 Good afternoon. I'm Pat Smith,

00:00:03.840 --> 00:00:07.360
 the chair of the city of dead bond oversight committee.

00:00:07.360 --> 00:00:09.360
 This afternoon, we are having

00:00:09.360 --> 00:00:11.640
 a regularly scheduled meeting for

00:00:11.640 --> 00:00:15.640
 the bond oversight committee via zoom.

00:00:15.640 --> 00:00:19.640
 The first agenda item will be consideration

00:00:19.640 --> 00:00:25.160
 of the meeting minutes for February 4th, 2021.

00:00:25.160 --> 00:00:28.560
 Is everyone had an opportunity to review the minutes?

00:00:28.560 --> 00:00:34.680
 Can I get a motion for approval?

00:00:34.680 --> 00:00:37.320
 I'll move.

00:00:37.320 --> 00:00:40.680
 Thank you. Randy Robinson.

00:00:40.680 --> 00:00:42.800
 Can I get a second?

00:00:42.800 --> 00:00:44.800
 I'll second.

00:00:44.800 --> 00:00:47.440
 Thank you, Eric. Any discussion,

00:00:47.440 --> 00:00:52.200
 comments or amendments to the meeting minutes?

00:00:52.200 --> 00:00:54.440
 All right. Seeing none,

00:00:54.440 --> 00:00:58.000
 all in favor of approving the meeting minutes as presented,

00:00:58.000 --> 00:01:01.560
 please signify by raising

00:01:01.560 --> 00:01:04.560
 your hand or saying I for the phone or zoom.

00:01:04.560 --> 00:01:12.320
 I. Janet, are you able to vote?

00:01:12.320 --> 00:01:26.360
 Did you hear anything from Janet, Cassie?

00:01:26.360 --> 00:01:29.840
 No, it looks like she's joined via phone,

00:01:29.840 --> 00:01:32.560
 but it looks like she's still muted.

00:01:32.560 --> 00:01:36.840
 Okay. Do we have enough votes?

00:01:36.840 --> 00:01:39.880
 I thought we had quorum,

00:01:39.880 --> 00:01:42.800
 but if she doesn't vote, I don't know if we have quorum.

00:01:42.800 --> 00:01:47.760
 I think we're okay, Mac.

00:01:47.760 --> 00:01:49.600
 It's very well.

00:01:49.600 --> 00:01:53.760
 Just counting answers are four numbers.

00:01:53.760 --> 00:01:55.480
 Yeah. Eric, myself,

00:01:55.480 --> 00:01:58.760
 Randy, and Brandon.

00:01:58.760 --> 00:02:01.480
 There's seven total on the board?

00:02:01.480 --> 00:02:02.520
 Yes.

00:02:02.520 --> 00:02:04.120
 Yes. We still have a quorum.

00:02:04.120 --> 00:02:05.800
 Okay. All right.

00:02:05.800 --> 00:02:07.720
 That motion is approved.

00:02:07.720 --> 00:02:11.040
 Moving on to the next agenda item.

00:02:11.040 --> 00:02:14.560
 BOC 21-006.

00:02:14.560 --> 00:02:16.720
 Receive a report, hold a discussion,

00:02:16.720 --> 00:02:19.160
 give staff direction regarding 2012,

00:02:19.160 --> 00:02:24.160
 2014, and 2019 general obligation funded capital projects.

00:02:24.160 --> 00:02:26.040
 I'll turn it over to you, Cassie.

00:02:26.040 --> 00:02:30.120
 Thank you. We have three presentations for you today,

00:02:30.120 --> 00:02:33.120
 similar to last time.

00:02:33.120 --> 00:02:37.080
 Gary Packen is going to present the parks projects,

00:02:37.080 --> 00:02:38.960
 and then we'll have Rachel Wood from

00:02:38.960 --> 00:02:43.800
 Capital Projects present and then Scott Gray from facilities.

00:02:43.800 --> 00:02:48.480
 You'll have an opportunity to ask questions with each presenter.

00:02:48.480 --> 00:02:51.040
 With that, I'll turn it over to Gary.

00:02:51.720 --> 00:02:56.120
 Good afternoon, Gary Packen, Director of Parks and Recreation.

00:02:56.120 --> 00:03:01.160
 I'm going to go through the 2014 bond election proposition number 4,

00:03:01.160 --> 00:03:03.840
 and our projects associated with that.

00:03:03.840 --> 00:03:06.840
 We've completed all of the playground replacements.

00:03:06.840 --> 00:03:10.560
 In fact, we completed an extra one at Joe Skiles Park,

00:03:10.560 --> 00:03:13.760
 and we had money left over that was relocated and approved

00:03:13.760 --> 00:03:16.480
 by the Bond Oversight Committee last meeting.

00:03:16.480 --> 00:03:18.360
 That's been moved to the tennis court,

00:03:18.360 --> 00:03:20.640
 North Lakes Tennis Center project.

00:03:20.640 --> 00:03:24.240
 That is pending construction,

00:03:24.240 --> 00:03:27.120
 and I'll talk about that here in a future slide.

00:03:27.120 --> 00:03:33.680
 This is the park improvements phase 1 at Lake Forest Park in Milan.

00:03:33.680 --> 00:03:35.240
 We completed a playground,

00:03:35.240 --> 00:03:38.040
 a pavilion, and a basketball court.

00:03:38.040 --> 00:03:44.200
 Phase 2, park improvements at South Lakes Park.

00:03:44.200 --> 00:03:46.080
 We are in the bidding process.

00:03:46.080 --> 00:03:50.960
 We're going to our solicitation review committee next Wednesday

00:03:50.960 --> 00:03:56.080
 to get that out to bid, so that should be out very soon.

00:03:56.080 --> 00:03:57.960
 We're excited to get that project moving.

00:03:57.960 --> 00:04:00.840
 That's two additional courts with lights,

00:04:00.840 --> 00:04:04.080
 and then an option to put lights on the other courts as well.

00:04:04.080 --> 00:04:13.400
 Property acquisition, we had a little over $1 million in the bond program,

00:04:13.400 --> 00:04:17.080
 and we have an additional $5 million for 2019.

00:04:17.080 --> 00:04:22.920
 We have submitted an offer on one property down in South Denton,

00:04:22.920 --> 00:04:29.600
 and Real Estate is working on another offer in the same general area,

00:04:29.600 --> 00:04:31.160
 and then we're working with a developer

00:04:31.160 --> 00:04:33.720
 to potentially buy some land off of them as well.

00:04:33.720 --> 00:04:37.960
 So there's three properties that we're specifically talking to.

00:04:37.960 --> 00:04:42.680
 There is a fourth one that's close to Lake Forest Park

00:04:42.680 --> 00:04:44.680
 that's owned by an energy company,

00:04:44.680 --> 00:04:47.280
 and they haven't been real responsive,

00:04:47.280 --> 00:04:50.720
 so we keep trying to move forward on that.

00:04:50.720 --> 00:04:53.640
 So we're trying to work with them as we move forward.

00:04:53.640 --> 00:04:59.120
 Southwest Park Master Plan design.

00:04:59.120 --> 00:05:02.560
 We have a focus group that's been walking through us

00:05:02.560 --> 00:05:06.120
 this process since July of 2020.

00:05:06.120 --> 00:05:08.920
 It's about 20, 25 people.

00:05:08.920 --> 00:05:11.640
 We take it at the park board and brief them

00:05:11.640 --> 00:05:13.200
 and gain some feedback,

00:05:13.200 --> 00:05:17.320
 and then we plan on taking it to city council in the near future.

00:05:17.320 --> 00:05:19.880
 And once we get feedback from them, then we'll go back,

00:05:19.880 --> 00:05:23.520
 make some updates, and then put it back through the process again

00:05:23.520 --> 00:05:29.600
 with park board and city council for eventual approval to the master plan.

00:05:29.600 --> 00:05:34.040
 The master plan itself right now is three sections.

00:05:34.040 --> 00:05:37.280
 The northern section is open space and park.

00:05:37.280 --> 00:05:39.960
 The bottom left, which you see a footprint of a building,

00:05:39.960 --> 00:05:42.360
 that could be anything at this point in time.

00:05:42.360 --> 00:05:47.200
 It just kind of really articulate what size of a building could go there.

00:05:47.200 --> 00:05:51.560
 Over the course of the next 20 years, we may decide that it's, you know,

00:05:51.560 --> 00:05:56.000
 an ice rink, a field house, whatever, a library, a rec center,

00:05:56.000 --> 00:05:57.320
 could be any one of those.

00:05:57.320 --> 00:06:00.760
 So we're just going to leave it as general footprint space

00:06:00.760 --> 00:06:04.240
 with its capabilities based on its parking options

00:06:04.240 --> 00:06:08.400
 and the building space overall with the square footage.

00:06:08.400 --> 00:06:11.440
 And then the bottom right side is what could be put there

00:06:11.440 --> 00:06:14.000
 in regards to athletic fields.

00:06:14.000 --> 00:06:15.920
 None of this needs to be built at one time.

00:06:15.920 --> 00:06:18.160
 It could be built in three different phases

00:06:18.160 --> 00:06:21.080
 with the park open space, the indoor building,

00:06:21.080 --> 00:06:23.280
 and then the field space in the bottom right.

00:06:23.280 --> 00:06:27.840
 And each one of those phases could be rolled out at a slower pace as well.

00:06:27.840 --> 00:06:33.200
 So this entire property could be phaseable.

00:06:33.200 --> 00:06:35.080
 And currently, there's no funding for this.

00:06:35.080 --> 00:06:41.880
 So this is just to kind of get a master plan in line for future opportunities.

00:06:41.880 --> 00:06:43.840
 Spray ground, this was completed.

00:06:43.840 --> 00:06:46.080
 We're going to be opening it up on May 15th.

00:06:46.080 --> 00:06:49.200
 It did not open last year because of COVID.

00:06:49.200 --> 00:06:54.240
 But we're excited to get it back open and provide that service to the community.

00:06:54.240 --> 00:06:55.720
 And this is in Carl Young Park.

00:06:55.720 --> 00:07:03.360
 Our trail system, this is a component that has been done that basically starts

00:07:03.360 --> 00:07:09.720
 at North Lakes Park and goes up to North Point Park and then points east.

00:07:09.720 --> 00:07:13.320
 This is a component of our entire trails plan.

00:07:13.320 --> 00:07:17.080
 We've been working on our parks recreation and trail system master plan

00:07:17.080 --> 00:07:19.640
 since January of 2019.

00:07:19.640 --> 00:07:24.240
 We've been very focused on our trail section of that plan.

00:07:24.240 --> 00:07:28.280
 We have currently over 200 miles of trails that are planned in parks,

00:07:28.280 --> 00:07:33.240
 along major roadways, along major greenways or creeks.

00:07:33.240 --> 00:07:38.400
 And then connections between under or over text dot roads.

00:07:38.400 --> 00:07:42.920
 And then we're also planning paddling trails as well, both along our creeks

00:07:42.920 --> 00:07:47.560
 and around the entire perimeter of Lewisville Lake in partnership

00:07:47.560 --> 00:07:52.640
 with the Army Corps, Texas Parks and Wildlife, and neighboring cities.

00:07:52.640 --> 00:07:58.960
 The tennis center, the Pro Shop has been completed.

00:07:58.960 --> 00:08:02.680
 It was actually done about three months ahead of time.

00:08:02.680 --> 00:08:04.200
 So that's ready to go.

00:08:04.200 --> 00:08:09.080
 We are not yet ready for our flat work.

00:08:09.080 --> 00:08:10.200
 We're getting close.

00:08:10.200 --> 00:08:14.360
 We've been working through permitting and design on that.

