WEBVTT

00:00:00.000 --> 00:00:12.020
 Good afternoon. I'm Pat Smith. I'm chair of the Bond Oversight Committee for the City

00:00:12.020 --> 00:00:20.480
 of Denton. We're convening today, Thursday, February 4th, 2021 at 12 p.m. in a hybrid

00:00:20.480 --> 00:00:28.820
 session in the council workroom as well as via Zoom. We have quorum present and so our

00:00:28.820 --> 00:00:38.140
 first agenda item will be to consider approval of the meeting minutes of November 5th, 2020.

00:00:38.140 --> 00:00:42.560
 Do I have a motion to consider the approval of those minutes?

00:00:42.560 --> 00:00:45.900
 I moved. Thank you, Tim.

00:00:45.900 --> 00:00:50.560
 Is there a second out there? I'll second it.

00:00:50.560 --> 00:01:00.480
 Thank you, Randy. Any discussion? All right. Seeing none, discussion. All those in favor

00:01:00.480 --> 00:01:04.800
 of approving the minutes as presented, please signify by raising your hand.

00:01:04.800 --> 00:01:11.700
 Aye. Or by voice in it. Thank you, Janet.

00:01:11.700 --> 00:01:19.220
 Motion carries. We'll move on to item B, receive a report, hold a discussion, give staff direction

00:01:19.220 --> 00:01:27.540
 regarding general obligation funded capital projects. And I'll turn it over to you, Cassie.

00:01:27.540 --> 00:01:33.520
 Yes. Thank you. So in your backup, you'll see the GEO funded projects report, which

00:01:33.520 --> 00:01:40.580
 we bring every meeting. You'll have a presentation from parks, capital projects, and facilities

00:01:40.580 --> 00:01:45.860
 on the update of their projects. And then there's also a bond issuance timeline in your

00:01:45.860 --> 00:01:52.260
 backup, which we will actually discuss during item D. And so with that, I will turn it over

00:01:52.260 --> 00:02:05.020
 to Gary to give you a parks update. Thank you, Cassie. Let me bring this up.

00:02:05.020 --> 00:02:15.820
 Okay. Can you guys see that? Yes. Okay. Gary Pack and Director of Parks and Recreation.

00:02:15.820 --> 00:02:22.420
 We also have Drew Huffman, Assistant Director, and Heather Gray, our business manager, on

00:02:22.420 --> 00:02:31.220
 the call as well. So they may chime in as we move along. So sorry, wrong one. Got the

00:02:31.220 --> 00:02:59.380
 reallocation PowerPoint. Okay. Okay. Okay. Okay. Okay. Okay. Okay. Okay. Okay. Okay.

00:02:59.380 --> 00:03:15.540
 Okay. Sorry about that. All right. Gary Pack and Parks and Recreation. So go ahead and

00:03:15.540 --> 00:03:23.240
 get started on this slide. Okay. Proposition 4, 2014 bond program. We've been working diligently

00:03:23.240 --> 00:03:29.900
 to wrap up all of the projects. We've been very aggressive in playground replacements.

00:03:29.900 --> 00:03:35.860
 As per the bond election, we completed all of the projects. And in addition to we were

00:03:35.860 --> 00:03:41.580
 able to add Joe Skiles to that funding source and gives us an opportunity to replace that

00:03:41.580 --> 00:03:49.740
 playground as well. And with that, we still have $177,000 remaining in that account. We're

00:03:49.740 --> 00:03:55.380
 going to have a request later on in the meeting to reallocate that balance to the tennis court

00:03:55.380 --> 00:04:04.180
 project at the North Lakes Tennis Center. The Lake Forest and Milam Park project, this

00:04:04.180 --> 00:04:12.580
 has already been completed and been in use for a year or two. So that is done and in

00:04:12.580 --> 00:04:20.900
 use for the public. South Lakes Tennis Courts, per the bid package or the bond package, we

00:04:20.900 --> 00:04:27.540
 had two new courts with lights. The existing courts do not have lights. So what we're looking

00:04:27.540 --> 00:04:34.620
 to do is complete the package as requested with two courts and lights and then the possibility

00:04:34.620 --> 00:04:39.900
 of adding additional lights to that court, the existing court, and then resurface it

00:04:39.900 --> 00:04:45.620
 as well. So everything would be kind of up to the same standard. We do have to work through

00:04:45.620 --> 00:04:51.580
 some logistics in regards to the electric capabilities in the panel. So that's working

00:04:51.580 --> 00:04:58.940
 through that right now. We did have some estimates come through and we had to adjust our projected

00:04:58.940 --> 00:05:06.420
 costs and that's at $450,000. The timeline completion is this fall, approximately September

00:05:06.420 --> 00:05:13.960
 of 2021. Property acquisition, a lot of development

00:05:13.960 --> 00:05:20.680
 activity throughout the city, even during COVID. We've been looking at a number of parcels.

00:05:20.680 --> 00:05:26.780
 This funding was kind of geared towards South Denton. So we have been looking at a handful

00:05:26.780 --> 00:05:34.620
 of property for acquisition for the park system, as well as locations where a library could

00:05:34.620 --> 00:05:42.260
 be placed, whether it was a new library or the South Library being relocated. So we've

00:05:42.260 --> 00:05:47.700
 been actively pursuing that in tandem with our real estate division and providing City

00:05:47.700 --> 00:05:58.780
 Council periodic updates. Southwest Park Design, this is very active

00:05:58.780 --> 00:06:05.140
 at this point in time, with an anticipation of it being completed in April or so, early

00:06:05.140 --> 00:06:12.260
 spring. We did have a focus group created to help us guide through this process, a cross

00:06:12.260 --> 00:06:19.420
 section of the community. We have a consultant on board that has given us three renderings.

00:06:19.420 --> 00:06:24.740
 We shared those renderings with the focus group and they went back and took all that

00:06:24.740 --> 00:06:30.460
 information and narrowed it down to one concept. We're going to be meeting with the focus group

00:06:30.460 --> 00:06:35.280
 again and then eventually presenting to the park board in the near future to get some

00:06:35.280 --> 00:06:40.100
 feedback from them as well and then eventually take and get the City Council for feedback.

00:06:40.100 --> 00:06:44.860
 And we'll have a public meeting sprinkled in there as well.

00:06:44.860 --> 00:06:51.260
 There is no funding for the construction of this. It is a long-term project and most likely

00:06:51.260 --> 00:06:58.900
 we need to be phased, assuming Bond Initiative would fund that construction effort. We do

00:06:58.900 --> 00:07:05.660
 have a balance, a significant balance of over $800,000 in that account that we're going

00:07:05.660 --> 00:07:12.920
 to request to be relocated to the tennis center as well.

00:07:12.920 --> 00:07:18.060
 Spray Brown was completed and open. It did not open last year. We are hoping that we

00:07:18.060 --> 00:07:25.140
 will have that facility open this spring and look forward to post COVID activities within

00:07:25.140 --> 00:07:28.980
 our parks.

00:07:28.980 --> 00:07:34.420
 Our trail system expansion, this project has been completed as well. This is North Lakes.

00:07:34.420 --> 00:07:42.640
 It goes all the way up to North Point Park and then proceeds east. This has been a great

00:07:42.640 --> 00:07:47.500
 addition to our trail system. It is a major opportunity and a connection point to the

00:07:47.500 --> 00:07:53.780
 Cooper Creek trail that we have proposed in our trail system master plan that has over

00:07:53.780 --> 00:08:01.180
 215 miles of trails proposed long-term for the city that's going to be in our parks recreation

00:08:01.180 --> 00:08:06.580
 and trail system master plan.

00:08:06.580 --> 00:08:11.500
 Tennis center construction, this is broken out into two separate phases. Originally we

00:08:11.500 --> 00:08:18.540
 went out to bid for the tennis center pro shop itself and ALH to be possibly bid together

00:08:18.540 --> 00:08:23.340
 with the same contractor and when we got the bids back it was actually cheaper to split

00:08:23.340 --> 00:08:29.340
 them up with two separate contractors. The contractor that did get the tennis center

00:08:29.340 --> 00:08:36.780
 pro shop was fantastic. They completed a few months ahead of schedule. So the tennis center

00:08:36.780 --> 00:08:41.660
 project, the pro shop is completed and done. If you're interested in a tour, we'd love

00:08:41.660 --> 00:08:46.060
 to take you over there and show it to you. So that was supposed to be done in October

00:08:46.060 --> 00:08:53.100
 and was actually done in January and it was done in October.

00:08:53.100 --> 00:08:58.980
 Phase two is the actual flat work. We've had a few permitting challenges and some design

00:08:58.980 --> 00:09:03.140
 challenges we had to change. We had to move the road and eventually we're going to have

00:09:03.140 --> 00:09:10.740
 to pave the entry into the airfield, the gravel driveway into the airfield parking lot and

00:09:10.740 --> 00:09:15.700
 then we had some drainage obstacles we had to work through. So that's getting close to

00:09:15.700 --> 00:09:21.860
 being finalized and that should be out to bid hopefully in the near future and timeline

00:09:21.860 --> 00:09:25.300
 of that has been pushed to March of 2022.

00:09:25.300 --> 00:09:34.180
 Gary, is that completed or to start construction? That's completed.

