us by
the citizens and the presentation today is going to be
mostly from Freese and Nichols. They're
one of our engineering consultants that we've used to help
manage this program and Kendall King is
the vice president energy division manager for Freese and
Nichols. I'll have him come up here in
just a moment and he's going to highlight our project
management processes and tools that we use
and he will give an overview of the DME/CIP leadership team
. Then Aaron Freke is the project
manager with Freese and Nichols. He will then come up and
show us some of the process swim lane and
the diagrams that we use, the individual project schedules,
the overall program schedule, a couple
of the tools, web portal and e-builder, describe our weekly
project meetings that we have,
show a current executive dashboard and project
accomplishments that we've done this year
and that'll be a pretty amazing slide when you see that.
They're going to do that before four o'clock. Well we
definitely will try to do that. Kendall's
then going to update us on the status of the Freese and
Nichols contract for our CIP program
and then I will conclude with some of the major
accomplishments that we've done
in our CIP program. So with that outline in mind I'd like
to go ahead and invite Kendall King from
Freese and Nichols to come up and go through his portion.
Thank you Brent. I appreciate the
opportunity to be here and especially because there's some
new members on the council that
weren't here when we started our project two years ago and
so this is a chance for me to kind of give
a little bit of a refresher on what Freese and Nichols role
is on this project. Just kind of
quickly, Freese and Nichols has got a lot of program
management experience as a company. My
group that I manage has a lot of experience helping energy
clients implement really large
programs of work to try to meet a peak workload that they
have to without having to increase
their staff significantly to make that happen and so we do
that by plugging in a couple of a few key
people into the program and really our goal is to take some
of the day-to-day project workload off of
the staff so that they can focus on the things that they
really need to do. That key decision making
type of involvement that only they can provide, the
communications that is best carried out by
staff, things like that, but to take some of the day-to-day
project management workload off of
those staff so that they can focus on the things that they
need to do. We do that by putting some
people in that have some experience that can do that. We
also do that by deploying some technology
and some tools that we've developed over a number of years
to that we know works and can really help
lighten the load of everybody. Well the first things we do
when we come into a program like this
is we help document the business processes and as you can
see on the slide we documented 21 separate
business processes that it takes to execute a either
transmission line project or a substation
project. It's everything from purchasing to how we engineer
a project, how do we procure
right away, all of those different processes get documented
. We do that for a number of reasons.
One is it really helps our folks come up to speed really
quickly on how does DME do its business.
The other thing it does is it gives us a road map for a
very repeatable process. Essentially what
we're doing here is building a machine to help churn out
these projects at a much faster rate
than what the DME staff was used to doing. We went from
doing a project every you know maybe a project
or two a year to where we've got eight or ten or twelve or
more going all at the same time and what
we've tried to do is help put the the machinery together to
be able to churn out that work at a
lot higher rate without DME having to add a bunch of staff.
The other thing we did and continue to
do is we've developed a bunch of very detailed project
schedules. Aaron's going to show you that
in a little while. It's really critical for being able to
keep track of where we're at and manage
our resources. We can start to see when we put all those
project schedules together and you'll see
this when Aaron shows it to you. We can see where the peak
workload is going to happen, where our
resources limitations are going to impact our schedules and
then we can work around that.
We've developed a web portal that Aaron's going to show you
which really gives us the ability to
let all the team members see the current maps and and
locations and routings and things like that
without worrying about people working off of outdated
information. We deployed a software
platform called eBuilder which has helped all of the team
collaborate. It keeps all of our cost and
financial information all in the same location. We share
records and documents and manages many
of our processes and then developing tracking tools and
reporting tools so that everybody knows
where we stand. The other thing we kind of helped with and
this was a team effort with DME's lead
team was we helped kind of devise what's the right project
structure from a management standpoint and
this is what it looks like currently. This evolved over the
first several months of the program
with key senior members of DME serving in lead roles in
different areas. So Galen Gillum is over
land acquisition and permitting, Brent's over the program
management and also the site selection.
Brian Dascombe and Chris Lutrick are really involved in
site selection, public relations
and purchasing and then Chuck Sears oversees all the
engineering and construction.