00:08:14.360 --> 00:08:18.600
 So we're just about at the point where we can get it out on the street

00:08:18.600 --> 00:08:23.320
 and get a meeting set up with finance and purchasing for the SRC

00:08:23.320 --> 00:08:25.880
 to get that approved and out to bid.

00:08:25.880 --> 00:08:30.560
 We did get $40,000 in grants from the USTA for that project.

00:08:30.560 --> 00:08:33.640
 Our goal is to put 12 courts out there.

00:08:33.640 --> 00:08:35.960
 We are going to provide some alternates.

00:08:35.960 --> 00:08:40.400
 So the base bid is 10 courts with two courts as an alternate.

00:08:40.400 --> 00:08:44.880
 And then the pickleball courts will be alternates as well.

00:08:44.880 --> 00:08:47.880
 That gives us an opportunity to accept or decline

00:08:47.880 --> 00:08:50.760
 that based on what the cost comes in and what the budget allows.

00:08:54.600 --> 00:09:00.960
 Waterpark additions with the wave pool and the concessions,

00:09:00.960 --> 00:09:03.160
 we're getting ready to reopen our pools.

00:09:03.160 --> 00:09:05.160
 They were not open last year.

00:09:05.160 --> 00:09:10.000
 We have been challenged with getting enough people to return,

00:09:10.000 --> 00:09:12.520
 to operate at full capacity.

00:09:12.520 --> 00:09:16.120
 Since we were closed, we are shorthanded this year.

00:09:16.120 --> 00:09:19.200
 We lost a lot of our reoccurring staff to other jobs.

00:09:19.200 --> 00:09:22.600
 Since we were not open, they went and sought other employment.

00:09:22.600 --> 00:09:26.480
 We did talk to a community last week--

00:09:26.480 --> 00:09:30.000
 actually, this week-- that did open their pools last year.

00:09:30.000 --> 00:09:31.920
 And they are not having a hiring challenge.

00:09:31.920 --> 00:09:35.560
 So it definitely impacted us by closing the pools.

00:09:35.560 --> 00:09:38.440
 And that staff went and found other employment

00:09:38.440 --> 00:09:39.600
 during that time frame.

00:09:39.600 --> 00:09:43.560
 So we have to rebuild our staffing and our aquatics team.

00:09:43.560 --> 00:09:50.080
 Vela Athletic Complex, this project is completed.

00:09:50.080 --> 00:09:54.560
 The only thing that we're working on is finalizing two signs,

00:09:54.560 --> 00:09:57.440
 two plaques that are going to go in the property.

00:09:57.440 --> 00:10:00.760
 And we received one, and there was a misprint on it.

00:10:00.760 --> 00:10:02.960
 So the company has to redo it.

00:10:02.960 --> 00:10:05.720
 When they printed the logo, it didn't come out correctly.

00:10:05.720 --> 00:10:07.800
 So they're redoing that right now

00:10:07.800 --> 00:10:11.800
 and going to be sending that back to us.

00:10:11.800 --> 00:10:15.480
 And the sculpture that is going towards the entrance

00:10:15.480 --> 00:10:17.600
 of the park, it's called the Trophy.

00:10:17.600 --> 00:10:20.520
 That is under fabrication right now

00:10:20.520 --> 00:10:23.440
 and looking for installation in August of this summer.

00:10:23.440 --> 00:10:30.640
 There's a rendering with the footprint.

00:10:30.640 --> 00:10:33.960
 We are going to be putting some landscaping around the perimeter

00:10:33.960 --> 00:10:35.960
 of this just to kind of soften that up a little bit.

00:10:35.960 --> 00:10:39.840
 And there's another angle.

00:10:39.840 --> 00:10:46.240
 Lake Forest Park, Drew's been working on this

00:10:46.240 --> 00:10:48.120
 with our public works team.

00:10:48.120 --> 00:10:50.400
 The fish have been relocated.

00:10:50.400 --> 00:10:52.040
 The water was drained out.

00:10:52.040 --> 00:10:54.920
 I think we may have some more water in there now

00:10:54.920 --> 00:10:56.160
 since the recent rains.

00:10:56.160 --> 00:10:59.280
 But you can see in the picture that the dam

00:10:59.280 --> 00:11:02.640
 is being reconstructed and refortified.

00:11:02.640 --> 00:11:06.560
 They removed some trees out of the base of the dam itself.

00:11:06.560 --> 00:11:08.880
 And then we'll start dredging in the near future.

00:11:15.160 --> 00:11:17.480
 Public art transportation.

00:11:17.480 --> 00:11:19.840
 So if you remember a few years ago,

00:11:19.840 --> 00:11:24.000
 we were going to put some medallions on I-35.

00:11:24.000 --> 00:11:28.440
 There are currently medallions right there by UNT that exist.

00:11:28.440 --> 00:11:33.880
 But there were ones to be placed at Brinker and Lillian Miller.

00:11:33.880 --> 00:11:36.000
 It was determined that that could not occur.

00:11:36.000 --> 00:11:37.720
 So we have the funding available.

00:11:37.720 --> 00:11:41.280
 There was discussion of putting them on the ground more

00:11:41.280 --> 00:11:43.120
 as a monument.

00:11:43.120 --> 00:11:47.080
 And the Public Art Committee didn't like that idea.

00:11:47.080 --> 00:11:50.320
 And there was some discussion to use the funding for gateway

00:11:50.320 --> 00:11:51.680
 signs.

00:11:51.680 --> 00:11:53.600
 And the Public Art Committee felt

00:11:53.600 --> 00:11:58.640
 that that's not signages and sculptures as an art

00:11:58.640 --> 00:12:00.080
 from that perspective.

00:12:00.080 --> 00:12:02.960
 So we've been sitting on the money

00:12:02.960 --> 00:12:05.280
 looking for what to do with that.

00:12:05.280 --> 00:12:07.920
 Currently, we have been talking with TxDOT

00:12:07.920 --> 00:12:13.280
 in regards to the continuation of I-35 basically from UNT

00:12:13.280 --> 00:12:15.840
 to US-77.

00:12:15.840 --> 00:12:18.600
 So the thought process there is we

00:12:18.600 --> 00:12:24.720
 could continue those medallions moving north along 35

00:12:24.720 --> 00:12:28.400
 at those interchanges where it could be at the Merge,

00:12:28.400 --> 00:12:34.480
 at Oak, at 380, and some areas along that corridor

00:12:34.480 --> 00:12:39.120
 where the medallions are embossed into the walls

00:12:39.120 --> 00:12:43.360
 as opposed to freestanding structures attached

00:12:43.360 --> 00:12:45.680
 to the wall with illumination.

00:12:45.680 --> 00:12:48.040
 That would be a little cheaper, a little more affordable.

00:12:48.040 --> 00:12:52.080
 So between the $311,000 that we have currently

00:12:52.080 --> 00:12:56.040
 in the bond project and then additional $290,000

00:12:56.040 --> 00:12:59.120
 that we just received from the Governor's Community Achievement

00:12:59.120 --> 00:13:02.080
 Award, Denton received and Keep Denton Beautiful received

00:13:02.080 --> 00:13:03.360
 first place.

00:13:03.360 --> 00:13:07.400
 So we will be receiving a grant of $290,000

00:13:07.400 --> 00:13:10.200
 to go towards TxDOT right-of-ways for beautification

00:13:10.200 --> 00:13:11.720
 and enhancement.

00:13:11.720 --> 00:13:14.240
 So we have almost $600,000 that we

00:13:14.240 --> 00:13:17.720
 could utilize for future projects.

00:13:17.720 --> 00:13:20.880
 So option one basically says funding for sculptures

00:13:20.880 --> 00:13:23.960
 on Carroll Dallas Bonnie Bray Roundabout.

00:13:23.960 --> 00:13:25.400
 I think it was last meeting that it

00:13:25.400 --> 00:13:27.840
 was mentioned about putting a sculpture in the roundabout

00:13:27.840 --> 00:13:29.640
 on Bonnie Bray.

00:13:29.640 --> 00:13:34.520
 If we decided to reallocate that $311,000 towards sculptures

00:13:34.520 --> 00:13:37.800
 that were put in the city along major roadways,

00:13:37.800 --> 00:13:41.680
 we could use that money in the very near future.

00:13:41.680 --> 00:13:44.400
 With it being bond money, I know we've

00:13:44.400 --> 00:13:47.040
 been trying to utilize the bond money quickly

00:13:47.040 --> 00:13:49.680
 and get it back into the community.

00:13:49.680 --> 00:13:52.560
 This is the fastest way to do that.

00:13:52.560 --> 00:13:55.840
 Option two does cause some delays.

00:13:55.840 --> 00:13:57.760
 They're in the process of planning,

00:13:57.760 --> 00:14:00.000
 so it's going to be a number of years before they

00:14:00.000 --> 00:14:03.000
 were able to start that project.

00:14:03.000 --> 00:14:08.800
 I think it's 2025 is the date in regards to that construction.

00:14:08.800 --> 00:14:10.880
 So that would delay the spending and utilize

00:14:10.880 --> 00:14:15.200
 that for the aesthetics on I-35 for the embossment

00:14:15.200 --> 00:14:18.040
 of the medallions and beautification.

00:14:18.040 --> 00:14:22.160
 So we'd be sitting on that for four or five years.

00:14:22.160 --> 00:14:24.800
 So that's the downside of that.

00:14:24.800 --> 00:14:29.960
 So we do have $600,000, but don't have the $290,000 yet.

00:14:29.960 --> 00:14:35.560
 We have a meeting next week with GCA regarding the grant.

00:14:35.560 --> 00:14:39.600
 And so those are the two options that we're

00:14:39.600 --> 00:14:41.000
 thinking about right now and wanted

00:14:41.000 --> 00:14:43.800
 to get some feedback from the Bond Oversight Committee

00:14:43.800 --> 00:14:46.840
 in what your preferred direction would be.

00:14:46.840 --> 00:14:54.240
 Thanks, Gary.

00:14:54.240 --> 00:14:55.040
 So thoughts?

00:14:55.040 --> 00:14:59.840
 Janet, are you on?

00:14:59.840 --> 00:15:01.840
 Yeah.

00:15:01.840 --> 00:15:02.840
 Are you on?

00:15:02.840 --> 00:15:04.480
 OK, good.

00:15:04.480 --> 00:15:05.680
 Can you hear me?

00:15:05.680 --> 00:15:06.600
 Yeah.

00:15:06.600 --> 00:15:08.640
 OK, good.

00:15:08.640 --> 00:15:12.040
 Gary, this is Brain.

00:15:12.040 --> 00:15:12.680
 Oh, go ahead.

00:15:12.680 --> 00:15:18.960
 Did traffic have any thoughts about putting a sculpture

00:15:18.960 --> 00:15:19.880
 in that roundabout?

00:15:25.240 --> 00:15:27.200
 Hang on a second.

00:15:27.200 --> 00:15:29.680
 She's getting over to the computer.

00:15:29.680 --> 00:15:30.160
 OK.

00:15:30.160 --> 00:15:38.680
 Hello.

00:15:38.680 --> 00:15:41.480
 Becky Devaney, City Engineer.

00:15:41.480 --> 00:15:45.040
 This traffic department is happy to coordinate with the Parks

00:15:45.040 --> 00:15:46.720
 Department and a sculpture.

00:15:46.720 --> 00:15:49.560
 This is a typical type situation that

00:15:49.560 --> 00:15:51.040
 has been used in other cities.

00:15:51.040 --> 00:15:52.680
 So if that's something that the committee

00:15:52.680 --> 00:15:58.160
 would like to consider, we would absolutely look into it.