00:09:34.180 --> 00:09:40.560
 We did get a $40,000 grant from USDA so that should help out. With paving of the road and

00:09:40.560 --> 00:09:47.100
 some of the design changes we had to do, we anticipated the cost being a little bit more.

00:09:47.100 --> 00:09:50.460
 So that was the reason why we're asking for some of the balances that the other projects

00:09:50.460 --> 00:09:55.700
 that have been completed to be transferred to this just in case we need it.

00:09:55.700 --> 00:10:00.340
 Waterworks parts addition, this was completed and open. Obviously again, we didn't open

00:10:00.340 --> 00:10:07.740
 last year. We are planning to open this summer with staffing needs. It takes us a few months

00:10:07.740 --> 00:10:12.660
 to get ramped up. So we're planning as if we are opening and if something changes then

00:10:12.660 --> 00:10:18.700
 we'll shift gears as needed.

00:10:18.700 --> 00:10:25.700
 Bella Athletic Complex, this is completed. There's two small things that we're finalizing

00:10:25.700 --> 00:10:31.700
 and that is the addition of a sculpture, the Bella Trophy. I think we shared this with

00:10:31.700 --> 00:10:39.140
 you at our last meeting. This is set to be completed this coming summer. Obviously Dr.

00:10:39.140 --> 00:10:44.020
 Bella passed away recently and we're sad that he's not going to be able to see this but

00:10:44.020 --> 00:10:50.700
 we did share this design with Bella family earlier this summer. So we're looking forward

00:10:50.700 --> 00:10:55.100
 to having a dedication this summer for the trophy itself and then we're installing two

00:10:55.100 --> 00:11:01.720
 plaques that will be placed on the entryway here that you can see in the photo that will

00:11:01.720 --> 00:11:07.620
 talk about who Dr. Bella was and just a little bit about the project.

00:11:07.620 --> 00:11:17.300
 Hey Gary, I'm in leadership North Texas and we had a presentation last week on rugby leagues

00:11:17.300 --> 00:11:22.060
 and we're getting a professional rugby team in the Dallas-Fort Worth area and they're

00:11:22.060 --> 00:11:29.180
 looking for tournament areas and their point was if you got a soccer field we can play

00:11:29.180 --> 00:11:34.500
 rugby on it but we can't play rugby on a football field. Is that something we'd ever consider

00:11:34.500 --> 00:11:35.500
 doing?

00:11:35.500 --> 00:11:41.540
 Gary, I can chime into that. So we do have a local rugby group and we do have rugby goals

00:11:41.540 --> 00:11:46.340
 on one of the fields right now at Bella for that purpose.

00:11:46.340 --> 00:11:47.340
 Okay.

00:11:47.340 --> 00:11:52.300
 They do use those fields and we have had discussions with the rugby groups in the area about putting

00:11:52.300 --> 00:11:57.940
 more goals out at Bella to host some of those rugby tournaments. So yes.

00:11:57.940 --> 00:12:02.860
 Okay, great.

00:12:02.860 --> 00:12:06.820
 Then there's an image of what it will look like when it's installed. We are going to

00:12:06.820 --> 00:12:11.500
 put some planners around the base of that just to kind of spruce it up a little bit

00:12:11.500 --> 00:12:19.660
 and soften it but that's what it will look like later this summer.

00:12:19.660 --> 00:12:24.140
 And there's the entry point looking at it.

00:12:24.140 --> 00:12:29.220
 Lake Forest Park, this is a project that Drew has been working on in cooperation with our

00:12:29.220 --> 00:12:37.820
 engineering team. We've done a number of studies in regards to the lake itself and the spillway

00:12:37.820 --> 00:12:43.460
 and we're going to be making improvements to the dam, reopening the trail and dredging

00:12:43.460 --> 00:12:49.220
 the actual lake. We have received bids. We're going to be going to council here in the real

00:12:49.220 --> 00:12:54.220
 near future either end of February or early March with a completion date of tentatively

00:12:54.220 --> 00:13:02.680
 12 months. So we'll see how that works out. Drew, you want to mention how many tons of

00:13:02.680 --> 00:13:05.180
 silt will be moved from there?

00:13:05.180 --> 00:13:13.020
 This is approximately 63,000 tons of material, so 45,000 yards of silt debris will be taken

00:13:13.020 --> 00:13:19.300
 out of the pond during that construction.

00:13:19.300 --> 00:13:26.140
 So this is a project that Samaritan has been really excited to see moving forward. We've

00:13:26.140 --> 00:13:30.440
 had Drew's met with them a number of times communicating on timelines and the project

00:13:30.440 --> 00:13:36.460
 status and that I'm sure they'll be very excited to see the lake getting dredged sooner than

00:13:36.460 --> 00:13:37.460
 later.

00:13:37.460 --> 00:13:42.660
 Gary and Drew, you guys had to get a permit from the Corps of Engineers to do this, right?

00:13:42.660 --> 00:13:46.100
 Yes, there are lots of different permits from the Corps of Engineers. We worked through

00:13:46.100 --> 00:13:50.620
 that process for the last year. We have all our permits. Everything's good to go. We're

00:13:50.620 --> 00:13:52.760
 ready for construction.

00:13:52.760 --> 00:13:55.220
 Great. Congratulations.

00:13:55.220 --> 00:14:00.260
 Thank you.

00:14:00.260 --> 00:14:06.100
 And that's it for Parks and Recreation. Any questions about any of the projects?

00:14:06.100 --> 00:14:12.300
 I have just two, Gary. One is you mentioned the tours of the Tennis Center. I know some

00:14:12.300 --> 00:14:17.660
 folks who would probably love to do that. What should we do to make that happen?

00:14:17.660 --> 00:14:24.940
 Tim, if you just want to email me a convenient time and we could set something up and take

00:14:24.940 --> 00:14:26.700
 you over there for sure.

00:14:26.700 --> 00:14:33.500
 Okay. Okay. And then my other question is more just tongue in tweak, but a million dollars

00:14:33.500 --> 00:14:37.680
 for land acquisition. How far does that go?

00:14:37.680 --> 00:14:45.260
 Right now, not very. We've been fortunate. We do have $5 million from the 2019 bond program

00:14:45.260 --> 00:14:52.940
 that has not been sold. It's scheduled to be sold in '21, '22 and I'm sorry, '21, '22

00:14:52.940 --> 00:14:57.660
 and then '23, '24 as of right now. We are looking at a number of parcels throughout

00:14:57.660 --> 00:15:04.620
 the city with the amount of development that's going on. So with, we don't want to lose opportunities,

00:15:04.620 --> 00:15:09.660
 especially on some of the larger lots throughout the city. So we've master planned where we

00:15:09.660 --> 00:15:15.340
 think we need city parks, neighborhood parks and linear parks as well. So we're working

00:15:15.340 --> 00:15:21.440
 on a number of initiatives, whether it's an outright purchase or it's a partnership with

00:15:21.440 --> 00:15:25.660
 our local developers through our parkland dedication and development ordinance where

00:15:25.660 --> 00:15:31.020
 we can get land through that process as well. So we have a number of balls in the air in

00:15:31.020 --> 00:15:37.180
 regards to that effort to try to conserve open space as well as identify active space

00:15:37.180 --> 00:15:43.460
 for the community, not necessarily now, but maybe 20 years from now as well.

00:15:43.460 --> 00:15:54.220
 Thank you, Gary. Gary, one question on the tennis center flatwork.

00:15:54.220 --> 00:15:58.460
 Maybe that rendering wasn't 100% up to date. I'm not sure, but I remember you had brought

00:15:58.460 --> 00:16:06.540
 us back the information of having to pave that access road in there. And at the time,

00:16:06.540 --> 00:16:13.360
 I think the Hinkle reconstruction and resurfacing was still going on and now that's completed.

00:16:13.360 --> 00:16:20.740
 Are there plans to tie in that trail that runs along the west border of that facility

00:16:20.740 --> 00:16:25.900
 into the Hinkle protected bike lane there? I didn't see any curb ramp or anything in

00:16:25.900 --> 00:16:35.780
 that rendering so far. Let me bring it back up.

00:16:35.780 --> 00:16:45.780
 Okay. Are you talking about right here on the south side?

00:16:45.780 --> 00:16:52.500
 Yeah, on that southwest corner, if you go south from the western on the left side, right

00:16:52.500 --> 00:16:57.340
 there, just below your mouse is the Hinkle protected bike lane.

00:16:57.340 --> 00:17:04.580
 Right. We can look at, I don't know, there's stop signs here where you could cross to get

00:17:04.580 --> 00:17:10.140
 on that bike lane hitting south on Hinkle, but we can work with traffic and see how we

00:17:10.140 --> 00:17:19.380
 can make sure that that's identified and marked. Yeah, just trying to think of do it once instead

00:17:19.380 --> 00:17:23.740
 of twice, if you will. The one thing that you don't see here, and

00:17:23.740 --> 00:17:28.740
 it's not a part of a bond project, is we are planning, doing some master planning for Bowling

00:17:28.740 --> 00:17:37.100
 Green Park, which ties into North Lakes to put some additional trail that would go north

00:17:37.100 --> 00:17:43.740
 and Bowling Green and connect to the southern side of Windsor. And then we do have a design

00:17:43.740 --> 00:17:50.700
 to run that sidewalk east west over to North Lakes and tie into the fireside development.