Then you can see these other folks around the outside.
These are key people from either
Freezing Nichols or some of the many design consulting
engineering firms that are involved
to support DME and so we've created these teams that focus
on special areas, specific areas,
and with that specialization and that focus, but everybody
working together on a day-to-day basis,
we've been able to really increase the amount of work that
we've put through the program.
So now I'm going to introduce Aaron Fricke who's going to
show you some of the details of what we
do on a weekly basis. Good afternoon council and mayor.
Thank you all for having us here.
I just scroll down is that what it is? Okay this is uh
Kendall told you all about all the tools we
use and everything we've done. I'm going to go in a little
bit more depth not not bore you but not
keep you here till six o'clock either. This is an example
of a swim lane. This is the the product,
the byproduct of sitting down with the DME staff and asking
them what all happens in these 21
processes that we dug up as we talked to them and found out
what is their day-to-day
tasks that they do and this is a swim lane. What it is is
each, I mean with the mouse I can,
this says Tignall and Perkins. Each participant in a
process has their own lane so Tignall and
Perkins they have this top row then Power Engineers has
this next one, DME the next one
and you'll see down here City Council. So in this process
specifically it's site and route
selection. So when we go into a process of selecting a
route for a route or a site for a
substation or a transmission line we have to go through all
these steps and navigate through it
to get to our end product where we actually have a site we
can move forward with or a transmission
line alignment that we can move forward with. This helps us
visually step back and see who
who participates the most, when do they participate, who
has who's carrying the ball before the next
person is and who does it go to after that. So this this is
what Kendall was talking about when
we documented 21 different processes and the next slide zo
oms in at the bottom so you can read it a
little bit better but it just shows some of the tasks that
bounce around. We go from one lane to
the next lane it's there for two or three steps then it
goes to this one splits and then comes back.
So all these things happen in order to go from the
beginning infancy stage to actually having a
product we can work with. So after we did this we sat down
and we put a duration to all these tasks.
Does it take three weeks? How long does it take to get on
city council's agenda, have the meeting
with city council and then group back together and then go
to our next step. So that's where we go
from our process or our swim lane to our individual project
schedules. So we also sat down with Chuck
and said what all happens Chuck Sears what all happens to
build this project in site selection,
land acquisition, permitting, construction, all the stuff
that has to happen design,
what are all the tasks and these projects have somewhere
between 8 and 1200 tasks to get to
to the end of the project into from the beginning to the
end if it's a full project with site
selection and so you're not seeing all the tasks here some
of them are rolled up into
higher tasks higher echelons above that but you can see
here the different tasks we have these
are durations the longer it is the longer it takes to go
through this one shows a land acquisition
we've already finished the route and site selection on this
one so this just shows the remaining tasks
we did this for all the projects we have and there's about
40 something transmission line and
substation projects and then there's another 30 something
upgrades where Chuck has to plan out
that usually those are just design and construction they
don't take all the site selection and stuff
so there's about 70 something projects 77 I think that have
a detailed timeline all the way
planned out this gave us an understanding of how long it's
going to take to start this project
and finish this project from that now we have 77 projects
we need to figure out which ones do we
do first so we asked Chuck we said in order for this in
order for this entire program to go and
to be built and be effective you don't want to build a
substation over here and have a transmission
line over here you want to build the transmission line that
goes to that substation that connects
to the next one to the next one so that as you upgrade your
system it's upgrading in an efficient
way that can be used at that time and not just sporadic so
we went and prioritize all these
projects and that's why you see them cascading down to when
we expect to complete them and that
gave us this is what we call a program schedule this is all
70 something projects rolled up in
a program schedule so the little the processes led to a
duration schedules individual project
schedules which led to an overall program schedule and uh
and so on that chart when you see a
particularly long line that means that that particular
thing takes a long time to accomplish
yes sir okay it's usually the long ones you see here there
's a significant uh 12 18 months worth
of route or site selection and then um of course design and
land acquisition and all that stuff
makes it a long project some of these short ones it's a the
substation might already be there and
we're just expanding it um so we don't have all the site
selection going along with it
so you see and just explain the the blue ones are the subst
ations the orange ones are the
transmission lines and you see these yellow ones those are