00:15:58.160 --> 00:16:01.480
 I was just curious if that was--

00:16:01.480 --> 00:16:06.080
 having participated in the event of driving around

00:16:06.080 --> 00:16:08.920
 the roundabout on numerous occasions,

00:16:08.920 --> 00:16:11.800
 I was just curious if that was any kind of a safety

00:16:11.800 --> 00:16:16.000
 concern of having a monument or a sculpture

00:16:16.000 --> 00:16:18.880
 in the middle of that.

00:16:18.880 --> 00:16:22.280
 The roundabout at Bonnie Bray is larger in nature

00:16:22.280 --> 00:16:26.000
 than maybe the other roundabout that's located at Hinkle.

00:16:26.000 --> 00:16:28.080
 And so it does have the ability to have

00:16:28.080 --> 00:16:29.360
 a structure in that area.

00:16:29.360 --> 00:16:34.960
 But obviously, sight distance and the considerations

00:16:34.960 --> 00:16:37.600
 would be put into play for safety concerns.

00:16:37.600 --> 00:16:39.520
 We would want to make sure that everyone still

00:16:39.520 --> 00:16:41.360
 has the appropriate sight distance all the way

00:16:41.360 --> 00:16:46.200
 around the roundabout from not only the vehicular movements,

00:16:46.200 --> 00:16:50.840
 but then also the pedestrian traffic or bicycle traffic

00:16:50.840 --> 00:16:51.680
 is in that area.

00:16:51.680 --> 00:16:53.200
 So those would be all things that

00:16:53.200 --> 00:16:55.640
 would be put into consideration.

00:16:55.640 --> 00:16:57.600
 If we decided to go that route of putting

00:16:57.600 --> 00:16:59.240
 a monument in that location, we would

00:16:59.240 --> 00:17:03.320
 look into all those things from a safety perspective also.

00:17:03.320 --> 00:17:04.480
 Thank you.

00:17:04.480 --> 00:17:07.520
 Absolutely.

00:17:07.520 --> 00:17:12.600
 Gary, what were the committee's thoughts on--

00:17:12.600 --> 00:17:16.240
 what's an example of Carroll Boulevard and Dallas Drive?

00:17:21.600 --> 00:17:23.400
 Are you asking me?

00:17:23.400 --> 00:17:23.920
 Yes.

00:17:23.920 --> 00:17:25.640
 OK, sorry, I missed that.

00:17:25.640 --> 00:17:29.520
 So the thought process, we'd put two or three--

00:17:29.520 --> 00:17:31.440
 actually, probably three or four--

00:17:31.440 --> 00:17:36.320
 pads along that roadway on Carroll on the east side.

00:17:36.320 --> 00:17:38.840
 And we could actually put temporary art there

00:17:38.840 --> 00:17:39.480
 if we wanted to.

00:17:39.480 --> 00:17:41.880
 And we could rotate it out every couple of years

00:17:41.880 --> 00:17:45.880
 and basically lease artwork from artists

00:17:45.880 --> 00:17:47.880
 that could display their artwork.

00:17:47.880 --> 00:17:50.680
 And then we'd have a constant changeover.

00:17:50.680 --> 00:17:53.280
 Or we could go out and actually purchase it

00:17:53.280 --> 00:17:57.720
 and put those three or four sprinkled along that right away.

00:17:57.720 --> 00:17:59.800
 And there's a trail that follows that as well

00:17:59.800 --> 00:18:03.320
 to provide that experience for both the people walking

00:18:03.320 --> 00:18:05.760
 and driving that corridor.

00:18:05.760 --> 00:18:08.400
 So we're talking, like, between south of University

00:18:08.400 --> 00:18:11.800
 down to Congress Street, that area?

00:18:11.800 --> 00:18:13.360
 Yes, approximately, yes.

00:18:13.360 --> 00:18:18.520
 And Brandon also asked about Dallas Drive.

00:18:18.520 --> 00:18:19.680
 What are your thoughts there?

00:18:19.680 --> 00:18:21.520
 Dallas and Teasley, if you remember,

00:18:21.520 --> 00:18:24.480
 there is an old right of way that used to be there.

00:18:24.480 --> 00:18:26.800
 About a year and a half ago, we wanted to remove that

00:18:26.800 --> 00:18:29.000
 and put some landscaping in there,

00:18:29.000 --> 00:18:31.440
 put some benches and some seating in there.

00:18:31.440 --> 00:18:33.920
 And the thought process is we would put a pad out there

00:18:33.920 --> 00:18:38.640
 and put a structure in that park to help beautify that,

00:18:38.640 --> 00:18:40.880
 something that probably a little bit on the brighter side

00:18:40.880 --> 00:18:42.640
 so you could see it.

00:18:42.640 --> 00:18:46.840
 But that was the thought process of putting a pad or a foundation

00:18:46.840 --> 00:18:49.920
 there that we could put a sculpture.

00:18:49.920 --> 00:18:52.400
 OK, anyone?

00:18:52.400 --> 00:18:53.880
 Eric?

00:18:53.880 --> 00:18:58.080
 I guess, to me, it sort of looks like a decision

00:18:58.080 --> 00:19:03.040
 between some investments that would be where local residents

00:19:03.040 --> 00:19:07.520
 would be often versus something that is more of a--

00:19:07.520 --> 00:19:12.040
 call it marketing slash general beautification

00:19:12.040 --> 00:19:14.600
 to let people know who are driving through Denton,

00:19:14.600 --> 00:19:19.720
 that this is our city and we're proud of it, right?

00:19:19.720 --> 00:19:23.560
 My preference would be for the first,

00:19:23.560 --> 00:19:26.800
 for putting it where our residents are.

00:19:26.800 --> 00:19:30.200
 But I would certainly defer to the Public Art Committee

00:19:30.200 --> 00:19:33.800
 because I think they deal with those questions a lot.

00:19:33.800 --> 00:19:36.120
 Just out of curiosity, is the match

00:19:36.120 --> 00:19:41.800
 for the potential funding along 35,

00:19:41.800 --> 00:19:44.080
 does that require a local match?

00:19:44.080 --> 00:19:46.720
 Would it require the entire amount

00:19:46.720 --> 00:19:49.000
 that we have available and that sort of thing?

00:19:49.000 --> 00:19:51.240
 So we're going to be meeting with TxDOT.

00:19:51.240 --> 00:19:53.520
 So basically, there is no match.

00:19:53.520 --> 00:19:58.560
 But if there's things above and beyond what their base options

00:19:58.560 --> 00:20:00.280
 are that they will provide and fund,

00:20:00.280 --> 00:20:02.760
 we would have to find above and beyond that.

00:20:02.760 --> 00:20:03.720
 OK.

00:20:03.720 --> 00:20:07.960
 Yeah, I just-- especially when you think of the Bonnebray

00:20:07.960 --> 00:20:14.560
 roundabout, and well, that could be sort of a way to really

00:20:14.560 --> 00:20:19.000
 activate that space with Razor Ranch South coming in,

00:20:19.000 --> 00:20:21.360
 drawing people over through that area

00:20:21.360 --> 00:20:24.720
 and being something to remember and enjoy

00:20:24.720 --> 00:20:26.400
 as we're going through our town.

00:20:26.400 --> 00:20:30.440
 And also, I don't know if this is the specific parcel you're

00:20:30.440 --> 00:20:33.520
 referring to on the Eagle and Elm area,

00:20:33.520 --> 00:20:38.040
 but it's kind of an older triangle

00:20:38.040 --> 00:20:41.960
 that was recently changed for the sidewalk and the drainage.

00:20:41.960 --> 00:20:43.560
 Is that what we're talking about there

00:20:43.560 --> 00:20:45.320
 on that northeast corner?

00:20:45.320 --> 00:20:48.040
 Yeah, there's two right-of-ways that we've improved.

00:20:48.040 --> 00:20:50.400
 Dallas and Teasley has been completed,

00:20:50.400 --> 00:20:52.920
 and they both had old abandoned right-of-ways.

00:20:52.920 --> 00:20:58.840
 And then Eagle and Elm is just right there at 377.

00:20:58.840 --> 00:21:00.520
 They had an old right-of-way as well,

00:21:00.520 --> 00:21:05.520
 and we're actually currently moving dirt on that property

00:21:05.520 --> 00:21:07.480
 for improvement and beautification.

00:21:07.480 --> 00:21:08.120
 OK.

00:21:08.120 --> 00:21:09.600
 Yeah, when I think of that, I think

00:21:09.600 --> 00:21:13.920
 that has a big opportunity to kind of be an entrance

00:21:13.920 --> 00:21:17.200
 to downtown, if you will, as people are coming in

00:21:17.200 --> 00:21:22.000
 from the south and be sort of a gathering place potentially

00:21:22.000 --> 00:21:23.760
 for some of those apartments and things that

00:21:23.760 --> 00:21:25.680
 have been built down there.

00:21:25.680 --> 00:21:28.400
 So those are just my thoughts.

00:21:28.400 --> 00:21:29.400
 Thanks, Eric.

00:21:29.400 --> 00:21:32.560
 Randy, Janet, any thoughts?

00:21:32.560 --> 00:21:36.240
 Yeah, I mean, personally, I think the--

00:21:36.240 --> 00:21:38.760
 I look at it more--

00:21:38.760 --> 00:21:42.600
 the highway medallions are great.

00:21:42.600 --> 00:21:47.760
 But if it's going to be unknown time and unknown,

00:21:47.760 --> 00:21:50.600
 what the cost is actually going to be,

00:21:50.600 --> 00:21:54.040
 I think we probably ought to just take the burden to hand

00:21:54.040 --> 00:21:58.320
 and say, hey, we have a place to use it.

00:21:58.320 --> 00:22:00.720
 The bond funds are authorized.

00:22:00.720 --> 00:22:03.000
 I don't want to hang on to them for another five years.

00:22:03.000 --> 00:22:06.600
 Janet, how about you?

00:22:06.600 --> 00:22:16.440
 She may not be hearing us.

00:22:16.440 --> 00:22:21.160
 So with that, sounds like there's kind of a sense here.

00:22:21.160 --> 00:22:23.800
 Could I get a motion for one of those two options?

00:22:29.320 --> 00:22:31.040
 For a vote or just for direction?

00:22:31.040 --> 00:22:33.040
 Well, let me ask, Cassie, you wanting a vote

00:22:33.040 --> 00:22:34.920
 or you just wanting feedback?

00:22:34.920 --> 00:22:36.520
 We just need direction.

00:22:36.520 --> 00:22:38.920
 I think that sense is option one.

00:22:38.920 --> 00:22:45.080
 We can move forward with planning that.

00:22:45.080 --> 00:22:47.800
 We'll run back through the public art committee.

00:22:47.800 --> 00:22:51.280
 And then the $290,000 we get from the GCA,

00:22:51.280 --> 00:22:54.360
 we'll continue to work with TXOT to see if that's an option.

00:22:54.360 --> 00:22:56.640
 We definitely need to figure out what the time frame is

00:22:56.640 --> 00:22:58.160
 on that when we meet with them.

00:22:58.160 --> 00:22:59.600
 In regards to how quickly they want

00:22:59.600 --> 00:23:02.640
 that to be utilized as well.

00:23:02.640 --> 00:23:04.760
 And if we needed to do something down the road

00:23:04.760 --> 00:23:08.080
 for the complement, the GCAA, we could always

00:23:08.080 --> 00:23:10.480
 put that in the next bond package.

00:23:10.480 --> 00:23:12.720
 It's going to be years before that's done.

00:23:12.720 --> 00:23:19.640
 OK, is that what you needed, Gary?

00:23:19.640 --> 00:23:22.720
 Yes, and make sure I didn't have another slide down.

00:23:22.720 --> 00:23:23.720
 I had one other slide.

00:23:23.720 --> 00:23:25.280
 Just let me bring that back up.

00:23:25.280 --> 00:23:26.600
 Can you see that?