00:17:50.700 --> 00:17:54.940
 So that would be a southern side trail that it's obviously not depicted on this that we're

00:17:54.940 --> 00:17:58.180
 also working on. Okay, thanks.

00:17:58.180 --> 00:18:06.620
 You're welcome. Any other questions for parks?

00:18:06.620 --> 00:18:14.900
 Okay. So do we need to, will we talk about the change later or now?

00:18:14.900 --> 00:18:24.100
 The appropriations will be in a separate PowerPoint after the presentation.

00:18:24.100 --> 00:18:32.740
 The reallocation request will be item C on your agenda.

00:18:32.740 --> 00:18:38.180
 And next we're going to have Becky DeViney, our director of capital projects and city

00:18:38.180 --> 00:18:44.740
 engineer present on the status of the capital projects.

00:18:44.740 --> 00:18:49.620
 And just a quick reminder, if we can have everyone mute their microphones, we're getting

00:18:49.620 --> 00:18:59.660
 some feedback. Good afternoon, Becky DeViney, city engineer,

00:18:59.660 --> 00:19:04.940
 director of capital projects. Today, I have on the phone with me, deputy

00:19:04.940 --> 00:19:11.020
 director, Rachel Wood, who is the deputy director of capital projects. And then I also have

00:19:11.020 --> 00:19:18.340
 our deputy director of operations, Danny Kramer, who is over streets, drainage and traffic.

00:19:18.340 --> 00:19:38.700
 So with that, let me get the presentation. Hey, Nick, let me back out.

00:19:38.700 --> 00:19:56.140
 I might not have shared correctly. Hold on. I need to share first.

00:19:56.140 --> 00:20:12.860
 All right. Everybody seeing it? Can you see the presentation?

00:20:12.860 --> 00:20:16.060
 Yes. All right. Fantastic. It looks a little different

00:20:16.060 --> 00:20:21.100
 on my end. So sorry about that. All right. So let's move forward the bond

00:20:21.100 --> 00:20:25.780
 committee capital project overview for the capital projects division.

00:20:25.780 --> 00:20:30.140
 I'm going to turn this slide over to Cassie and let her go through this slide, and then

00:20:30.140 --> 00:20:33.860
 I will go through the rest of the presentation for you.

00:20:33.860 --> 00:20:41.860
 Thanks, Becky. We presented this slide last meeting, and we did include the COs that were

00:20:41.860 --> 00:20:48.980
 scheduled for issuance this year, the 8.9. Those are included in the left chart for 2014

00:20:48.980 --> 00:20:52.580
 and '12 bond programs. And just a reminder, this chart is only showing

00:20:52.580 --> 00:20:57.700
 the street improvement portion of the bonds, and it's related to the funding completion.

00:20:57.700 --> 00:21:04.500
 So where we're at on the funding component. So the '12 and '14, we've lumped together

00:21:04.500 --> 00:21:09.020
 between GOs and COs. You can see what's been approved and issued

00:21:09.020 --> 00:21:12.940
 to date, and then how much has been completed as far as funding.

00:21:12.940 --> 00:21:16.900
 And then the 2019 bond program, obviously, we've just started, so we have quite a bit

00:21:16.900 --> 00:21:20.900
 remaining to issue. So if you have any questions, happy to answer

00:21:20.900 --> 00:21:29.260
 them now or at the end of the presentation. All right, Becky, I'll turn it back over to

00:21:29.260 --> 00:21:32.100
 you. Awesome. Thank you, Cassie.

00:21:32.100 --> 00:21:37.540
 So the first thing I wanted to do is go through the update on the 2014 bond proposition one

00:21:37.540 --> 00:21:40.780
 projects. I'm going to focus in on any of the projects

00:21:40.780 --> 00:21:47.220
 that you see, the yellow dot or the red dot. The first project that I will discuss is the

00:21:47.220 --> 00:21:53.300
 Bonnebrae Phase 4B. Currently, we have the schedule shown as yellow, really due to the

00:21:53.300 --> 00:21:58.500
 fact that we're working with external resources for funding, which is the reason why you see

00:21:58.500 --> 00:22:02.740
 the budget shown in red. Due to the fact that we're working through

00:22:02.740 --> 00:22:08.660
 that construction funding piece, obviously, that makes it very difficult to plan the anticipated

00:22:08.660 --> 00:22:13.460
 schedule. And so until we have that funding in our hands,

00:22:13.460 --> 00:22:18.420
 we're going to continue to work through that and work with our partners at Cog. So that's

00:22:18.420 --> 00:22:22.220
 a project that we're working through moving forward on the funding piece and hoping to

00:22:22.220 --> 00:22:26.940
 give an update on that at the next committee meeting with positive news.

00:22:26.940 --> 00:22:31.940
 The next project that you see is the Hickory Street project. We have that project shown

00:22:31.940 --> 00:22:38.340
 yellow simply because we're currently working through with Atmos on some issues that have

00:22:38.340 --> 00:22:42.940
 come up throughout the project. Some Atmos gas lines needed to be relocated

00:22:42.940 --> 00:22:46.820
 as a part of that project. We have been meeting with them on a very regular

00:22:46.820 --> 00:22:51.660
 basis and coordinating with them, but it's taking a little bit longer than we had originally

00:22:51.660 --> 00:22:55.540
 anticipated. So just wanted to let you know we're of hopes

00:22:55.540 --> 00:23:00.620
 that they're going to have some of that completed even as early as this week on one of the phases

00:23:00.620 --> 00:23:05.500
 of the project so that we can move forward. So we're really excited to see that collaboration

00:23:05.500 --> 00:23:11.020
 with Atmos and we're working really strong with them to help them complete that portion

00:23:11.020 --> 00:23:15.500
 of their project through their contractor and our coordination efforts.

00:23:15.500 --> 00:23:20.900
 The next project I'll highlight is the Moore Street project which is from loop 288 to Mayhill.

00:23:20.900 --> 00:23:26.540
 You see yellow on scope, schedule and budget. The reason for that is we're looking to define

00:23:26.540 --> 00:23:32.020
 the overall scope of the project. We're also looking to see how that overall

00:23:32.020 --> 00:23:36.980
 scope will then ultimately impact the schedule and then give us a good idea of what the budget

00:23:36.980 --> 00:23:41.900
 is going to need to be in order to complete that entire project.

00:23:41.900 --> 00:23:48.520
 There's several things that are being looked at in that area and we understand from Kimberly

00:23:48.520 --> 00:23:54.860
 over to Mayhill, we're looking to keep that cross section similar except for adding our

00:23:54.860 --> 00:24:00.380
 right tour lane at Mayhill and then from Kimberly back to the west at loop 288 and we're looking

00:24:00.380 --> 00:24:06.300
 at how we can either reconstruct or do some resurfacing to that roadway and so we're working

00:24:06.300 --> 00:24:12.660
 through a scoping effort on that project which then will ultimately impact and give us some

00:24:12.660 --> 00:24:17.180
 great path forward on the schedule and the budget.

00:24:17.180 --> 00:24:23.420
 The next project you see with the yellow and red is the Roodale extension at Mingo.

00:24:23.420 --> 00:24:27.300
 This is really a project that's been kind of an exciting effort that we've been taking

00:24:27.300 --> 00:24:34.100
 forward with TWU and we've been meeting with them monthly and collaborating on really looking

00:24:34.100 --> 00:24:39.180
 at this project from a holistic perspective of all things that are happening in the TWU

00:24:39.180 --> 00:24:40.380
 area.

00:24:40.380 --> 00:24:47.100
 We are calling it kind of that TWU area program and because of that it's allowing us the opportunity

00:24:47.100 --> 00:24:51.700
 to not only see what's happening from Gary's perspective with parks, what projects water

00:24:51.700 --> 00:24:58.020
 and wastewater might have that need to be replaced in that area, also roadway improvements,

00:24:58.020 --> 00:25:03.300
 there's some quiet zones that are a part of that, possibly some DME relocations and then

00:25:03.300 --> 00:25:08.380
 some interesting things that we're working through on Bell as far as some temporary or

00:25:08.380 --> 00:25:11.340
 possibly permanent roundabouts in that area.

00:25:11.340 --> 00:25:15.300
 So we're really excited about this new way of kind of looking at it from a holistic approach

00:25:15.300 --> 00:25:20.740
 so that we're constructing in a matter that makes sense and really phasing that project

00:25:20.740 --> 00:25:22.900
 out.

00:25:22.900 --> 00:25:26.460
 Currently you see the scope as yellow simply because we're working to define that scope

00:25:26.460 --> 00:25:28.580
 into phases like I mentioned.

00:25:28.580 --> 00:25:33.140
 The schedule is dependent upon the scoping and at this point all of the things that really

00:25:33.140 --> 00:25:39.020
 need to happen in that area currently do not have complete funding based on the overall

00:25:39.020 --> 00:25:41.660
 holistic scope for that area.

00:25:41.660 --> 00:25:47.220
 I'm going to move to the next 2014 bond.

00:25:47.220 --> 00:25:48.220
 I'm sorry.

00:25:48.220 --> 00:25:49.220
 Was there a question?