uh tmpa upgrades some of our system
requires tmpa to upgrade some of their parts to it in order
for it to um help us out so we have
those put in here as well this is a screenshot of our web
portal freeston nickels has this uh tool
that we've used on other projects it's um kind of similar
to your your google earth if you're
familiar with that you can zoom in zoom out pan around um
we've got the we've got the system
dme's infrastructure input in here with all the substation
all the transmission lines
the yellow is the 69 kv and the red is the um 138 kv and
then you see some um there's some encore
lines coming in and out just to show where everything
connects we can um we can zoom into
this into a particular project i've got them bookmarked
over here you can click on not on
this but on our program we can actually click on hickory it
zooms straight into the hickory substation
we can we have it loaded with the dcab data straight from
um city of denton so we went or
the county we bring that in you can look at the parcels how
many properties are um how many
properties will be affected on a certain a certain site and
um we've also got the information of the
the acreage the landowners um all that information from d
cat imported into this program that helps us
yes sir real quick question on the you said that the yellow
or green or whatever that color is
represents the would you say 68 kv what 69 69 yes sir but i
know that on some of these
we're we're redoing uh upgrading so that they can handle
130 138 138 so this is what's currently
they're like i look at the bonnie bray substation uh and i
know that they put in new poles along
bonnie bray that are still 69 kv but it's so that they can
handle a 138 kv so is that
this is what's current this isn't what is projected to be
right that's current what's on the ground
upgraded currently it's 69 correct me if i'm wrong
currently it's 69 but it's it's built to where it
can the poles can handle 138 conductors is that correct i
think what would be interesting and
you could just do this an informal staff report on what do
you see is your schedule for energizing
those lines that we're upgrading to handle 138 actually
being 138 what what's the time frame of
needing that and so that's really not for you guys but i
just was curious because i yeah
um i wrote just a little list of some of the other things
you can do on this we have a
follow-up i'm sorry yes i think just add to that and then
the ultimate kind of lifespan
of that upgraded project in other words we're doing this
assuming to avoid having to go back
and upgrade in the near future how long does that take
right yep i'm sorry go ahead okay on the
right side i have just some of the highlights of our of our
program you can you can search
i can search for a landowner's name and type it into a
search function and it'll let me know where
all their properties are it works that that was helpful
when dealing with the landowner that comes
up several times like i believe waski was um we were
dealing with him on two or three different
projects rather than going to him different times and then
finding out after we just closed with him
we got another project we could do it all at once and say
hey we got these projects on the on the
table and it helps us uh be more efficient at our dealings
with certain landowners who have a lot of
property we have a print function which we can give we can
make exhibits for landowners because
they want to see when you say you're going to affect their
property they want to know how are
you going to affect my property cutting right through the
middle of my house are you cutting
on the neighbor on the side or or how and we can make
exhibits showing the transmission lines and
how they affect the properties and of course we got
directions like google does and street view and
we use being maps for our background we also have brought
in recently um city of denton pays for uh
net cog um imagery you all the council governments where y'
all bring in the imagery for your gis data
we're allowed to use that on this project as well so we
have these maps updated with the latest uh
the latest maps that you have that y'all have already paid
for for through net cog we upload
those straight into our system as well so it gives us real
time i believe last one was flown over this
year like april or something and we're and we're in the
process of uploading that so this is a
screenshot of our of e-builder which is our main program
management platform um kindle discussed
mentioned that it has the document storage um but what also
has is all those all those um timelines
all those schedules we built are imported into here and
with every task is a um is a is a cost
how much does it cost for construction how much does it
cost for land acquisition how much it costs
for permitting all that is loaded in in as resources into
the um into e-builder from those costs we can
if this project for some reason site selection is taking a
long time and we're having to push this
one to next year um we can slide that whole project to the
next year and then we can run an
analysis and say how does that affect our budget because we
always we always have to put together a
budget for the next fiscal year and find funding for it and
make sure that um you know because the
budget it changes as some projects progress fast other
projects progress slowly and we have to keep
that uh that budget number accurate so that we know how
much to ask for so we don't over over uh
under ask or over ask so um all those resource numbers are
added to this um
all the tasks are also broken down by transmission or um or
substation cost that helps on the back