00:23:26.600 --> 00:23:29.280
 Nope, let me re-share it.

00:23:29.280 --> 00:23:41.840
 The last slide was the 2019 bond program.

00:23:41.840 --> 00:23:45.800
 I mentioned this earlier on the 2014 bond program

00:23:45.800 --> 00:23:47.440
 for land acquisition.

00:23:47.440 --> 00:23:50.920
 We do have $5 million, and we're working with real estate

00:23:50.920 --> 00:23:55.640
 on some due diligence and offers for potential park property

00:23:55.640 --> 00:23:57.040
 for future park space.

00:23:57.040 --> 00:24:02.360
 And we continue to work with local developers

00:24:02.360 --> 00:24:05.920
 on their projects to try to acquire park space

00:24:05.920 --> 00:24:08.120
 in their properties and their development

00:24:08.120 --> 00:24:10.120
 and hopefully provide connectivity

00:24:10.120 --> 00:24:12.880
 to other parcels and other city assets,

00:24:12.880 --> 00:24:20.240
 whether it's park space, trails, neighborhoods, major roadways.

00:24:20.240 --> 00:24:21.160
 And that's all I had.

00:24:25.080 --> 00:24:27.440
 Thanks, Gary.

00:24:27.440 --> 00:24:29.480
 Capital Projects.

00:24:29.480 --> 00:24:34.440
 Next up, we have Rachel Wood from Capital Projects.

00:24:34.440 --> 00:24:36.320
 We'll be doing a joint presentation.

00:24:36.320 --> 00:24:45.120
 And I'm just looking for where the presentation is saved.

00:24:45.120 --> 00:24:52.920
 Do you need me to share it?

00:24:52.920 --> 00:24:55.160
 That might get challenging, just because I need to drive

00:24:55.160 --> 00:24:57.160
 for the majority of the slides.

00:24:57.160 --> 00:25:04.600
 There we go.

00:25:22.920 --> 00:25:26.840
 So similar to the previous presentations we've given you,

00:25:26.840 --> 00:25:31.400
 we'll go through the financial updates of each bond program

00:25:31.400 --> 00:25:36.040
 first before we get into the detailed project updates.

00:25:36.040 --> 00:25:38.280
 And then Rachel's going to go over some project management

00:25:38.280 --> 00:25:40.560
 and process improvement updates as well.

00:25:40.560 --> 00:25:42.960
 So I'm going to go through some of those first.

00:25:42.960 --> 00:25:45.480
 And then Rachel's going to go over some project management

00:25:45.480 --> 00:25:48.000
 and process improvement updates as well.

00:25:48.000 --> 00:25:50.600
 And then Rachel's going to go over some project management

00:25:50.600 --> 00:25:52.640
 and process improvement updates as well.

00:25:52.640 --> 00:25:54.960
 And then Rachel's going to go over some project management

00:25:54.960 --> 00:25:56.600
 updates from Capital Projects.

00:25:56.600 --> 00:26:05.240
 You can see from the charts that we've broken out

00:26:05.240 --> 00:26:08.920
 the 2012 bond and the 2014 bond program

00:26:08.920 --> 00:26:12.600
 to show you really how much has been spent

00:26:12.600 --> 00:26:15.560
 and is still remaining from each bond program.

00:26:15.560 --> 00:26:17.080
 And I do want to remind you this is just

00:26:17.080 --> 00:26:21.240
 for the street improvement part of the bond program.

00:26:21.240 --> 00:26:27.520
 There's additional CO issuances that will be sold this year.

00:26:27.520 --> 00:26:29.440
 They're included in our reimbursement ordinance

00:26:29.440 --> 00:26:31.720
 but haven't officially been sold yet.

00:26:31.720 --> 00:26:41.080
 And then the 2019 street bond program, we're still at 1%,

00:26:41.080 --> 00:26:48.520
 but have future projects coming down the pipeline

00:26:48.520 --> 00:26:52.040
 to start spending this money allocated for street projects.

00:26:52.040 --> 00:26:58.440
 OK, thank you, Cassie.

00:26:58.440 --> 00:27:00.000
 So good afternoon, bond committee.

00:27:00.000 --> 00:27:02.920
 I'm Rachel Wood, Deputy Director of Capital Projects.

00:27:02.920 --> 00:27:05.000
 And as Cassie mentioned, this is really

00:27:05.000 --> 00:27:08.120
 going to flow similarly to previous presentations

00:27:08.120 --> 00:27:10.640
 that Becky Devaney and myself have given to the bond

00:27:10.640 --> 00:27:13.680
 committee, providing updates on the status of projects.

00:27:13.680 --> 00:27:16.320
 And then at the end, we'll talk about some process improvements

00:27:16.320 --> 00:27:20.320
 that we have going on to improve the efficiency of the projects

00:27:20.320 --> 00:27:22.080
 that we're delivering.

00:27:22.080 --> 00:27:25.640
 So first, we'll go through the street reconstruction bond,

00:27:25.640 --> 00:27:29.480
 the status of how we are delivering the 434 segments

00:27:29.480 --> 00:27:32.760
 from the 2012 and 2014 bond.

00:27:32.760 --> 00:27:34.960
 So we're pleased to announce that when

00:27:34.960 --> 00:27:39.120
 you saw this chart at the last meeting,

00:27:39.120 --> 00:27:41.840
 we were projecting to complete eight segments

00:27:41.840 --> 00:27:44.920
 during the first quarter of 2021.

00:27:44.920 --> 00:27:47.280
 Thanks to the excellent work of our project managers

00:27:47.280 --> 00:27:50.680
 and our contractors, we've actually completed 11 segments.

00:27:50.680 --> 00:27:54.040
 So just to kind of keep things clear for the remainder

00:27:54.040 --> 00:27:56.480
 of the next two years-- and we are still

00:27:56.480 --> 00:27:59.040
 projecting to complete all of the remaining segments

00:27:59.040 --> 00:28:02.520
 by quarter four of calendar year 2022--

00:28:02.520 --> 00:28:04.520
 we're just going to keep the same numbers

00:28:04.520 --> 00:28:08.280
 and just kind of show with color differentiations what's

00:28:08.280 --> 00:28:10.200
 been completed and what's been remaining,

00:28:10.200 --> 00:28:13.040
 just because I know it can get confusing trying to do the math

00:28:13.040 --> 00:28:14.920
 and look from presentation to presentation

00:28:14.920 --> 00:28:18.880
 to compare how many segments we have remaining.

00:28:18.880 --> 00:28:21.640
 So a lot of exciting progress has been made.

00:28:21.640 --> 00:28:23.900
 We've actually got one of our projects.

00:28:23.900 --> 00:28:25.280
 We had a pre-construction meeting

00:28:25.280 --> 00:28:27.280
 for what we're calling the outsource bundle that

00:28:27.280 --> 00:28:30.280
 consists of 47 different segments.

00:28:30.280 --> 00:28:32.400
 We had that earlier this week and had a community

00:28:32.400 --> 00:28:35.320
 meeting on that project two weeks ago with our project

00:28:35.320 --> 00:28:37.040
 manager, Dustin Draper.

00:28:37.040 --> 00:28:38.840
 And then we've got a portion of what

00:28:38.840 --> 00:28:41.920
 we're calling our 2020 bundle that's

00:28:41.920 --> 00:28:46.440
 going to council on June 8 for consideration of the construction

00:28:46.440 --> 00:28:47.480
 contract.

00:28:47.480 --> 00:28:50.960
 And it will go into construction shortly thereafter.

00:28:50.960 --> 00:28:53.480
 So other than that, there aren't a ton

00:28:53.480 --> 00:28:56.880
 of updates other than we've got a lot of active construction.

00:28:56.880 --> 00:28:59.160
 2019 Street Reconstruction Project

00:28:59.160 --> 00:29:04.560
 is on track to complete in quarter four of 2021.

00:29:04.560 --> 00:29:07.440
 And that does include Windsor Drive.

00:29:07.440 --> 00:29:10.880
 And we do still have the note that there

00:29:10.880 --> 00:29:13.760
 are seven segments that are being programmed

00:29:13.760 --> 00:29:16.600
 as parts of other projects.

00:29:16.600 --> 00:29:19.000
 Becky and I actually had a conversation yesterday

00:29:19.000 --> 00:29:19.880
 with TextDOT.

00:29:19.880 --> 00:29:21.960
 We should be getting some additional information

00:29:21.960 --> 00:29:25.120
 from them very soon on Trinity Road

00:29:25.120 --> 00:29:28.120
 and the timing of TextDOT's Trinity Bridge project

00:29:28.120 --> 00:29:31.080
 because we're trying to sync those projects up.

00:29:31.080 --> 00:29:34.200
 For Mulberry Street, which includes two segments,

00:29:34.200 --> 00:29:36.840
 that's going to be a part of the Pecan Crate Tributary

00:29:36.840 --> 00:29:39.440
 for phases three and four projects.

00:29:39.440 --> 00:29:43.080
 We did submit a funding request as a part of our CIP budget

00:29:43.080 --> 00:29:45.800
 request this year for additional funding

00:29:45.800 --> 00:29:47.320
 to fully fund that project.

00:29:47.320 --> 00:29:49.000
 So really, that timing is going to be

00:29:49.000 --> 00:29:52.000
 dependent on identifying those drainage funds that we

00:29:52.000 --> 00:29:54.920
 need to complete that project.

00:29:54.920 --> 00:29:58.000
 On Westgate, we've got a community meeting coming up

00:29:58.000 --> 00:30:01.560
 May 13 and then a presentation to city council

00:30:01.560 --> 00:30:04.320
 through a work session on May 18 where

00:30:04.320 --> 00:30:07.160
 we're going to be talking about the scope and some potential

00:30:07.160 --> 00:30:10.680
 options to improve connectivity in the Westgate area

00:30:10.680 --> 00:30:14.960
 in the broader context of Denton High School's new location,

00:30:14.960 --> 00:30:17.800
 a significant amount of multifamily and single family

00:30:17.800 --> 00:30:20.320
 residential that's going on in the area,

00:30:20.320 --> 00:30:23.120
 plus the upcoming 35 widening project.

00:30:23.120 --> 00:30:26.200
 So we've got a lot of good traction on that.

00:30:26.200 --> 00:30:27.880
 Once we get some direction regarding

00:30:27.880 --> 00:30:30.680
 what the scope of that project should entail,

00:30:30.680 --> 00:30:32.880
 we'll begin budgeting accordingly

00:30:32.880 --> 00:30:35.640
 and then develop a final design and ultimately go

00:30:35.640 --> 00:30:39.840
 to construction on that project as well.

00:30:39.840 --> 00:30:43.760
 So going through our 2014 bond Proposition 1 projects,

00:30:43.760 --> 00:30:46.480
 I'm not going to go through every single project.

00:30:46.480 --> 00:30:49.000
 I know you've seen this slide a couple of times.

00:30:49.000 --> 00:30:52.600
 So all I'm going to do is highlight a few updates.

00:30:52.600 --> 00:30:55.440
 Updates include-- we actually had a really productive

00:30:55.440 --> 00:30:55.960
 meeting.

00:30:55.960 --> 00:30:58.400
 Our project manager, Kyle Pedigo,

00:30:58.400 --> 00:31:01.480
 met with Union Pacific Railroad, one of their consultants,

00:31:01.480 --> 00:31:04.120
 Vinish, and Kimley Horn this morning.

00:31:04.120 --> 00:31:07.000
 And it seems like we are still on track

00:31:07.000 --> 00:31:10.440
 for completion of the downtown quiet zones

00:31:10.440 --> 00:31:13.600
 by the end of calendar year 2021.

00:31:13.600 --> 00:31:16.320
 There is, of course, the hang up that ultimately

00:31:16.320 --> 00:31:18.280
 the activation of the quiet zones

00:31:18.280 --> 00:31:20.480
 is on Union Pacific Railroad.