00:25:49.220 --> 00:25:50.220
 Yeah.

00:25:50.220 --> 00:25:55.300
 Would that funding for the Rodel extension, would that have to slip into another bond

00:25:55.300 --> 00:26:00.380
 program or what do you see as the way ahead on that?

00:26:00.380 --> 00:26:04.860
 We're actually working on that overall scope to look at a phasing and then the constructability

00:26:04.860 --> 00:26:11.460
 that actually will work through what timeframe of which would make sense.

00:26:11.460 --> 00:26:18.320
 There may be some portions of it that we'll look at for using actually external resources.

00:26:18.320 --> 00:26:22.060
 There could always be the possibility that some of that might come back as an additional

00:26:22.060 --> 00:26:27.540
 bond program in the future, but right now we're trying to focus in on what the original project

00:26:27.540 --> 00:26:28.540
 was.

00:26:28.540 --> 00:26:33.580
 There are some utility components that utility is looking to fund, but really at this point

00:26:33.580 --> 00:26:37.780
 we're trying to focus in on what's the best way to execute that project from a phasing

00:26:37.780 --> 00:26:43.660
 perspective which ultimately will give us that overall ballpark figure of the entire

00:26:43.660 --> 00:26:48.780
 budget that's needed to do everything in that area and then we can look into that phasing

00:26:48.780 --> 00:26:49.780
 approach.

00:26:49.780 --> 00:26:55.020
 At this time there's several different ways to look at that option and we don't have that

00:26:55.020 --> 00:27:00.340
 answer completely defined as we look at this from a more holistic approach.

00:27:00.340 --> 00:27:05.380
 Did that answer your question, sir?

00:27:05.380 --> 00:27:10.940
 Yeah, for now.

00:27:10.940 --> 00:27:11.940
 Okay.

00:27:11.940 --> 00:27:18.780
 So 2014 bond proposition three, the only project really that we have to report on for this

00:27:18.780 --> 00:27:23.020
 proposition is that downtown storm sewer trunk line phase two.

00:27:23.020 --> 00:27:27.780
 I'm sure if you've driven along McKinney Street, you can see that downtown storm sewer trunk

00:27:27.780 --> 00:27:33.140
 line phase one is actively under construction, so we're very excited about that.

00:27:33.140 --> 00:27:40.180
 The downtown storm sewer trunk line phase two, really from the schedule and the budget

00:27:40.180 --> 00:27:45.900
 perspective, the schedule's on yellow simply because it's directly impacted on that additional

00:27:45.900 --> 00:27:47.900
 construction funding that's needed.

00:27:47.900 --> 00:27:52.300
 Currently there's insufficient funding to complete that project in the order of about

00:27:52.300 --> 00:27:58.380
 $2 million, and so we're working through some funding opportunities and how we're going

00:27:58.380 --> 00:28:05.280
 to execute that project.

00:28:05.280 --> 00:28:11.500
 So the next project that we'd like to talk about is the street construction 2012 and

00:28:11.500 --> 00:28:18.180
 2014 bond program, and as Cassie mentioned, she kind of walked through with you the overall

00:28:18.180 --> 00:28:21.860
 funding for this program in particular.

00:28:21.860 --> 00:28:28.500
 What we've tried to do today is walk through with you and explain to you kind of the approach

00:28:28.500 --> 00:28:32.980
 of what it's going to take to be able to get the bond program completed.

00:28:32.980 --> 00:28:38.460
 As you can see, we've broken it down into quarters of this current calendar year and

00:28:38.460 --> 00:28:43.620
 next calendar year, and what it's going to take for the total remaining segments to be

00:28:43.620 --> 00:28:47.620
 completed along with the projected segments completed.

00:28:47.620 --> 00:28:53.380
 And so really our overall goal with explaining this is to let you know that we have been

00:28:53.380 --> 00:28:59.540
 working on getting projects out the door, and several of those have already come forward

00:28:59.540 --> 00:29:00.660
 to counsel.

00:29:00.660 --> 00:29:06.380
 There will be more that will be coming forward in the near future, and our anticipation at

00:29:06.380 --> 00:29:14.060
 this point is to have the entire '12 and '14 bond program completed by the end of '22,

00:29:14.060 --> 00:29:19.620
 minus we're really working through, there's seven segments in particular that are currently

00:29:19.620 --> 00:29:23.380
 being programmed, and we're working through really those completion dates.

00:29:23.380 --> 00:29:28.460
 And let me explain that to you because I think that deserves some explanation.

00:29:28.460 --> 00:29:32.700
 So there are two segments that were a part of the original bond program that were on

00:29:32.700 --> 00:29:34.860
 Mulberry Street.

00:29:34.860 --> 00:29:39.940
 Mulberry Street is planned to be a part of the PEC for phase three and four project,

00:29:39.940 --> 00:29:45.220
 and so we want to make sure that we're coordinating that large drainage and utility project in

00:29:45.220 --> 00:29:49.580
 that area, and we don't replace a roadway that's ultimately going to be torn up as part

00:29:49.580 --> 00:29:51.420
 of that PEC four.

00:29:51.420 --> 00:29:57.020
 There's also two segments along Trinity Road, and we're currently coordinating with Textod.

00:29:57.020 --> 00:30:01.780
 Textod is actually doing a Trinity Bridge project in that area, and so we're waiting

00:30:01.780 --> 00:30:06.500
 on those segments to be completed until that bridge project is completed.

00:30:06.500 --> 00:30:10.860
 And then there's three segments that are along Westgate Drive.

00:30:10.860 --> 00:30:15.060
 We're working through that coordination effort with Bronco Way.

00:30:15.060 --> 00:30:19.540
 Right now, Westgate really is kind of a dead end as you travel north.

00:30:19.540 --> 00:30:25.460
 There's no way for residents to go north and connect to the roadway that's due south of

00:30:25.460 --> 00:30:27.260
 the outlet mall.

00:30:27.260 --> 00:30:32.060
 And so the project that needs to happen there includes some utility work that needs to be

00:30:32.060 --> 00:30:37.040
 completed along with some drainage work, and then, of course, ultimately the roadway.

00:30:37.040 --> 00:30:41.660
 But at this time, until Bronco Way is extended, which will be on the northern side of the

00:30:41.660 --> 00:30:48.420
 DISD high school, there's not a way for us to construct that project without having a

00:30:48.420 --> 00:30:55.260
 connection piece so the residents or emergency vehicles would be able to access this neighborhood.

00:30:55.260 --> 00:30:58.260
 And so we're working through and coordinating with DISD.

00:30:58.260 --> 00:31:02.980
 We actually have a meeting later today to talk to DISD, so just wanted to let you know

00:31:02.980 --> 00:31:08.180
 here are seven segments that we're kind of working on from a little bit different perspective.

00:31:08.180 --> 00:31:15.900
 And as you will recall, there are five segments that were from this 2012 and 2014 bond program

00:31:15.900 --> 00:31:20.940
 that were moved into the 2019 bond program just for the ability to look at that from

00:31:20.940 --> 00:31:29.100
 a holistic view and really touching the neighborhoods at one point.

00:31:29.100 --> 00:31:33.220
 Alrighty let me move to the next slide.

00:31:33.220 --> 00:31:41.780
 So the next slide goes through the 2019 proposition one, and what I wanted to bring to your attention

00:31:41.780 --> 00:31:45.140
 is the Bonnie Bray phase five project.

00:31:45.140 --> 00:31:48.700
 Currently we have the schedule is yellow and the budget is red.

00:31:48.700 --> 00:31:56.460
 Currently that's simply because we're working with the NCT cog to identify additional construction

00:31:56.460 --> 00:31:57.700
 funding.

00:31:57.700 --> 00:32:02.500
 As soon as that funding is allocated, then that will help us facilitate that ultimate

00:32:02.500 --> 00:32:05.980
 schedule to get that project completed.

00:32:05.980 --> 00:32:10.420
 For Bonnie Bray phase six, the schedule is really dependent upon all of the right away

00:32:10.420 --> 00:32:12.420
 acquisition that is needed.

00:32:12.420 --> 00:32:16.200
 And that's why you see that schedule as yellow.

00:32:16.200 --> 00:32:21.060
 On the Hickory Creek road phase three, what I will tell you on that one, we have schedule

00:32:21.060 --> 00:32:23.360
 and budget as yellow.

00:32:23.360 --> 00:32:28.460
 Net cog has indicated they are providing the $10 million that's needed to complete for

00:32:28.460 --> 00:32:31.180
 the construction funding of that project.

00:32:31.180 --> 00:32:34.680
 And so we're very excited to be able to receive that funding.

00:32:34.680 --> 00:32:40.260
 And we did have a call with them last week and we'll be filling out all the paperwork

00:32:40.260 --> 00:32:43.580
 to move forward with receiving that $10 million.

00:32:43.580 --> 00:32:49.020
 And there's potential schedule delays due to an encore transmission line relocation

00:32:49.020 --> 00:32:52.460
 that needs to happen in advance of the roadway.

00:32:52.460 --> 00:32:58.380
 On the Ryan road widening, we currently have yellow for the scope schedule and budget.

00:32:58.380 --> 00:33:03.740
 We're currently working to define that scope and the schedule is dependent upon that scope

00:33:03.740 --> 00:33:04.740
 and funding.