end when we file for t-cost because uh when you get to a
substation a certain percentage of it
certain percentage of the equipment is transmission certain
percentage of it is um substation side
or distribution side so only the transmission part can be
um sent up to t-cost for reimbursement so
this is a this is a copy of our our status report that we
use every thursday we have a team meeting
um basically all the leaders all the players on our team
sit again sit down and we we discuss all
the projects that are currently going on um this this is
just our statuses on a weekly basis we
update what our latest actions are um when we go to council
when we go to pub when we have approval
from you guys all that information is dictated on these
status reports on a weekly basis
and this just gives us a visual as well as some of the some
of the timelines some of the um dates
we've hit on these uh on these projects we sit around and
um we we do a lot of our strategizing
and problem solving when we have problems on where um which
side is better than others we we kick
around ideas we have probably about 10 to 12 people in
these meetings on average and we always
have input coming from paul williamson freese nickles and
several of the dme staff as well as
uh city legal larry colister's there so we have a huge team
there that everybody's looking at it
from different angles to to make sure that we try to
analyze all the different pros and cons of
different sites and routes for the for the executive team
for um what we call phil williams and um
howard we put we put together what we call an executive
dashboard phil and howard don't need
to know all the details about all the all the landowners
and all the um the little stuff we're
working on they need to see big picture so we came up with
this dashboard that in a in a one sheet
main dashboard page they can get a lot of information just
from this one sheet this top
box over here it shows um all the different phases we got
selection site selection or route selection
acquisition land acquisition permitting and construction
and then this last one is completed
in a snapshot phil can say we have seven projects in site
selection and as you can tell
and the projects move from left to right so you can tell
that bonnie bray north lakes is my time up
bonnie bray north lakes is getting close to going in the
way that it takes
man here let me get to the fun slide so real quick phil can
tell that we're about to have something
going to the next phase and uh he knows when he's uh when
he has something he needs to be involved in
the this this one right here t cost is a big deal is
getting that stuff filed getting projects
completed getting the books squared away and then send them
up for t cost this lets uh as well as
our whole program um system this tells us when things are
when we expect things to come online
this is 2015 and then you got 2016 so we have two years
projected out and come this next year we'll
slide this over and show what we expect to have in 2016 and
then 2017 this gives phil an idea of how
many projects transmission lines substations and upgrades
we should have online at different
points of time throughout the year um also as you know we
're in this um in city council meetings
uh closed and open sessions public hearings as well as pub
all the time you see dme i think we're on
the agenda every time for most of the items today this is
uh this keeps phil aware of when we put
things on the agenda of all the pub meetings we have coming
up in the next uh two months and then
all the city council meetings we have in the next two
months whether they're open or closed or public
hearings and then on the right here these two uh kind of
the same thing this one has the contracts
for the uh for the consultants and this bottom one has all
the contracts for the materials
it shows how much is left in all these contracts so phil
can see when it's red we need to start
thinking about are we done with that vendor or are we done
with that consultant do we need to go back
and get more money because it's a it's a decent process to
go through and get a an rfp out for a
new contract um but this this helps us understand where we
are in all these contracts that we have
going yes that's the uh yes the percentage that's the
overall overall contract amount and then of
course the percentage is how much is that that's how much
is left yes anything else
um this this is a this is another timeline per se um for
the executive dashboard this this kind
of breaks down our um projects by by color for the
different phases in today's date you know that um
anything that crosses the green it means those projects are
in right and south right route and
site selection anything that crosses the blue is in
construction that uh that way we know that when
when we're coming up to a project that might have a lot of
blue projects at the same time are going
to be in construction we need to start looking at our uh
construction contractors and knowing
can we handle five can our can our contractor handle being
at five different um substations at
one time or do we need to bring another contractor on board
same with surveying and permitting we
need to manage our resources using this um it just it's
another way of breaking down our um current
projects that we're working on to know what phase they're
in and what resources will be used at them
now last year we came in we um we we spent spent most of
the year getting up to speed getting the
processes in place making it more efficient and um revising
any issues we see in those processes
at as year went on this year we've got a lot of those
systems in place and we've been very