00:31:20.480 --> 00:31:23.160
 But we did at least get some verbal confirmation

00:31:23.160 --> 00:31:25.960
 that we're following all the steps that we need to follow.

00:31:25.960 --> 00:31:28.600
 And that project is being delivered in concert

00:31:28.600 --> 00:31:30.840
 with the downtown storm sewer project

00:31:30.840 --> 00:31:34.480
 that project manager, Kyle Pedigo, is also delivering

00:31:34.480 --> 00:31:37.400
 currently in the downtown area.

00:31:37.400 --> 00:31:40.520
 New to this slide is the mingo quiet zones.

00:31:40.520 --> 00:31:43.840
 And those are the quiet zones that kind of hug mingo road

00:31:43.840 --> 00:31:45.760
 from fish trap to frame.

00:31:45.760 --> 00:31:47.800
 I won't name every intersection.

00:31:47.800 --> 00:31:51.240
 But city council recently approved a design contract

00:31:51.240 --> 00:31:55.840
 with Bridge Farmer to design those intersections.

00:31:55.840 --> 00:31:58.840
 And so once we've got the design in a firmer opinion

00:31:58.840 --> 00:32:00.920
 and probable construction costs, we'll

00:32:00.920 --> 00:32:03.200
 then look at what the remaining budget we have.

00:32:03.200 --> 00:32:09.240
 I believe we had about $930,000 from the 2014 bond earmarked

00:32:09.240 --> 00:32:10.280
 for that project.

00:32:10.280 --> 00:32:12.840
 And so just knowing that it's been several years

00:32:12.840 --> 00:32:15.040
 since that original estimate was developed,

00:32:15.040 --> 00:32:17.600
 we most likely will need to identify additional funds.

00:32:17.600 --> 00:32:20.680
 But we'll know for sure once we've got that design completed.

00:32:20.680 --> 00:32:24.040
 But we are excited about that project getting delivered.

00:32:24.040 --> 00:32:27.440
 And it's being delivered as part of the overall TWU area

00:32:27.440 --> 00:32:31.680
 program that project manager Tracy Beck is managing.

00:32:31.680 --> 00:32:35.400
 A part of that project is also the Rudel extension at mingo.

00:32:35.400 --> 00:32:38.600
 So the same council meeting where city council approved

00:32:38.600 --> 00:32:42.440
 the contract with Bridge Farmer for the mingo road quiet zones,

00:32:42.440 --> 00:32:45.880
 they also approved a contract to go to 30% design

00:32:45.880 --> 00:32:47.520
 for that project.

00:32:47.520 --> 00:32:51.520
 And what we plan to do is later this calendar year

00:32:51.520 --> 00:32:55.800
 have a presentation where we get feedback from bond committee,

00:32:55.800 --> 00:32:58.240
 also get feedback from council on what

00:32:58.240 --> 00:33:01.880
 the scope of the TWU area program should be.

00:33:01.880 --> 00:33:04.480
 There are several projects that are bond funded,

00:33:04.480 --> 00:33:06.200
 several projects that are also in need

00:33:06.200 --> 00:33:08.680
 from an infrastructure project, and some projects that

00:33:08.680 --> 00:33:12.120
 have been requested from a pedestrian safety perspective

00:33:12.120 --> 00:33:14.480
 by Texas Women's University.

00:33:14.480 --> 00:33:16.360
 And so we want to get some feedback on how

00:33:16.360 --> 00:33:19.800
 we prioritize those projects and which ones we should look

00:33:19.800 --> 00:33:21.720
 at funding and delivering first.

00:33:21.720 --> 00:33:24.320
 They're definitely all needed and just need to figure out

00:33:24.320 --> 00:33:27.280
 the best way to prioritize those projects.

00:33:27.280 --> 00:33:29.240
 The only other thing I'll note on this slide

00:33:29.240 --> 00:33:31.560
 is Becky and I've been having some really positive

00:33:31.560 --> 00:33:34.640
 conversations with the cog with Denton County.

00:33:34.640 --> 00:33:38.000
 So as we look at funding needs for the different remaining

00:33:38.000 --> 00:33:40.200
 phases of Bonnie Bray, we're hopeful

00:33:40.200 --> 00:33:43.320
 that as Denton County is preparing a potential bond

00:33:43.320 --> 00:33:46.280
 program and as we're looking at some additional funding

00:33:46.280 --> 00:33:48.440
 opportunities from the cog that we

00:33:48.440 --> 00:33:51.280
 can use those funds to augment and ultimately complete

00:33:51.280 --> 00:33:54.240
 Bonnie Bray as that is one of our top priority projects

00:33:54.240 --> 00:33:54.960
 to get completed.

00:33:54.960 --> 00:34:04.920
 So next, going into some of our proposition three projects,

00:34:04.920 --> 00:34:08.360
 most noteworthy on this is we have removed Eagle Drive

00:34:08.360 --> 00:34:09.600
 Drainage from the list.

00:34:09.600 --> 00:34:11.280
 That is a completed project.

00:34:11.280 --> 00:34:14.440
 And thanks to the work of our business services team,

00:34:14.440 --> 00:34:16.440
 as well as the finance accounting team,

00:34:16.440 --> 00:34:19.160
 we have closed that project out and actually used that

00:34:19.160 --> 00:34:22.400
 as a model for closing out projects.

00:34:22.400 --> 00:34:24.320
 It is a pretty complicated process

00:34:24.320 --> 00:34:27.200
 to close out and ultimately capitalize a project.

00:34:27.200 --> 00:34:29.880
 And so we've got an SOP in the works.

00:34:29.880 --> 00:34:31.400
 And I'm delighted to say that we're

00:34:31.400 --> 00:34:33.280
 going to have several more projects coming down

00:34:33.280 --> 00:34:36.360
 the pipeline that we're going to be ready to close out very soon.

00:34:36.360 --> 00:34:37.760
 So it's been great that we've been

00:34:37.760 --> 00:34:39.680
 able to get that process documented just

00:34:39.680 --> 00:34:41.160
 so that we know all the steps that we

00:34:41.160 --> 00:34:45.200
 need to go through in order to properly close out projects.

00:34:45.200 --> 00:34:48.040
 So just only other thing I'll note here,

00:34:48.040 --> 00:34:49.760
 as I mentioned, downtown storm sewer,

00:34:49.760 --> 00:34:51.640
 we're doing a lot of coordination with that.

00:34:51.640 --> 00:34:54.120
 And the Quiet Zone project, and it

00:34:54.120 --> 00:34:58.240
 is on track to be completed by quarter 3 of 2021.

00:34:58.240 --> 00:35:00.240
 They're currently looking at potentially starting

00:35:00.240 --> 00:35:02.680
 the punch list for closing out that project

00:35:02.680 --> 00:35:04.320
 around the September time frame.

00:35:04.320 --> 00:35:09.360
 So trying to be more like parks.

00:35:09.360 --> 00:35:12.360
 You will notice in upcoming bond committee presentations

00:35:12.360 --> 00:35:15.440
 that we're going to try to have more pictures and help you

00:35:15.440 --> 00:35:17.440
 see the status of some of these projects

00:35:17.440 --> 00:35:19.840
 rather than just showing you the boring Gantt chart

00:35:19.840 --> 00:35:21.360
 that you've seen on previous slides.

00:35:21.360 --> 00:35:23.800
 So this is our first step in that direction,

00:35:23.800 --> 00:35:26.400
 and we're going to try to have the next presentation be even

00:35:26.400 --> 00:35:27.160
 more engaging.

00:35:27.160 --> 00:35:29.840
 We've talked maybe about videos, no promises at this point,

00:35:29.840 --> 00:35:31.280
 but that is a potential.

00:35:31.280 --> 00:35:33.400
 But just wanted to highlight some of those projects

00:35:33.400 --> 00:35:37.040
 that we are nearing completion on right now.

00:35:37.040 --> 00:35:38.880
 One of those is West Hickory Street.

00:35:38.880 --> 00:35:42.600
 We're currently projecting a quarter 3 calendar year 2021

00:35:42.600 --> 00:35:44.040
 completion date.

00:35:44.040 --> 00:35:46.920
 Recently completed is the London Dairy Sidewalk,

00:35:46.920 --> 00:35:50.760
 which is a part of the 2018 sidewalk improvements project.

00:35:50.760 --> 00:35:53.720
 That was actually completed in April,

00:35:53.720 --> 00:35:56.520
 and we've had a lot of feedback from residents, particularly

00:35:56.520 --> 00:35:59.040
 those whose students walk to McMath Middle School,

00:35:59.040 --> 00:36:01.320
 that that's really helped the safety for those students

00:36:01.320 --> 00:36:03.120
 walking to school.

00:36:03.120 --> 00:36:06.200
 I've already mentioned the 2019 Street Reconstruction Project

00:36:06.200 --> 00:36:08.800
 Windsor Drive is a part of that project,

00:36:08.800 --> 00:36:12.960
 and we are on track for a quarter 4 2021 completion date

00:36:12.960 --> 00:36:13.880
 there.

00:36:13.880 --> 00:36:15.800
 Hickory Creek Road, phase one, I'm

00:36:15.800 --> 00:36:18.880
 going to call it all but complete at this point,

00:36:18.880 --> 00:36:22.840
 but we will complete it this quarter, quarter 2 2021.

00:36:22.840 --> 00:36:26.040
 And then we are doing some final punch list items on West

00:36:26.040 --> 00:36:28.400
 Hercules right now, but that project

00:36:28.400 --> 00:36:32.480
 is set to wrap up later this month.

00:36:32.480 --> 00:36:34.280
 So hopefully we'll be able to come back to you

00:36:34.280 --> 00:36:36.680
 with some big completed signs like Gary

00:36:36.680 --> 00:36:40.840
 had during our next bond committee presentation.

00:36:40.840 --> 00:36:44.720
 Couple of exciting updates on the 2019 bond program.

00:36:44.720 --> 00:36:48.040
 So actually at the April 27th city council meeting,

00:36:48.040 --> 00:36:50.600
 the city council approved construction contracts

00:36:50.600 --> 00:36:54.520
 for what we're calling the MCFC and LOFT.

00:36:54.520 --> 00:36:57.800
 That's our first two bid packages of the 2019 bond

00:36:57.800 --> 00:36:58.920
 program.

00:36:58.920 --> 00:37:03.040
 That was also our first project that we selected the contractor

00:37:03.040 --> 00:37:05.640
 using competitive sealed proposals.

00:37:05.640 --> 00:37:08.160
 We took that approach just so that it wasn't low bid.

00:37:08.160 --> 00:37:11.120
 We were actually able to take in other factors,

00:37:11.120 --> 00:37:13.880
 including the qualifications of the contractors,

00:37:13.880 --> 00:37:16.760
 into account as we were selecting the contractors.

00:37:16.760 --> 00:37:19.880
 So we are now under contract with SEMA.

00:37:19.880 --> 00:37:24.560
 And these are what we're calling our early out packages.

00:37:24.560 --> 00:37:26.080
 I'm knocking on wood as I say that,

00:37:26.080 --> 00:37:29.520
 but they're relatively simple roadway construction projects

00:37:29.520 --> 00:37:31.560
 that do not include any utilities.

00:37:31.560 --> 00:37:33.440
 And so we're hopeful that we're going

00:37:33.440 --> 00:37:35.520
 to be able to complete those projects by the end

00:37:35.520 --> 00:37:37.080
 of the calendar year.

00:37:37.080 --> 00:37:39.840
 And then work is currently underway

00:37:39.840 --> 00:37:43.480
 for the design of the first phase of Southeast Denton.

00:37:43.480 --> 00:37:46.400
 And so we plan to advertise that project.