00:33:04.740 --> 00:33:08.500
 And it will likely require additional funding.

00:33:08.500 --> 00:33:13.260
 This project we're actually going to be bringing forward to council in the next couple of weeks

00:33:13.260 --> 00:33:18.900
 from an overall perspective of getting a 30% design schematic completed.

00:33:18.900 --> 00:33:21.980
 And it's going to be a project that we're going to be moving forward with a new type

00:33:21.980 --> 00:33:29.420
 of way for the city to move forward with alternative delivery and looking at using CMAR in order

00:33:29.420 --> 00:33:36.020
 to execute this project.

00:33:36.020 --> 00:33:41.460
 And on the 2019 reconstruction bond progress, we have some great news to share.

00:33:41.460 --> 00:33:47.980
 The phase one and two, which you can see in this kind of a red orange color, that that

00:33:47.980 --> 00:33:53.580
 area includes Mistywood Lane, Craig Lane, Freedom Lane and Chevy Lane.

00:33:53.580 --> 00:33:58.260
 We currently are in the process of advertising that project right now.

00:33:58.260 --> 00:34:03.100
 And that construction is scheduled to be completed by the end of the calendar year.

00:34:03.100 --> 00:34:09.500
 The other phase is phase two, which you can see in this area in blue and then down here

00:34:09.500 --> 00:34:16.180
 in blue, that's Lido Way, Balboa, Olympia, Fox Hollow and Timber Ridge.

00:34:16.180 --> 00:34:20.940
 Phase one and two are both a part of the same bid package.

00:34:20.940 --> 00:34:28.940
 We're actually bidding this as a concealed competitive sealed proposal solicitation.

00:34:28.940 --> 00:34:35.260
 And so the reason why these two phases were selected is because these areas do not have

00:34:35.260 --> 00:34:40.740
 utility relocations from a water/wastewater perspective that need to be completed in advance

00:34:40.740 --> 00:34:42.340
 of the roadway.

00:34:42.340 --> 00:34:46.140
 And so we wanted to have an opportunity to go ahead and work through getting some of

00:34:46.140 --> 00:34:50.100
 these streets constructed and under our belt.

00:34:50.100 --> 00:34:57.100
 On phase three, which you can kind of see in purple, down in this area is the Hill Martin

00:34:57.100 --> 00:35:02.740
 Jackson Mill Johnson and then down in the far corner of your screen, you can see the

00:35:02.740 --> 00:35:06.180
 Winston Waterford Way area.

00:35:06.180 --> 00:35:10.540
 We're currently working on this overall scope development.

00:35:10.540 --> 00:35:16.340
 We have an internal meeting scheduled with all departments to see if we can work on an

00:35:16.340 --> 00:35:20.420
 idea of having this more holistic approach, like I keep mentioning.

00:35:20.420 --> 00:35:26.260
 We want to make sure that we're including, if it is needed and we can coordinate it,

00:35:26.260 --> 00:35:30.180
 sidewalks, streetlights, water/wastewater utilities.

00:35:30.180 --> 00:35:33.500
 And so that schedule meeting is happening next week.

00:35:33.500 --> 00:35:39.500
 And we're really wanting to have some neighborhood collaboration and receive some feedback from

00:35:39.500 --> 00:35:45.540
 the neighborhood kind of as what they're interested in, really in this area that we're focusing

00:35:45.540 --> 00:35:47.460
 in on for phase three.

00:35:47.460 --> 00:35:53.740
 We're hoping to advertise in 2021 with looking to have construction completed in quarter

00:35:53.740 --> 00:36:01.440
 three of 2022, but we're still looking at that overall holistic approach and that scoping.

00:36:01.440 --> 00:36:05.980
 Currently as it scoped, phase one through three comprises about 7%.

00:36:05.980 --> 00:36:12.900
 We're looking at making that actually a larger portion of the overall 2019 street reconstruction.

00:36:12.900 --> 00:36:17.160
 As we're thinking, it makes maybe a little bit more sense or there's some more economies

00:36:17.160 --> 00:36:22.100
 of scale of actually approaching this entire neighborhood that you see in this area at

00:36:22.100 --> 00:36:23.740
 one time.

00:36:23.740 --> 00:36:26.220
 And so we're very excited.

00:36:26.220 --> 00:36:32.660
 After bid package three is advertised for construction, we'll begin the goal to look at actually working

00:36:32.660 --> 00:36:40.020
 through all of the other phases and programming that entire bond program out with an anticipation

00:36:40.020 --> 00:36:43.220
 of design and construction completion.

00:36:43.220 --> 00:36:48.700
 And our hopes are to have it all completed by the end of 2025, but we will be working

00:36:48.700 --> 00:36:53.180
 through that program.

00:36:53.180 --> 00:36:55.700
 And with that, I will open it up to questions.

00:36:55.700 --> 00:37:00.540
 If anyone has any questions for myself or Rachel or like I mentioned, Daniel Kramer

00:37:00.540 --> 00:37:02.900
 is on the call.

00:37:02.900 --> 00:37:11.380
 Hey, Becky, on the 2019 street reconstruction, it looks like a lot of good progress.

00:37:11.380 --> 00:37:13.480
 So thank you.

00:37:13.480 --> 00:37:21.140
 Do we have sort of a goal of the phasing of that entire program to complete it by 2026

00:37:21.140 --> 00:37:25.940
 so that we could start to look at linearity along that timeframe as we go forward?

00:37:25.940 --> 00:37:31.380
 Or is that something that is limited in our ability to project?

00:37:31.380 --> 00:37:32.580
 Actually that's a great question.

00:37:32.580 --> 00:37:38.260
 So really, what our goal is at this point is we're looking at it really how can we have

00:37:38.260 --> 00:37:42.420
 a, you know, that holistic approach I talk about, I really would like to go in and be

00:37:42.420 --> 00:37:47.500
 able to do street lights, sidewalks, if there's any bike lanes that are needed, you know,

00:37:47.500 --> 00:37:52.180
 any improvements that are needed also from a utility perspective, water, wastewater.

00:37:52.180 --> 00:37:57.860
 We actually have hired a consultant to work on programming that entire project from beginning

00:37:57.860 --> 00:38:03.220
 to end that will have all of the street segments and then we'll be able to give you an anticipation

00:38:03.220 --> 00:38:08.380
 of we broke it into neighborhoods, this neighborhoods anticipated to be designed in this calendar

00:38:08.380 --> 00:38:13.220
 year or this quarter with completion in this calendar year or this quarter.

00:38:13.220 --> 00:38:15.620
 And so that is forthcoming.

00:38:15.620 --> 00:38:20.900
 We're not quite there yet, but that absolutely is something that we hope to be able to present

00:38:20.900 --> 00:38:22.980
 to you in the near future.

00:38:22.980 --> 00:38:23.980
 Sounds great.

00:38:23.980 --> 00:38:24.980
 Thank you.

00:38:24.980 --> 00:38:28.280
 I just, I want to make sure that we stay on schedule with that one since we obviously had

00:38:28.280 --> 00:38:32.180
 funding issues with previous programs due to timing.

00:38:32.180 --> 00:38:33.180
 So thanks.

00:38:33.180 --> 00:38:39.780
 That was going to be my question with the growth in the construction market and the

00:38:39.780 --> 00:38:44.940
 area, what kind of cost pressure are we seeing on our projects?

00:38:44.940 --> 00:38:45.940
 I'm sorry.

00:38:45.940 --> 00:38:46.940
 Can you repeat that again?

00:38:46.940 --> 00:38:47.940
 I didn't.

00:38:47.940 --> 00:38:54.620
 Yeah, with the rapid growth of the housing market in Denton County and across the area,

00:38:54.620 --> 00:38:59.220
 what impact are we seeing if any on our construction projects?

00:38:59.220 --> 00:39:03.300
 You know, at this time, I don't think we're really seeing a whole lot of impact on our

00:39:03.300 --> 00:39:05.980
 construction projects.

00:39:05.980 --> 00:39:10.980
 We're really working through trying to make sure that we program the projects.

00:39:10.980 --> 00:39:14.940
 I will tell you the thing that probably is a little bit different from the way things

00:39:14.940 --> 00:39:16.860
 that have been done in the past.

00:39:16.860 --> 00:39:21.820
 And we're very excited about is using, like I mentioned, that competitive SIL proposal

00:39:21.820 --> 00:39:23.540
 or then alternative delivery.

00:39:23.540 --> 00:39:27.960
 We're actually looking at for neighborhood three, possibly using that CMAR approach.

00:39:27.960 --> 00:39:32.620
 So with that comes different ways to deliver projects, which ultimately comes in, you know,

00:39:32.620 --> 00:39:36.200
 kind of different contractor relationships.

00:39:36.200 --> 00:39:39.940
 But at this point, we're not really seeing a whole lot of things in the market that are

00:39:39.940 --> 00:39:45.300
 really impacting our projects and just really working to try to get them completed and move

00:39:45.300 --> 00:39:51.860
 forward with being able to kind of check those boxes that these projects are moving forward.

00:39:51.860 --> 00:39:52.860
 Thank you.

00:39:52.860 --> 00:39:55.900
 No problem.