successful at pushing projects through the pro through the
system to get um to get some uh
progress and uh this is an animated slide i'm going to go
click by click and you can just see that
at the beginning of two at 2014 yes before you do that can
you just go back one slide real quick
is the ultimate goal to stay efficient to have a little bit
of each color you know uh so you're not
doing too much construction at one time too much land
acquisition at one time or uh a land acquisition
team we can ramp up and ramp down pretty easily but um
construction we have contracts out for uh
certain certain contractors and if we see that a lot of
substations are going to hit at one time
we need to be on board with that contractor and know can
cam for uh or can chapman be out there
doing six substations or do we need to go out there and
have another one on standby right but
yes and no okay some some resources we can we can explode
and get a lot more going at one time
and others we're gonna have to put a large contract out to
get somebody else on board
it's important to have a project completed on time but it's
also important to have a project
completed on budget is your organization responsible for
bringing projects in on budget
and it is this big project of the upgrade on budget or is
it over budget is that is the overall cip
the whole project of the transmission line upgrade and all
the substations uh going in okay
yeah that's excuse me that's absolutely a great question
and yes we are on some of our projects
were actually ahead of schedule we had anticipated to do
some of the work this fall and we were able
to complete it at the start of the summer so we were
approximately three months early on some of
the projects of the overall programs we feel very good
about that now related to the financial
portion as far as on budget we i saw a breakdown this last
thursday to where we've capitalized
or not capitalized we've uh listed every one of our
projects since the cip program has began
and we actually are under budget as far as what has been
budgeted in the cip budget book versus
what has been actually spent and what has been encumbered
but has not yet been invoiced to be
paid so we are under budget is there any chance i could see
that spreadsheet i bet there is a chance
okay thank you any other questions on this one before i
move forward
i don't see any thank you okay um again this is the
animated slide at the beginning of this year
this is where we stood the projects migrate from the left
to the right these are our different
phases we got site selection then it goes into land
acquisition once we own the land we go into
permitting and then design is kind of ongoing it can be
going during this time and then construction
so we put those in the same column and then once they're
completed they're over here so last year
we started the year off with these four projects in
completion so here's some of the animation to show
you so those projects are all now completed as of from the
beginning of this year to the end of
this year and or at least to november
and then we have a lot of projects currently in
construction or in design most of them are construction
and then these went to permitting
land acquisition and these are the current projects in site
selection so this just shows that stuff is
migrating but they're progressing from all of our phases to
our completion phase which is what we
want to get it's the ultimate goal and we just use this
slide to animate and show you how things
have progressed along the program and that's the last slide
i have and kindles kindles on board next
so two years ago when we started this project we came with
a an estimated budget of in round
numbers 12 million dollars i failed to mention in my first
slide that the freezing nickels team
is also providing the right-of-way acquisition we are
partnered with the north fleet group nicky
costanza who's here and i'm sure you've seen before is a
subcontractor to freezing nickel so the
contract was split roughly half and half six million for
program management and engineering
uh that also includes a construction inspection that our
folks are doing and then roughly six
million dollars for the land acquisition so you can see
that through the end of october
we had spent just a little over three million dollars i
guess it was through september so we're
two years through the contract and we're just a little over
halfway through the engineering
budget and the program management budget we spent about
seven hundred and fifty thousand dollars on
the land acquisition part of that there's a couple reasons
for that a lot of the work that we've done
up to this point has been focused on a few sites uh subst
ation sites and so there's a number of
projects yet to come where there's going to be lots of
tracks to acquire for for transmission lines
and so at that point the rate of spend on the uh on the
right away will increase as nicky's group
has to bring on some more folks to help get that done so uh
the thing that um i'll call your
attention to is that this was a three-year agreement it
would uh it would expire at the end of uh
october of uh this of the coming year 2016 uh we don't
think that the work that we're engaged in
will be finished by that time uh certainly the construction
will not we would really like to
think that we're going to be through all the site uh
selection and and um and planning part of it but
that's probably a little bit optimistic so we could be back
here uh talking to you some point
in the summer about a time extension yes because i wasn't
on council when your contract was signed
for those three years what was the total cost of the