00:37:46.400 --> 00:37:49.440
 It's 22 segments of the Southeast Denton neighborhood,

00:37:49.440 --> 00:37:51.280
 primarily roadway construction, but there

00:37:51.280 --> 00:37:52.920
 will be some utilities.

00:37:52.920 --> 00:37:55.680
 We're also looking at sidewalks and streetlights

00:37:55.680 --> 00:37:57.400
 for those first 22 segments.

00:37:57.400 --> 00:38:00.160
 So we're hoping to advertise by the end of the calendar year

00:38:00.160 --> 00:38:01.640
 for that project.

00:38:01.640 --> 00:38:03.400
 And then in concert with that, we've

00:38:03.400 --> 00:38:07.880
 got phase B, or phase two, which includes 51 segments

00:38:07.880 --> 00:38:09.480
 of the Southeast Denton neighborhood.

00:38:09.480 --> 00:38:12.600
 We're looking at delivering those 51 segments

00:38:12.600 --> 00:38:15.360
 using the construction manager at risk methodology.

00:38:15.360 --> 00:38:19.240
 So the design contractor and the construction manager

00:38:19.240 --> 00:38:21.360
 would be selected at the same time,

00:38:21.360 --> 00:38:24.040
 so that the construction manager can provide feedback

00:38:24.040 --> 00:38:27.440
 on constructability and give us a little more predictability

00:38:27.440 --> 00:38:28.720
 in terms of price.

00:38:28.720 --> 00:38:30.840
 And so we hope to have that advertised

00:38:30.840 --> 00:38:32.960
 by the end of the calendar year as well.

00:38:32.960 --> 00:38:36.280
 So a lot of really exciting traction

00:38:36.280 --> 00:38:38.040
 in the Southeast Denton neighborhood.

00:38:38.040 --> 00:38:40.560
 We plan on having another community meeting later

00:38:40.560 --> 00:38:41.640
 this summer.

00:38:41.640 --> 00:38:44.400
 And so we're really excited about the opportunity

00:38:44.400 --> 00:38:47.080
 to use the construction manager at risk methodology,

00:38:47.080 --> 00:38:49.560
 particularly for those 51 segments,

00:38:49.560 --> 00:38:53.560
 just because it's going to require a lot of coordination

00:38:53.560 --> 00:38:56.360
 and in a very tight geography.

00:38:56.360 --> 00:38:59.880
 So having one contractor, one design firm

00:38:59.880 --> 00:39:01.960
 will be really helpful for all the coordination

00:39:01.960 --> 00:39:06.120
 with franchise utilities and other city departments,

00:39:06.120 --> 00:39:09.000
 just to ensure that we're minimizing the impact

00:39:09.000 --> 00:39:11.240
 to residents and getting them the highest quality

00:39:11.240 --> 00:39:14.600
 infrastructure in the process.

00:39:14.600 --> 00:39:16.520
 Bonnie Bray, phase six.

00:39:16.520 --> 00:39:19.520
 Right now we're under right of way acquisition.

00:39:19.520 --> 00:39:21.240
 We have several properties that we're still

00:39:21.240 --> 00:39:23.760
 in negotiations with.

00:39:23.760 --> 00:39:24.840
 We have regular meetings.

00:39:24.840 --> 00:39:26.760
 We actually have one later today, I believe,

00:39:26.760 --> 00:39:28.680
 with Denton Independent School District,

00:39:28.680 --> 00:39:30.360
 kind of talking about this project,

00:39:30.360 --> 00:39:34.840
 talking about the scope given the Denton High School Project.

00:39:34.840 --> 00:39:40.840
 And so we are currently tracking for a 2023 completion

00:39:40.840 --> 00:39:43.480
 date for Bonnie Bray phase six.

00:39:43.480 --> 00:39:46.920
 The completion date is 100% dependent on that right

00:39:46.920 --> 00:39:48.880
 of way acquisition right now.

00:39:48.880 --> 00:39:50.600
 We do hope to be ready to go to bid

00:39:50.600 --> 00:39:52.000
 by the end of this calendar year,

00:39:52.000 --> 00:39:55.680
 hopefully this fall for the construction contract.

00:39:55.680 --> 00:39:58.120
 But just want to note that we are doing everything

00:39:58.120 --> 00:40:01.600
 in our power to get the portions of Bonnie Bray

00:40:01.600 --> 00:40:03.800
 immediately adjacent to the new high school

00:40:03.800 --> 00:40:05.520
 open as quickly as possible.

00:40:05.520 --> 00:40:08.400
 And as a part of that May 13th Westgate meeting,

00:40:08.400 --> 00:40:10.800
 we will also be talking with residents

00:40:10.800 --> 00:40:13.480
 about the status of the Bonnie Bray phase six project,

00:40:13.480 --> 00:40:17.040
 just because it's in such close proximity to the Westgate

00:40:17.040 --> 00:40:20.360
 project and all of the connectivity kind of comes

00:40:20.360 --> 00:40:24.040
 into play, particularly around the new high school.

00:40:24.040 --> 00:40:25.640
 The last thing I'll note on this slide

00:40:25.640 --> 00:40:28.280
 is right now we've got some schedule uncertainty

00:40:28.280 --> 00:40:32.200
 for Ryan Road and Hickory Creek Road phase three.

00:40:32.200 --> 00:40:35.080
 I know Becky's mentioned in a few previous presentations

00:40:35.080 --> 00:40:37.920
 that we were getting $10 million from the COG

00:40:37.920 --> 00:40:39.920
 to help fully fund that project.

00:40:39.920 --> 00:40:41.720
 And that is the case.

00:40:41.720 --> 00:40:44.880
 We actually submitted what's called a tip modification,

00:40:44.880 --> 00:40:48.000
 just kind of formally earmarking that $10 million

00:40:48.000 --> 00:40:51.240
 from the COG on April 23rd.

00:40:51.240 --> 00:40:55.200
 But because of the funding source of that $10 million,

00:40:55.200 --> 00:40:57.000
 there are some schedule impacts.

00:40:57.000 --> 00:41:00.800
 And so knowing that both the portion of Hickory Creek Road

00:41:00.800 --> 00:41:05.160
 phase three touches 1830 and Ryan Road

00:41:05.160 --> 00:41:09.680
 will connect 2181 to 1830, we want to minimize impact

00:41:09.680 --> 00:41:12.920
 and ensure there's that connectivity from 2181

00:41:12.920 --> 00:41:14.040
 to 1830.

00:41:14.040 --> 00:41:15.680
 And so we don't want both projects

00:41:15.680 --> 00:41:18.360
 to be under construction at the same time.

00:41:18.360 --> 00:41:21.920
 So we should know by the end of this month what truly

00:41:21.920 --> 00:41:24.560
 the schedule impact is going to be of that additional $10

00:41:24.560 --> 00:41:27.320
 million that we've gotten from the COG.

00:41:27.320 --> 00:41:30.880
 And after we have that confirmation on schedule impact,

00:41:30.880 --> 00:41:33.240
 we're working with the design firm, HDR, who's

00:41:33.240 --> 00:41:36.800
 designing the Hickory Creek Road phase three project right now.

00:41:36.800 --> 00:41:40.400
 We'll be able to determine, is Ryan Road going to go first,

00:41:40.400 --> 00:41:44.000
 or is Hickory Creek Road phase three going to go first?

00:41:44.000 --> 00:41:45.800
 And so by our next bond committee meeting,

00:41:45.800 --> 00:41:47.600
 we'll be able to share that with you.

00:41:47.600 --> 00:41:49.680
 But just wanted to be transparent right now

00:41:49.680 --> 00:41:51.720
 that the dates that we have listed,

00:41:51.720 --> 00:41:53.720
 there's just some uncertainty just because we're

00:41:53.720 --> 00:41:56.040
 wanting to make sure we're coordinating those projects,

00:41:56.040 --> 00:41:58.680
 minimizing impact to residents, and making sure

00:41:58.680 --> 00:42:01.120
 that we're maximizing those outside dollars that we're

00:42:01.120 --> 00:42:05.320
 getting from the COG.

00:42:05.320 --> 00:42:06.840
 So really quickly, I'll talk about some

00:42:06.840 --> 00:42:09.080
 of the exciting project management and process

00:42:09.080 --> 00:42:11.880
 improvement updates we have going on.

00:42:11.880 --> 00:42:14.320
 I've mentioned several community meetings already.

00:42:14.320 --> 00:42:16.840
 I think this is the only week in May

00:42:16.840 --> 00:42:19.800
 where we don't have a community meeting on a Thursday night.

00:42:19.800 --> 00:42:22.040
 So if you're ever bored on a Thursday night,

00:42:22.040 --> 00:42:23.720
 I can almost guarantee you we're going

00:42:23.720 --> 00:42:25.720
 to be having a community meeting.

00:42:25.720 --> 00:42:27.760
 We've got a kind of renewed emphasis

00:42:27.760 --> 00:42:29.920
 in concert with our public affairs department

00:42:29.920 --> 00:42:32.640
 to make sure that we're not just talking to residents

00:42:32.640 --> 00:42:34.320
 as we're ready to go to construction,

00:42:34.320 --> 00:42:37.480
 but that we're also talking to residents early on in the design

00:42:37.480 --> 00:42:41.080
 process so that residents have an opportunity to impact it.

00:42:41.080 --> 00:42:43.480
 Once we've already selected the construction contractor,

00:42:43.480 --> 00:42:46.080
 well, yes, we could make change orders in the field.

00:42:46.080 --> 00:42:47.800
 Those changes are much more complicated,

00:42:47.800 --> 00:42:48.880
 much more expensive.

00:42:48.880 --> 00:42:50.800
 And so we're really wanting to hear earlier

00:42:50.800 --> 00:42:55.080
 on from the residents as these projects are getting mobilized

00:42:55.080 --> 00:42:58.000
 what they'd like to see, concerns they may have,

00:42:58.000 --> 00:43:00.640
 if there is some sequencing considerations

00:43:00.640 --> 00:43:03.360
 that we need to make as we're scheduling these projects out.

00:43:03.360 --> 00:43:06.160
 And so as I mentioned, if you're ever

00:43:06.160 --> 00:43:08.920
 curious on a Thursday night what you're going to be doing,

00:43:08.920 --> 00:43:11.680
 you're always welcome to join us at one of our virtual community

00:43:11.680 --> 00:43:12.800
 meetings.

00:43:12.800 --> 00:43:15.760
 We're also developing tools for improved coordination

00:43:15.760 --> 00:43:17.680
 with our franchise utilities.

00:43:17.680 --> 00:43:20.920
 Becky and I are having regular conversations with Atmos.

00:43:20.920 --> 00:43:23.160
 We're looking at what we can do from a city resource

00:43:23.160 --> 00:43:25.400
 perspective to improve those coordinations

00:43:25.400 --> 00:43:28.480
 and have somebody in-house that can help kind of serve

00:43:28.480 --> 00:43:31.920
 as the primary point of contact just so that Atmos knows truly

00:43:31.920 --> 00:43:33.720
 what our priorities are.

00:43:33.720 --> 00:43:36.680
 We're working on getting Atmos an updated list of all

00:43:36.680 --> 00:43:38.640
 of our capital projects just so that they

00:43:38.640 --> 00:43:42.240
 know what the current sequencing is because that sequencing is

00:43:42.240 --> 00:43:45.400
 dynamic and so that they know who they should be contacting

00:43:45.400 --> 00:43:48.200
 should they have questions.

00:43:48.200 --> 00:43:50.880
 I've mentioned several times the construction manager at risk

00:43:50.880 --> 00:43:52.880
 alternative delivery method in addition

00:43:52.880 --> 00:43:55.080
 to the Southeast Denton neighborhood being delivered

00:43:55.080 --> 00:43:56.600
 with construction manager at risk.