00:39:55.900 --> 00:39:58.900
 Anything else?

00:39:58.900 --> 00:39:59.900
 And I apologize.

00:39:59.900 --> 00:40:02.740
 I forgot to take my screen down and stop sharing.

00:40:02.740 --> 00:40:05.860
 I'm having technically technical challenges today.

00:40:05.860 --> 00:40:06.860
 My apologies.

00:40:06.860 --> 00:40:13.180
 All right, Cassie is.

00:40:13.180 --> 00:40:14.180
 Thank you.

00:40:14.180 --> 00:40:15.180
 Thanks, Becky.

00:40:15.180 --> 00:40:21.700
 We have one more presentation on the bond program update from facilities.

00:40:21.700 --> 00:40:29.380
 And so Scott is on the line and we have Nick is going to run the presentation from here.

00:40:29.380 --> 00:40:56.700
 So give us just a minute to get it set up and then we will will present that.

00:40:56.700 --> 00:40:57.700
 Good afternoon.

00:40:57.700 --> 00:41:00.860
 I'm Mark Gray, director of airport facilities and real estate.

00:41:00.860 --> 00:41:02.340
 Thank you for the opportunity to be here today.

00:41:02.340 --> 00:41:06.240
 I have a quick presentation on a couple of our bond projects.

00:41:06.240 --> 00:41:07.300
 Next slide, please.

00:41:07.300 --> 00:41:08.620
 Next one.

00:41:08.620 --> 00:41:14.300
 The first one is the 2014 bond proposition number two, which included fire station number

00:41:14.300 --> 00:41:18.180
 three and the demolition of the existing station.

00:41:18.180 --> 00:41:22.860
 As you can see, we had some challenges with schedule and budget over the course of this

00:41:22.860 --> 00:41:28.100
 project, but I'm happy to report that the new station will be completed next week and

00:41:28.100 --> 00:41:32.660
 the fire department personnel will be moving in in the next few days after that.

00:41:32.660 --> 00:41:37.180
 And they'll occupy the new facility and start operating from there, which will allow us

00:41:37.180 --> 00:41:42.380
 to move to the second phase of the project, which is the demolition of the old station,

00:41:42.380 --> 00:41:44.020
 which you see pictured there.

00:41:44.020 --> 00:41:48.740
 And then the cleanup of the site landscaping and things of that nature, which will be completed

00:41:48.740 --> 00:41:49.740
 in April.

00:41:49.740 --> 00:41:54.420
 So I hope when I return at the next bond meeting, I will be telling you that this project is

00:41:54.420 --> 00:41:58.100
 complete and we will be moving on to some other projects.

00:41:58.100 --> 00:42:04.700
 As you can see, the budget of this project was $9.4 million with the split of the GOCOs

00:42:04.700 --> 00:42:06.140
 to date.

00:42:06.140 --> 00:42:11.660
 I know that the chief is excited about moving into this building and although not a bond

00:42:11.660 --> 00:42:14.980
 project, we're finishing a second building here in two weeks after that.

00:42:14.980 --> 00:42:19.420
 So the fire station will be moving into two different buildings over the next couple of

00:42:19.420 --> 00:42:20.900
 days.

00:42:20.900 --> 00:42:25.260
 Any questions on this particular project?

00:42:25.260 --> 00:42:27.700
 Okay.

00:42:27.700 --> 00:42:28.900
 Next slide.

00:42:28.900 --> 00:42:30.060
 Next one after that, please, Nick.

00:42:30.060 --> 00:42:31.060
 Thank you.

00:42:31.060 --> 00:42:38.020
 So the next project is the 2019 bond proposition number one project, which was the public safety

00:42:38.020 --> 00:42:43.500
 buildings, which is actually two different sites, three different buildings.

00:42:43.500 --> 00:42:49.940
 The first one being the police headquarters building that is co-located in City Hall East

00:42:49.940 --> 00:42:55.100
 and then the police substation and firing range, which are both located at vintage and

00:42:55.100 --> 00:42:56.700
 Bonnie Bray.

00:42:56.700 --> 00:43:01.820
 The notice to proceed of these projects was just done a couple of weeks ago on January

00:43:01.820 --> 00:43:02.820
 15th.

00:43:02.820 --> 00:43:09.360
 And then since that time, we've created a lot of havoc over at City Hall East and almost

00:43:09.360 --> 00:43:15.740
 all of the PD personnel have been relocated within that building so that the construction

00:43:15.740 --> 00:43:24.980
 crews can start their demolition and construction activities in the existing headquarters footprint.

00:43:24.980 --> 00:43:30.140
 We expect that all three of these facilities will be substantially completed in the second

00:43:30.140 --> 00:43:36.060
 quarter of 2022 with completion of the project in the third quarter.

00:43:36.060 --> 00:43:43.860
 So this bond project was for $61.9 million, which is all three of these buildings and

00:43:43.860 --> 00:43:47.900
 any of the alternates that were included in that.

00:43:47.900 --> 00:43:56.040
 So far today we have $47.3 million issued and our construction contractor has just getting

00:43:56.040 --> 00:44:00.540
 started on the second site, but most of the activity so far has been on the police headquarters

00:44:00.540 --> 00:44:01.540
 side.

00:44:01.540 --> 00:44:04.780
 And there's the renderings that I think that I presented the last time and I don't think

00:44:04.780 --> 00:44:11.040
 anything's changed relevant to the design at this point.

00:44:11.040 --> 00:44:14.860
 Those are the two projects I had pretty quick and to the point, and I'd be happy to answer

00:44:14.860 --> 00:44:22.140
 any questions on those projects.

00:44:22.140 --> 00:44:23.140
 Thank you.

00:44:23.140 --> 00:44:24.140
 Seeing none.

00:44:24.140 --> 00:44:25.140
 Thank you very much.

00:44:25.140 --> 00:44:30.460
 You have a great day.

00:44:30.460 --> 00:44:37.020
 That is all we had for item B unless there are any other questions.

00:44:37.020 --> 00:44:40.260
 Okay.

00:44:40.260 --> 00:44:42.620
 Thank you very much, Cassie.

00:44:42.620 --> 00:44:47.540
 Moving on to item C, receive report, hold a discussion, give staff direction regarding

00:44:47.540 --> 00:44:52.900
 the reallocation of project funds and the estimated completion cost for associated projects.

00:44:52.900 --> 00:44:56.460
 So over to you, Cassie.

00:44:56.460 --> 00:45:02.740
 And Gary Packin, our director of parks is going to present the reallocation request.

00:45:02.740 --> 00:45:09.540
 I think we're having some technical difficulties today.

00:45:09.540 --> 00:45:29.660
 Give us one minute and we'll share the screen.

00:45:29.660 --> 00:45:31.740
 Can you guys see that?

00:45:31.740 --> 00:45:32.740
 We can.

00:45:32.740 --> 00:45:33.740
 Thank you, Gary.

00:45:33.740 --> 00:45:34.740
 Okay.

00:45:34.740 --> 00:45:42.740
 All right, so as mentioned earlier, we have a few projects that are anticipated to be

00:45:42.740 --> 00:45:47.660
 underfunded and some that are overfunded that we have completed.

00:45:47.660 --> 00:45:52.580
 So I'm going to go through the three requests for reallocation.

00:45:52.580 --> 00:45:59.180
 So from our playground program, we had $773,000 for replacement of playgrounds.

00:45:59.180 --> 00:46:05.400
 We did complete that entire list that was in the bond package, and we completed one

00:46:05.400 --> 00:46:07.500
 additional playground.

00:46:07.500 --> 00:46:14.680
 So with that in mind, we had $177,000, almost $178,000 remaining.

00:46:14.680 --> 00:46:20.400
 We like to request $150,000 of that to be transferred to South Lake Park improvements,

00:46:20.400 --> 00:46:24.940
 and that is the two new tennis courts with lights and the possibility of adding lights

00:46:24.940 --> 00:46:32.240
 to the existing court to help with that anticipated funding gap that doesn't include a contingency.

00:46:32.240 --> 00:46:39.420
 That would leave a balance of $27,000 in change in the playground replacement project account

00:46:39.420 --> 00:46:43.620
 specifically.

00:46:43.620 --> 00:46:48.780
 We have been pretty aggressive in replacing our playgrounds, so we have been using other

00:46:48.780 --> 00:46:51.900
 funding sources if we could to match that up.

00:46:51.900 --> 00:46:56.660
 That is one of the reasons why we had some balance left over to try to use our parkland

00:46:56.660 --> 00:47:02.460
 dedication and development funds where available specifically gave us the ability to be a little

00:47:02.460 --> 00:47:06.860
 bit more flexible with that funding and actually have the balance left over and do that additional

00:47:06.860 --> 00:47:10.620
 play structure at Joe Skiles.

00:47:10.620 --> 00:47:16.580
 So with that, I'll entertain any questions regarding the request number one.

00:47:16.580 --> 00:47:24.020
 All right, seeing no questions, Cassie, do we need to take these individually or as one

00:47:24.020 --> 00:47:26.700
 collective motion?

00:47:26.700 --> 00:47:33.980
 I believe we did it as one motion last time, but I'll refer to, I'll defer to Mac.