contract roughly 12 million dollars your two
year company yeah well to manage the to yeah that's correct
that was my question and and like i said
six million for the program management and the engineering
and construction management and about
six million in round numbers for the right away acquisition
so if we don't meet meet the deadline
in october of 2016 how much additional time do you do you
see this project taking you know i don't
i'm not prepared to answer that here today uh we're trying
to project and see how long some of these
projects are going to go on and then what kind of
assistance you're going to continue to need
it could be that uh there may not be a lot of need for uh
site selection type support uh and that kind
of help for very long or maybe not at all but there could
be construction going on which we might have
some construction inspection services continuing so as we
work through the summer and start
approaching the time frame when this contract is going to
expire we'll we'll try to we will have a
better forecast of what tasks remain to be finished and
what kind of effort that'll involve but the
good news is that we're i think we're in very good shape on
the budget it'd just be the time
council member johnson so i think i know the answer based
on what you just said but just for
clarification so when you when you give us a a quote you're
quoting based on the scope of work
right assuming it's going to get done in a certain amount
of time so if the work takes longer
are you are you is my understanding that the the amount of
money that you're charging in the
contract is for the work or is it for the time it well it's
really getting paid for our time
it's really difficult to budget a project like this by task
because when we started it we didn't
know you really know what the exactly all that i mean not
time in terms of man hours
time in terms of the the contract is projected to be for
three years or two years or whatever so
i'm assuming your your your budget is based on man hours
that's correct so and we just haven't
expended the man hours at the rate that we thought we would
when we put together the budget right so
if so if there's more time required it doesn't mean that
the amount of the contract increases
that's correct thank you yeah and that's what i was trying
to show is that we're half we're two
thirds of the way through the time and just a little over
halfway through the the budget so i
think we're in good shape on the budget any questions yes
councilmember it's kind of generally
speaking and understanding that these are some pretty
substantial development projects going on
in the city of denton that have to go through a lot of the
same processes that any other development
project would have to go through you're going through
engineering going through permitting
you're working with different utilities and whatnot right
away and there's been a lot of
discussion of our own kind of development process and how
that works and so you guys
as consultants and and even our dme team has probably
learned a lot along the way in terms of
potential obstacles and things that work well things that
don't and i hope that there's some
interdisciplinary conversation going on with our planning
department engineering department and
all that sort of stuff but not for today's discussion but
at some point it probably would
be helpful for council to hear maybe even an informal staff
report about some of the things
that you've learned through that process any suggestions
you have for other departments in
terms of how to streamline things because you're trying to
get some significant things through
and then if any changes have been made in our own internal
processes based on what you guys have
done so to me that's just a whole separate area of interest
that we're benefiting from probably
just want to make sure we're learning from that when we
when uh erin showed you the swim lane
diagrams that we developed we spent a lot of time with with
the other departments in helping to come
up with those and and how the different departments interf
aced with dme on executing these projects
and there was a lot learned a lot of lessons learned and
there already have been a bunch of
improvements in everybody's processes to kind of help
facilitate things so i think it's been a
valuable experience thank you kendall thank you erin as you
can tell we've been very busy this
past year working on not only projects but also the entire
program it's so much work and so many
things that we've done it would have been well it would
have been impossible for us have done it with
the staff that we have and so it's great to have some
experts that have done work for chesapeake
energy they've done work for encore as well as other
private entities bring their knowledge and
their experience to be the subject matter experts to help
us prepare some of these swim lane diagrams
to bring efficiencies to the city of denton and to dme so
with that i'd like to see if y'all have
any questions we are working fast working furious towards
solving the problem that denton has
system growth and agent infrastructure and with your help
and assistance we uh
we aim to keep the lights on question yes and it's it's and
this is i think this is within the
posting whenever i say that her she always gets a very
intent look on her face this is regarding a
specific project within this cip project plan and that is
the hickory bonnie bray substation
we had seen a picture from uh that uh mr williams had
presented i guess a couple weeks back about
what would it look like if there were a gis at that
location with the facade at least that was