00:43:56.600 --> 00:43:59.800
 We're also looking at Ryan Road being

00:43:59.800 --> 00:44:02.600
 delivered with construction manager at risk.

00:44:02.600 --> 00:44:05.400
 And we've got Frisa Nichols on contracts

00:44:05.400 --> 00:44:08.840
 kind of serving as our primary consultant helping us navigate

00:44:08.840 --> 00:44:11.920
 the development of the contract templates

00:44:11.920 --> 00:44:13.800
 and then also getting staff trained

00:44:13.800 --> 00:44:16.360
 on the nuances of the construction manager at risk

00:44:16.360 --> 00:44:20.000
 methodology both from a contracting perspective

00:44:20.000 --> 00:44:22.720
 as well as from a project delivery perspective.

00:44:22.720 --> 00:44:25.880
 So we had a formal kickoff on February 1st.

00:44:25.880 --> 00:44:28.920
 We had an internal training that several cross-departmental

00:44:28.920 --> 00:44:32.560
 representatives attended on April 21st.

00:44:32.560 --> 00:44:35.040
 And we're hopeful that within the month or so

00:44:35.040 --> 00:44:37.440
 we're going to have that contract template finalized.

00:44:37.440 --> 00:44:39.800
 And then as I mentioned, our plan right now

00:44:39.800 --> 00:44:43.600
 is to advertise by the end of the calendar year

00:44:43.600 --> 00:44:47.160
 for construction manager for the Southeast Denton phase 2

00:44:47.160 --> 00:44:47.920
 project.

00:44:47.920 --> 00:44:49.880
 So we're really excited about the progress

00:44:49.880 --> 00:44:51.600
 that we're making there.

00:44:51.600 --> 00:44:53.960
 And then depending on what we decide with Ryan Road,

00:44:53.960 --> 00:44:55.800
 we'd be advertising for Ryan Road

00:44:55.800 --> 00:44:58.600
 should we decide for it to go before Hickory Creek Road phase

00:44:58.600 --> 00:45:00.800
 3 shortly thereafter.

00:45:00.800 --> 00:45:02.960
 The other really exciting and important effort

00:45:02.960 --> 00:45:05.760
 that we've got going on that I wanted to mention for bond

00:45:05.760 --> 00:45:08.920
 committee is we've got an external review of our estimates

00:45:08.920 --> 00:45:09.960
 at completion.

00:45:09.960 --> 00:45:12.640
 And because some of these projects

00:45:12.640 --> 00:45:15.040
 do have some shelf life to them, because we've

00:45:15.040 --> 00:45:17.400
 got some new team members, we're wanting

00:45:17.400 --> 00:45:20.280
 to make sure that we have a third party look at the cost.

00:45:20.280 --> 00:45:22.720
 We know we've got some significant increases

00:45:22.720 --> 00:45:26.600
 in materials that are projected and escalation,

00:45:26.600 --> 00:45:28.240
 just given the economic conditions

00:45:28.240 --> 00:45:29.360
 that we have right now.

00:45:29.360 --> 00:45:31.400
 And so we're wanting to make sure that we're

00:45:31.400 --> 00:45:34.120
 factoring in that escalation appropriately.

00:45:34.120 --> 00:45:36.720
 And so that's something that our team is working closely

00:45:36.720 --> 00:45:39.160
 with the finance team on, making sure

00:45:39.160 --> 00:45:42.480
 that our estimates at completion are as accurate as possible.

00:45:42.480 --> 00:45:45.880
 The firm that we've selected is not only reviewing our projects,

00:45:45.880 --> 00:45:48.920
 they're also training our team on cost estimation best

00:45:48.920 --> 00:45:52.200
 practices, and they're helping us develop templates

00:45:52.200 --> 00:45:54.360
 that we can use for future projects

00:45:54.360 --> 00:45:56.240
 so that we've got that in-house talent.

00:45:56.240 --> 00:45:58.360
 But we do have them on call.

00:45:58.360 --> 00:46:00.640
 And so we're trying to prioritize those projects,

00:46:00.640 --> 00:46:02.680
 particularly those ones that are time sensitive

00:46:02.680 --> 00:46:06.040
 without external funding first.

00:46:06.040 --> 00:46:09.320
 And then we're working through the list of other projects

00:46:09.320 --> 00:46:11.000
 that have not yet gone to construction

00:46:11.000 --> 00:46:13.760
 just to make sure that we have adequate budgets

00:46:13.760 --> 00:46:18.080
 for the full completion of those projects.

00:46:18.080 --> 00:46:20.840
 And not listed on the slide, but just one other note,

00:46:20.840 --> 00:46:23.320
 we are in the process of implementing our project

00:46:23.320 --> 00:46:26.160
 management software system and hope

00:46:26.160 --> 00:46:28.560
 to have that rolled out by the end of the calendar year

00:46:28.560 --> 00:46:29.080
 as well.

00:46:29.080 --> 00:46:31.520
 We're working with the finance department,

00:46:31.520 --> 00:46:34.040
 working with our business services department,

00:46:34.040 --> 00:46:37.360
 and several other utilities as well has been involved in that.

00:46:37.360 --> 00:46:38.760
 And so that's really going to help

00:46:38.760 --> 00:46:42.560
 us have a far more sophisticated way of keeping tabs

00:46:42.560 --> 00:46:45.520
 on the status of our projects, having the financials

00:46:45.520 --> 00:46:47.320
 available in the same location.

00:46:47.320 --> 00:46:49.640
 And so we're really excited about that

00:46:49.640 --> 00:46:52.480
 and hope to be able to show off that new tool to the bond

00:46:52.480 --> 00:46:53.840
 committee at a future meeting.

00:46:53.840 --> 00:46:56.800
 So with that, I'll stop talking and gladly answer

00:46:56.800 --> 00:46:58.080
 any questions that you have.

00:46:58.080 --> 00:47:02.920
 Thanks, Rachel.

00:47:02.920 --> 00:47:04.080
 Great presentation.

00:47:04.080 --> 00:47:09.960
 Did you say who is the cost estimating company you're using?

00:47:09.960 --> 00:47:11.600
 Sure, it's OCMI.

00:47:11.600 --> 00:47:13.360
 They also go by O'Connor.

00:47:13.360 --> 00:47:16.080
 So they do have a Dallas office, but they're actually

00:47:16.080 --> 00:47:19.320
 the firm that does a lot of the estimation for Las Vegas,

00:47:19.320 --> 00:47:23.040
 Nevada, several large cities in California.

00:47:23.040 --> 00:47:24.840
 And then they also do Henderson County.

00:47:24.840 --> 00:47:28.240
 But they are an expanding presence in Texas as well.

00:47:28.240 --> 00:47:31.800
 And they've been using local numbers and local cost

00:47:31.800 --> 00:47:34.280
 estimates as they're preparing the estimates that they've

00:47:34.280 --> 00:47:34.840
 done for us.

00:47:34.840 --> 00:47:37.160
 We've been very impressed with the work that they've done.

00:47:37.160 --> 00:47:39.520
 And they're actually very fast in their review process.

00:47:39.520 --> 00:47:44.680
 I'm doing some construction projects right now.

00:47:44.680 --> 00:47:50.160
 And I had to lock in steel prices just a month ago at risk

00:47:50.160 --> 00:47:54.480
 because if I didn't, I'd have experienced a 20% increase.

00:47:54.480 --> 00:47:57.320
 Is that something we're going to be concerned about in this bond

00:47:57.320 --> 00:48:01.480
 program, especially for 2019, where we based it

00:48:01.480 --> 00:48:04.760
 on these estimates, which we already have inflated,

00:48:04.760 --> 00:48:08.400
 but those inflation factors are pretty much--

00:48:08.400 --> 00:48:12.720
 Yes, that's absolutely why we've got OCMI on board right now.

00:48:12.720 --> 00:48:15.800
 And we're having to have those tough conversations internally

00:48:15.800 --> 00:48:21.320
 right now around how much do we want to budget additionally.

00:48:21.320 --> 00:48:23.880
 And then also talking about the sequencing of our projects.

00:48:23.880 --> 00:48:25.480
 That's something that we're looking at,

00:48:25.480 --> 00:48:28.480
 particularly as we look at Hickory Creek and Ryan Road.

00:48:28.480 --> 00:48:31.760
 What's the cost of pausing one of those projects going to be?

00:48:31.760 --> 00:48:36.440
 And we're looking at 5 and 1/2% potentially per year.

00:48:36.440 --> 00:48:39.480
 And that's probably a conservative estimate.

00:48:39.480 --> 00:48:42.480
 I'd say it's very conservative.

00:48:42.480 --> 00:48:46.440
 Any other questions or comments for Rachel?

00:48:46.440 --> 00:48:48.280
 Eric?

00:48:48.280 --> 00:48:53.280
 Yeah, I guess more a comment/request for the future.

00:48:53.280 --> 00:48:55.680
 I was trying to go through and figure out

00:48:55.680 --> 00:48:59.760
 what the funding and process status was

00:48:59.760 --> 00:49:02.640
 for each of the individual sections of Bonnie Bray.

00:49:02.640 --> 00:49:08.640
 And it seems like the estimates versus the funding buckets

00:49:08.640 --> 00:49:11.560
 combine different segments of that project.

00:49:11.560 --> 00:49:14.200
 So it's very difficult for me to follow.

00:49:14.200 --> 00:49:15.280
 Maybe it's just me.

00:49:15.280 --> 00:49:18.360
 But I guess in the future, if we could just

00:49:18.360 --> 00:49:22.280
 get sort of a more per segment breakdown instead

00:49:22.280 --> 00:49:25.880
 of these lumps of this much money for phases five, six,

00:49:25.880 --> 00:49:30.120
 and seven, and that sort of thing, that would help me.

00:49:30.120 --> 00:49:31.880
 Sure, we can work on that.

00:49:31.880 --> 00:49:34.520
 And that is a various to observation, Eric.

00:49:34.520 --> 00:49:36.640
 And so that's something that we are working on.

00:49:36.640 --> 00:49:38.840
 They are very commingled.

00:49:38.840 --> 00:49:40.840
 But I think that's something that we can find a way

00:49:40.840 --> 00:49:42.880
 to maybe more graphically represent

00:49:42.880 --> 00:49:45.920
 the different funding buckets, the status of the funding,

00:49:45.920 --> 00:49:47.240
 the status of the project.

00:49:47.240 --> 00:49:48.320
 That's something we can certainly

00:49:48.320 --> 00:49:50.120
 work with the project manager and the finance

00:49:50.120 --> 00:49:52.040
 team on for next time.

00:49:52.040 --> 00:49:52.520
 Thanks.

00:49:52.520 --> 00:49:58.320
 Any other questions?

00:49:58.320 --> 00:50:01.880
 OK, Cassie, back to you, ma'am.

00:50:01.880 --> 00:50:02.400
 Thank you.

00:50:02.400 --> 00:50:04.440
 So next up, we have Scott Gray here

00:50:04.440 --> 00:50:06.400
 to talk about the facility projects.

00:50:09.440 --> 00:50:14.040
 Just give him a minute to get up and running.

00:50:14.040 --> 00:50:24.360
 Chair, members of the committee, good afternoon.

00:50:24.360 --> 00:50:27.040
 Scott Gray, director of airport and facilities.

00:50:27.040 --> 00:50:29.480
 And give me just a moment to pull up the presentation.

00:50:39.440 --> 00:50:39.940
 OK.

00:50:39.940 --> 00:50:58.360
 OK, just a couple of projects to update you on.

00:50:58.360 --> 00:51:00.760
 Pleased to be back again to give you

00:51:00.760 --> 00:51:04.240
 the good news on these projects.