00:47:33.980 --> 00:47:37.460
 You can do it as one unless you want to break it out separately if you'd like to discuss

00:47:37.460 --> 00:47:39.460
 them separately, but if you want to handle those ones.

00:47:39.460 --> 00:47:43.380
 We'll do it as one, if that's all right.

00:47:43.380 --> 00:47:44.380
 Okay.

00:47:44.380 --> 00:47:48.300
 So number two is again, the playground replacement fund.

00:47:48.300 --> 00:47:57.260
 As with request number one, we have a balance of $27,955.29.

00:47:57.260 --> 00:48:02.340
 We'd like to move that to North Lakes Tennis Center with the anticipated paving of the

00:48:02.340 --> 00:48:05.600
 road and some other adjustments plus cost increases.

00:48:05.600 --> 00:48:09.760
 We wanted to make sure we had enough funding to complete all of our projects, so we'd like

00:48:09.760 --> 00:48:16.140
 to move that money over to North Lakes Tennis Center and we'll close the playground account

00:48:16.140 --> 00:48:17.140
 out.

00:48:17.140 --> 00:48:24.660
 So that is buttoned up and then we'll move on to request number two, which ties into

00:48:24.660 --> 00:48:26.660
 that as well.

00:48:26.660 --> 00:48:28.240
 Request number three, sorry.

00:48:28.240 --> 00:48:31.460
 And that is the balance of the Southwest Park Master Plan Design.

00:48:31.460 --> 00:48:36.840
 Originally, it was $1.2 million for the entire design process.

00:48:36.840 --> 00:48:41.200
 We do have a balance of $856,000.

00:48:41.200 --> 00:48:47.760
 Right now, we've hired a consultant to do the master plan for the park itself and we

00:48:47.760 --> 00:48:54.620
 requested over the past year, two years actually, some funding to be put towards our park recreation

00:48:54.620 --> 00:48:57.820
 and trail system master plan from this project.

00:48:57.820 --> 00:49:03.580
 So we're able to do both of those projects as of right now and still have this balance.

00:49:03.580 --> 00:49:07.220
 We could handle this in two different ways that we could suggest.

00:49:07.220 --> 00:49:11.700
 One is as presented, move the balance over to North Lakes Tennis Center.

00:49:11.700 --> 00:49:16.460
 This gives us the funding available to make sure that we hopefully have enough once the

00:49:16.460 --> 00:49:23.860
 bids come back to complete that bond project or it could remain in the account and be used

00:49:23.860 --> 00:49:30.580
 for future design whenever additional funding is available for that park.

00:49:30.580 --> 00:49:35.820
 $856,000 isn't going to be enough for the total design of the entire park.

00:49:35.820 --> 00:49:41.300
 It could be enough for design of a portion of the park, but at this point in time, we're

00:49:41.300 --> 00:49:48.540
 not sure when that will be until that process is approved and we're taking our next steps.

00:49:48.540 --> 00:49:52.860
 At this time, staff's recommending that we move it to the North Lakes Tennis Center so

00:49:52.860 --> 00:49:59.940
 we can make sure that that project is completed and our 2014 bond program in parks and recreation

00:49:59.940 --> 00:50:06.440
 is completed as soon as possible.

00:50:06.440 --> 00:50:11.500
 So in summary, the three requests, two of them coming from the playground replacements

00:50:11.500 --> 00:50:17.200
 of approximately $177,000 towards South Lake Park Improvement, which is the two tennis

00:50:17.200 --> 00:50:21.980
 courts and the development of the North Lakes Park Tennis Center.

00:50:21.980 --> 00:50:27.860
 And then the third one was the Southwest Park Master Plan and $856,000 that's currently

00:50:27.860 --> 00:50:34.500
 balanced in that account for a total of $1 million that we'd be shifting to other projects

00:50:34.500 --> 00:50:36.860
 within the bond program.

00:50:36.860 --> 00:50:45.900
 Gary, why were we so far off in what we estimated the Southwest Park design to be versus what

00:50:45.900 --> 00:50:46.900
 it actually costs?

00:50:46.900 --> 00:50:47.900
 I mean, is

00:50:47.900 --> 00:50:49.620
 Yeah, we, I mean, go back.

00:50:49.620 --> 00:50:57.260
 We completed all the appropriate steps that we need to with the consultant, the environmental

00:50:57.260 --> 00:50:59.020
 and the survey work.

00:50:59.020 --> 00:51:03.060
 The only thing I could think of that that may have been thought about when this was

00:51:03.060 --> 00:51:08.060
 originally appropriated was the anticipation of doing design work for the construction.

00:51:08.060 --> 00:51:16.740
 You know, design work is typically 10 to 12% of a project with the plan for that park.

00:51:16.740 --> 00:51:21.100
 It's going to be a significant investment for improvements that could be broken out

00:51:21.100 --> 00:51:26.900
 into smaller phases for sure and do some preliminary improvements, but we do not have any funding

00:51:26.900 --> 00:51:29.260
 for any of the improvements at this time.

00:51:29.260 --> 00:51:35.820
 So it's really whether we want to hold on to it and see when that happens, or reallocate

00:51:35.820 --> 00:51:39.060
 it and use the funding for another project.

00:51:39.060 --> 00:51:40.060
 Okay.

00:51:40.060 --> 00:51:41.060
 Thank you.

00:51:41.060 --> 00:51:44.180
 Well, is that the last of the requests?

00:51:44.180 --> 00:51:45.180
 From Parks and Recreation?

00:51:45.180 --> 00:51:47.260
 Yes, that is correct.

00:51:47.260 --> 00:51:48.260
 All right.

00:51:48.260 --> 00:51:57.180
 Any comments, or can I get a motion to consider this approving?

00:51:57.180 --> 00:52:04.340
 Gary just one question on the Southwest Park.

00:52:04.340 --> 00:52:11.660
 What impacts do we have from future park fees that might be collected from development in

00:52:11.660 --> 00:52:12.660
 that area?

00:52:12.660 --> 00:52:17.620
 Does that factor into what we think we will have from a future funding capability perspective

00:52:17.620 --> 00:52:18.620
 in that area?

00:52:18.620 --> 00:52:23.060
 Or am I stepping out of my understanding?

00:52:23.060 --> 00:52:24.660
 No, we do.

00:52:24.660 --> 00:52:28.940
 We do have a development on the north side and a development on the south side of the

00:52:28.940 --> 00:52:33.620
 park that are in the planning stages in various ways.

00:52:33.620 --> 00:52:37.060
 Hunter Ranch is directly to our west.

00:52:37.060 --> 00:52:42.340
 So we do have parks planned for that perspective down the road.

00:52:42.340 --> 00:52:45.440
 That's a little bit more of a long-term plan.

00:52:45.440 --> 00:52:50.540
 But as of right now, we are working to update our 9/15/16 or our park land dedication and

00:52:50.540 --> 00:52:51.540
 development ordinance.

00:52:51.540 --> 00:52:56.900
 We're hoping to take that to council in March for discussion and consideration.

00:52:56.900 --> 00:53:01.540
 That would probably take effect in the fall at the earliest.

00:53:01.540 --> 00:53:06.100
 So we're a little bit ways there, but the funding that would be available for that,

00:53:06.100 --> 00:53:12.000
 whether it's land acquisition or park development, and if there's not land needed in an area,

00:53:12.000 --> 00:53:15.300
 we can reallocate that for park improvements.

00:53:15.300 --> 00:53:21.100
 So we could use that money from there, but there's not a significant amount there for

00:53:21.100 --> 00:53:23.460
 construction of that park.

00:53:23.460 --> 00:53:24.460
 Okay.

00:53:24.460 --> 00:53:25.460
 Thanks.

00:53:25.460 --> 00:53:26.460
 That helps.

00:53:26.460 --> 00:53:35.560
 I think it's a big chunk of money comparatively, but given the fact that there's lots of plans

00:53:35.560 --> 00:53:43.340
 down there, but construction hasn't really started on all those projects yet, I'd hate

00:53:43.340 --> 00:53:47.740
 to see that much money just sit there and not benefit the community for a long time

00:53:47.740 --> 00:53:49.220
 as well.

00:53:49.220 --> 00:53:57.940
 Gary, just for clarity purposes, when this funding, assuming that everybody approves

00:53:57.940 --> 00:54:08.020
 this, is moved over there to the tennis center, that builds what portion of the master plan

00:54:08.020 --> 00:54:14.860
 for those courts, and what is unbuilt?

00:54:14.860 --> 00:54:17.540
 The bond package was 12 courts.

00:54:17.540 --> 00:54:25.000
 The master plan is more than 18 long-term, plus some pickleball courts.

00:54:25.000 --> 00:54:31.220
 The way we have that bid is the base bid is 10, just in case, with an alternate of two

00:54:31.220 --> 00:54:35.620
 additional courts that would get us to the 12, so we could see exactly how much those

00:54:35.620 --> 00:54:37.840
 two courts would cost us.

00:54:37.840 --> 00:54:43.220
 And then we also have an option in there for one set of the pickleball courts if we decided

00:54:43.220 --> 00:54:45.020
 we wanted to build those.

00:54:45.020 --> 00:54:50.780
 Those pickleball courts were not part of the original bond package, but we wanted to see

00:54:50.780 --> 00:54:54.540
 what that would cost us if we had the funding and we wanted to do that, we could make the

00:54:54.540 --> 00:54:58.780
 decision as an alternate and take that under consideration.