structured for so we didn't really talk much about that or
give any direction and i would like to
really put that forward to the council if not today in the
near future to say hey i would like
to see that be a gis just because it's a major thoroughfare
not only for our city but for the
university it's close to the historic uh district there on
on west oak street and i think based upon
our discussion last time with the with council members john
son's observation that although
there's a cost difference that seemed to be fairly major it
was pointed out that part of that or some
of that or most of it is is due to an increase in capacity
with the gis so i just i mean if council
is ready to give any kind of direction today that's fine if
not i really want to before we get too far
in that process on hickory and bonnie bray to where it's
sort of a failsafe point of beyond
able to make that that change i just wanted to put that
forward because i think that's something
especially at that location that would be appropriate given
its its location and maybe the cost
yes council member i appreciate you bringing that up mayor
i think
uh i think some of the direction that we gave last time was
because the facade that we see now is
really really high walls right because of trying to hide a
lot of the equipment in there so i thought
what we had asked for and correct me if i'm wrong brent was
to go look at okay if we if we build a
gis a gas insulated substation there let's see an updated
budget because while there will it will
cost more to put a gis versus ais the um as erin's later
yes we should be able to save some money on
the we need more acronyms around here we should be able to
save some money on the facade because we
wouldn't have to build it as tall and we might have other
options on the facade so is that does
everybody else remember that i think we asked okay okay i
would like to see but i think to your point
we need to do that sooner rather than later great to get an
update on the what will the cost be
sure um but i would also like to see that we did because i
think that was kind of a
an aha moment for me last time looking at it and i don't
know if that information was in there
before and i just didn't see it but when you see you know
it's one and a half times the cost but
it's one and a half times the capability well that changes
all the thinking in my mind so
to see a the cost difference but also to understand really
understand the capacity
difference between the two like expansion ability in there
could we add more later
because of the size of the parcel because we already own it
now right we do so not just to look
at you know apple to apple gis versus ais of the capacity
we're planning to build but if there could
be more capacity later and then how would you construct it
and just a comprehensive either that
hey guys here's the real deal if we go that route here's
all the benefits and here's the costs
and the facade benefits too and so we just make a decision
yep okay and i my mind is slowly
recollecting i was asking because that wasn't driving thank
you thank you for remembering that
um it's important and of all the locations i think that's
the one so appreciate staff putting that
together for us and again before we get too deep and down
the road to really study it all before
we actually say yes okay sounds great yeah all right the
action items i'm taking from this
briefing today is we'll look at the hickory substation the
gis the direction to consider
that shorter facade look at the cost revisit what the look
would look like also to talk about the
69 to 138 kv conversion in a time frame and then look at
how long the new infrastructure life cycle
might be on that so those are the items i'm taking from
today's meeting that sounds accurate yes
any other questions any more presentation from staff on
that is it we just appreciate y'all's
help and input and we appreciate all the citizens
suggestions recommendations and we definitely want
to do what least impacts the citizens at the lowest cost
possible any more questions for staff
on this presentation okay seeing none thank you thank you
all very much thank you very much for
your presentation appreciate it we'll now go to our conclud
ing items worksheet or work session
which is item two any concluding items you know yes i would
i would like to ask legal or staff to
look at and update us on the update us on the process of
citizen input at work sessions because
i think that we looked at that before in our community in
our engagement group but then
it's really unclear about the exact process when to do it
and what it can be done yeah just so
because we've had citizens question that and come to speak
and just kind of i'd like to see that
okay anything else shout out to ryan raiders and gar wildc
ats they got too deep into the playoffs
and i'm really proud of those those those guys and gals and
everybody that participated in on
the field and either on the team or in the band and all the
community that came out to support them
i was at the game saturday at at&t stadium and boy it was
you know the whole lower level was full
you know almost wrapped around and then some in the upper
level so it was a great environment and
great to see the community come together and really support
support the kids and their
accomplishments so lots of fun look forward to next year
any other concluding items
seeing none okay that concludes our open portion of the
city council meeting for tuesday december
the eighth we will now proceed we'll now convene the closed
session at 2 47 p.m. and we will consider
the following items consultation with attorneys under text.