00:51:04.240 --> 00:51:07.600
 The first is the 2014 bond proposition number two,

00:51:07.600 --> 00:51:10.040
 which included fire station number

00:51:10.040 --> 00:51:12.640
 three, the construction of the new facility.

00:51:12.640 --> 00:51:14.960
 Plus, as you can see there on the right,

00:51:14.960 --> 00:51:19.280
 and then plus the demolition of the older facility

00:51:19.280 --> 00:51:21.640
 and construction of the new one, which is the artist rendering

00:51:21.640 --> 00:51:23.280
 at the bottom.

00:51:23.280 --> 00:51:27.280
 Happy to inform the group that that station is complete.

00:51:27.280 --> 00:51:30.480
 The fire folks have moved into the new building,

00:51:30.480 --> 00:51:34.240
 are very excited about its layout and usability.

00:51:34.240 --> 00:51:35.600
 So we're pleased with that.

00:51:35.600 --> 00:51:41.120
 We have a few final items to complete on that project

00:51:41.120 --> 00:51:42.600
 to close it out.

00:51:42.600 --> 00:51:44.480
 So probably the next time I'm with you,

00:51:44.480 --> 00:51:46.840
 it will be the last report on that project

00:51:46.840 --> 00:51:48.720
 to finish this one off.

00:51:48.720 --> 00:51:56.200
 And lastly is the 2019 bond project,

00:51:56.200 --> 00:51:58.520
 which I believe I brought to you last month--

00:51:58.520 --> 00:52:00.560
 or excuse me, the last meeting.

00:52:00.560 --> 00:52:04.040
 This was the project for the police headquarters,

00:52:04.040 --> 00:52:07.040
 the substation, and the firing range.

00:52:07.040 --> 00:52:09.640
 Obviously the headquarters in one location and the other two

00:52:09.640 --> 00:52:13.120
 are co-located off Vintage Drive.

00:52:13.120 --> 00:52:14.640
 The notice to proceed on that project

00:52:14.640 --> 00:52:18.760
 was January 15 of this year.

00:52:18.760 --> 00:52:21.480
 It is moving along fairly well.

00:52:21.480 --> 00:52:25.320
 A number of challenges, as is typical with what

00:52:25.320 --> 00:52:27.000
 is called a messy renovation, which

00:52:27.000 --> 00:52:29.400
 is the headquarters building.

00:52:29.400 --> 00:52:32.440
 But nothing that the team hasn't worked through.

00:52:32.440 --> 00:52:35.040
 At this point, the projections for completion

00:52:35.040 --> 00:52:37.120
 is still unchanged.

00:52:37.120 --> 00:52:40.440
 And the budget is still intact with all three

00:52:40.440 --> 00:52:43.120
 of these portions of the projects.

00:52:43.120 --> 00:52:45.880
 To date, there's been about $47.3 million

00:52:45.880 --> 00:52:49.720
 of GOCOs issued from a cash flow perspective

00:52:49.720 --> 00:52:52.200
 to get us through the end of this fiscal year.

00:52:52.200 --> 00:52:54.840
 And then finance will assist us with the rest of the funding

00:52:54.840 --> 00:52:58.160
 to complete our construction needs for all three

00:52:58.160 --> 00:52:58.960
 of these projects.

00:52:58.960 --> 00:53:02.560
 So very short and to the point with two

00:53:02.560 --> 00:53:05.360
 very exciting projects that we're happy to report on.

00:53:05.360 --> 00:53:07.800
 And I'll be happy to answer any questions you may have.

00:53:07.800 --> 00:53:14.400
 Thanks, Scott.

00:53:14.400 --> 00:53:18.040
 Any questions for Scott?

00:53:18.040 --> 00:53:20.040
 All right.

00:53:20.040 --> 00:53:20.520
 Thank you.

00:53:20.520 --> 00:53:25.880
 Cassie, back to you, ma'am.

00:53:25.880 --> 00:53:28.440
 That is all the presentations we have on that item.

00:53:28.440 --> 00:53:33.200
 So we can, if you want to, move on to item C.

00:53:33.200 --> 00:53:33.960
 Sure.

00:53:33.960 --> 00:53:39.040
 So item C, BOC 21-07, receive a report, hold a discussion,

00:53:39.040 --> 00:53:41.840
 give staff direction regarding the reallocation

00:53:41.840 --> 00:53:45.720
 of funds associated with the 2014 bond election.

00:53:45.720 --> 00:53:48.240
 And I'm going to pass it over to our assistant director

00:53:48.240 --> 00:53:49.600
 of finance, Nick Vincent.

00:53:49.600 --> 00:53:52.280
 He's going to do a short presentation for you.

00:53:52.280 --> 00:53:56.000
 And we'll ask for direction on the reallocation request.

00:53:56.000 --> 00:53:57.280
 Good afternoon, bond committee.

00:53:57.280 --> 00:53:59.480
 Let me get the presentation pulled up really quickly.

00:53:59.480 --> 00:54:10.040
 So we are in front of you today to seek approval

00:54:10.040 --> 00:54:13.480
 to reallocate some project dollars that were associated

00:54:13.480 --> 00:54:16.800
 with the 2014 bond proposition.

00:54:16.800 --> 00:54:19.600
 Originally, that proposition is approved by voters,

00:54:19.600 --> 00:54:22.120
 included a transportation facility.

00:54:22.120 --> 00:54:25.440
 Originally had a budget of $1.5 million.

00:54:25.440 --> 00:54:27.800
 This has come forward to the bond committee

00:54:27.800 --> 00:54:32.400
 in 2018 for reallocation based on where that money currently

00:54:32.400 --> 00:54:36.000
 resides, which is the 651 South Mayhill project.

00:54:36.000 --> 00:54:38.240
 Staff is requesting to reallocate that money

00:54:38.240 --> 00:54:41.160
 to another facility owned by the city, which

00:54:41.160 --> 00:54:44.640
 is the service center facility off of Rootdale.

00:54:44.640 --> 00:54:47.240
 So currently, the money we are requesting to reallocate

00:54:47.240 --> 00:54:55.400
 is $1,249,612.07.

00:54:55.400 --> 00:54:56.960
 That's it.

00:54:56.960 --> 00:54:58.960
 I'll answer any questions that you may have.

00:54:58.960 --> 00:55:06.200
 Any questions for Vincent?

00:55:06.200 --> 00:55:07.560
 Pull the screen down really quick.

00:55:07.560 --> 00:55:15.760
 All right.

00:55:15.760 --> 00:55:18.040
 Cassie, do we need a motion and a second on this?

00:55:18.040 --> 00:55:19.880
 Yes, we do need a vote on this one.

00:55:19.880 --> 00:55:25.080
 So I'll take a motion to approve the reallocation.

00:55:25.080 --> 00:55:26.560
 So I'll move.

00:55:26.560 --> 00:55:27.760
 Thank you, Janet.

00:55:27.760 --> 00:55:28.600
 I'll second.

00:55:28.600 --> 00:55:32.840
 Second.

00:55:32.840 --> 00:55:33.360
 Excuse me.

00:55:33.360 --> 00:55:34.040
 Second.

00:55:34.040 --> 00:55:35.360
 Thank you, Randy.

00:55:35.360 --> 00:55:36.360
 Any discussion?

00:55:36.360 --> 00:55:44.840
 Seeing not, all in favor of the motion as presented,

00:55:44.840 --> 00:55:47.240
 please signify by saying aye or raising your hand.

00:55:47.240 --> 00:55:53.320
 Janet, you good with that?

00:55:53.320 --> 00:55:54.200
 Aye.

00:55:54.200 --> 00:55:55.240
 OK.

00:55:55.240 --> 00:55:55.960
 Motion carries.

00:55:55.960 --> 00:56:04.840
 Moving on to the next agenda item, right, Cassie?

00:56:04.840 --> 00:56:07.120
 Yes.

00:56:07.120 --> 00:56:11.600
 DOC 21-008, receive a report, hold discussion,

00:56:11.600 --> 00:56:15.720
 provide information related to 2019 on the election street

00:56:15.720 --> 00:56:19.480
 improvements plan issuance schedule.

00:56:19.480 --> 00:56:21.680
 So I am going to present this item.

00:56:21.680 --> 00:56:24.000
 I have a very short presentation.

00:56:24.000 --> 00:56:27.280
 You already heard Rachel present on kind

00:56:27.280 --> 00:56:32.160
 of moving the sequence of the 2019 bond program segments

00:56:32.160 --> 00:56:34.520
 up, which is why we are asking--

00:56:34.520 --> 00:56:37.400
 or we just wanted to give you an update of the bond timeline.

00:56:37.400 --> 00:56:41.040
 So let me share my screen, and we will get started.

00:56:41.040 --> 00:56:51.960
 So as Rachel mentioned, they have

00:56:51.960 --> 00:56:56.680
 begun on two different segments--

00:56:56.680 --> 00:57:02.120
 well, not segments, the packages of the 2019 bond program.

00:57:02.120 --> 00:57:04.120
 The contracts were approved April 27,

00:57:04.120 --> 00:57:07.720
 and so they're estimated to begin construction

00:57:07.720 --> 00:57:09.160
 beginning in June.

00:57:09.160 --> 00:57:13.720
 And so with that, they're going to need additional funding.

00:57:13.720 --> 00:57:18.840
 We had planned to fund those projects next year,

00:57:18.840 --> 00:57:21.320
 but we will be funding them this year instead.

00:57:21.320 --> 00:57:24.840
 And then Hickory Creek Road, phase three.

00:57:24.840 --> 00:57:28.840
 So you heard her talk about the connection between Hickory

00:57:28.840 --> 00:57:31.840
 Creek and Ryan Road.

00:57:31.840 --> 00:57:35.080
 We're still waiting on the final review,

00:57:35.080 --> 00:57:37.160
 but we want to have the money just

00:57:37.160 --> 00:57:40.640
 in case this project needs to get kickstarted this year.

00:57:40.640 --> 00:57:43.560
 And so we adjusted the bond timeline accordingly.

00:57:43.560 --> 00:57:50.880
 And so you can see the top part of the slide

00:57:50.880 --> 00:57:54.840
 shows the original bond issuance timeline,

00:57:54.840 --> 00:57:58.200
 and the highlighted portions on the bottom show the adjustment.

00:57:58.200 --> 00:58:04.040
 Basically, we've moved up some funding from next year's bond

00:58:04.040 --> 00:58:07.320
 issuance to this year to be able to start some of those projects

00:58:07.320 --> 00:58:10.640
 earlier than what we initially planned.

00:58:10.640 --> 00:58:14.680
 And it's a total of $4.3 million is

00:58:14.680 --> 00:58:18.920
 what we moved up from next year, and that's $2.3 million

00:58:18.920 --> 00:58:21.720
 for the street reconstruction and $2 million

00:58:21.720 --> 00:58:25.640
 for Hickory Creek Road.

00:58:25.640 --> 00:58:30.640
 If we do go back to council for our bond parameters ordinance,

00:58:30.640 --> 00:58:34.440
 June 8th, and if we do have the information from TxDOT

00:58:34.440 --> 00:58:36.760
 at that time about Hickory Creek,

00:58:36.760 --> 00:58:40.480
 the final determination, we will adjust the timeline accordingly.

00:58:40.480 --> 00:58:43.400
 But this is our tentative plan as of right now.

00:58:43.400 --> 00:58:45.400
 So just wanted to give the committee an update.

00:58:49.000 --> 00:58:52.120
 OK, thank you.

00:58:52.120 --> 00:58:55.880
 All right, any other questions or comments for Cassie

00:58:55.880 --> 00:58:57.400
 or anyone else on the call?

00:58:57.400 --> 00:59:03.920
 All right, seeing none, I guess we can adjourn.