00:54:58.780 --> 00:55:05.700
 But from the bond package, we're obligated to follow up on that, and that's 12 courts

00:55:05.700 --> 00:55:08.940
 with lights in the pro shop.

00:55:08.940 --> 00:55:15.940
 And I know that one of the plans included some junior courts.

00:55:15.940 --> 00:55:19.180
 Are the junior courts in the mix here at all?

00:55:19.180 --> 00:55:21.300
 The junior courts are the pickleball courts.

00:55:21.300 --> 00:55:23.020
 We designed them so it would be one and the same.

00:55:23.020 --> 00:55:25.000
 That was a little more flexibility.

00:55:25.000 --> 00:55:34.060
 And then we could also mark some of the full-sized courts with the mid-range court as well.

00:55:34.060 --> 00:55:35.060
 Thank you.

00:55:35.060 --> 00:55:36.060
 Yes, sir.

00:55:36.060 --> 00:55:37.060
 Okay.

00:55:37.060 --> 00:55:38.060
 All right.

00:55:38.060 --> 00:55:53.020
 Anyone want to put forward a motion to consider this reallocation as presented?

00:55:53.020 --> 00:55:54.020
 I'll move it.

00:55:54.020 --> 00:55:55.020
 Okay.

00:55:55.020 --> 00:55:56.020
 Thank you, Tim.

00:55:56.020 --> 00:55:58.060
 Do I have a second?

00:55:58.060 --> 00:56:00.260
 Thank you, Eric.

00:56:00.260 --> 00:56:02.260
 Any other discussion?

00:56:02.260 --> 00:56:11.300
 All right, seeing none, all in favor of reallocation of approximately $1 million to the tennis

00:56:11.300 --> 00:56:15.740
 court projects, please signify by saying, yeah, you're raising your hand.

00:56:15.740 --> 00:56:16.740
 Yeah.

00:56:16.740 --> 00:56:17.740
 Janet.

00:56:17.740 --> 00:56:18.740
 Yeah.

00:56:18.740 --> 00:56:19.740
 Thank you.

00:56:19.740 --> 00:56:20.740
 All right.

00:56:20.740 --> 00:56:21.740
 Anyone opposed?

00:56:21.740 --> 00:56:22.740
 Same sign.

00:56:22.740 --> 00:56:23.740
 Motion carries.

00:56:23.740 --> 00:56:32.220
 Mr. Smith, just to add to that, if, you know, hopefully we don't need all that funding,

00:56:32.220 --> 00:56:36.180
 but if there is a balance, then we'll come back to the committee with a recommendation

00:56:36.180 --> 00:56:40.380
 on opportunities or where that could be reallocated.

00:56:40.380 --> 00:56:41.380
 Thank you, Gary.

00:56:41.380 --> 00:56:42.380
 Appreciate it.

00:56:42.380 --> 00:56:43.380
 All right.

00:56:43.380 --> 00:56:44.380
 Very good.

00:56:44.380 --> 00:56:47.380
 I think the last item.

00:56:47.380 --> 00:56:50.460
 Pat, if you don't mind, let me just ask one quick question.

00:56:50.460 --> 00:56:58.220
 Gary, I believe that there was some funding related to the tennis courts back in 2005,

00:56:58.220 --> 00:57:01.220
 a 2005 bond package.

00:57:01.220 --> 00:57:02.340
 Is that correct?

00:57:02.340 --> 00:57:03.340
 Yes.

00:57:03.340 --> 00:57:05.340
 That's included in our balance.

00:57:05.340 --> 00:57:06.340
 Okay.

00:57:06.340 --> 00:57:11.900
 And so the point, the only point I would want to add to that is that that was something the

00:57:11.900 --> 00:57:17.780
 voters approved in 2005 and it's finally going to get done in 2022.

00:57:17.780 --> 00:57:20.460
 And that's a long time to wait on that.

00:57:20.460 --> 00:57:26.180
 So I think that it's, I just think this is important to move forward on.

00:57:26.180 --> 00:57:28.300
 Yep.

00:57:28.300 --> 00:57:34.540
 Okay, moving on, item D, receive a report, hold a discussion, provide information on

00:57:34.540 --> 00:57:42.100
 the 2020-2021 reimbursement ordinance and updated bond issuance timeline.

00:57:42.100 --> 00:57:44.020
 Over to you, Cassie.

00:57:44.020 --> 00:57:45.020
 Thank you.

00:57:45.020 --> 00:57:50.420
 So we took this item to council actually in January, but we wanted to give the bond committee

00:57:50.420 --> 00:57:57.300
 an update of where we are and what bond packages or projects were included in the ordinance.

00:57:57.300 --> 00:58:00.780
 And so we have on the line, Erin Nguyen, our budget manager, who's actually going to give

00:58:00.780 --> 00:58:01.780
 you the presentation.

00:58:01.780 --> 00:58:08.020
 And so I will turn it over to her and obviously we'll be here if you have any questions.

00:58:08.020 --> 00:58:09.020
 All right.

00:58:09.020 --> 00:58:10.020
 Thank you, Cassie.

00:58:10.020 --> 00:58:12.020
 Go ahead and get this started.

00:58:12.020 --> 00:58:18.860
 All right, like Cassie said, I'm Erin Nguyen, budget manager, got a very brief presentation

00:58:18.860 --> 00:58:19.860
 for you.

00:58:19.860 --> 00:58:24.940
 We're going to first go over the general obligation projects that were approved and included in

00:58:24.940 --> 00:58:26.940
 our reimbursement ordinance.

00:58:26.940 --> 00:58:30.860
 We'll update you on a slight adjustment to our bond issuance schedule and of course,

00:58:30.860 --> 00:58:33.320
 be able to answer any questions.

00:58:33.320 --> 00:58:38.340
 So last month, city council approved $168 million reimbursement ordinance.

00:58:38.340 --> 00:58:42.860
 Essentially, this just gives us permission to spend money now for projects that were

00:58:42.860 --> 00:58:47.180
 included in the fiscal year of 2020-21 CIP.

00:58:47.180 --> 00:58:51.340
 We'll pay ourselves back when we issue debt later this spring.

00:58:51.340 --> 00:58:55.960
 Below are the projects that are funded with GO dollars that were included.

00:58:55.960 --> 00:59:00.820
 You'll see both the budget amount and also the amount that was approved in the reimbursement

00:59:00.820 --> 00:59:05.460
 ordinance for street reconstruction, Bonnie Bray and sidewalks.

00:59:05.460 --> 00:59:12.620
 We got the entirety of the budget amount approved so we can move forward with all of those projects.

00:59:12.620 --> 00:59:19.660
 The public safety facility, we included $40 million of the almost $43 million that's part

00:59:19.660 --> 00:59:20.660
 of the budget amount.

00:59:20.660 --> 00:59:23.960
 We'll talk about that in just a little bit.

00:59:23.960 --> 00:59:29.060
 This is a table that shows the issuance schedule for the 2019 bond program.

00:59:29.060 --> 00:59:36.340
 Initially, we had planned to issue $42.9 million for Prop 2 for the 2019 bond program this

00:59:36.340 --> 00:59:37.740
 fiscal year.

00:59:37.740 --> 00:59:42.540
 However, after honing in more on the project and what's needed this year in terms of cash

00:59:42.540 --> 00:59:46.020
 flow, we are reducing that issuance to $40 million.

00:59:46.020 --> 00:59:50.020
 Essentially, we do not want to issue debt before we need it and we're shifting that

00:59:50.020 --> 00:59:53.780
 additional $2.9 million to next fiscal year.

00:59:53.780 --> 01:00:01.860
 So the totals at the bottom, the total issuance for fiscal year 2021 decreased and it increased

01:00:01.860 --> 01:00:08.820
 for fiscal year 2021-22, but of course the total amount that was voter approved to issue

01:00:08.820 --> 01:00:11.260
 will stay the same.

01:00:11.260 --> 01:00:16.500
 Any questions about either the reimbursement ordinance or the updated issuance schedule?

01:00:16.500 --> 01:00:24.260
 It doesn't appear so Erin, thank you.

01:00:24.260 --> 01:00:29.500
 Okay, thank you.

01:00:29.500 --> 01:00:32.340
 So Cassie, that's just for information, correct?

01:00:32.340 --> 01:00:35.560
 Yes, we don't need any action taken on that item.

01:00:35.560 --> 01:00:40.380
 We just wanted to give you an update on where we were as far as the bond issuance timeline.

01:00:40.380 --> 01:00:44.020
 Okay, thank you.

01:00:44.020 --> 01:00:50.180
 All right, I think we're about ready to complete our work for the day.

01:00:50.180 --> 01:00:55.460
 Any concluding remarks or comments?

01:00:55.460 --> 01:01:00.100
 Our next meeting I believe is May 6th at noon, is that correct?

01:01:00.100 --> 01:01:02.220
 Yes, that is correct.

01:01:02.220 --> 01:01:14.100
 Okay, can I get a, Randy do you have anything?

01:01:14.100 --> 01:01:19.340
 Okay, well, hearing none, no other comments, we'll adjourn at this time.